METHOD STATEMENT Sluice Gates Install

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

SDHO Increment II, Initial Site Development

Pk1 (6600041347) & Pk2 (6600042398)


METHOD STATEMENT FOR SLUICE & BASKET
SCREEN INSTALLATION

Package 01/02 Doc. No. Rev. No.

METHOD STATEMENT
FOR
SLUICE GATE & BASKET SCREEN INSTALLATION

Checked By Checked By Approved By Approved By


Engineering Manager Construction Manager Project Manager Project Manager

Ayhan Umarogullari Mesut Tasar Mehmet Kasaboglu Salih Kasaboglu

METHOD STATEMENT FOR SLUICE GATE & BASKET SCREEN INSTALLATION 1


SDHO Increment II, Initial Site Development
Pk1 (6600041347) & Pk2 (6600042398)
METHOD STATEMENT FOR SLUICE & BASKET
SCREEN INSTALLATION

Package 01/02 Doc. No. Rev. No.

INDEX

1. SCOPE

2. PURPOSE

3. REFERENCES DOCUIMENTS

4. DEFINITIONS / ABBREVIATIONS

5. RESPONSIBILITY

6. RESOURCES

7. WORK EXECUTION PROCEDURE

8. QUALITY ASSURANCE / QUALITY CONTROL

9. HSE REQUIREMENTS

10. DRAWINGS - ATTACHMENTS

METHOD STATEMENT FOR SLUICE GATE & BASKET SCREEN INSTALLATION 2


SDHO Increment II, Initial Site Development
Pk1 (6600041347) & Pk2 (6600042398)
METHOD STATEMENT FOR SLUICE & BASKET
SCREEN INSTALLATION

Package 01/02 Doc. No. Rev. No.

1. SCOPE:

This method statement covers the activities and procedures to be implemented for
installation of sluice gates & basket screens with the Contract Specification and without
any safety violations within our project.

2. PURPOSE:

The purpose of this method statement is to outline the general requirements and
precautionary measures, which should be taken into consideration for installation of
sluice gates & basket screen. Furthermore, to ensure that significant health and safety
risk have been identified and what further control measures must be taken to reduce risk
to an acceptable level.

3. REFERENCE DOCUMENTS:

Relevant approved IFC Drawings, Basic Drawings and Shop Drawings.


ITP & Checklist
ARAMCO Standards and Project Specifications
Project Quality Plan
Construction Safety Manual
* Any conflicts between the following references contractor shall be brought to the
attention of the company for a final decision.

4. DEFINITIONS / ABBREVIATIONS:

PQP Project Quality Plan


HSE Health, Safety and Environment
PPE Personal Protective Equipment
Company Saudi Aramco
Contractor Kolin Company
ITL Independent Testing Lab

5. RESPONSIBILITIES:

Construction Manager
 Responsible to perform the activity according to the progress targets, project
specifications and typical drawings.
 Ensure that all preparation and works are carried out according to project
specifications, method statement and Aramco Standard.
 Ensure that the progressing of work is carried out according to the planned program
and as per the approved Method Statement.
 Finding solution in order to eliminate bottlenecks during execution of the activity

METHOD STATEMENT FOR SLUICE GATE & BASKET SCREEN INSTALLATION 3


SDHO Increment II, Initial Site Development
Pk1 (6600041347) & Pk2 (6600042398)
METHOD STATEMENT FOR SLUICE & BASKET
SCREEN INSTALLATION

Package 01/02 Doc. No. Rev. No.

 Ensure that all the manpower, equipment and materials required executing the
work are available.
 Ensure that all related quality procedures are practiced and implemented.
 Ensure that all safety matters related to this procedure are being observed.

Surveyor
 Responsible to provide correct line, level and alignment as per IFC, documents
and services before, during and after execution of the activity. The main activities
to be done by surveying engineer are as follows:

 Checking the application done by survey crew according to specifications and


drawings.
 Joining daily meetings with construction crew to share and report situation
regarding to the activity.

Site Engineer
 Responsible to perform the activity according to quality requirements, the
specifications and typical drawings.
 Inspecting site, crew and machinery conditions daily prior to commencement of
work.
 Instructing the crew according to safety rules.
 Assuring the quality during performing the work according to specification and
drawings.

