BS-VI Projects For Panipat Refinery - Hydrogen Generation Unit (HGU) Daily Progress Report
BS-VI Projects For Panipat Refinery - Hydrogen Generation Unit (HGU) Daily Progress Report
FRONT Release of
SL.NO. Description UOM Actual Quantity Completion of
RELEASE Percentage (%) WORK Front Till Previous
work Percentage Today Cumm Balance Next Day PLAN REMARKS
COMPLETED Available Day
(%)
1 EQUIPMENT (LAGGING) RMT 2,530.00 2,530.00 100.00 % 2,530.00 100.00 % 0.00 2,530.00 - 2,530.00 - ### -
2 EQUIPMENT (CLADDING) RMT 2,530.00 2530.00 100.00 % 2,530.00 100.00 % - 2,530.00 - 2,530.00 0.00
### -
3 PIPING (LAGGING) RMT 12,053.00 5,000.00 41.48 % 3,110.00 25.80 % 865.00 4,135.00 - 4135.00 7,918.00 250.00 HEAVY RAIN
4 PIPING (CLADDING) RMT 12,053.00 5,000.00 41.48 % 2,465.00 20.45 % 1,830.00 3,120.00 50.00 3,170.00 8,883.00 130.00 HEAVY RAIN
6 REFORMER PACKAGE (LAGGING) RMT 2,000.00 2,000.00 100.00 % 1,435.00 505.00 1495.00 0.00 1495.00 505.00 20.00 HEAVY RAIN
7 REFORMER PACKAGE (CLADDING) RMT 2,000.00 2,000.00 100.00 % 1,180.00 700.00 1260.00 40.00 1,300.00 800.00 20.00 HEAVY RAIN
CHOPSAW MACHINE 1
Page 1 of 1