Professional Documents
Culture Documents
METHOD STATEMENT Sluice Gates Install
METHOD STATEMENT Sluice Gates Install
METHOD STATEMENT Sluice Gates Install
METHOD STATEMENT
FOR
SLUICE GATE & BASKET SCREEN INSTALLATION
INDEX
1. SCOPE
2. PURPOSE
3. REFERENCES DOCUIMENTS
4. DEFINITIONS / ABBREVIATIONS
5. RESPONSIBILITY
6. RESOURCES
9. HSE REQUIREMENTS
1. SCOPE:
This method statement covers the activities and procedures to be implemented for
installation of sluice gates & basket screens with the Contract Specification and without
any safety violations within our project.
2. PURPOSE:
The purpose of this method statement is to outline the general requirements and
precautionary measures, which should be taken into consideration for installation of
sluice gates & basket screen. Furthermore, to ensure that significant health and safety
risk have been identified and what further control measures must be taken to reduce risk
to an acceptable level.
3. REFERENCE DOCUMENTS:
4. DEFINITIONS / ABBREVIATIONS:
5. RESPONSIBILITIES:
Construction Manager
Responsible to perform the activity according to the progress targets, project
specifications and typical drawings.
Ensure that all preparation and works are carried out according to project
specifications, method statement and Aramco Standard.
Ensure that the progressing of work is carried out according to the planned program
and as per the approved Method Statement.
Finding solution in order to eliminate bottlenecks during execution of the activity
Ensure that all the manpower, equipment and materials required executing the
work are available.
Ensure that all related quality procedures are practiced and implemented.
Ensure that all safety matters related to this procedure are being observed.
Surveyor
Responsible to provide correct line, level and alignment as per IFC, documents
and services before, during and after execution of the activity. The main activities
to be done by surveying engineer are as follows:
Site Engineer
Responsible to perform the activity according to quality requirements, the
specifications and typical drawings.
Inspecting site, crew and machinery conditions daily prior to commencement of
work.
Instructing the crew according to safety rules.
Assuring the quality during performing the work according to specification and
drawings.
Civil Foreman
Responsible for performing the work according to instructions given by responsible
engineer.
Checking the situation of all personnel, machinery & equipment and material
before, during and after execution of the work.
Fulfilling the instructions given by responsible site engineer.
Reporting major problems during execution of the work at once to responsible Site
Engineer.
Assuring and monitoring safety requirements for crew.
Following the maintenance issues for machinery and equipment.
Reporting progress and issues to responsible Site engineer in daily basis.
QC inspector
Perform surveillance and ensure that work performed meet the project
requirements and method statement.
Shall be responsible to carry out inspections by signing various inspections and
test plan as proof record of inspection conforming to MOS.
Shall be responsible for inspection and field testing, material sampling and related
laboratory works as required by MOS.
6. RESOURCES:
6.1 EQUIPMENTS:
Mobile Crane/ lifting equipment
Hammers
Web sling
Drilling machine
Grouting mixing equipment.
6.2 MANPOWER:
Construction Manager
Site Engineer
Safety Officer
Dispatcher
Flagman
Labors
Align invert of the gate opening with invert of pipe or concrete opening. Place
temporary support blocks under frame to maintain position.
With a level, ensure that the invert of the gate is level.
To pre- position, the gate where it will be mounted to
mark holes for anchors. If pre-positioning the gate is not
possible, carefully measure and mark the mounting
surface for holes.
After Drilling the hole and fixing the anchor bolts with
epoxy chemical, allow 12 hours to set.
Anchors of any type must be sufficiently long to account
for a grout seal, see #6 below. Fill all mounting holes
with anchors.
Fix the top plate cover on Top slab for support of Fig. 04: Secure Gate with Grout
pedestal using anchor bolts.
After fixation of rising stem & pedestals, wall bracket shall be installed to support
the alignment of rising stem pipe.
All wall brackets should be install at equal spacing to support the guide rail.
Before make the drill for anchor in wall brackets, re-check the
horizontal distance shall be as per requirement of guide rail.
Step No. 02- Position the Guide Rail
9. HSE REQUIREMENTS