The document provides a schedule for the FIRST FIRE of BQPS-III Unit#1. It outlines 21 key systems and activities involved in the commissioning and first ignition of the power unit. These include construction and installation of the power train, heat recovery steam generator, boiler feed water pump system, piping, electrical systems, instrumentation and control systems. The schedule spans from March 2020 to July 2021 and involves over 50 sub-activities for the successful first fire of the unit.
The document provides a schedule for the FIRST FIRE of BQPS-III Unit#1. It outlines 21 key systems and activities involved in the commissioning and first ignition of the power unit. These include construction and installation of the power train, heat recovery steam generator, boiler feed water pump system, piping, electrical systems, instrumentation and control systems. The schedule spans from March 2020 to July 2021 and involves over 50 sub-activities for the successful first fire of the unit.
The document provides a schedule for the FIRST FIRE of BQPS-III Unit#1. It outlines 21 key systems and activities involved in the commissioning and first ignition of the power unit. These include construction and installation of the power train, heat recovery steam generator, boiler feed water pump system, piping, electrical systems, instrumentation and control systems. The schedule spans from March 2020 to July 2021 and involves over 50 sub-activities for the successful first fire of the unit.
1 Power Train (GT & ST House#1) 2 (HRSG#1) Heat Recovery Steam Generator 3 Boiler Feed Water Pump System 4 Condensate Pump System 5 GIS Main Tunnel & Cable Trenches 6 GSU/ UAT/ Stand By Transformers/GCB/IPB 7 PIPE RACKS INSTALLATION 8 Piping Activities of Unit 1 & BOP (Balance of Plant System) 9 Field Instrumentation Installation Activities of Unit 1 & BOP 10 220KV Electrical System(220KV GIS/Gantry Area/Relay Control Building) 11 Center Control Building(CCB) 12 Black Start Diesel Generator/Emergency Diesel Generator System) 13 Fuel Gas System (RLNG) 14 Fuel Oil System (Distillate) 15 Circulated Water System CCCW& OCCW 16 Raw Water System with Demin Water Treatment Plant 17 Gas Conditioning System 18 Compressed Air System (Plant & Instrument Air) 19 Fire Fighting System 20 Hydrogen Generation System 21 DCS(Plant Control System & NCS(Grid Control System) 22 Commissioning & First Fire of Unit#1 BQPS-III Unit#1 FIRST FIRE Original S.No Activity ID Activity Name Start Date Finish Date Comments Duration 1-Power Train (GT & ST MPB#1)
1 CC1010 #1 main building foundation pile construction 60 17-Mar-20 16-May-20
2 CC1040 #1 GT&ST foudation pile construction 20 21-May-20 10-Jun-20 3 CC1341 #1 Backfilling Work 15 2-Jul-20 22-Feb-21 4 CC1180 #1 main building steel structure foundation construction 45 10-Jul-20 23-Sep-20 5 CC1340 #1 GT/GTG/ST foundation baseplate construction 31 12-Jul-20 14-Oct-20 6 CC1710 #1 main building steel structure and cladding construction 120 29-Aug-20 27-Feb-21 7 CC1780 #1 GT/GTG/ST above-ground foundation construction 45 14-Oct-20 28-Nov-20 8 CC1720 #1 main building auxiliary equipment foundation construction 120 16-Oct-20 27-Feb-21 9 