Professional Documents
Culture Documents
CH 10 Long Term Contracts
CH 10 Long Term Contracts
CH 10 Long Term Contracts
II - Performance Obligations
Cabalen Pools, Inc. constructs outdoor swimming pools for wealthy individuals. Recently it obtained
an order to build a three-lane swimming pool of 25 yards in length in the customer’s backyard. Under
the contract, Cabalen is also obligated to install a water heater and a filtration system, which are
necessary to make a swimming pool fully functional. Total price for the construction was P55,000.
Each of these smaller components would typically cost P40,000, P10,000, and P20,000 if installed
separately. Given the information above, how many performance obligations are included in this
contract?
Answers - Problem II
Number of performance obligations in the contract: 1.
Answer - Problem IV
A performance obligation is satisfied over time if at least one of the following three criteria is met:
1. The customer consumes the benefit of the seller’s work as it is performed,
2. The customer controls the asset as it is created, or
3. The seller is creating an asset that has no alternative use to the seller, and the seller can receive
payment for its progress even if the customer cancels the contract.
Required: Compute the amount of gross profit recognized during 20x4 and 20x5.
1. Assume that Beavis uses the overtime (percentage-of-completion) method for revenue
recognition.
Answer - Problem VI
1. Input Measure - Percentage of Completion Method (Cost to Cost Method)
20X4:
Contract price P 1,800,000
Actual costs to date P 450,000
Estimated costs to complete 1,200,000
Total estimated project costs 1,650,000
Estimated total gross profit 150,000
Percentage of completion:
P450,000 / P,1650,000 27.27%
Gross profit recognized P 40,905
20X5: P 1,800,000
Contract price
Costs incurred:
20X4 P 450,00
20X5 1,100,000
Total cost 1,550,000
Total gross profit 250,000
Recognized in 20X4 40,905
Recognized in 20X5 P 209,095
2. Assume that Beavis uses the point-in-time (cost recovery) method for revenue recognition.
Answer - Problem VI
2. Input Measure - Cost Recovery Method
20X4: (all costs not yet recovered) P -0-
20X5:
Contract price 1,800,00
Costs incurred: 20X4 P 450,000
20X5 1,100,000
Total cost 1,550,000
Total gross profit P 250,000
During 20x4 the customer agrees to a variation with increases expected revenue from the contract by
P12,000 and causes additional costs of P7,200. At the end of 20x4 there are materials stored on site for
use during the following period which cost P6,000.
DJD Builders have decided to determine the stage of completion of the contract by calculating the
proportion that contract costs incurred for work to date bear to the latest estimated total contract costs.
The contract costs incurred at the end of each year (costs incurred to date), billings and collections for
each year were as follows:
Year Direct and Allocable Costs to date Billings Collections
20x3 P126,048 P144,000 P120,000
20x4 370,080 (including materials in store) 240,000 228,000
20x5 492,000 156,000 192,000
Required:
1. Prepare the journal entries, under:
The revenue, expenses (costs) and profit will be recognized in profit or loss as follows:
Recognized in Recognized in
20x3 To date prior years current year
Revenue (P528,000 x 26%) P 137,280 - P 137,280
Costs/Expenses (P484,800 x 26%) 126,048 - 126,048
Gross Profit (P43,200 x 26%) P 11,232 - P 11,232
Recognized in Recognized in
20x4 To date prior years current year
Revenue (P540,000 x 74%) P 399,600 P 137,280 P 262,320
Costs/Expenses (P492,000 x 74%) _364,080 _126,048 238,032
Gross Profit (P48,000 x 74%) P 35,520 P 11,232 P 24,288
Recognized in Recognized in
20x5 To date prior years current year
