Professional Documents
Culture Documents
Project Management - Earned Value Analysis
Project Management - Earned Value Analysis
Project Management - Earned Value Analysis
Assignment Requirement
Your team has been assigned to help Christopher Martin determine what went wrong with
the project and develop a presentation and recommendation for Terry Baker.
1. Which of the two components is underperforming according to the plan? How do you
know this?
Based on the article, the TWO major components of the project are, (1) Technical
Infrastructure (TI) setup and (2) Software Customization (SC).
Martin realizes that base on the Microsoft Project Gantt chart, he could not find out
which component is responsible for the delay. He figured out that, using data obtained
from his project staff, and by creating Earned Value Analysis, he could find which
component causing the delay.
Earned Value Analysis will give him 4 project performance indicators, which is:
Using the given Earned Valued Analysis template, here is the calculated results, base on
information received from Martin’s project staff.
Page 1 of 4
ARIBA implementation
Using calculated results from Earned Value Analysis above, the project performance
can be summarized as follow:
Conclusion, based on the calculation in Earned Value Analysis and summary of it above,
we can conclude that Technical Infrastructure component implementation is BEHIND
the schedule and OVER the estimated budget. While Software Customization
implementation is AHEAD of the schedule and UNDER the estimated budget.
Page 2 of 4
ARIBA implementation
2. Are the components of the project within the budget? How do you know?
To determine whether both components of the project within the budget, we have to
look at the calculated values of Cost Variance (CV). Using again Earned Value Analysis
above, the results reveal that, all CV shows POSITIVE values for Software Customization
component, and exactly 0 in May, NEGATIVE in June, July, and August, and only POSITIVE
in September for Technical Infrastructure component.
3. What can you conclude by looking at the combined earned value data for the
project?
By looking at the combined earned value, we can see that all most of the indicator show
POSITIVE results except in the month of June. Therefore, based on this information, we
can conclude that if the data from both components combines, the project appears to
be WITHIN and UNDER the estimated budget and implemented AHEAD of the schedule.
4. Why did Terry Baker think that the project was going according to plan the entire
time?
Terry Baker thinks that the project was according to plan because of:
• Christopher Martin the Project Manager did not communicate the problems he
faced and not comfortable reporting it to her.
• She has been reviewing the budget variance and combine earned value reports
and everything is thought to be fine, but unaware that if the project components
earned value calculated separately, she will see there is delays in Technical
Infrastructure component project implementation.
Page 3 of 4
ARIBA implementation
To calculate how many additional days for the project to be completed, several
information from the project needs to be identified:
• No. of days for project completion based on schedule from May to September.
= May (31d) + June (30d) + July (31d) + August (31d) + September (30d)
= 153 days
• Since only Technical Infrastructure component causing the delay, and both
components are independent from each other, therefore the required
completion days only taken from the requirement from Technical Infrastructure
component
• Schedule Performance Index (SPI) for Technical Infrastructure component in
September is 0.9635.
• Numbers of additional days can be calculated by dividing no. of days (until
September) with SPI in September
Therefore, number of additional days required the project will take is.
6. What should Martin have done earlier in the project timeline to prevent delays?
7. What should Martin do when managing future projects to prevent similar problems
from developing?
• Progress meeting should be held in regular basis with vendors and involved
parties.
• Improve and manage effective communication within key project members.
• Have a clear and establish project scope and objectives.
• Have a clear resources management reports.
• Add more (if any)
• Add more (if any)
Page 4 of 4