Professional Documents
Culture Documents
Poo Scrubber Tank
Poo Scrubber Tank
Poo Scrubber Tank
2ZAPU5
VERSION CREATED ON / VERSION / STATUS
Contents
1. Purpose ....................................................................................................................................... 3
2. Scope ........................................................................................................................................... 3
3. Definitions ................................................................................................................................... 3
4. PST-X Qualification Aims ............................................................................................................. 4
5. PST-X Facility ............................................................................................................................... 5
5.1 PST-X ....................................................................................................................................... 5
5.2 Extract Fan .............................................................................................................................. 6
5.3 Steam Supply System .............................................................................................................. 6
5.4 Hot Air Supply System ............................................................................................................. 7
5.5 Tracer Gas Supply System ....................................................................................................... 7
5.6 Dust Dosing System................................................................................................................. 7
5.7 Deuterium Dosing ................................................................................................................... 8
5.8 Chilled Water System .............................................................................................................. 8
5.9 Gas-Liquid Separators ............................................................................................................. 9
5.10 Pipework ................................................................................................................................. 9
5.11 Valves .................................................................................................................................... 10
5.12 Gas Sampling System ............................................................................................................ 10
5.13 Instrumentation .................................................................................................................... 10
5.14 Workshop .............................................................................................................................. 11
5.15 Utilities .................................................................................................................................. 11
5.16 Labour ................................................................................................................................... 12
5.17 Analysis needs: ...................................................................................................................... 12
6. Commissioning .......................................................................................................................... 13
7. Safety and Environment............................................................................................................ 13
8. Control and Surveillance ........................................................................................................... 13
9. Quality ....................................................................................................................................... 14
10. Contract Management .............................................................................................................. 14
10.1 Project Kick-off Meeting ....................................................................................................... 14
10.2 Monthly Progress Report ...................................................................................................... 14
10.3 Document Review Duration .................................................................................................. 15
10.4 Monitoring ............................................................................................................................ 15
11. Schedule and Deliverables ........................................................................................................ 15
12. References ................................................................................................................................ 16
13. Appendix 1 – PST-X Facility Piping and Instrumentation Diagram ........................................... 17
ITER_D_2ZAPU5 v2.3
1. Purpose
The Pool Scrubber Tank (PST), a key component of the Hydrogen Mitigation System (HMS), a sub-
system of the Vacuum Vessel Pressure Suppression System (VVPSS) provides a number of safety
functions that must be qualified prior to the manufacture and assembly of the VVPSS.
An experimental facility, known as the PST-X Facility, will be established to demonstrate and qualify
the safety-related functions of the PST. This document describes the PST-X Facility and gives the
technical requirements for the components that form the facility.
2. Scope
The Contractor will procure the necessary equipment, assemble, commission and enable the
operation of a PST-X facility that meets the requirements of this specification.
At the core of the facility will be a full-scale prototype PST, known as the PST-X. The PST-X is
currently being manufactured under contract for the ITER Organization (IO). This prototype tank will
be provided by IO to the facility for the duration of the PST-X Facility operation.
The scope of this document is therefore the remainder of the facility; the equipment and the
services required to realize and operate the PST-X. It is possible that this specification could be used
for multiple procurement activities, each providing as little as a single component, or to enable a
single supplier to provide the full scope of supply.
3. Definitions
Term / acronym Definition
AOC Award of Contract
D2O Deuterium Oxide or Heavy Water
FAT Facility Acceptance Test
HMS Hydrogen Mitigation System
IO ITER Organization
LOCA Loss Of Coolant Accident
LOVA Loss Of Vacuum Accident
MIP Manufacturing & Inspection Plan
PIC Protection Important Component (as defined in [6])
PIA Protection Important Activity (as defined in [6])
PST Pool Scrubber Tank
PST-X Experimental Pool Scrubber Tank
QP Quality Plan
SC1 Seismic Class 1
VVPSS Vacuum Vessel Pressure Suppression System
ITER_D_2ZAPU5 v2.3
5. PST-X Facility
This section will describe all equipment required to form the PST-X Facility. A description of the PST-
X is first given for information, as this central component will have interfaces with most of the other
equipment that forms the experimental facility. The Piping and Instrumentation Diagram for the
facility is given in Appendix 1 – PST-X Facility Piping and Instrumentation Diagram.
