Professional Documents
Culture Documents
Environmental Impact Assessment & Management
Environmental Impact Assessment & Management
CHAPTER 10
The main aim of the EIA study is to establish present environmental conditions
along the proposed metro corridors; predict the impacts on relevant
environmental attributes due to the construction and operation of the proposed
project and recommend adequate mitigation measures to minimize/reduce
adverse impacts. The different components of environment in which changes are
likely to occur include water, land, air, ecology, noise, socio-economic issues, etc.
Majority of data on water quality, vegetation, air and noise quality was collected
during field studies in May 2008.
The city lies near the convergence point of rivers Mula and Mutha. The
northwestern outskirts of Pune’s urban area serve as the crossway for two other
rivers, namely Pavana and Indrayani. The Bhima River also flows from the north-
western part about 8-9 km away from the main city.
The topography of the city is hilly and uneven. Pune is located 560m (1,837 ft)
above sea level on the western margin of the Deccan plateau. It is a relatively
hilly city, with its tallest hill rising to 800m (2,625 ft) above sea level. Situating on
the leeward side of the Sahyadri mountain range (the Western Ghats), which
separate it from the Arabian sea parts of Sahyadri Hills are spread from West to
South of the city. Pune is approximately 50 km from the Western Ghats and 100
km to the east of the Konkan i.e. the west coast.
The altitude of the city is variable from west to east and north to centre and
centre to south. The lowest altitude is 547m above MSL found in the eastern part
the highest is more than 820m in the southern part. In the northern area of the
city the altitude is 559m to 755m above MSL and in the western part the altitude
is rising to more than 750 m above MSL. The central part i.e the main part of the
has the altitude within 549-600m above MSL
average meteorological condition prevailing at the project route is given in table
10.1
Table 10.1: Meteorological Data (IMD)
Table 9.1: Average Meteorological Conditions of 30 yrs data-(1951-1980) of Pune
IMD from March-May,2008
Parameters Maximum Minimum
Temperature (˚C) 38.1 16.5
Relative Humidity (%) 58 21
Wind Speed (kmph) 10.2 5.7
Wind Direction Predominant wind direction are W and NW
Rainfall (mm) 721.7
Source: Climatological Tables 1951-1980, IMD
The water environment refers to the surface and ground water characteristics in
the study area. Following section describes the different hydrological
characteristics of surface water and groundwater depth or level below the
ground level. Water analysis was done for the physico-chemical and biological
as per norms. For the groundwater, samples are being collected from the hand
pumps and tested in the laboratories
The groundwater table of the Pune city as collected from the ESR
(Environmental Status Report) of PMC (Pune Municipal Corporation) is
mentioned in Table 10.2
Ground water samples from 4 representative areas were taken from sources near
the alignments and described in Table 10.3.
Drinking water
Khadki station
Kunbi sahkari
Bharat petrol
Shivaji nagar
pump ( karve
Ashoka mall
Agricultural
(durbankar)
Sr.
Desirable
Parameters
No
college
Limit)
road)
Bank
units
Drinking water
Khadki station
Kunbi sahkari
Bharat petrol
Shivaji nagar
pump ( karve
Ashoka mall
Agricultural
(durbankar)
Sr.