INS1160 #1 main building overhead crane installation 20 23-Nov-20 25-Nov-20 10 INS1650 #1 GT on position 12 1-Jan-21 12-Jan-21 11 INS1880 #1 GTG on position 15 5-Jan-21 20-Jan-21 12 CC2220 #1 main building roof closure plate installation finish 60 14-Dec-20 2-Mar-21 13 INS1340 #1 GT& GTG fixator bedplate installation 20 16-Dec-20 24-Dec-20 14 INS1660 #1 GT air intake system installation 104 12-Jan-21 21-May-21 15 INS1720 #1 GT air exhaust system installation 62 25-Jan-21 9-Apr-21 16 INS1560 #1 ST bedplate and fixator installation 6 27-Jan-21 5-Feb-21 17 INS1830 #1 condenser in position and installation 23 28-Jan-21 5-Mar-21 18 INS1670 #1 Main building auxiliary equipment installation 90 4-Feb-21 18-May-21 19 INS1760 #1 ST HP&IP&LP cylinder in position 4 10-Feb-21 13-Feb-21 20 INS1780 #1 ST installation 43 11-Feb-21 3-Apr-21 21 INS1680 #1 PCC in position and installation 3 21-Feb-21 23-Feb-21 22 INS1890 #1 GT>G&ST priliminary alignment 11 22-Feb-21 4-Mar-21 23 INS1020 #1 main building cable tray installation 60 11-Mar-21 10-May-21 24 INS1900 #1 Lube oil and sealing oil pipeline construction 39 20-Mar-21 27-Apr-21 25 INS1910 #1 Hydraulic oil pipeline construction 30 20-Mar-21 18-Apr-21 26 INS1850 #1 main steam pipelines installation and insulation 90 29-Mar-21 27-Jun-21 27 INS1920 #1 SFC system installation 7 30-Mar-21 5-Apr-21 28 INS1380 #1 GTG Outlet cable and GCB installation 50 30-Mar-21 18-May-21 29 INS1950 #1 Excitation system installation 7 3-Apr-21 9-Apr-21 30 INS1930 #1 ST body 'I & C installation 75 3-Apr-21 17-Jun-21 31 INS2040 #1 GT body and ST body pipeline construction 41 4-Apr-21 14-May-21 32 INS1970 #1 GTG body electrical part installation 25 5-Apr-21 29-Apr-21 33 INS1370 #1 main building electrical cable laying and wiring 90 10-Apr-21 9-Jul-21 34 INS2190 #1 GT casing ventilating system installation 20 12-Apr-21 1-May-21 35 INS1420 #1 Main building I & C cable laying and wiring 80 17-Apr-21 6-Jul-21 36 INS1290 #1 Gas Conditioning Skid & pipe connection 60 23-Apr-21 21-Jun-21 37 INS2120 #1 GT body I & C installation 75 26-Apr-21 9-Jul-21 38 INS2180 #1 Lube oil and hydraulic oil flushing 37 28-Apr-21 3-Jun-21 39 INS1860 #1 IP&LP pipeline construction 91 28-Apr-21 28-Jul-21 40 INS2130 #1 GTG body I & C installation 69 3-May-21 10-Jul-21 41 INS2270 #1 GT body thermal insulation construction 30 15-May-21 13-Jun-21 42 INS2410 #1 Lube oil qualified 0 3-Jun-21 43 INS2400 #1 Final Alignment 10 4-Jun-21 13-Jun-21 44 INS2430 #1 Reaming and coupling 11 14-Jun-21 24-Jun-21 45 INS2440 #1 ST body thermal insulation construction 20 25-Jun-21 14-Jul-21 46 INS2480 Unit 1 turning gear 0 14-Jul-21 15-Jul-21 47 TC1210 #1 GT & GTG cold commissioning 44 1-Jun-21 15-Jul-21 48 TC1320 #1 GT & GTG hot commissioning 16 15-Jul-21 31-Jul-21 49 TC1440 #1 GT first ignition(on RLNG) 0 31-Jul-21 31-Jul-21 2-(HRSG#1) Heat Recovery Steam Generator 1 CC1000 #1 HRSG pile construction 26 16-Feb-20 13-Mar-20 2 CC1001 #1 HRSG Excavation Work 20 17-Apr-20 7-May-20 3 CC1002 #1 HRSG Backfilling Work 30 7-May-20 24-Feb-21 4 CC1003 #1 HRSG Pile Head Breaking Work 15 6-Jun-20 21-Jun-20 5 CC1320 #1 HRSG foundation construction 45 21-Jun-20 12-Sep-20 6 CC1750 #1 HRSG auxiliary foundation and structure construction 60 22-Sep-20 2-Mar-21 7 INS1030 #1 HRSG steel structure installation 88 25-Sep-20 23-Feb-21 8 INS1390 #1 HRSG stack installation 90 10-Nov-20 25-Mar-21 9 INS1730 #1 HRSG module installation 30 6-Jan-21 25-Jan-21 10 INS2010 #1 HRSG HP&IP&LP drum in position and installation 3 10-Feb-21 23-Feb-21 11 INS1990 #1 HRSG flue-gas baffler construction 31 11-Feb-21 20-Mar-21 12 INS2000 #1 HRSG inlet and outlet flue-gas duct construction 31 11-Feb-21 12-Mar-21 13 INS2070 #1 HRSG steam-water pipe ( in the scope of hydro test ) installation 92 22-Feb-21 24-May-21 14 INS2090 #1 HRSG electrical equipments installation 100 22-Feb-21 1-Jun-21 15 INS2100 #1 HRSG I&C equipments installation 100 22-Mar-21 30-Jun-21 16 INS2330 #1 HRSG steam-water pipe ( out of scope of hydro test ) installation 30 25-Apr-21 24-May-21 17 INS2420 #1 HRSG insulation 15 10-Jul-21 25-Jul-21 18 TC1330 #1 HRSG hydraulic pressure test 10 3-Jul-21 13-Jul-21 19 TC1370 #1 HRSG hydraulic pressure test finish 0 8-Jul-21 13-Jul-21 20 TC1410 #1 HRSG chemical cleaning 7 17-Jul-21 24-Jul-21 21 TC1450 #1 HRSG chemical cleaning finish 0 19-Jul-21 24-Jul-21 3-Boiler Feed Water Pump & System 1 CC1740 Pilling or Excavation and dewatering (Depending upon approved Design) 15 6-Aug-20 22-Sep-20 2 CC1860 Pump foundation construction 60 1-Dec-20 17-Mar-21 3 CC2120 Architectural Work 20 18-Mar-21 6-Apr-21 4 INS2030 1# HRSG Feed Water Pump installation 30 2-Apr-21 1-May-21 5 INS2360 2# HRSG Feed Water Pump installation 30 6-Apr-21 6-May-21 6 T&C Testing and Commissioning 5 10-May-21 15-May-21 4-(Condensate Pump & System ) 1 INS1750 1# Condensate Water Pump & Pipe installation 90 17-Mar-21 15-Jun-21 2 INS2220 2# Condensate Water Pump & Pipe installation 90 6-May-21 16-Jun-21 5-(GIS Main Tunnel & Cable Trenches ) 1 CC1030 Cable Tunnel Excavation 165 15-Jun-20 26-Feb-21 2 CC1050 Cable Tunnel Concrete 180 25-Jun-20 15-Mar-21 3 CC1850 Outdoor Interconnection Cable Trenches 120 2-Oct-20 4-May-21 6-(GSU/ UAT/ Stand By Transformers) 1 CC1060 Main GSU,UAT,Standby Transformers, BBR & IPB Pile construction 15 31-Jul-20 15-Sep-20 2 CC1270 Transformer BBR & IPB foundation construction 50 30-Sep-20 25-Dec-20 3 CC1460 1# Fireproof wall 50 12-Oct-20 14-Jan-21 4 INS1190 Transformers on position 7 28-Jan-21 1-Feb-21 5 INS1200 Transformers installation 45 15-Feb-21 27-Mar-21 6 INS1600 Oil filtration 15 27-Mar-21 11-Apr-21 a-(GCB Generator Circuit Breaker) 1 INS1060 1# GCB installation 20 15-Apr-21 5-May-21 b-(IPB Isolation Phase Bus Duct Installation ) 1 INS1350 1# IPB installation 60 5-May-21 4-Jul-21 c-(T&C of GSU/UAT/Stand By Transformers ) 1 TC1010 Standby/Station Transformer Testing 20 6-Mar-21 25-Mar-21 2 TC1040 Transformer commissioning 20 20-Jul-21 9-Aug-21 3 TC1130 Transformer ready for power backfeed 0 9-Aug-21 10-Aug-21 7-PIPE RACK INSTALLATION 1 CC1520 East pipe rack foundation construction 120 17-Dec-20 22-Apr-21 2 CC1670 South pipe rack foundation construction 90 23-Dec-20 7-Apr-21 3 CC1590 Main Steam pipe rack pile construction 15 2-Feb-21 5-Mar-21 4 CC1730 Main Steam pipe rack foundation construction 60 29-Mar-21 28-May-21 5 INS1234 