BS-VI Projects For Panipat Refinery - Hydrogen Generation Unit (HGU) Daily Progress Report
BS-VI Projects For Panipat Refinery - Hydrogen Generation Unit (HGU) Daily Progress Report
FRONT Release of
SL.NO. Description UOM Actual Quantity Completion of
RELEASE Percentage (%) WORK Front Till Previous
work Percentage Today Cumm Balance Next Day PLAN REMARKS
COMPLETED Available Day
(%)
1 EQUIPMENT (LAGGING) M2 2,183.12 1,900.00 87.03 % 1,900.00 87.03 % 0.00 1,900.00 - 1,900.00 283.12### -
2 EQUIPMENT (CLADDING) M2 2,183.12 1900.00 87.03 % 1,900.00 87.03 % - 1,900.00 - 1,900.00 283.12
### -
3 PIPING (LAGGING) M2 15,840.00 3,560.00 22.47 % 580.00 3.66 % 2,950.00 580.00 30.00 610.00 15,230.00 20.00 scaffolding is progress
4 PIPING (CLADDING) M2 15,840.00 3,560.00 22.47 % 540.00 3.41 % 3,000.00 540.00 20.00 560.00 15,280.00 20.00 scaffolding is progress
5 REFORMER PACKAGE (LAGGING) M2 2,856.00 2,165.00 75.81 % 1,150.00 1,015.00 1110.00 40.00 1150.00 1,706.00 60.00
6 REFORMER PACKAGE (CLADDING) M2 2,856.00 2,165.00 75.81 % 900.00 1,265.00 860.00 40.00 900.00 1,956.00 60.00
CHOPSAW MACHINE 1