BS-VI Projects For Panipat Refinery - Hydrogen Generation Unit (HGU) Daily Progress Report
BS-VI Projects For Panipat Refinery - Hydrogen Generation Unit (HGU) Daily Progress Report
FRONT Release of
SL.NO. Description UOM Actual Quantity Completion of
RELEASE Percentage (%) WORK Front Till Previous
work Percentage Today Cumm Balance Next Day PLAN REMARKS
COMPLETED Available Day
(%)
1 EQUIPMENT (LAGGING) M2 2,183.12 1,900.00 87.03 % 1,900.00 87.03 % 0.00 1,900.00 - 1,900.00 283.12### -
2 EQUIPMENT (CLADDING) M2 2,183.12 1900.00 87.03 % 1,900.00 87.03 % - 1,900.00 - 1,900.00 283.12
### -
3 PIPING (LAGGING) M2 15,840.00 500.00 3.16 % 460.00 2.90 % 40.00 460.00 - 460.00 15,380.00 0.00 scaffolding is progress
4 PIPING (CLADDING) M2 15,840.00 500.00 3.16 % 460.00 2.90 % 40.00 460.00 - 460.00 15,380.00 0.00 scaffolding is progress
5 REFORMER PACKAGE (LAGGING) M2 2,856.00 1,450.00 50.77 % 640.00 810.00 630.00 10.00 640.00 2,216.00 20.00 scaffolding is progress
6 REFORMER PACKAGE (CLADDING) M2 2,856.00 1,450.00 50.77 % 120.00 1,330.00 100.00 20.00 120.00 1,210.00 20.00 scaffolding is progress
CHOPSAW MACHINE 1