Installation of Structure of Pipe Racks 30-Mar-21 30-May-21 8-Piping Activities of Unit 1 & BOP (Balance of Plant System 1 INS1040 Piping installation of GT/ST HRSG & Auxilaries 100 1-Apr-21 10-Jul-21 2 Piping installation of BOP System and Interfacing with UNIT#1 System 5-Apr-21 10-Jul-21 3 Flushing Blowing Activities of All areas Piping 10-Jul-21 25-Jul-21 9-Field Instrumentation of Unit 1 & BOP (Balance of Plant System ) 1 INS1040 Field Instrumentation installation of GT/ST /HRSG & Auxilaries 90 15-Apr-21 15-Jul-21 2 Field Instrumentation installation of BOP System 90 20-Apr-21 20-Jul-21 3 Calibration and Loop Testing of All Field Instrumentation 60 25-May-21 25-Jul-21
10-(Electrical System 220KV )
a- Switchgear 220 Kv 1 CC1160 Excavation and dewatering 15 31-Mar-21 15-Apr-21 2 CC1300 foundation and trench 30 15-Apr-21 15-May-21 3 CC1690 Structure construction 30 15-May-21 14-Jun-21 b-Gantry & Outdoor Equipment Foundation 1 CC2710 Gantry & outdoor Equipment Foundation 60 1-Feb-21 20-Mar-21 2 ICI & PIPRI-3 Equipment Installation 25-Mar-21 31-Mar-21 c- GIS Building 220 kV 1 CC1150 GIS building Excavation and dewatering 10 9-Jul-20 12-Aug-20 2 CC1310 GIS building foundation Work 75 13-Aug-20 19-Sep-20 3 CC1560 Sub-Structural & Super Structural construction 59 1-Sep-20 29-Jan-21 4 CC1810 GIS building architecture construction 90 17-Jan-21 25-Apr-21 d- GIS System 220kV 1 INS1050 220kV GIS installation for Back Feed 60 12-Apr-21 10-Jun-21 2 INS1150 220kv cable laying and termination 90 26-Apr-21 25-Jul-21 3 INS1051 220KV GIS Installation Complete 60 11-Jun-21 9-Aug-21 4 INS1120 Reactor installation 30 14-Jun-21 14-Jul-21 e- GIS GRID Relay & Control Building 220KV 1 CC1130 Grid control building Excavation and dewatering 15 24-Sep-20 1-Oct-20 2 CC1290 Foundation 30 1-Oct-20 26-Oct-20 3 CC1540 Grid control building Structural Work 60 27-Oct-20 27-Feb-21 4 CC1980 Grid control building Architectural Work 60 1-Mar-21 30-Apr-21 f- Grid Protection & Control System 220KV 1 INS1220 Grid control building electrical equipments installation 60 20-Apr-21 19-Jun-21 2 TC1030 Grid control building electrical equipments commissioning 32 19-Jun-21 21-Jul-21 3 TC1140 Grid control building ready for power back feed 0 21-Jul-21 21-Jul-21 g- GIS Testing & Commissioning 220kV 1 TC1050 220kv GIS unit commissioning(for Back Feed) 45 11-Jun-21 25-Jul-21 2 TC1100 220kv switchyard electric equipments system commissioning 15 25-Jul-21 9-Aug-21 3 TC1161 220KV GIS Commissioning Complete 45 31-Jul-21 13-Sep-21 4 TC1160 Power Back Feed to MV 3 9-Aug-21 12-Aug-21 5 TC1150 220kv GIS ready for power back feed 0 12-Aug-21 13-Aug-21 11-Center Control Building(CCB) 1 CC1020 CCB Pilling 57 17-Mar-20 13-May-20 2 CC1120 CCB Foundation Work 75 15-Jun-20 5-Sep-20 3 CC1390 CCB Structural Work 120 7-Sep-20 11-Feb-21 4 CC1840 CCB Architectural Work 180 21-Jan-21 6-Jul-21 5 INS1241 CCB 6.6kV Installation for Temporary Backfeed 45 23-Mar-21 7-May-21 6 INS1450 CCB DCS installation 120 30-Mar-21 28-Jul-21 7 INS1240 CCB electrical equipment installation(Power back feed scope) 85 31-Mar-21 24-Jun-21 8 INS2140 CCB electrical equipment installation(Other scope) 145 7-Apr-21 30-Aug-21 