5.1 PST-X
The Contractor shall prepare a suitable foundation for the PST-X, receive and install the vessel into
the facility.
The PST-X is a vertical cylindrical vessel with elliptical top and bottom heads supported with legs. The
vessel is formed from stainless steel dual grade 304/304L. The vessel has an internal volume of 7000
litres and has a half-pipe cooling coil on the external surface of the shell part of the vessel. The upper
head is flanged to allow for removal. The PST-X is formed of the vessel and a set of internals. The
internals are comprised of a “Riser” tube, three gas distribution ring-spargers and supports. The PST-
X internals are removable from the vessel to allow modification or replacement as required by the
testing programme. A drawing of the PST-X is given in Appendix 2 – PST General Arrangement
Drawing.
The reaction forces at the vessel support locations have been determined [5] by calculation for all
relevant loading conditions. The following figure shows the four support anchor plates, the
coordinate system and indicates the reaction forces and moments.
It is anticipated that M30 anchor bolts with adhesive and an embedded depth of 550mm will be
suitable to secure the PST-X Vessel. The Contractor shall perform the necessary calculation to
demonstrate the suitability of the anchor system and provide the calculations to IO for acceptance.
ITER_D_2ZAPU5 v2.3
Parameter Value
Maximum Air flow rate 350 Nm³/h (0.126 kg/s)
Minimum Air flow rate 70 Nm³/h (0.025 kg/s)
Inlet pressure 0.9 – 2.0 bar(a)
Inlet temperature 15 – 35 °C
Maximum outlet temperature 230 °C
Minimum outlet temperature 100 °C
Heating power required 40 kW
Table 3 below gives the key data for the Powder Metering System. The provisionally selected
powder is magnesium and/or magnesium oxide. This powder choice may change prior to the start of
the experimental campaign. All other data will remain the same.
ITER_D_2ZAPU5 v2.3
Parameter Value
Powder Mg/MgO blend
(provisionally)
Powder particle size 0.1 – 50 micron
Maximum required flow rate 17 g/s
Minimum required flow rate 1 g/s
Hopper capacity 15 kg
Gas pressure in line 0.8 – 1.0 bar(a)
Gas temperature 130 – 230 °C
Parameter Value
Liquid D2O (heavy water), 99.9%
Maximum required flow rate 3 ml/min
Minimum required flow rate 0.25 ml/min
Hopper capacity 1000 ml
Gas pressure in line 0.8 – 1.0 bar(a)
Gas temperature 130 – 230 °C
Parameter Value
Nominal required flow rate 12.8 kg/s
Reduced flow rate 6.4 kg/s
Inlet pressure 7 bar(g)
Pressure drop through PST-X Up to 2 bar
Inlet temperature 6 °C
Maximum outlet temperature 14 °C
Maximum cooling power required 160 kW
PST-X cooling coil nozzle size DN65
ITER_D_2ZAPU5 v2.3
Parameter Value
Liquid phase Water
Gas phase Air
Maximum gas flow rate 700 Nm³/h (0.25 kg/s)
Minimum gas flow rate 400 Nm³/h (0.144 kg/s)
Gas velocity 2.0 - 3.5 m/s
Gas pressure 0.8 bar(a)
Gas temperature 6 – 50 °C
Separator efficiency DS0001 100% removal @ 20µm and above
Separator efficiency DS0002 100% removal @ 5µm and above
Liquid loading Low
5.10 Pipework
The Contractor shall supply and install all necessary interconnecting pipework, fittings, instrument
connections and supports.
