BS-VI Projects For Panipat Refinery - Hydrogen Generation Unit (HGU) Daily Progress Report

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 1

BS-VI Projects for Panipat Refinery – Hydrogen Generation Unit (HGU)

Daily Progress Report

Owner IOCL, Panipat


PMC Engineers India Limited Progress Date 7/4/2019
Contractor Technip India Limited Reporting Date 7/5/2019
Sub Contractor Lloyd Insulation India Ltd Weather Rainey
Dailey Progress Report

FRONT Release of
SL.NO. Description UOM Actual Quantity Completion of
RELEASE Percentage (%) WORK Front Till Previous
work Percentage Today Cumm Balance Next Day PLAN REMARKS
COMPLETED Available Day
(%)

1 EQUIPMENT (LAGGING) M2 2,183.12 1,328.40 60.85 % 1,319.00 60.42 % 9.40 1,319.00 - 1,319.00 864.12### 2.90

WORK IS EFFECTED
2 EQUIPMENT (CLADDING) M2 2,183.12 1319.00 60.42 % 1,255.00 57.49 % 64.00 1,245.00 10.00 1,255.00 928.12
### 50.00 DUE TO HEAVY RAIN

3 PIPING (LAGGING) M2 15,840.00 275.00 1.74 % 275.00 1.74 % - 275.00 - 275.00 15,565.00

4 PIPING (CLADDING) M2 15,840.00 275.00 1.74 % 275.00 1.74 % - 275.00 - 275.00 15,565.00 0.00

5 REFORMER PACKAGE (LAGGING) M2 2,856.00 250.00 8.75 % 450.00 90.00 10.00 100.00 2,756.00 40.00 scaffolding is progress

6 REFORMER PACKAGE (CLADDING) M2 2,856.00 250.00 8.75 % 450.00 scaffolding is progress

Manpower and Machinery Status

Indirect Manpower Direct Manpower Equipment & Machinery

Sl No Description Available Sl No Description Available Description Available

1 Project Incharge 1 1 Foreman 3 ROLLING MACHINE 1

2 Planning Engineer 1 2 Fabricator 1 GROOVING MACHINE 2

3 QA/QC 1 3 Fitter 4 MACHINE BENCH VICE 1

4 Safety officer 1 4 Insulator 10 MACHINE SHEARING 1

5 Store keeper/ Accountant 1 5 Helper 7 ELECTRIC DRILL MACHINE 8

6 Scaffolder supervisor 1 6 scaffolder 6 BAND TIGHTENING MACHINE 1

7 supervisor 1 MACHINE SEALER FOR STRIP TIGHT 1

CHOPSAW MACHINE 1

TOTAL 7 TOTAL 31 TOTAL 16

Page 1 of 1

You might also like