12-Black Start Diesel Generator (BSDG) 1 CC1380 Pilling Work 30 10-Nov-20 5-Dec-20 2 CC1550 Foundation 75 5-Mar-21 18-May-21 3 CC1820 Structure 30 19-May-21 17-Jun-21 4 CC1990 Architecture 20 18-Jun-21 7-Jul-21 5 INS1870 Diesel generator installation 20 8-Jul-21 27-Jul-21 6 INS1980 Diesel generator electrical equipment installation 30 28-Jul-21 26-Aug-21 7 TC1280 Black Start Diesel generator commissioning 30 12-Aug-21 10-Sep-21 a-Emergency Diesel Generator (EDG) 1 CC1570 Pilling Work 28 10-Nov-20 5-Dec-20 2 CC1790 Foundation construction 75 5-Mar-21 18-May-21 3 CC2160 Structure 25 19-May-21 12-Jun-21 4 CC2230 Architectural Work 20 13-Jun-21 2-Jul-21 5 INS1320 Diesel generator installation 20 13-Jun-21 2-Jul-21 6 INS1400 Diesel generator electrical equipment installation 30 13-Jun-21 12-Jul-21 7 TC1020 Diesel generator commissioning 30 13-Jul-21 11-Aug-21 13-Fuel Gas System (RLNG) Customer Metering Station & Distribution 1 CC1370 Excavation and dewatering 28 16-Dec-20 30-Dec-20 2 CC1530 Foundation construction 75 31-Dec-20 25-Jan-21 3 CC2020 Structure 25 5-Apr-21 30-Apr-21 4 CC2100 Architectural Work 5 30-Apr-21 5-May-21 Fuel Gas System BQPS-III 1 CC1610 Excavation and dewatering 21 12-Sep-20 19-Sep-20 2 CC1830 Foundation construction 75 21-Sep-20 30-Sep-20 3 CC2170 Structure 25 31-Mar-21 25-Apr-21 4 CC2250 Architectural Work 5 25-Apr-21 30-Apr-21 RLNG Gas and Fuel Oil Pipe Line 1 CC1090 Gas line foundation from BQPS III to metering and distribution station 90 9-Feb-21 29-Mar-21 BQPS III Fuel Gas System 1 INS1310 BQPS-III Fuel Gas System Equipment Installation 90 8-Jan-21 16-Mar-21 2 INS1000 Interconnection Line from Metering Station to Gas Station of BQPS-III 70 12-Feb-21 18-Apr-21 3 INS1530 BQPS-III gas system electrical installation 73 16-Mar-21 28-May-21 4 INS1329 Metering Skid Installation Work 30 16-Mar-21 15-Apr-21 5 INS1590 BQPS-III gas system I&C installation 68 23-Mar-21 30-May-21 6 INS1330 BQPS-III Fuel Gas Piping from GT Gas Skid to Gas Station 60 23-Apr-21 21-Jun-21 BQPS III Fuel Gas System Commissioning 1 TC1270 BQPS III gas system commissioning 31 30-May-21 29-Jun-21 2 TC1350 BQPS III gas ready for ignition 1 30-Jun-21 30-Jun-21 14-Fuel Oil System (Distillate Oil) Fuel Oil System BQPS III 115 22-Jun-20 5-Mar-21 1 CC1250 Fuel Oil tank pile construction 30 22-Jun-20 26-Jun-20 2 CC1400 Fuel Oil tank & equipment foundation construction 60 12-Aug-20 5-Mar-21 3 INS1040 Fuel Oil tank installation 120 5-Apr-21 2-Aug-21 4 INS1110 Fuel Oil pipe installation 120 10-Jun-21 7-Oct-21 5 INS1360 Fuel Oil tank electrical installation 28 7-Jul-21 3-Aug-21 6 INS1430 Fuel Oil tank I&C installation 25 12-Jul-21 5-Aug-21 7 INS1500 BQPS III pump installation 30 15-May-21 14-Jun-21 8 INS1690 Fuel system electrical construction 53 30-May-21 22-Jul-21 9 INS1700 Fuel system I&C construction 55 30-May-21 24-Jul-21 10 INS1820 BQPS II pump installation 30 14-Jun-21 14-Jul-21 Fuel Oil Pump Shed BQPS II 150 1-Mar-21 29-Jul-21 1 CC1620 Excavation and dewatering 45 1-Mar-21 15-Apr-21 2 CC1960 Foundation construction 75 15-Apr-21 29-Jun-21 3 CC2240 Structure 25 29-Jun-21 24-Jul-21 4 CC2280 Architectural Work 5 24-Jul-21 29-Jul-21 Fuel Oil Pump Shed