Professional Documents
Culture Documents
A1D8E4 - Condition 7 - Line 2 - Joining Program Appendix 1 Specification For Facility Construction Section 12
A1D8E4 - Condition 7 - Line 2 - Joining Program Appendix 1 Specification For Facility Construction Section 12
A1D8E4 - Condition 7 - Line 2 - Joining Program Appendix 1 Specification For Facility Construction Section 12
FACILITY CONSTRUCTION
SECTION 12
August 1, 2007
SECTION 12
Facility Piping Construction Specification for Facility Construction
TABLE OF CONTENTS
1. GENERAL........................................................................................................................................................ 3
3. MATERIALS ................................................................................................................................................... 3
5. WELDING........................................................................................................................................................ 4
6. CONSTRUCTION PRACTICES................................................................................................................... 6
9. UNDERGROUND PIPING............................................................................................................................. 9
August 1, 2007 12 - 2
SECTION 12
Facility Piping Construction Specification for Facility Construction
1. GENERAL
Piping materials, fabrication, installation, inspection and testing shall conform to the latest edition of CSA Standard
Z662, Oil and Gas Pipeline Systems and shall also comply with the applicable standards referenced in CSA Z662
and with National Energy Board Onshore Pipeline Regulations.
Where an item or activity is not covered by CSA Z662, it shall be completed in accordance with the latest edition of
ANSI B31.3 - Chemical Plant and Petroleum Refinery Piping.
The term ‘piping’ as used herein includes the pipe itself, valves, fittings, flanges, gaskets, bolting, piping
components, gauge and other instrument connections, vents, drains and the pipe support system. For instrument
connections, piping includes the branch up to and including the first block valve.
Shop fabrication scope of work shall be approved by the Company.
3. MATERIALS
In general, the Company will supply all piping materials larger than NPS6 and the Contractor shall supply all piping
materials NPS6 and smaller. Exceptions to this general rule will be identified in the Drawings.
Materials supplied by the Company will be specified on the Drawings or in the Contract. The Contractor shall
supply all remaining material required to complete the Work. All Contractor supplied piping materials shall be new,
unused and undamaged and shall conform to requirements of the Drawings and the Specifications. The Contractor
may propose alternative materials to the Company.
The Contractor shall notify the Company, within 48 hours of receipt of materials, if the materials have not been
supplied in accordance with the requirements of the Drawings or the Specifications. Permitted misalignment
(diameter, wall thickness, out-of-roundness) of piping shall not exceed that allowed by CSA Z662. The Company
must be notified within 48 hours of receipt of materials if materials dimensional tolerances exceed CSA Z662.
4. QUALITY ASSURANCE
The Company may identify additional quality assurance requirements during the bidding period.
• NDE Records
The Company reserves the right to inspect radiographic film and ultrasonic (UT) reports/readings for auditing
purposes. Film and reports/readings shall be catalogued according to the isometric weld map drawings. All
film and reports/readings must be forwarded to the Company for record retention prior to final payment for
Work.
August 1, 2007 12 - 3
SECTION 12
Facility Piping Construction Specification for Facility Construction
• Documentation
Prior to the shipment of fabricated piping, the Contractor shall supply one copy of the following documentation
for the Company's review and approval:
- Weld Procedures;
- Weld Maps (a weld map shall accompany each package of x-rays);
- NDE reports (radiography, UT, MPI, DP);
- Material traceability maps;
- Material test reports and mill certificates;
- Weld Inspection and Repair Records;
- Welder qualifications and tickets; and
- Pressure testing records (see Section 14 – Pressure Testing-Facility Piping).
The Contractor and the Inspector shall ensure all welds are identified as per the isometric weld map drawings,
on x-ray films and/or UT report, final weld map, as-built and NDT report.
After approval of the above documentation, the Company will allow the Contractor to ship the material to site.
The Contractor shall supply the Company, within one week of shipping, one additional copy of the full
documentation outlined above.
• Identification of Welds
The work of each welder shall be identified according to a number assigned by the Contractor. Identification of
welding shall be by a non-erasable crayon or paint-type pencil approved by the Company. Should any welder
leave the job, the number shall not be duplicated on the job. Steel dies shall not be used for identification
purposes.
