LIFTING/RIGGING PLAN
DG ORE SCREEN BUILDING MODIFICATION
CHECK OK
D. Summary
Max SWL of Lifting Equipment (SWL < 1) 0.47 Safety Factor (SF > 1) 2.00
Conclusion :
Conclusion from the calculation is Safe for Lifted The Material
30 m
18 m
52°
18 m
DOS 1
R 18 M
DOS #1
25 M
DG ORE
SCREEN DRYER