The pipework design configuration and associated nominal sizes are shown on Appendix 1 – PST-X
Facility Piping and Instrumentation Diagram.
The piping system contains four main categories of piping: Gas ambient and hot, and liquid ambient
and hot. The following table gives the basic requirements for the different piping categories.
Table 7. Piping Requirements
The Contractor shall produce a pipework layout that is suited to the specific layout of equipment
that is employed in their workshop.
5.11 Valves
The contractor shall supply and install all valves necessary for the operation of the PST-X facility.
Appendix 1 – PST-X Facility Piping and Instrumentation Diagram identifies all valves and valve types
for the PST-X Facility.
Valves are generally manually operated and shall be located such that manual operation is easily
facilitated.
Three actuated control valves (VG-0001, VG-0003 and VG-0004) are also required to control the
three principal gas flows into the system (steam, compressed air and tracer gas). The actuated
control valves will be controlled via a local panel where a flow rate set point can be input and the
valve automatically controls the flow to the set point as measured by the related flow meter. A
manual mode to control the valve position directly will also be available from the panel.
5.12 Gas Sampling System
The contractor shall supply a helium gas sampling system.
Helium gas will be used in the PST-X as a simulant for hydrogen. Helium will be injected into the PST-
X through the tracer gas supply system. A key outcome of the PST-X facility is to determine the gas
mixing effectiveness of the internal arrangement of the PST-X Vessel. An on-line gas sampling system
will be installed in the DN300 outlet of the PST-X vessel. The sampling system will have four
connections to the DN300 outlet, three sampling the gas close to the pipe wall at 120° intervals and
one sampling at the centre of the pipe. The sampling system shall continuously measure the
concentration of helium at the four connections. The following figure shows a cross-section of the
DN300 outlet pipe and the arrangement of the sampling connections.
Figure 3. Cross Section through DN300 PST-X Vessel Outlet showing Sampling Connections
Each of the sampling connections shall be welded to the DN300 outlet line to ensure the absence of
air in-leakage.
The average concentration of helium at the PST-X Outlet will be in the range 0-10% v/v. The
sampling system shall have a minimum measurement range of 0-50% v/v helium.
5.13 Instrumentation
The Contractor shall supply all necessary instrumentation, cabling and associated control equipment
necessary to deliver the functionality of the PST-X Facility.
The Contractor shall supply a data acquisition system that enables all the signals generated by the
facility’s instrumentation to be viewed in real time and recorded for later review.
ITER_D_2ZAPU5 v2.3
Appendix 5 – Instrumentation List identifies all required instrumentation to be supplied and provides
their technical parameters to enable selection.
Appendix 6 – Proposed Cabling Diagram gives a proposed architecture for the electrical and control
equipment.
The Contractor shall provide all necessary power cables, sensitive and signal cables and earthing
cables as required for the specific layout of the PST-X Facility.
Power cable is anticipated to be formed of 5 core, 35 sq. mm and 2 core 4 sq. mm Cu power cables.
Power cable continuity and insulation will be tested after termination to validate the installation.
Sensitive cable is anticipated to be formed of 1.5 SQ mm sensitive cable. Loop checks shall be
performed on all instrument loops installed.
For maintaining quality in measurement & data acquisition, all Instrument hook up & installation
shall be validated by IO and for the earthing and cabling of electric & electronics devices, IEC 61000-
5-2 guidelines shall be followed.
5.14 Workshop
A total workshop area of approximately 100 m² is required to house the PST-X Facility. The workshop
space will be formed of several areas:
PST-X Testing Area – a dedicated indoor space of at least 10m x 5m, with a vertical height of not
less than 8m, equipped with a 10Te overhead crane to facilitate the
installation and movement of equipment and maintained between 15 and
35°C. The largest and heaviest piece of equipment will be the PST-X at 5.2m
tall and having a mass of approximately 8700 kg.
