Professional Documents
Culture Documents
Standard Format For PR For OC Mine
Standard Format For PR For OC Mine
Standard Format For PR For OC Mine
VOLUME-I
CONTENTS / INDEX
- SUMMARISED DATA
- EXECUTIVE SUMMARY
BRIEF OF CHAPTERS : Paragraphs of Chapters in Volume II
Executive Summary will contain one to two paragraphs addressing salient
details (all relevant technical, environmental & financial data) each of every
chapter. The number of paragraphs will have one to one correspondence with
the numbering of chapters.
VOLUME-II
CONTENTS
- TEXT:
Chapter-I (Introduction),
Chapter-II (Marketability & Justification),
Chapter-III (Project Site Information),
Chapter-IV (Geology and Deposit Appraisal),
Chapter-V (Mine Boundary, Reserves & Mine Life),
Chapter-VI (Method of Mining),
Chapter-VII (Mining & Dumping Strategy),
Chapter-VIII (Mining Schedule & Equipment Phasing),
Chapter-IX (Coal Quality),
Chapter-X (Pumping & Drainage),
Chapter-XI (Coal Handling & Despatch Arrangement),
Chapter-XII (Workshop, Store and Magazine),
Chapter-XIII (Power Supply, Illumination & Communication),
Chapter-XIV (Civil Construction),
Chapter-XV (Safety and Conservation),
Chapter-XVI (Environment Management),
Chapter-XVII (Land Requirement),
Chapter-XVIII (Mine Closure Planning),
Chapter-XIX (Manpower, Productivity & Training),
Chapter-XX (Project Implementation Schedule),
Chapter-XXI (Financial Evaluation),
Chapter-XXII (A Chapter on Outsourcing)
- APPENDICES
- ANNEXURES
VOLUME-III
2
B. GEOLOGICAL
1 Name of geological blocks considered Name
2 Area of the geological blocks sq. km
3 Borehole Density within blocks BHs / sq.km
4 Description of all coal seams within block
Stratigraphic Thickness (m) No. of Geological Remarks
Sequence Min. Max. borehole Reserves (Mt)
intersections
Seam
Parting
Seam
TOTAL
C. TECHNICAL
1 Area of the proposed mine block (with sq. km
break-up of different geological blocks)
2 Borehole density within mine area BHs/sq. km
3 Mine parameters (seam-wise)
Extent along strike (min. – max.) km
Extent along dip (min.-max.) km
4 Description of coal seams proposed to be
worked along with the parting details
Name Thickness range Av. Av. Av. Depth Mineable Volume of
of considered Thickness / Grade gradient range Reserves OB (Mcum)
seam (m) Parting (UHV/ (1 in …) (m) (Mt)
Thickness GCV)
(m)
Top
OB
Seam
Parting
Seam
Parting
4
E. FINANCIAL
1 Total Capital Investment Rs. crores
Existing
Additional
Total
2 Specific Investment Rs. / tonne
Total
Additional
Rs./m3
Total
Additional
3 Total Capital Investment on P&M Rs. crores
Existing
Additional
4 Specific Investment on P&M Rs. / tonne
Total
Additional
5 Capital requirement upto target year Rs. crores
6 Year of opening of Revenue account
(from zero date)
7 Earnings per manshift (EMS) Rs.
8 Estimated Cost of Production Rs. / tonne
At 100% production level
At 85% production level
9 Estimated average selling price Rs. / tonne
(at 95% sales realization)
10 Estimated Profit Rs. / tonne
At 100% production level
At 85% production level
11 Financial Internal rate of return (FIRR) %
At 100% production level
At 85% production level
7
VOLUME-II
TEXT
CHAPTER-I INTRODUCTION
2.4 Justification of opening the project based on Marketability (to fulfil the
gap in demand) and/or firm linkage (FSA)
3.1 Location
3.1.1 Broad location of project area in relation to geological block and
coalfield with latitudes and longitudes
3.1.2 Area of the Project in sq. kms.
3.1.3 Limiting boundaries of the projectised area
4.1 Background/Introduction
4.1.1 Different GRs prepared at different period for the blocks under
reference
4.1.2 Block Boundaries
4.1.3 Any other relevant details
(Broad exploration input and findings-whether OC or UG block.
10
Table 4.2 : Sequence and brief description of Coal Seams in the block
4.7 Recommendation
4.7.1 Future exploration requirement, if any
(Mention number of boreholes and likely total meterage)
4.7.2 Suggestion for sectional mining, if advantageous
4.7.3 Utility of coal e.g. Power/Steel/Cement/any other industry
5.1 Introduction
5.2 Pit formulation strategy
5.3 Mine boundaries
Delineation of sectors as per GR, if any.
13
Mineable Reserves
Seamwise details of Mineable reserves (Mt)
Zero Date:
The zero date may be defined as the date of land acquisition (physical
possession), PR and EMP approval and other necessary clearance
whichever is later.
Mine Life:
The mine life for nominal production is ........... years. The break-up is
as under:
Construction period.
Production build-up period.
Production period.
Tapering period.
Total period
5.7 Any further exploration required with total meterage and number of
boreholes to be drilled and area of further drilling
6.1 General
6.2 Geo-mining characteristics
6.2.1 Seam Gradient - Variation, Av. gradient of quarry floor
15
The above information is to be furnished for each section and all combined together in
tabular form as above.
