DEPARTEMEN POM & PROJECT

BILL OF QUANTITY
OWNER : PT. ENERGI UNGGUL PERSADA
PEKERJAAN : PEMBUATAN TANKI AIR CAP. 5 TON DAN ACCESSORIES
LOKASI : SEGENDIS - BONTANG
TAHUN : 2021

UNIT PRICE (Rp) TOTAL PRICE


No DETAIL PEKERJAAN QTY UNIT
MATERIAL UPAH (Rp)
A FOUNDATION & GROUND BEAM
Foundation
1 Excavation 4.80 m3 -
2 Refill with Soil 3.57 m3 -
3 Disposal Soil 1.23 m3 -
4 Sandfill thk : 100 mm (Under Foundation) 0.40 m3 -
5 Lean Concrete 1 : 3 : 5 MC (50 mm thk) 0.20 m3 -
6 Formwork Plywood 10.48 m2 -
7 Concrete K250 Grade 1.40 m3 -
8 Reinforced bar dia. 12 135.74 kg -
9 Reinforced bar dia. 6 13.41 kg -
Ground Beam 250 x 250 mm
1 Soil Excavating 0.63 m3 -
2 Disposal Soil 0.63 m3 -
3 Formwork 5.00 m2 -
4 Reinforcing bar dia. 12 36.25 kg -
5 Reinforcing bar dia. 10 43.16 kg -
6 Concreting K250 Grade 0.63 m3 -
B STRUCTURE
Coulum
1 Anchor Bolt 1" - 350 16.00 pcs -
2 Plat 16 mm 300 x 300 46.08 kg -
3 L.60 x 60 x 6 - @5.42kg/m 130.08 kg
Breacing
1 L. 50 x 50 x 5 - @3.78kg/m 238.90 kg -
2 Plat 9 mm 108.00 kg -
3 Bolt & Nut 15 - 1.5" 100.00 pcs -
Platform -
1 L.60 x 60 x 6 - @5.42kg/m 257.99 kg -
2 Plat Bodres 4.5 mm 225.00 kg -
3 Stair case & Handdrill 1.00 Lot -
4 Pengecetan Meni, Second & Finish 75µ, 75µ dan 100µ 201.21 m2 -

C Pekerjaan Lain-Lain
1 Pengadaan Tandon 5 Ton 1.00 Unit -
2 Pipa PVC 2" Main Line 128.00 m' -
3 Tee Reducer HDPE 10" x 2" 1.00 Pcs -
4 Tee PVC 2" 4.00 Pcs -
5 Reducer 2" x 1/2" 3.00 Pcs -
6 Elbow PVC 2" 8.00 Pcs -
7 Ball Valve PVC 2" 3.00 Pcs -
8 Accessoris Tandon 1.00 Ls -
9 Galian dan penanaman Pipa 2" 9.40 m3 -

TOTAL -
ROUND -

Bontang, 23 Februari 2021


Dibuat Oleh;

Azis Fahri Hasibuan