Desirable
Parameters
No
college
Limit)
road)
Bank
units
17 Cyanide BD
BDL BDL BDL BDL BDL 0.05
mg/l L
18 Aluminium BD
BDL BDL BDL BDL BDL 0.03
mg/l L
19 Arsenic BD
BDL BDL BDL BDL BDL 0.05
mg/l L
20 Cadmium BD
BDL BDL BDL BDL BDL 0.01
mg/l L
+6
21 Chromium as Cr BD
BDL BDL BDL BDL BDL 0.05
mg/l L
22 Iron 0.1
0.7 0.1 0.16 0.17 0.2 0.3
mg/l 5
23 Copper BD
BDL BDL BDL BDL BDL 0.05
mg/l L
24 Lead BD
BDL BDL BDL BDL BDL 0.05
mg/l L
25 Manganese BD
BDL BDL BDL BDL BDL 0.1
mg/l L
26 Mercury BD
BDL BDL BDL BDL BDL 0.001
mg/l L
27 Zinc mg/l 1 BDL 0.5 1 0.6 0.7 5
Source: Field Monitoring, Note: Units of all the parameters are mg/l except pH,
Colour and Turbidity Water
The quality of the well water was inferred in comparison with the National
Standards of Drinking Water Quality (IS: 10500, 1992). All the well water
samples were colourless, odourless and with agreeable taste. One sample had
high turbidity and the samples showed well-balanced pH. The chemical
characteristics such as total hardness, chlorides, dissolved solids, sulphates and
nitrates were within limits. Among the metals analyzed iron, copper, zinc,
chromium, magnesium, cadmium, selenium, mercury and arsenic were not
detected or were within stipulated limits.
The source of surface water of Pune is the Mula and Mutha river. The water has
been collected from this river at different locations. Table 10.4
describes the Surface water quality of the Pune City as analysed from the
samples taken from Mula-Mutha River.
Sangam Bridge
GarwareBridge
Desirable limit
(Mula -Mutha)
Bund Garden
(Mutha river)
(Mutha river)
(Mula river)
Vitthalwadi
S. No. Parameters Unit
Light Light Light
1 Colour Hazan Brownish darkish darkish greyish 5
Objection Objectio Objectio Objectio
2 Odour - able nable nable nable U/O
3 Turbidity NTU 26 32 30 28 5
7.50 7.35 7.30 7.40 6.5-
4 pH -- 8.5
5 Conductivity uS/cm 550 640 690 460 -
Total Dissolve Solids
6 sum mg/l 360 448 476 325
7 Alkalinity as CaCO3 mg/l 140 165 173 115 200
Total Hardness as
8 CaCo3 mg/l 162 188 195 113 300
9 Calcium as Ca mg/l 35 52 60 27 75
10 Magnesium as Mg mg/l 18 14 11 11 30
11 Sodium mg/l 29.0 45.0 52.0 21.0 _
12 Potassium mg/l 8.0 11.0 9.0 11.0 _
13 Bicarbonate mg/l 171 201 211 140 _
14 Chloride as Cl mg/l 43 67 58 35 250
15 Sulphate as SO4 mg/l 35 42 47 23 200
16 Nitrate as NO3 mg/l 3.5 11.4 14 3 45
17 Fluorides as F mg/l 0.2 0.4 0.5 0.3 1
Phenolic compound as 0.0
18 C6H5OH mg/l BDL BDL BDL BDL 01
0.0
19 Cyanide mg/l BDL BDL BDL BDL 5
0.0
20 Aluminium mg/l BDL BDL BDL BDL 3
0.0
21 Arsenic mg/l BDL BDL BDL BDL 5
Sangam Bridge
GarwareBridge
Desirable limit
(Mula -Mutha)
Bund Garden
(Mutha river)
(Mutha river)
(Mula river)
Vitthalwadi
Unit
S. No. Parameters
0.0
22 Cadmium mg/l BDL BDL BDL BDL 1
0.0
23 Chromium as Cr+6 mg/l BDL 0.02 0.035 BDL 5
24 Iron mg/l 0.25 0.6 0.48 0.05 0.3
0.0
25 Copper mg/l BDL BDL BDL 0.02 5
0.0
26 Lead mg/l BDL BDL BDL BDL 5
27 Manganese mg/l BDL BDL BDL BDL 0.1
0.0
28 Mercury mg/l BDL BDL BDL BDL 01
29 Zinc mg/l 0.4 1.6 1.5 0.8 5
30 DO mg/l 1.2 0.6 0.5 2.5 _
31 COD mg/l 21 35 42 16 _
32 BOD mg/l 12 12 15 5 _
Almost the entire morphological strata of the city comprises of stratified trap, beds
of basalt and amygdaloid alternate, whose upper and lower planes are strikingly
parallel to each other. Barometric measurements and the course of the rivers
show a fall in level to the east, and Southeast.
