BS-VI Projects For Panipat Refinery - Hydrogen Generation Unit (HGU) Daily Progress Report

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 1

BS-VI Projects for Panipat Refinery – Hydrogen Generation Unit (HGU)

Daily Progress Report

Owner IOCL, Panipat


PMC Engineers India Limited Progress Date 8/6/2019
Contractor Technip India Limited Reporting Date 8/7/2019
Sub Contractor Lloyd Insulation India Ltd Weather CLEAR
Dailey Progress Report

FRONT Release of
SL.NO. Description UOM Actual Quantity Completion of
RELEASE Percentage (%) WORK Front Till Previous
work Percentage Today Cumm Balance Next Day PLAN REMARKS
COMPLETED Available Day
(%)

1 EQUIPMENT (LAGGING) M2 2,183.12 1,900.00 87.03 % 1,900.00 87.03 % 0.00 1,900.00 - 1,900.00 283.12### -

2 EQUIPMENT (CLADDING) M2 2,183.12 1900.00 87.03 % 1,900.00 87.03 % - 1,900.00 - 1,900.00 283.12
### -

3 PIPING (LAGGING) M2 15,840.00 425.00 2.68 % 380.00 2.40 % 45.00 360.00 20.00 380.00 15,460.00 30.00
scaffolding is progress

4 PIPING (CLADDING) M2 15,840.00 425.00 2.68 % 370.00 2.34 % 55.00 345.00 25.00 370.00 15,470.00 30.00 scaffolding is progress

5 REFORMER PACKAGE (LAGGING) M2 2,856.00 450.00 15.76 % 210.00 240.00 0.00 240.00 2,616.00 0.00

6 REFORMER PACKAGE (CLADDING) M2 2,856.00 450.00 15.76 % 450.00

Manpower and Machinery Status

Indirect Manpower Direct Manpower Equipment & Machinery

Sl No Description Available Sl No Description Available Description Available

1 Project Incharge 1 1 Foreman 1 ROLLING MACHINE 1

2 Planning Engineer 1 2 Fabricator 1 GROOVING MACHINE 2

3 QA/QC 1 3 Fitter 4 MACHINE BENCH VICE 1

4 Safety officer 1 4 Insulator 5 MACHINE SHEARING 1

5 Store keeper/ Accountant 1 5 Helper 5 ELECTRIC DRILL MACHINE 8

6 Scaffolder supervisor 1 6 scaffolder 5 BAND TIGHTENING MACHINE 1

7 supervisor 1 MACHINE SEALER FOR STRIP TIGHT 1

CHOPSAW MACHINE 1

TOTAL 7 TOTAL 21 TOTAL 16

Page 1 of 1