PST-X Control Area – a dedicated indoor space local to the PST-X Testing Area to house the data
acquisition system, control system terminals and document storage. The
facility operators would operate and monitor the plant from this area. An area
of around 20m² is envisioned to be necessary.
Utility Supply Area – an indoor or outdoor space to house a steam supply unit, chiller unit, chilled-
water pump and air-heater. This space could be contiguous to the PST-X
Testing Area or remote with piping to supply the utilities.
Workshop Area – an indoor workshop fitted with necessary tools and equipment to undertake
fabrication and modification of stainless and carbon steel piping and supports.
Welding, cutting, machining, forming and testing activities are envisioned.
5.15 Utilities
The PST-X facility will require utility services as defined in Table 1 below. The provision of these
utility services may be provided from existing in-house systems where available or could be provided
by temporary equipment, such as a package steam boiler.
Table 8. PST-X Facility Utility Requirements
5.16 Labour
The Contractor shall provide all necessary labour to construct, commission, operate, deactivate and
disassemble the PST-X Facility.
The PST-X Facility will require a team of mechanical and electrical technicians to assemble the
facility.
The commissioning phase will require the equivalent to one full-time mechanical and electrical
technician to implement repairs, changes and to test equipment. The Contractor shall enable
flexibility in the availability of the labour force, as during commissioning phase there will be peaks
and troughs of demand for the labour force.
Two full-time workshop operators – a mechanical and an instrumentation technician will be required
during the testing phase. One of the technicians shall be capable of operating the overhead crane.
An hourly rate for the provision of Labour above that provided for in the Contract will be agreed
between IO and the Contractor.
5.17 Analysis needs:
A gas analysis capability will be required.
The Contractor shall identify a method of analysing gas samples taken from the PST-X facility to
determine composition (including helium and other tracer gases). This may be provided by an
external service in an off-site location.
The Contractor shall identify a method of providing analysis of liquid samples for D 2O concentration.
This may be provided by an external service in an off-site location.
ITER_D_2ZAPU5 v2.3
6. Commissioning
The Contractor shall commission the PST-X facility and demonstrate that all equipment and
instrumentation is functional, safe and operates within the range of operational parameters
described in this document.
At the completion of the commissioning phase, the Contractor will undertake a Facility Acceptance
Test (FAT) to demonstrate the functionality of all equipment and instrumentation.
The flows of all feeds to the facility will be verified as being available and within the required
operating ranges.
The accuracy of instrumentation will be verified and the ability to read and record the data from
instrumentation demonstrated.
At the successful completion of the FAT and the acceptance by IO that the facility meets all
necessary requirements the facility will be handed over to IO for the initiation of testing activity.
For the purposes of performing surveillance, the Contractor shall grant representatives of the IO and
the French Nuclear Regulator (ASN) access to its facilities, relevant records and to those of its
subcontractors at all stages of the contract. The surveillance shall include follow-up and verification
of any corrective actions that are to be implemented.
Test protocols will be established by IO and agreed by the Contractor prior to initiation of the tests.
No changes shall be made to the PST-X facility without the approval of the IO Technical Responsible
Officer.
Access to the PST-X Facility shall be controlled. Only IO staff members and those of the Contractor’s
workforce with specific involvement in PST-X activities shall be permitted to access the facility.
9. Quality
The Contractor shall have either an ISO 9001 accredited quality system or an ITER approved Quality
Assurance Program.
Prior to commencement of work under this Contract, a Quality Plan shall be produced by the
Contractor and submitted to the IO for approval. This Quality Plan shall be produced in line with [2].
The overseeing of the quality control operation by the IO shall not release the Contractor from his
responsibility in meeting any aspect of this Technical Specification.
Documentation developed as the result of this Contract shall be retained by the Contractor for a
minimum of 5 years and then may be discarded at the direction of the IO.