Health and Safety Engineer


 Responsible for monitoring and checking the activities according to safety
requirements. All safety issues will be governed by the Construction Safety Manual
and must be strictly followed.
 Ensure all personal work having appropriate PPE's
 Giving proper training & instructions regarding safety.
 Toolbox meeting shall be conducted before starting the work.
 Inspecting activity daily for possible cave-ins, hazardous atmospheres or other
hazardous conditions. Inspection shall also be done after rains and any other
outside effects. lf there is an unsafe condition, workers shall not be allowed to enter
the work area.
 Ensure all work activities shall be carried out as per HSE plan
 Carryout daily HSE site inspections and take corrective actions.
 Do not allow workers stay under any load and train them to stay clear of the back
of vehicles.

METHOD STATEMENT FOR SLUICE GATE & BASKET SCREEN INSTALLATION 4


SDHO Increment II, Initial Site Development
Pk1 (6600041347) & Pk2 (6600042398)
METHOD STATEMENT FOR SLUICE & BASKET
SCREEN INSTALLATION

Package 01/02 Doc. No. Rev. No.

Civil Foreman
 Responsible for performing the work according to instructions given by responsible
engineer.
 Checking the situation of all personnel, machinery & equipment and material
before, during and after execution of the work.
 Fulfilling the instructions given by responsible site engineer.
 Reporting major problems during execution of the work at once to responsible Site
Engineer.
 Assuring and monitoring safety requirements for crew.
 Following the maintenance issues for machinery and equipment.
 Reporting progress and issues to responsible Site engineer in daily basis.

QC inspector
 Perform surveillance and ensure that work performed meet the project
requirements and method statement.
 Shall be responsible to carry out inspections by signing various inspections and
test plan as proof record of inspection conforming to MOS.

ITL lab technician

 Shall be responsible for inspection and field testing, material sampling and related
laboratory works as required by MOS.

6. RESOURCES:

6.1 EQUIPMENTS:
 Mobile Crane/ lifting equipment
 Hammers
 Web sling
 Drilling machine
 Grouting mixing equipment.

6.2 MANPOWER:
 Construction Manager
 Site Engineer
 Safety Officer
 Dispatcher
 Flagman
 Labors

METHOD STATEMENT FOR SLUICE GATE & BASKET SCREEN INSTALLATION 5


SDHO Increment II, Initial Site Development
Pk1 (6600041347) & Pk2 (6600042398)
METHOD STATEMENT FOR SLUICE & BASKET
SCREEN INSTALLATION

Package 01/02 Doc. No. Rev. No.

6.3 SAFETY EQUIPMENT:


 Personal Protective Equipment (PPE)
 Fire Extinguisher
 First Aid Kit

7. WORK EXECUTION PROCEDURE:

7.1 Sluice Gate Installation Procedure


For installation of sluice gates inside wastewater pump
stations, following steps shall be followed:
Step No. 01- Position the Gate

 Measure inside diameter of pipe or concrete opening


width and height. Record dimension and compare
penstocks opening size. The gate openings should not
be smaller than the mating inside diameter of the pipe or
the concrete opening.
 Carefully lower gate adjacent to the mating surface
using suitable lifting equipment and following all
necessary safety precautions.

Fig. 01: Pre Position the Gates


Step No. 02- Position Anchors

 Align invert of the gate opening with invert of pipe or concrete opening. Place
temporary support blocks under frame to maintain position.
 With a level, ensure that the invert of the gate is level.
 To pre- position, the gate where it will be mounted to
mark holes for anchors. If pre-positioning the gate is not
possible, carefully measure and mark the mounting
surface for holes.

Step No. 03 –Place Anchors

 After Drilling the hole and fixing the anchor bolts with
epoxy chemical, allow 12 hours to set.
 Anchors of any type must be sufficiently long to account
for a grout seal, see #6 below. Fill all mounting holes
with anchors.

Fig. 02: Anchors

METHOD STATEMENT FOR SLUICE GATE & BASKET SCREEN INSTALLATION 6


SDHO Increment II, Initial Site Development
Pk1 (6600041347) & Pk2 (6600042398)
METHOD STATEMENT FOR SLUICE & BASKET
SCREEN INSTALLATION

Package 01/02 Doc. No. Rev. No.

