TECHNICAL DEPARTMENT-CIVIL (Rev No.) Rev02
Shop Drawings-Check List Issue Date August 2011
CSI No Subject Doc Type Rev. Date 17th April 2020
032111T Reinforcement for Post tension Slab Check List Rev: 2 Page 1 of 3
1. Scope
This Checklist is for reviewing the shop drawings for rebar used in Post tensioned Slab.
2. Project Details
Project Name Project Code
Consultancy Drawings No
3. Check List.
Sr.
Description OK/Not OK Remarks
No.
A GENERAL NOTES
B CHECKLIST
B1 GRIDS
4 Anti-shear Zigzag
Page 1 of 3
Doc. No. TEC-032111T-SPD-CLT-
TECHNICAL DEPARTMENT-CIVIL (Rev No.) Rev02
Shop Drawings-Check List Issue Date August 2011
CSI No Subject Doc Type Rev. Date 17th April 2020
032111T Reinforcement for Post tension Slab Check List Rev: 2 Page 2 of 3
Sr.
Description OK/Not OK Remarks
No.
B2 BEAMS
COLUMNS
SLAB
13
OPENINGS
15
DEAD END AND LIVE END
16 Anti-bursting Spiral
Page 2 of 3
Doc. No. TEC-032111T-SPD-CLT-
TECHNICAL DEPARTMENT-CIVIL (Rev No.) Rev02
Shop Drawings-Check List Issue Date August 2011
CSI No Subject Doc Type Rev. Date 17th April 2020
032111T Reinforcement for Post tension Slab Check List Rev: 2 Page 3 of 3
4. Summary result.
Signature
Received from
Subcontractor
Return this shop drawing to
Subcontractor ☐
Date
Transmittal to
Consultant on
Forward this shop drawing to
Subcontractor ☐
Received from
Name
consultant back on
Designation
Page 3 of 3