Years Yearwise
Calendar Year
Coal in Mt
Total OB in Mcum
Stripping Ratio (cum/t)
Main Mining Size As per Existing Additional Total
Equipment Approved PR Equipment
Additional
OB
COAL
Replacement
OB
COAL
Total Fleet
OB
COAL
10.1 Introduction:
Following parameters should be covered briefly under this heading-
• Location of the project,
• General topography of the project,
• Planning of pumping and drainage system to be followed during
excavation.
• Rainfall characteristics
• Hydrogeological studies, if any, etc.
10.2 Source of Water:
19
NB: The external dump area will not be considered in the area beyond
excavation because gradient of dump should be opposite of the quarry. Mined
out area will include areas of working benches also.
21
Pumping capacity per day thus worked out as: xxxxx Cum
The Plant & machinery will match with the scope of work. In general
workshop (P&M) will include:
- Item wise and shop wise list of workshop P&M with their cost
and phasing of cost.
- Summary of shop wise capital Investment with phasing.
12.8 Drawings
- Location plan and General layout drawing of workshop and
stores.
- Mention of overall areas, covered areas, paved area, roads,
gates etc.
- Provision of repair bays.
- Separate complex for different functional shops/ workshops.
- Bracket height/ height of different shops.
- Location of washing and fuel delivery station.
- Separate complex for stores with separate entry.
- Common facilities at one place.
- Shop offices at mezzanine floor.
12.9 Magazines
- Capacity and Type of the Magazine
- Locations of the Magazines
- Purpose of the Magazine
25
14.1 General
14.1.1 Life and type of Specification
14.1.2 Nature of Soil
14.1.3 External Services
17.1 General
17.2 Land requirement for proposed excavated area, infrastructure, external
dumping, colony, approach road with break-up of forest land, Govt.
land and tenancy land in each case in tabular form as per MoEF
requirement.
17.3 Status of Land acquisition
20.1 Introduction
20.2 Project Schedule
20.3 Bar Chart of Major activities (PERT Network)
b) Stores Cost:
Stores Cost has been estimated taking into account provision for
Repair & Maintenance, POL, Explosive, Timber/Roof Bolting
and miscellaneous stores cost. The estimated Stores Cost has
been worked out to Rs............/Te.
c) Power Cost:
Estimated Energy Consumption is given in the relevant chapter
for Power Supply. The power cost has been taken as
Rs......./unit. The average power cost per tonne of coal
production works out to Rs............... and Rs........... at 100% and
85% level of operation.
d) Misc. Expenditure:
This cost has been estimated to cover expenditure on Printing &
Stationary, Postage, Telephone, repair & Maintenance of assets
other than P&M, Workshop Workshop Debit, Ins. & Taxes for
vehicles and other repairs and a further provision has been
made for deterioration of coal stock.
e) Administrative Charges:
A provision has been made in total revenue cost estimate for
Administrative charges based on the Adm. Cost per tonne of
coal production as was appearing in the last Annual Report
of .................... Ltd. Total Adm. Cost has been calculated at
100% level and treated as fixed cost. As such for all other
estimated level of operation the absolute Adm. Cost has been
taken as it worked out for 100% level of operation. The Adm.
Cost comes to Rs............/Te.
h) Depreciation:
Straight line method of depreciation has been provided to arrive
at Depreciation cost per tonne of coal production.
21.11 EMS
21.12 Financial IRR -Separate for Departmental and Partial Hiring Options
- Economic IRR – only in case of projects to be approved by Govt.
21.15 Desired Selling Price: Desired selling price to achieve 12% IRR at
100% and 85% level is worked to Rs................. & Rs.................. (To be
given if the project is unable achieve required IRR).
32
22.1 Introduction
22.2 Scope of work proposed to be outsourced
22.3 Scope of work proposed to be done depatmentally
22.4 Annual work load for external agency
22.5 Outsourcing Rates
22.6 Safety aspects for Outsourcing of HEMM
22.7 Project economics
33
LIST OF APPENDICES
LIST OF PLATES
1. Location Plan
2. Topographical / Surface Plan showing important surface infrastructure such as river,
nalla, forest area, power line, villages, surface contours, etc.
3. Geological Plan
4. Lithologs/graphic lithologs of representative boreholes
5. Seam-wise seam folio plans (seam extent and iso-chores)
6. Plan showing Floor contours and Iso-grade lines of coal seams and Iso-pachytes of
parting between seams
7. Final stage quarry plan
8. Elements of Mining System
9. Box cut plan with access trench
10. Intermediate (e.g. 5th year, 10th year, etc.) stage quarry plans showing surface and
bottom of quarry
11. Plan showing Iso-pachytes of Total excavation
12. Quarry/Mining cross-sections
13. Dragline balancing diagram (where applicable)
14. Alignment of dragline cuts (where applicable)
15. Final stage dump plan
16. Surface Layout Plan showing quarry boundary, external dumps, CHP, railway siding,
workshop, stores, colony, etc.
17. Land use plan
18. Post Mining Land use plan
19. Schematic layout of workshop and stores
20. Schematic Single-line diagram showing electrical power distribution
21. Sub-station layout diagram
22. CHP flow diagram (or Key plan of CHP)
23. Schematic layout of railway siding (where applicable)
24. PERT Network
25. Revenue Plan (if available)
26. Any other plans specific to project or choice of planners (as per technology proposed)
*******