Non-conforming conditions shall be promptly reported to IO as per the requirements of [4], upon
identification of the Non-conforming condition. No further work shall be performed until IO provides
approval of the proposed disposition of the non-conforming condition.
12. References
[1] WXGALP - Hydrogen Mitigation System Qualification and Verification Plan
[2] 22MFMW - Requirements for Producing a Quality Plan
[3] SBSTBM - Provisions for Implementation of the Generic Safety Requirements by the External
Actors/Interveners
[4] 22F53X - Procedure for management of Nonconformities
[5] 32DMXM - Structural Analysis for PST-X Tank
[6] 7M2YKF - Order dated 7 February 2012 relating to the general technical regulations applicable
to INB - EN
ITER_D_2ZAPU5 v2.3
OPERATING CONDITION
AMB. ACCURACY
NOR. MAX. NOR. INST. PROCESS WETTED
Proposed Process NOR. MAX. MAX. CONDITIONS MEASURING OUTPUT (% of PROCESS INSTRUMENT
Inst. Tag Parameters SERVICE QTY OPER. OPER. OPER. CONNECTION PART ACCESSORIES REMARKS
sensors fluid OPER. OPER. OPER. (PRESS. (Bara), RANGE SIGNAL Measurement PIPE SIZE MOUNTING
TEMP. TEMP. VELOCI SIZE MOC
PRESS. PRESS. VELOCITY TEMP(Deg. C) & or Better)
(ºC) (ºC) TY
HUM )
Chilled
water outlet CHILLED 6.4
PT-0021 1 5 Bar g 14 12.8 Kg/sec 1 35 , 50% 0-8 Bar g 4-20mA 0.25% DN80 1/2"NPT(M) SS316 2" PIPE MOUNT
from PST WATER Kg/sec
pressure
DIFFERENTIAL DP across 75 Kpa
DPT- Bellows/ DIRECT With
PRESSURE filter FE- 1 GAS+DUST Abs (HP 50 800 Nm3/hr 1 35 , 50% 0-1500 Pa 4-20mA 0.25% DN150 1/2"NPT(M) SS316
0029 Capsule MOUNTING Diaphragm seal
TRANSMITTER 0002 side)
Dilution air
DIRECT
TT-0012 temp. to 1 AIR 1 Bar a 15 35 1 35 , 50% 0-50 Deg C 4-20mA Class-A RTD DN100 1/2"NPT(M) THERMOWELL
MOUNTED
PST
SUPERHEA
Temperatur
TED DIRECT THERMOWELL ON
TT-0037 e Buffer 1 1 Bar a 127 230 1 35 , 50% 0-300 Deg C 4-20mA Class-A RTD NOZZLE N5 1/2"NPT(M)
STEAM+AI MOUNTED BUFFER VESSEL
vessel
R
Hot air
temp to 90 DIRECT
TT-0007 1 AIR 1 Bar a 1.3 Bar a 100 230 454 kg/hr 1 35 , 50% 0-300 Deg C 4-20mA Class-A RTD DN80 1/2"NPT(M) THERMOWELL
buffer kg/hr MOUNTED
vessel
AIR/GAS
DIRECT
TT-0018 inlet temp 1 AIR/GAS 1 Bar a 1.3 Bar a 15 35 1 35 , 50% 0-50 Deg C 4-20mA Class-A RTD DN80 1/2"NPT(M) THERMOWELL
MOUNTING
to PST
PST
