M/S Lloyd Insulations (I) LTD Date-30.11.19 Daily Progress Report Client-M/S TECHNIP FMC BS-VI Project Panipat Refinery Panipat
M/S Lloyd Insulations (I) LTD Date-30.11.19 Daily Progress Report Client-M/S TECHNIP FMC BS-VI Project Panipat Refinery Panipat
M/S Lloyd Insulations (I) LTD Date-30.11.19 Daily Progress Report Client-M/S TECHNIP FMC BS-VI Project Panipat Refinery Panipat
19
DAILY PROGRESS REPORT
Client- M/S TECHNIP FMC BS-VI Project Panipat Refinery Panipat
COMPLETED AREA TODAY PROGRESS BALANCE AREA
RELEASE FOR RELEASE FOR
INSULATION SCAFFOLDING NEXT DAY PLAN
S.N. Description TOTAL SCOPE UOM
LAGGING CLADDING LAGGING CLADDING LAGGING CLADDING
LAGGING CLADDING
1 EQUIPMENTS 2530 RMT 2530 0 2530 2530 0 0 0 0 0 0
2 REFORMER PACKAGE 2000 RMT 2000 0 1515 1270 20 20 465 710 30 30
3 PIPLINE-IH 10000 RMT 8000 2000 4345 3305 210 120 3445 4575 210 140
4 PIPLINE(VALVE & F) 1300 M2 Not released 0 0 0 0 0 0 0 0 0
FIREPROOFING SYSTEM
7 ON CABLE DUCTS/TRAYS 1038 RMT Not released 0 0 0 0 0 0 0 0 0
AND FITTING
TOTAL STAFF = 5
TOTAL MANPOWER =71
19 GATE PASS UNDER PROCESS