Step No. 04- Jam Nut/ Thrust Nut

 After fixation of anchors with chemical, install thrust


nuts on every anchor. Thrust nuts ate meant to
provide an adjustable surface against which the gate
will rest once it is plumb.
 Adjust the nuts at each corner of the gate so the gate
is plumb leaving a minimum 1 inch (25mm) space for
grout between mounting surface and gate.
 Then bring the remaining nuts up snug to the back of
the gate. Re-check for plumb.
Step No. 05- Secure the Gate.

 Place Jam nuts on each anchor and hand tighten to


secure the gate.
 Re-check plumb then firmly tighten jam nuts to Fig. 03: Nut Fixation
permanently secure the gate.
Step No. 06- Install Grout

 Mix a non- shrinking grout and fill the space


between the mounting surface and back of the gate
and all gate surfaces that make a seal, for example
an upper wiper seal across the top of the opening
as shown in Fig 4. It may be necessary to place a
removable form around the grout locations to hold
the grout in place until dry. Make sure there are no
voids in the grout.

Step No. 06- Install Top cover Plate / Pedestals

 Fix the top plate cover on Top slab for support of Fig. 04: Secure Gate with Grout
pedestal using anchor bolts.
 After fixation of rising stem & pedestals, wall bracket shall be installed to support
the alignment of rising stem pipe.

7.2 Basket Screen Installation Procedure


For installation of Basket screen inside wastewater pump stations, following steps shall
be followed:
Step No. 01- Position the Wall Brakets

 All wall brackets should be install at equal spacing to support the guide rail.

METHOD STATEMENT FOR SLUICE GATE & BASKET SCREEN INSTALLATION 7


SDHO Increment II, Initial Site Development
Pk1 (6600041347) & Pk2 (6600042398)
METHOD STATEMENT FOR SLUICE & BASKET
SCREEN INSTALLATION

Package 01/02 Doc. No. Rev. No.

 Before make the drill for anchor in wall brackets, re-check the
horizontal distance shall be as per requirement of guide rail.
Step No. 02- Position the Guide Rail

 Minimum two guide rails required for each basket screen.


 Before fixation of guide rail, mark all the position of anchor bolts
locations on base and on top slab.
 Re-check the distance between sluice gate & basket screen to
avoid the clash, before fixation of anchors
 Install the chain Sling hanger at top slab
 Fix the chain sling in basket screen to sling hanger.

Fig. 05: Basket screen

8. QUALITY ASSURANCE / QUALITY CONTROL :

 The field inspection notice of excavation/backfill works will be given to SAPMT in


advance.
 Site QA/QC Inspector/Site Engineer will be responsible for completing inspection
Reports for these activities.
 Kolin shall ensure that the area is ready for visual inspection before submitting
WIR’s.
 Kolin shall submit WIR’s for the area ready and at least 24 hours during weekdays
and 48 hours during Fridays and holidays.
 Kolin shall attach photos to each WIR’s.
 All the materials to be used should be approved by the company.

9. HSE REQUIREMENTS

 Protection and safety shall be in accordance with SA Construction Safety manual.


 All works shall comply with the safety procedure or instruction as set out in project
safety plan and municipality rules and regulations.
 All equipment will be visually inspected prior to use.
 Basic Personal Protective Equipment (PPE) shall be worn by all staff or laborers.
 Toolbox talk shall be conducted before the activity.
 Know the safe working load of the hoisting equipment and hardware before use. Never
exceed the Safe Working Load (SWL).
 Know the height and size of the precast element before rigging for lifting

METHOD STATEMENT FOR SLUICE GATE & BASKET SCREEN INSTALLATION 8


SDHO Increment II, Initial Site Development
Pk1 (6600041347) & Pk2 (6600042398)
METHOD STATEMENT FOR SLUICE & BASKET
SCREEN INSTALLATION

Package 01/02 Doc. No. Rev. No.

 Always inspect the rigging element prior to every use.


 Always use taglines with the precast element while lifting to keep the load steady.
 Always check the stability of the load before lifting.
 Check for any over head power lines.
 Never use damaged slings, blocks, hooks for lifting, all damaged lifting gears to be
returned to the store for repair or replacement

10. DRAWINGS - ATTACHMENTS:


1- INSTALLATION MANNUAL FROM VENDOR

2- SHOP DRAWINGS FOR SLUICE GATES & BASKET SCREENS

METHOD STATEMENT FOR SLUICE GATE & BASKET SCREEN INSTALLATION 9

You might also like