BQPS III 71 5-Feb-21 11-May-21 1 CC1430 Pilling or Excavation and dewatering (Depending upon approved Design) 15 5-Feb-21 13-Feb-21 2 CC1760 Foundation construction 45 14-Feb-21 3-Apr-21 3 CC2130 Structure 25 6-Apr-21 1-May-21 4 CC2210 Architectural Work 10 1-May-21 11-May-21 Fuel Oil Tank 10 8-Aug-21 17-Aug-21 1 TC1070 Fuel Oil tank pressure test 10 8-Aug-21 17-Aug-21 2 TC1090 Fuel Oil tank ready for filling 0 17-Aug-21 Fuel Oil System 45 8-Oct-21 21-Nov-21 1 TC1250 Fuel system commissioning 45 8-Oct-21 21-Nov-21 2 TC1390 Fuel Oil Ready for ignition 1 21-Nov-21 21-Nov-21 15-Circulated Water System CCCW& OCCW Circulated Water Pump Station CCCW & OCCW 1 CC1070 Pilling or Excavation and dewatering (Depending upon approved Design) 45 7-Oct-20 17-Oct-20 2 CC1200 Station foundation construction 60 11-Feb-21 13-Apr-21 3 CC1890 Structure Work 30 14-Apr-21 13-May-21 CW System 1 A34360 HDPE Piping Installation Work Complete Unit # 3 Including Temp Operation 130 1-Mar-21 9-Jul-21 2 A34370 HDPE Piping Installation Work Complete Unit # 4 105 2-Apr-21 16-Jul-21 3 INS1770 BQPS III #1 New pump equipment installation 40 5-May-21 13-Jun-21 4 INS1800 BQPS III #1 new pump electrical and I & C installation 40 5-May-21 13-Jun-21 5 INS2250 BQPS III #2 New pump equipment installation 45 5-May-21 18-Jun-21 6 INS2260 BQPS III #2 New pump electrical and I&C installation 40 8-May-21 16-Jun-21 CW Pump House 1 TC1400 BQPS III #2 New pump system test 7 9-Jul-21 16-Jul-21 2 TC1190 BQPS III #1 New pump system test 7 16-Jul-21 23-Jul-21 3 TC1420 BQPS III #2 Circulating water system ready for water circulating 0 23-Jul-21 4 TC1200 BQPS III #1 Circulating water system ready for water circulating 0 30-Jul-21 Closed Circulated Water System 1 INS1270 Closed circulated water pump electrical I&C installation 45 14-Apr-21 28-May-21 2 INS1140 Closed circulated water Pump & Piping installation 45 14-Apr-21 28-May-21 Closed Circulated Water System 1 TC1180 Closed circulated water pump commissioning 14 29-May-21 11-Jun-21 2 TC1240 Closed circulated water System ready 5 16-Jul-21 21-Jul-21 OCC Water System 1 INS0100 Open Circulating Cooling Water Pumps & Piping Installation Work 45 14-Apr-21 28-May-21 2 INS0102 Open Circulating Cooling Water Pumps electrical I&C installation 30 21-Apr-21 20-May-21 Open Circulated Colling Water System 1 TC1181 Open circulated water pump commissioning 14 29-May-21 11-Jun-21 2 TC1182 Open circulated water System ready 5 16-Jul-21 21-Jul-21 16-Raw Water /Demin Water Treatment Plant 1 CC1220 Pile construction 20 13-Jul-20 20-Jul-20 2 CC1440 Foundation construction 60 17-Oct-20 23-Nov-20 3 CC1930 Structural Work 30 31-Mar-21 30-Apr-21 4 CC2030 Architectural Work 30 30-Apr-21 30-May-21 6 INS1170 Demin water treatment system equipments and pipes installation 50 30-Apr-21 19-Jun-21 7 INS1540 Demin water treatment system electrical construction 45 7-May-21 21-Jun-21 8 INS1550 Demin water treatment system I&C construction 45 7-May-21 21-Jun-21 10 TC1170 Demin water treatment system commissioning 12 21-Jun-21 3-Jul-21 11 TC1230 Demin water Qualified 0 3-Jul-21 3-Jul-21 a-Chemical Sample Dosing System 1 INS1080 Sample Dosing equipment Installation 