BS-VI Projects For Panipat Refinery - Hydrogen Generation Unit (HGU) Daily Progress Report
BS-VI Projects For Panipat Refinery - Hydrogen Generation Unit (HGU) Daily Progress Report
FRONT Release of
SL.NO. Description UOM Actual Quantity Completion of
RELEASE Percentage (%) WORK Front Till Previous
work Percentage Today Cumm Balance Next Day PLAN REMARKS
COMPLETED Available Day
(%)
1 EQUIPMENT (LAGGING) M2 2,183.12 1,900.00 87.03 % 1,900.00 87.03 % 0.00 1,900.00 - 1,900.00 283.12### -
2 EQUIPMENT (CLADDING) M2 2,183.12 1900.00 87.03 % 1,900.00 87.03 % - 1,900.00 - 1,900.00 283.12
### -
3 PIPING (LAGGING) M2 15,840.00 480.00 3.03 % 460.00 2.90 % 20.00 460.00 - 460.00 15,380.00 0.00 scaffolding is progress
4 PIPING (CLADDING) M2 15,840.00 480.00 3.03 % 460.00 2.90 % 20.00 460.00 - 460.00 15,380.00 0.00
5 REFORMER PACKAGE (LAGGING) M2 2,856.00 1,450.00 50.77 % 580.00 870.00 570.00 10.00 580.00 2,276.00 20.00
6 REFORMER PACKAGE (CLADDING) M2 2,856.00 1,450.00 50.77 % 115.00 1,335.00 75.00 40.00 115.00 1,220.00 20.00 scaffolding is progress
CHOPSAW MACHINE 1