However, soil samples were collected and analyzed and the results are
presented in Table 10.5 and 10.6. It is observed that the soil of the project area is
sandy loamy to clayey loam in texture and dark grey to dark brown in colour.
Total Kjeldahl
10 Nitrogen (%) 0.015 0.028 0.034 0.038 0.022
kg/ha
11 Phosphorus 28 42 70 48 40
Kg /haas
K%
The proposed corridors do not pass through any reserve/protected forest in its
entire length. Moreover, no forests are found in its indirect impact zone as well
(7km radius). However, significant amounts of road side vegetation are observed
in 20 m band of metro corridor. There are over 2500 trees along the project site.
The main trees which were found on the site are, Eucalyptus, Sisham, Toot,
Arjun, Neem, Pipal, Banyan, Baigad, Kassod. Copper pod (Peltophorum
ferruginum), Gulmohar (Delonix regia), Silver Oak (Grevillea robusta ), Bottle
palm (Roystonea regia), Asoka (Polyalthia longifolia var. pendula) Fountain tulip
(Spathodea companulata) Sayami Cassia (Cassia siamea) Neelmohor
(Jacaranda mimisaefolia) and Cork (Millingtonia hortensis), & Mangnifera indica.
As part of the study, ambient air quality monitoring has been carried out by
setting up ambient air quality monitoring stations at 8 locations for the parameters
SPM, RPM, SO2 and NOx. The ambient air quality stations were selected taking
into the view of traffic flow and strategic locations on the proposed metro rail
route. Sampling was done during May 2008 at the 5 locations along the
proposed alignment. The sampling locations are given in Table 10.7.
With respect to pollutants the results of the monitoring program indicate the following:
Levels of SPM are high and exceed NAAQS. SPM levels exceeded the NAAQS
(Annual Average) in residential areas whereas in industrial areas they were within
the NAAQS (Annual Average).
Levels of RSPM are well within the limits of NAAQS.
Levels of SO2 are well within the prescribed limits of NAAQS at all receptors.
Levels of NOX are also within prescribed limit at some receptors, while at some
places like Swargate and Nalstop the values are slightly high.
10.7 SEISMICITY
The City spans over an area of 146 square kilometres with around 40 per cent of
area under greenery. Pune lies in the seismically active zone of Koyna Region,
which is about 100 km south of the city. Pune has experienced some moderate-
intensity and many low-intensity earthquakes.
The noise levels were measured at 7 locations along the project alignment at 1.0
km away from the source as per standard practice. The noise level ranges are
summarized in Table 10.9. It could be concluded that the noise levels recorded
at various stations are generally higher than the permissible level of 65db (day)
and 55db (night) for commercial areas and 55db (day) and 45db (night) for
residential areas.
Table-10.9: Noise levels at different Location
Day Night
Noise Location L Max L Min Leq L10 L50 L90 L Max L Min Leq L10 L50 L90
Karve road 72 63 68.58 70.5 68 65 65 56 62.02 65 61 57.4
Pimpri – chinchwad 72 61 67.48 70 66.5 63.5 64 54 60.54 64 59 55.4
Swargate 68 62 65.40 67 65.5 63 65 57 61.24 63.6 60.5 57
Nalstop 73 68 70.67 72 70 68 67 61 64.35 67 63.5 61
Khadki railway station 70 62 66.66 69 66 63.5 62 57 60.01 62 59.5 57
Agricultural university 70 62 67.09 69.5 66.5 63 64 58 61.95 64 61.5 58.7
Law college 67 55 62.62 65.5 62 56 62 53 58.33 61.3 57 53.7
10.9 SOCIO-ECONOMICS
From Table 9.9, it can be observed that the gender ratio of the area is low and
stands at 786. This is due the general low gender ratio in Maharashtra and also
the high rate of in-migration to the city of labourers who come alone and leave
their families behind in the villages. The population below 6 years was also found
to be low.