5. WELDING
5.1.2 DEFINITIONS
Welding terms and definitions will be as per the latest editions of CSA Z662 and AWS Standard A3.0.
August 1, 2007 12 - 4
SECTION 12
Facility Piping Construction Specification for Facility Construction
Electrode holders and electrodes shall not be placed in water for cooling purposes. Ground attachment devices shall
be of such design as to firmly grip the pipe and not arc, having as large a contact area as practical. Arc strikes on
pipe as a result of poor grounding shall be considered equal in severity to welding rod arc strikes.
August 1, 2007 12 - 5
SECTION 12
Facility Piping Construction Specification for Facility Construction
The Company may choose to ask for a demonstration that the non-destructive method can accurately detect weld
imperfections. Once satisfied, the Company shall approve the use of alternate examination techniques for the Work
being considered.
The Contractor shall co-operate with the radiographic inspectors in regard to informing and educating the welders in
their Work.
6. CONSTRUCTION PRACTICES
6.1 General
Tack welds are not permitted when using external line-up clamps unless preheating requirements are met.
The start of all weld passes shall overlap and no pass shall start closer than 50mm from the start of the preceding
pass.
Pipe shall be cut squarely followed by reaming, burring and cleaning before installation. Pipe runs shall be straight
and true.
Bolt holes of all flanges shall straddle the N-S or vertical centre lines unless otherwise noted on the drawings.
Electric welded pipe shall be aligned so that the longitudinal seam will be located on the upper surface of the line
within 300mm of the vertical (preferably at the 2 o’clock and 10 o’clock positions). Successive joints of pipe shall
be rotated to left or right by not less than 200mm to prevent the aligning of weld seams in adjacent pipe sections.
Longitudinal seams on pipe bends shall be located on the neutral axis of the bend.
The inside diameters of piping components shall be aligned accurately within existing tolerances on diameters, wall
thickness and out-of-roundness.
Dimensions of flanged branch connections from centre line of pipe to face of flange shall be equal to the dimensions
of a standard welding tee plus the length of a weld neck flange unless otherwise noted on the drawings.
For stub-ins, the hole cut for the branch shall have the bore the full size of the branch inner diameter.
Nipples for connections on insulated piping shall have enough length so as to extend beyond insulation by a
minimum of 38mm.
August 1, 2007 12 - 6
SECTION 12
Facility Piping Construction Specification for Facility Construction
7.1 General
At the discretion of the Company, piping assemblies may be fabricated at the Contractor’s shop or other fabrication
facility. The requirements for shop fabricated piping shall be the same as for site fabricated piping except for the
following:
When the Contractor fabricates piping, they shall determine the location of site welds. It is the Contractor's
responsibility to check existing facilities and its own work to verify location, elevations, etc. in order to ensure that
adequate field fit allowances are provided. For all piping, it is the Contractor's responsibility to field check and
verify all elevations and dimensions to ensure correct fit-up of the piping.
August 1, 2007 12 - 7
SECTION 12
Facility Piping Construction Specification for Facility Construction
7.4 Subcontracting
Should the Contractor subcontract any portion of the Work, the Subcontractor shall be subject to inspection and
testing by the Inspector as would be the case if the Contractor were to perform the fabrication in his own shop.
August 1, 2007 12 - 8
SECTION 12
Facility Piping Construction Specification for Facility Construction
9. UNDERGROUND PIPING
The Contractor shall install all piping to the grades, lines and elevations shown on the Drawings. Tolerances shall
be as follows:
• Underground piping shall be within 75mm of specified line and within 50mm of specified grade, with no sags
or low spots.
• Stub up risers shall be within 25mm in any direction of the location shown on the Drawings.
Buried flanges shall not be used for joining pipe sections unless specifically indicated in the Drawings.
When stringing alongside a pipe trench, pipe shall be securely supported on timber or sand-filled sacks supported by
skids in such a way as to prevent damage to the exterior surface and/or painting/coating of the piping.
Piping for underground service shall be checked before being lowered into the trench to ensure that no foreign
material, manufacturer's defects or cracks exist that might prevent the proper jointing of the pipe or its operation.
Piping shall be carefully lowered into the trench by means of derricks, ropes or other approved tools or equipment in
a manner that will prevent damage to the piping.
