BS-VI Projects for Panipat Refinery – Hydrogen Generation Unit (HGU)

Daily Progress Report

Owner IOCL, Panipat


PMC Engineers India Limited Progress Date 9/30/2019
Contractor Technip India Limited Reporting Date 10/1/2019
Sub Contractor Lloyd Insulation India Ltd Weather CLEAR
Dailey Progress Report

FRONT Release of
SL.NO. Description UOM Actual Quantity Completion of
RELEASE Percentage (%) WORK Front Till Previous
work Percentage Today Cumm Balance Next Day PLAN REMARKS
COMPLETED Available Day
(%)

1 EQUIPMENT (LAGGING) M2 2,183.12 1,900.00 87.03 % 1,900.00 87.03 % 0.00 1,900.00 - 1,900.00 283.12### -

2 EQUIPMENT (CLADDING) M2 2,183.12 1900.00 87.03 % 1,900.00 87.03 % - 1,900.00 - 1,900.00 283.12
### -

3 PIPING (LAGGING) M2 15,840.00 560.00 3.54 % 560.00 3.54 % - 560.00 - 560.00 15,280.00 0.00

4 PIPING (CLADDING) M2 15,840.00 560.00 3.54 % 480.00 3.03 % 80.00 480.00 - 480.00 15,360.00 10.00

5 REFORMER PACKAGE (LAGGING) M2 2,856.00 1,450.00 50.77 % 650.00 800.00 640.00 10.00 650.00 2,206.00 10.00 scaffolding is progress

6 REFORMER PACKAGE (CLADDING) M2 2,856.00 1,450.00 50.77 % 470.00 980.00 420.00 50.00 470.00 510.00 50.00 scaffolding is progress

Manpower and Machinery Status

Indirect Manpower Direct Manpower Equipment & Machinery

Sl No Description Available Sl No Description Available Description Available

1 Project Incharge 1 1 Foreman 1 ROLLING MACHINE 1

2 Planning Engineer 1 2 Fabricator 1 GROOVING MACHINE 2

3 QA/QC 1 3 Fitter 2 MACHINE BENCH VICE 1

4 Safety officer 1 4 Insulator 3 MACHINE SHEARING 1

5 Scaffolder supervisor 1 5 Helper 4 ELECTRIC DRILL MACHINE 8

6 scaffolder 4 BAND TIGHTENING MACHINE 1

MACHINE SEALER FOR STRIP TIGHT 1

CHOPSAW MACHINE 1

TOTAL 5 TOTAL 15 TOTAL 16