Professional Documents
Culture Documents
Executive Summary: Control Act of 1990
Executive Summary: Control Act of 1990
A. Introduction
B. Financial Highlights
The EMB’s financial position, performance and sources and application of funds
for CY 2015 are as follows:
Amount
Particulars
2015 2014
A. Financial Position
Assets P 2,149,709,936.83 P1,765,503,116.30
Amount
Particulars
2015 2014
Liabilities 169,958,179.61 103,947,283.89
Net Assets/Equity P 1,979,751,757.22 P1,661,555,832.41
B. Financial Performance
Revenue P 178,971,991.37 P 366,995,781.38
Net Financial Assistance/Subsidy 1,138,609,584.26 1,401,477,036.56
Gains 1,084,518.30 1,874,704.94
Total 1,318,666,093.93 1,770,347,522.88
Less: Current Operating Expenses 905,753,169.41 886,526,830.47
Losses 861,517.16 5,597,400.66
Surplus (Deficit) for the Period P 412,051,407.36 P 878,223,291.75
C. Sources and Application of Funds
Allotments P 1,211,331,369.25 P1,435,934,170.43
Obligation Incurred 1,158,398,170.52 1,425,945,644.64
Unobligated Balance P 52,933,198.73 P 9,988,525.79
The audit covered the accounts, financial transactions and operations of the EMB
for CY 2015. It was conducted to (a) ascertain the level of assurance that may be placed
on management’s assertions on the financial statements; (b) determine the propriety of
transactions as well as the extent of compliance with laws, rules and regulations;
(c) recommend agency improvement opportunities; and (d) determine the extent of
implementation of prior years’ audit recommendations.
A Value for Money (VFM) Audit was also conducted to assess EMB’s efficiency
on the implementation of the Air Quality Monitoring Project and Solid Waste
Management.
The consolidated financial statements are the combined financial statements of the
EMB-CO and 16 regional offices. Part II of this report are the observations and
recommendations pertaining to EMB-CO and regional offices, except Regions 4B, 7, 9
and 13 whose audit report were not yet received.
ii
E. Other Significant Observations and Recommendations
1. The goal to achieve cleaner, safer and healthier environment by reducing the water
pollution through the Adopt-an-Estero/Water Body Program has not yet been
attained for the past five years in the NCR, Regions 3, 6 and 11 due to: (a) non-
abatement of the dumping of domestic wastes and that only 10 percent of the total
water body in Metro Manila was adopted as of December 31, 2015; (b) the terms
and conditions of the MOA are not fully observed; (c) non-involvement of the
residents in the management of the estero; and (d) low enforcement of ordinance on
solid waste management in the barangay level. (Observation No. 1)
b. require the donor-partners to fully comply with all the undertakings, terms and
conditions of the MOA (Region 3);
c. include the LGUs among the parties to the MOA to enlist the
cooperation/involvement of the concerned residents in the clean-up drive
(Regions 3 and 6);
We recommended and the Director agreed to require the concerned officers of:
a. EMB-Region 8 to continuously communicate with DPWH to fast track the
implementation/execution of the project;
iii
b. EMB-Region 11 to (i) require the contractor to expedite the completion of the
laboratory and office building; (ii) determine possible overruns in the construction days
and if warranted, demand for liquidated damages from the contractor for the delay in
the construction; (iii) determine the persons responsible for the delays that have caused
possible losses of government funds and take appropriate action against them; and
(iv) inform EMB-CO on the status of the idle/unutilized equipment delivered to them
for possible redistribution to other EMB ROs which might be needing them or could
utilize them;
d. EMB-CO to stop the practice of procuring equipment not requested by its regional
offices instead inquire first on the equipment requirements of its regional offices before
procurement.
3. DOAS worth P10 million installed in Region 2 does not generate real-time
information thereby not achieving its objective. Furthermore, due to the damage on
light source the equipment cannot produce data on other gases for almost a year,
hence, the maximum benefits from the equipment could not be derived.
(Observation No. 3)
4. Trust receipts, dormant bank accounts, interest income, trust receipts and other
collections in the total amount of P1.329 million were not remitted to the National
Treasury. (Observation No. 4)
We recommended and the Director agreed to instruct the Chief Accountant to cause
the immediate remittance of all unnecessary special and trust funds, interest earned,
trust receipts and other collections to the National Treasury.
We recommended and the Director agreed to (a) require the implementing agencies
to fast track the implementation/execution of the project and settle immediately the
outstanding balance, otherwise, the said fund transfers will be suspended in audit;
(b) require the concerned Accountant to exert efforts in reconciling the balances
with the concerned implementing agencies based on the Fund Utilization Report
submitted; and (c) strictly observe the rules and regulations on the granting,
utilization and accounting of fund transfer granted to implementing agencies.
iv
6. Long delays in the deliveries/liquidation of advances to PS-DBM for the
procurement of office supplies and PPE amounting to P626.671 million resulted in
the accumulation of idle funds and delay in the utilization of office supplies and
PPE for their intended use. (Observation No. 6)