The Literacy rate of the area is quite high and stands at 88.9%. The female
literacy rate of the study area which is 87.73% is lower than the male literacy
rate.
The economy of the city and its local planning area is based mainly on trade and
commerce and on manufacturing industries including hosiery, cycle, sewing
machines, textiles and other industries. Real estates, financial and banking
services also contribute to the economic wellbeing of the city.
All the potentially significant environmental impacts from the project are tabulated
as below in Table 10.11
10.11.1 Land-Use Changes: The align will not have much affect on the landuse of the
city. The alignment contains both elevated and underground section along
the road divider. Some residential and commercial buildings will be affected
situated on the route of the alignment.
10.11.2 Loss of trees: The proposed metro lines are in urban/ city area and will not
pass through any forests.However, due to the proposed metro construction
about 685 mature trees are likely to be lost. With removal of these trees
the process for CO2 conversion will get effected and the losses are reported
below:
The total value of these trees lost is Rs. 8.22lacs as shown in table below.
Total Loss of trees (No.) 685
Average cost of one tree (Rs.) 1200
Total Loss (Rs.) Rs. 8.22 lacs
The main species are Githithi, Babul, Seshum, Neem, Peepal, Keekar, Pilkhan, Kakri,
Chokar, Laspasia, Sahtut, Bargad, Gulmohar, Baikan, Rudrakash, etc.
10.11.3 Displacement of the people: There will be land acquisition only near the
underground stations and places where there will be interchanges. It has
been estimated after preliminary survey that there will be 480 structures
affected due to land acquisition.
10.11.4 Shifting of Utilities and Drainages: There will be shifting of existing water
supply pipelines, electrical lines and sewerage lines. There is surface water
body such as drains and canals joining the Mula and Mutha River cutting the
proposed corridor. Therefore cross drainage works such as bridges, culverts
etc. will be required. Since this will affect construction and project
implementation time schedule/ costs for which necessary planning/ action
needs to be initiated in advance.
The most likely negative impacts related to the construction works are given
below.
10.12.2 Soil Erosion: The vegetation and top soil shall be disturbed during the
construction stage due to excavation and movement of vehicles and
equipment. The spillage of oil from machinery or cement residual from
concrete mixer plants might contaminate the soil if not properly collected and
disposed off.
10.12.3 Solid waste Generation: Problems could arise from dumping of construction
spoils (Concrete, bricks) waste materials (from contractor camps) etc. causing
surface and ground water pollution. However, it is proposed to have mix
concrete directly from batching plant for use at site. Batching plants will be
located away from the site. The other construction material such as steel,
bricks, etc. will be housed in a fenced stored yard. The balance material from
these yards will be removed for use/disposal.
10.12.4 Health Risk at Construction Site: At the project site direct exposure to dust
generation is likely to cause health related impact especially dust related
diseases. This would be minimized by providing suitable respiratory personal
protective equipments (PPE) such as nose mask with suitable filters etc.
10.12.5 Traffic Congestion and Diversion Problems: Most of the roads of the
project area are broad with traffic signals in proper places but in some areas
has congested stretches where traffic movement is very slow and roads are
very narrow. Hence, traffic congestion during the construction phase will be a
major issue.
10.12.6 Water Contamination Problems: Within the vicinity of project site no major /
designated water body except one irrigation canal are present. Also since all
10.12.7 Impact on Air quality: Potential impacts on the air quality during the
construction stage will be due to the fugitive dust and the exhaust gases
generated in and around the construction site.
