M/S LLOYD INSULATIONS (I) LTD Date-08-02-2020

DAILY PROGRESS REPORT


Client- M/S TECHNIP FMC BS-VI Project Panipat Refinery Panipat
COMPLETED AREA TODAY PROGRESS BALANCE AREA
RELEASE FOR
INSULATION NEXT DAY PLAN
S.N. Description TOTAL SCOPE UOM
LAGGING CLADDING LAGGING CLADDING LAGGING CLADDING

LAGGING CLADDING Remarks


1 EQUIPMENTS 2530 RMT 2530 2530 2530 0 0 0 0 0 0

2 REFORMER PACKAGE 2000 RMT 2000 1780 1710 220 290 50 40

3 PIPLINE-IH 10000 RMT 10000 9520 7400 35 80 480 2600 80 100 1500 was realsed on 08-01-2020

4 PIPLINE(VALVE & F) 1300 M2 Not released 0 0 0 0 0 0 Item are not available in work order

5 PIPLINE-IT 1000 RMT 1000 300 300 20 0 700 700 50 50 Released on 30-12-2019

6 PIPLINE-IS 1053 RMT 1053 230 140 20 40 823 913 0 0

FIREPROOFING SYSTEM
7 ON CABLE DUCTS/TRAYS 1038 RMT Not released 0 0 0 0 0 0 0 0
AND FITTING