Revenue (P540,000 x 100%) P 540,000 P 399,600 P 140,400
Costs/Expenses (P492,000 x 100%) _492,000 _364,080 _127,920
Gross Profit (P48,000 x 100%) P 48,000 P 35,520 P 12,480
Alternatively, the gross profit recognized each year may also be computed as follows:
20x3 20x4 20x5
Contract price:
Initial amount of contract…………....... P528,000 P528,000 P528,000
Variation…………………………………… _______- __12,000 12,000
Total contract price………………………… P528,000 P540,000 P540,000
Costs incurred each year…………………. P126,048 P240,032 P121,920
Add: Costs incurred in prior years……….. _______- _126,048 _370,080
Actual costs incurred to date (1)…..……. P126,048 P370,080 P492,000
Add: Estimated costs to complete……… _358,752 _121,920 _______-
Total estimated costs (3)……..……………. P484,800 P492,000 P492,000
Estimated gross profit……………………… P 43,200 P 48,000 P 48,000
Percentage of completion (1) / (3)……... ____26% ____74% ___100%
Gross profit to date…………………………. P 11,232 P 35,520 P 48,000
Less: Gross profit in prior years……………. _______- ___11,232 __35,520
Gross profit in current year -% of completion P 11,232 P 24,288 P 12,480
Gross profit in current year –cost recovery method P 0 P 0 P 48,000
3. To record collections:
Cash…………………………………..... 120,000 228,000 192,000
Accounts receivable…………… 120,000 228,000 192,000
The revenue, expenses (costs) and profit will be recognized in profit or loss as follows:
Recognized in Recognized in
20x3 To date prior years current year
Revenue* P 126,048 - P 126,048
Costs/Expenses 126,048 - 126,048
Gross Profit P 0 - P 0
* equivalent to costs incurred
Recognized in Recognized in
20x4 To date prior years current year
Revenue* P 364,080 P 126,048 P 238,032
Costs/Expenses _364,080 126,048 238,032
Gross Profit P 0 P 0 P 0
* equivalent to costs incurred
Recognized in Recognized in
20x5 To date prior years current year
Revenue (P540,000 x 100%) P 540,000 P 364,080 P 175,200
Costs/Expenses (P492,000 x 100%) _492,000 364,080 127,920
Gross Profit (P48,000 x 100%) P 48,000 P 0 P 48,000
Alternatively, the gross profit recognized each year may also be computed as follows:
20x3 20x4 20x5
Contract price:
Initial amount of contract…………....... P528,000 P528,000 P528,000
Variation…………………………………… _______- __12,000 12,000
Total contract price………………………… P528,000 P540,000 P540,000
Costs incurred each year…………………. P 126,048 P244,032 P 121,920
Add: Costs incurred in prior years……….. _______- _126,048 _370,080
Actual costs incurred to date ……...……. P 126,048 P370,080 P492,000
Add: Estimated costs to complete……… ____ _? ____ _? _______-
Total estimated costs …….…..……………. P ? P ? P492,000
Estimated gross profit………………………. P 0 P 0 P 48,000
Percentage of completion……………….. _ -___ _ -___ ___100%
Gross profit to date…………………………. P 0 P 0 P 48,000
Less: Gross profit in prior years……………. _______- _______- __ 0
Gross profit in current year………………... P 0 P 0 P 48,000
3. To record collections:
Cash…………………………………..... 120,000 228,000 192,000
Accounts receivable…………… 120,000 228,000 192,000
Current Liability:
Payables (“Payments on Account”)
Progress billings……………………………… P144,000
Less: Construction In Progress……………. _137,280
Contract Liability P 6,720
Current Liability:
Payables (“Payments on Account”)
Progress billings……………………………… P 137,280 P384,000
Less: Construction In Progress……………. _144,000 _364,080
Contract liability P 6,720 P 19,920
Construction In Progress Progress Billings
ANSWER - a. Input Measure - Percentage of Completion Method (refer to requirement 1 for detailed computation)
ANSWER - b. Input Measure – Cost Recovery Method (refer to requirement 1 for detailed computation)
Multiple Choices:
1. Over Time - A
2. 1–B
3. 1–B
4. (850,000 + 50,000) x 65% + (900,000 – 10,000) x 25% + (890,000 – 10,000) x 5% + (880,000 –
10,000) x 5% = 895,000 – A
5.