10.12.8 Impact on Noise Quality: Due to the various construction activities, there will
be short-term noise impacts in the immediate vicinity of the project corridor.
The impact will be felt more in the congested areas where utmost care has to
be taken to reduce noise generation by using acoustic enclosures.
10.12.9 Social Impact: As local labours will be hired from the vicinity of the project
site and shall be utilized for the construction purpose and all the activities
shall be confined to the project site only, hence no adverse social impacts are
envisaged due to the proposed project.
The project may cause the following negative impacts during operation of the
project due to the increase in the number of passengers and trains at the
stations:
10.13.1 Impact on Land Environment: As the metro corridor will pass through some
congested stretches of residential/commercial areas, there would be
increased scope for commercial, industrial and residential development along
the project corridor.
10.13.2 Noise Pollution: The maximum noise level has been estimated as 64 dB(A)
including background noise level as 20 dB(A) inside the Metro Noise level at a
distance of 12.5m, 25m, and 50m from the alignment have been calculated
similarly and these comes out to be 57.2, 54.2 and 45.2 dB(A) respectively.
10.13.3 Impact on Water System: Thus the water demand on one station works out
to be about 11kld, out of them 7.5 kld wastewater will be generated at each
station that will be treated in the treatment plant. In addition, water will be
required for contractor’s camps during construction.
- Employment Opportunities,
- Less Air Pollution,
- Quick Service and Safety,
- Less Fuel Consumption and Carbon Dioxide Reduction
10.14.2 Less Air Pollution: Introduction of Mass Rapid Transport System will reduce
the traffic load on the roads. Many vehicle owners and users of auto-rickshaw
will shift to metro rail as it will be a faster and convenient mode of transport.
Thus reduction of traffic will lead to reduction of automobile emission and
consequently air pollution.
10.14.3 Quick Service and Safety: The metro rail system would be more efficient
and faster as compared to the traditional mode of travel. Also reduction of
congestion will make the roads safer and will reduce the incidence of
accidents.
10.14.4 Less Fuel Consumption: Reduction of cars and other forms of personal
vehicles will help in reduction of fuel consumption in the city.
Operation Phase
Land-use & • Change of land use by squatter/ • Planning agencies and Collector/
Encroachment encroachment within ROW and Revenue Officer will be made involved
induced development outside the for controlled development and
ROW. prohibiting squatter/ encroachment within
ROW.
Drainage • Filthy environment due to improper • Drainage system will be properly
maintenance of drainage. maintained.
Air quality • The proposed project will provide a
reduced vehicular emission load
atmosphere
Noise level • Noise pollution due to operation • Regular monitoring of noise level at
phase of proposed Metro rail specified locations will be conducted.
corridor
Access • The proposed corridor will help to
increase the accessibility of the
project site
Road safety • Less vehicular movement will result • Road signs, road markings, kerb
to less accidental scenario paintings and road furniture like
overhead gantry signs, roadway
delineators etc. will be provided.
• Adequate illumination will be provided at
interchange locations
• Periodical inspection of the corridor will
be conducted to detect anomalies in
pavement.
e) Water supply and sanitation: The public health facilities such as water
supply sanitation and toilets are much needed at project location. Water
year after the completion of the project. Monitoring shall be carried out at
least four times a year to cover seasonal variations. The parameters for
monitoring will be pH, total dissolved solids, chlorides, nitrates,
sulphates, total suspended solids, calcium, iron, fluoride, total alkalinity,
oil and grease, etc. Locations for monitoring can be decided after the
construction phase. The cost of water quality analysis for four locations
works out to be Rs 4.00 lakhs.
b) Air quality and noise level: Ambient air quality and noise level should
be monitored one year before the construction, during the construction
phase, and for one year after the completion of the project. The
proposed monitoring program for field monitoring and laboratory analysis
of air and noise is given in Table 24. The cost of ambient air quality and
noise level monitoring works out to be Rs 15.20 lakhs.