BS-VI Projects For Panipat Refinery - Hydrogen Generation Unit (HGU) Daily Progress Report
BS-VI Projects For Panipat Refinery - Hydrogen Generation Unit (HGU) Daily Progress Report
BS-VI Projects For Panipat Refinery - Hydrogen Generation Unit (HGU) Daily Progress Report
FRONT Release of
SL.NO. Description UOM Actual Quantity Completion of
RELEASE Percentage (%) WORK Front Till Previous
work Percentage Today Cumm Balance Next Day PLAN REMARKS
COMPLETED Available Day
(%)
1 EQUIPMENT (LAGGING) M2 2,183.12 1,900.00 87.03 % 1,900.00 87.03 % 0.00 1,900.00 - 1,900.00 283.12### -
2 EQUIPMENT (CLADDING) M2 2,183.12 1900.00 87.03 % 1,900.00 87.03 % - 1,900.00 - 1,900.00 283.12
### -
3 PIPING (LAGGING) M2 15,840.00 425.00 2.68 % 380.00 2.40 % 45.00 360.00 20.00 380.00 15,460.00 30.00
scaffolding is progress
4 PIPING (CLADDING) M2 15,840.00 425.00 2.68 % 370.00 2.34 % 55.00 345.00 25.00 370.00 15,470.00 30.00 scaffolding is progress
5 REFORMER PACKAGE (LAGGING) M2 2,856.00 450.00 15.76 % 210.00 240.00 0.00 240.00 2,616.00 0.00
CHOPSAW MACHINE 1