75 Kpa DIRECT
TT-0030 discharge 1 GAS+DUST 50 800 Nm3/hr 1 35 , 50% 0-80 Deg C 4-20mA Class-A RTD DN150 1/2"NPT(M) THERMOWELL
Abs MOUNTED
GAS Temp
TW WILL BE
PST empty 80 Kpa TW T05 , SUPLLIED ALONG
TT-0024 1 GAS+DUST 6 80 1 35 , 50% 0-120 Deg C 4-20mA Class-A RTD 1/2"NPT(M) DIRECT MOUNT
space temp Abs DN25 WITH THE PST
TEMPERATURE TANK
RTD
TRANSMITTER TW WILL BE
PST water DM 100 Kpa TW T01 , SUPLLIED ALONG
TT-0027 1 100 1 35 , 50% 0-120 Deg C 4-20mA Class-A RTD 1/2"NPT(M) DIRECT MOUNT
temp WATER Abs DN25 WITH THE PST
TANK
TW WILL BE
PST water DM 100 Kpa TW T013 , SUPLLIED ALONG
TT-0028 1 100 1 35 , 50% 0-120 Deg C 4-20mA Class-A RTD 1/2"NPT(M) DIRECT MOUNT
temp WATER Abs DN25 WITH THE PST
TANK
Chilled
CHILLED 6.4
TT-0022 water inlet 1 7 Bar g 6 12.8 Kg/sec 1 35 , 50% 0-8 Deg C 4-20mA Class-A RTD DN80 1/2"NPT(M) DIRECT MOUNT THERMOWELL
WATER Kg/sec
temp
Chilled
CHILLED 6.4
TT-0023 water outlet 1 5 Bar g 14 12.8 Kg/sec 1 35 , 50% 0-16 Deg C 4-20mA Class-A RTD DN80 1/2"NPT(M) DIRECT MOUNT THERMOWELL
WATER Kg/sec
temp
Steam inlet SUPERHEA
10
TT-0003 to buffer 1 TED 1 Bar a 1.3 Bar a 127 100 g/sec 1 35 , 50% 0-180 Deg C 4-20mA Class-A RTD DN100 1/2"NPT(M) DIRECT MOUNT THERMOWELL
g/sec
vessel temp STEAM
TW WILL BE
PST water DM 100 Kpa TW T01 , SUPLLIED ALONG
TT-0040 100 1 35 , 50% 0-120 Deg C 4-20mA Class-A RTD 1/2"NPT(M) DIRECT MOUNT
temp WATER Abs DN25 WITH THE PST
TANK
Steam inlet Vortex
SUPERHEA
Flow to 10 STANCHION flowmeter with
FT-001 1 Vortex TED 1 Bar a 1.3 Bar a 127 100 g/sec 1 35 , 50% 5-120 g/sec 4-20mA <3% DN100 1/2"NPT(M) SS316
buffer g/sec MOUNTED integral
flowmeter/ STEAM
vessel pressure &
Differential
SUPERHEA temp.
Steam and Pressure
FLOW TED 200Nm 0-1000 STANCHION compensation.
FT-0004 Hot air flow 1 Flowmeter 1 Bar a 1.3 Bar a 127 230 800 Nm3/hr 1 35 , 50% 4-20mA <3% DN100 1/2"NPT(M) SS316
TRANSMITTER STEAM+AI 3/h Nm3/hr MOUNTED For DP flow
to PST
R meter,
Dilution air Thermal 200Nm 0-1000 DIRECT VENTURI with
FT-0011 1 AIR 1 Bar a 15 35 800 Nm3/hr 1 35 , 50% 4-20mA <3% DN 100
flow to PST Dispersion 3/h Nm3/hr MOUNTED condensate pot
CA supply (Mass flow)/ DIRECT for DPT
FT-0005 1 AIR 1 Bar a 15 35 90 kg/h 454 kg/hr 1 35 , 50% 0-600 kg/hr 4-20mA <3% DN 80
flow Vortex MOUNTED connection.