A 600mm x 300mm diameter protective cap, painted safety orange, shall be installed over all buried fittings
including all nipples and weldolets used for venting and draining.
Precaution shall be taken to ensure that displacement of underground pipe does not occur through soil displacement
or flotation due to the presence of trench water. Pipe that has been displaced shall be removed from the trench and
re-laid after the trench is dewatered and reshaped as necessary.
All underground piping shall be inspected and approved by the Inspector prior to backfilling.
August 1, 2007 12 - 9
SECTION 12
Facility Piping Construction Specification for Facility Construction
Piping shall not be run near the floor, across walkways or working spaces where it will create a hazard. Areas for
access shall be free of piping interference.
Under no circumstances shall buried threaded connections be used.
When piping of 48.3mm or smaller in diameter is routed from above to below grade, a union shall be provided 0.3
metres above grade.
The piping shall be installed with flanges or unions so that the removal of equipment can take place without the
cutting of any piping.
Lube oil, gland seal and cooling piping at equipment such as pumps, shall be supported independent of the
equipment and arranged to permit easy dismantling of the equipment without removal of block valves.
August 1, 2007 12 - 10
SECTION 12
Facility Piping Construction Specification for Facility Construction
13. INSULATION
Piping shall be insulated where indicated on the Drawings. The Contractor shall provide a complete and finished
insulation system.
Insulation shall not be installed until all radiographic inspection and testing is complete and all hydrostatic testing
and tracing installation is complete. Temporary support and handling of insulated pipe shall comply with the
insulation manufacturer's recommendations.
Insulated pipe shall only be primed as per Section 17 - Coatings.
When a line is to be insulated, the insulation shall extend to point of connection to an un-insulated line or to
equipment.
August 1, 2007 12 - 11
SECTION 12
Facility Piping Construction Specification for Facility Construction
• Jacketing shall be secured using 0.5 inch wide by 0.020 inch thick type 304 stainless steel bands on 12 inch
centres, using stainless steel wing seals.
• Joint sealant shall be Childers CP-70 or equal.
• Jacket joints shall be lapped a minimum of 2 inches. On horizontal piping, jacket seams shall be placed at the
side of the piping below the centreline, with a lap downwards to shed water.
• On piping entering the ground the last 300mm above ground shall be insulated with Foamglass and wrapped
with Pittwrap.
• The aluminum jacketing from the fibreglass section immediately above shall be extended to overlap the
Pittwrap by 100mm.
• All jacket joints and seams shall be sealed with caulking. All protrusions through the jacketing shall be flashed
and sealed as required to be watertight.
14. REVISIONS
August 1, 2007 12 - 12
SECTION 12
Facility Piping Construction Specification for Facility Construction
August 1, 2007 12 - 13
SECTION 12
Facility Piping Construction Specification for Facility Construction
Enbridge Pipelines Inc.
Lakehead Pipe Line
WELDING PROCEDURE SPECIFICATION
Enbridge Pipelines (NW) Inc. WPS No. UB-36, Rev.3, 06/96
PROJECT: Maintenance/Repair Welding CONTRACTOR: PLM
APPLICATION: Welding pipe and fittings with and without APPROVED BY: Enbridge Technical
notch toughness requirements Services
CODES: CSA Z662, ASME Section IX, API 1104 DATE: June 14, 1996
MATERIAL: P No. 1, Group 1/2 to P No. 1, Group 1/2, API SUPPORTING PQR NO(S): UB-36-SP4-1
5L Gr. X60 max.; CSA Z245 Gr. 414 max
CARBON EQUIVALENT (PER CSA): 0.45 max. #7-R87
DIAMETER: All
WALL THICKNESS: 4.7 to 22.3 mm (3/16 to 7/8 in.)
FILLER METAL: F3, A1; F4, A2
PROCESS: SMAW, Manual
POLARITY: DC Reverse (electrode +ve)
POSITION: All
August 1, 2007 12 - 14
SECTION 12
Facility Piping Construction Specification for Facility Construction
August 1, 2007 12 - 15
SECTION 12
Facility Piping Construction Specification for Facility Construction
August 1, 2007 12 - 16
SECTION 12
Facility Piping Construction Specification for Facility Construction
August 1, 2007 12 - 17
SECTION 12
Facility Piping Construction Specification for Facility Construction
August 1, 2007 12 - 18