Professional Documents
Culture Documents
BS-VI Projects For Panipat Refinery - Hydrogen Generation Unit (HGU) Daily Progress Report
BS-VI Projects For Panipat Refinery - Hydrogen Generation Unit (HGU) Daily Progress Report
BS-VI Projects For Panipat Refinery - Hydrogen Generation Unit (HGU) Daily Progress Report
FRONT Release of
SL.NO. Description UOM Actual Quantity Completion of
RELEASE Percentage (%) WORK Front Till Previous
work Percentage Today Cumm Balance Next Day PLAN REMARKS
COMPLETED Available Day
(%)
1 EQUIPMENT (LAGGING) M2 2,183.12 1,900.00 87.03 % 1,900.00 87.03 % 0.00 1,900.00 - 1,900.00 283.12### -
2 EQUIPMENT (CLADDING) M2 2,183.12 1900.00 87.03 % 1,900.00 87.03 % - 1,900.00 - 1,900.00 283.12
### -
3 PIPING (LAGGING) M2 15,840.00 560.00 3.54 % 560.00 3.54 % - 560.00 - 560.00 15,280.00 0.00
4 PIPING (CLADDING) M2 15,840.00 560.00 3.54 % 480.00 3.03 % 80.00 480.00 - 480.00 15,360.00 10.00
5 REFORMER PACKAGE (LAGGING) M2 2,856.00 1,450.00 50.77 % 650.00 800.00 640.00 10.00 650.00 2,206.00 10.00 scaffolding is progress
6 REFORMER PACKAGE (CLADDING) M2 2,856.00 1,450.00 50.77 % 470.00 980.00 420.00 50.00 470.00 510.00 50.00 scaffolding is progress
CHOPSAW MACHINE 1