ITER_D_2ZAPU5 v2.3
OPERATING CONDITION
AMB. ACCURACY
NOR. MAX. NOR. INST. PROCESS WETTED
Proposed Process NOR. MAX. MAX. CONDITIONS MEASURING OUTPUT (% of PROCESS INSTRUMENT
Inst. Tag Parameters SERVICE QTY OPER. OPER. OPER. CONNECTION PART ACCESSORIES REMARKS
sensors fluid OPER. OPER. OPER. (PRESS. (Bara), RANGE SIGNAL Measurement PIPE SIZE MOUNTING
TEMP. TEMP. VELOCI SIZE MOC
PRESS. PRESS. VELOCITY TEMP(Deg. C) & or Better)
(ºC) (ºC) TY
HUM )
INLINE
Tracer gas
FT-0008 1 GAS 1 Bar a 35 90 kg/h 454 kg/hr 1 35 , 50% 0-600 kg/hr 4-20mA <3% DN25 FLANGE SS316 INSTRUMENT,
flow
DIRECT MOUNT
AIR/GAS
DIRECT
FT-0017 inlet flow to 1 AIR/GAS 1 Bar g 35 90 kg/h 454 kg/hr 1 35 , 50% 0-600 kg/hr 4-20mA <3% DN80 SS316
MOUNTING
PST
PST
75 Kpa 400 0-1000 DIRECT
FT-0031 discharge 1 GAS+DUST 6 50 800 Nm3/hr 1 35 , 50% 4-20mA <3% DN150 SS316
Abs Nm3/h Nm3/hr MOUNTED
GAS FLOW
Chilled INLINE
CHILLED 6.4 FLANGE
FT-0019 water inlet 1 7 Bar g 6 12.8 Kg/sec 1 35 , 50% 0-60 m3/hr 4-20mA <2% DN80 SS316 INSTRUMENT,
WATER Kg/sec CONNECTION
flow Magnetic flow DIRECT MOUNT
DM water meter INLINE
DM
FT-0014 inlet flow 1 2 Bar g 35 15 m3/hr 1 35 , 50% 0-20 m3/hr 4-20mA <2% DN40 INSTRUMENT,
WATER
to PST DIRECT MOUNT
PST inside inside PST
DM 100 Kpa NOZZLE FLANGE
FT-0041 water 1 100 1 35 , 50% 0-1 m/sec 4-20mA <3% through nozzle
WATER Abs N24 CONNECTION
circulation Electromagnetic on tank
PST inside flow meter inside PST
DM 100 Kpa NOZZLE FLANGE
FT-0042 water 1 100 1 35 , 50% 0-1 m/sec 4-20mA <3% through nozzle
WATER Abs N24 CONNECTION
circulation on tank
For
monitoring,
control &
data
acquisition
of PST-X
with a
CONTROL Approximately Contractor to
24"screen
CUBICLE WITH 48 AI , 8 DI & 8 supply fully
CU-0001 PC based 1 1 35 , 50%
PLC AO channels programmed PLC
HMI station.
CONTROLLER required . controller & HMI.
4 nos
Cameras
will also be
monitored
from the
same PC
station.
Fixed camera WATER+
CAMERA PST inside NOZZLE To fit inside
CAMERA 1 inside PST GAS+ 1 Bar a 60 1 35 , 50%
-0035 monitoring N19 DN50 nozzle
under water DUST
Water proof
Fixed camera WATER+
CAMERA PST inside NOZZLE To fit inside camera with
CAMERA 1 inside PST GAS+ 1 Bar a 60 1 35 , 50%
-0036 monitoring N18 DN50 nozzle flange
under water DUST
connection,
Fixed camera WATER+
CAMERA PST inside NOZZLE To fit inside 4-channel DVR
CAMERA 1 inside PST GAS+ 1 Bar a 60 1 35 , 50%
-0038 monitoring N20 DN50 nozzle for video
under water DUST
recording
Fixed camera WATER+
CAMERA PST inside NOZZLE To fit inside
CAMERA 1 inside PST GAS+ 1 Bar a 60 1 35 , 50%
-0039 monitoring N21 DN50 nozzle
under water DUST
ITER_D_2ZAPU5 v2.3