Professional Documents
Culture Documents
BS-VI Projects For Panipat Refinery - Hydrogen Generation Unit (HGU) Daily Progress Report
BS-VI Projects For Panipat Refinery - Hydrogen Generation Unit (HGU) Daily Progress Report
FRONT Release of
SL.NO. Description UOM Actual Quantity Completion of
RELEASE Percentage (%) WORK Front Till Previous
work Percentage Today Cumm Balance Next Day PLAN REMARKS
COMPLETED Available Day
(%)
1 EQUIPMENT (LAGGING) M2 2,183.12 1,900.00 87.03 % 1,900.00 87.03 % 0.00 1,900.00 - 1,900.00 283.12### -
2 EQUIPMENT (CLADDING) M2 2,183.12 1900.00 87.03 % 1,900.00 87.03 % - 1,900.00 - 1,900.00 283.12
### -
3 PIPING (LAGGING) M2 15,840.00 425.00 2.68 % 425.00 2.68 % - 425.00 - 425.00 15,415.00 0.00
4 PIPING (CLADDING) M2 15,840.00 425.00 2.68 % 400.00 2.53 % 25.00 380.00 20.00 400.00 15,440.00 25.00
5 REFORMER PACKAGE (LAGGING) M2 2,856.00 1,450.00 50.77 % 1,190.00 240.00 20.00 260.00 2,596.00 30.00 scaffolding is progress
CHOPSAW MACHINE 1
Page 1 of 1