60 4-Apr-21 2-Jun-21 17-Gas Conditioning System 1 CC1350 Excavation and dewatering 15 14-Sep-20 21-Sep-20 2 CC1500 Skids foundation construction 60 22-Feb-21 22-Apr-21 3 INS Placement of Skid on Foundation 15 14-Sep-20 21-Sep-20 4 INS Mechnical and Electrical Equipment Installation 60 22-Feb-21 22-Apr-21 5 INS Piping Activity from BQPS-III Metering Station to GC Skid 22-Apr-21 23-May-21 6 T&C Testing and Commissioning 15-Jul-21 20-Jul-21 18-Compressed Air System (Plant & Instrument Air) 1 CC1140 Pilling or Excavation and dewatering (Depending upon approved Design) 30 15-Aug-20 22-Aug-20 2 CC1360 Foundation work of Compressed Air Station 30 12-Sep-20 23-Oct-20 3 CC1910 Structure work of Compressed Air Station 40 24-Oct-20 17-Mar-21 4 CC2090 Architecture work of Compressed Air Station 40 18-Mar-21 26-Apr-21 5 INS1130 Compressed air system equipments and pipes installation 90 7-Apr-21 5-Jul-21 6 INS1790 Compressed air system electrical installation 41 29-May-21 8-Jul-21 7 INS1840 Compressed air system I&C installation 37 2-Jun-21 8-Jul-21 8 TC1260 Compressed air system commissioning 7 9-Jul-21 15-Jul-21 9 TC1290 Compressed air system in operation 0 15-Jul-21 15-Jul-21 19-Fire Fighting System 1 CC1260 Fire fighting Pump House excavation & dewatering 30 16-Oct-20 23-Oct-20 2 CC1901 Fire Fighting Tanks Construction Work 60 23-Oct-20 17-Mar-21 3 CC1410 Fire fighting Pump House foundation construction 60 24-Oct-20 22-Jan-21 4 CC1900 Architectural Work 30 1-Mar-21 31-Mar-21 6 INS1470 Fire fighting water system for transformer and GIS 90 10-Mar-21 7-Jun-21 7 INS1460 Fire fighting water systemequipments and pipes installation for Unit # 01 80 8-Apr-21 26-Jun-21 8 INS1570 Fire fighting water system electrical construction 120 8-Apr-21 5-Aug-21 9 INS1620 Fire fighting water system I&C construction 120 8-Apr-21 5-Aug-21 10 INS1461 Fire fighting water systemequipments and pipes installation for Unit # 02 90 7-Jun-21 4-Sep-21 12 INS1480 Fire Fighting Detection System installation 180 10-Mar-21 5-Sep-21 14 TC1120 Fire fighting water system commissioning for transformer and GIS for Backfeed 6 8-Jun-21 13-Jun-21 15 TC1430 Fire fighting water system commissioning Complete 90 17-Jun-21 14-Sep-21 16 TC1121 Fire fighting water system for Unit # 01 25 2-Jul-21 26-Jul-21 20-Hydrogen Generation System 1 CC1210 H2 Station pile construction 15 27-Jun-20 30-Jun-20 2 CC1450 H2 Station Foundation construction 35 12-Aug-20 14-Sep-20 3 CC1700 Structural Work 60 15-Sep-20 1-Feb-21 4 CC2050 Architectural Work 60 1-Mar-21 30-Apr-21 6 INS1740 H2 Station equipments and pipes installation 60 12-Mar-21 10-May-21 7 INS1940 H2 Station electrical installation 60 22-Mar-21 20-May-21 8 INS2050 H2 Station I&C installation 60 27-Mar-21 25-May-21 10 TC1310 Hydrogen system commissioning 10 26-May-21 4-Jun-21 11 TC1380 H2 Qualified 0 4-Jun-21 4-Jun-21 21-DCS(Plant Control System & NCS(Grid Control System) Partial Commissioning 1 DCS energization 0 25-May-21 29-May-21 2 A34350 DCS Block 1 Commissioning 45 14-May-21 28-Jun-21 3 A34380 NCS Partial System Commissioning 45 14-May-21 28-Jun-21 22-Commissioning & First Fire of Unit#1 1 OC1000 GT 1# First Fire 1 30-Jul-21 31-Jul-21