Professional Documents
Culture Documents
Sale Estimate
Sale Estimate
Sale Estimate
Location : LOCATION
Duration : CD
CONSTRUCTION BAR CHART SCHEDULE AND S-CURVE
ITEM WEIGHT
SCOPE OF WORKS QUANTITY UNIT UNIT COST TOTAL COST(PHP) WORK DURATION
NO. (In Percent)
A SITE DEVELOPMENT QUARTER 1 QUARTER 2 QUARTER 3
1 MOVING IN 1.00 l.s 150,000.00 150,000.00 #REF! #REF! #REF!
3 Gravel Bedding 45.00 cu.m 2,833.96 127,528.10 #REF! #REF!
4 Reinforced Concrete #REF! cu.m #REF! #REF! #REF! #REF! #REF!
5 Formworks and Scaffoldings 6,000.00 bdft 162.44 974,629.60 #REF! #REF! #REF!
6 DOORS AND WINDOWS 1.00 l.s 287,500.00 287,500.00 #REF! #REF!
7 MASONRY WORKS 201.00 sq.m 1,332.52 267,837.30 #REF! #REF!
8 FINISHES (PLASTERING, TILEWOR 659.00 sq.m 646.65 426,140.55 #REF! #REF!
9 Electrical Works 1.00 l.s 131,000.00 131,000.00 #REF! #REF!
10 METALS and acessories 1.00 l.s 230,000.00 230,000.00 #REF!
11 Plumbing Works 1.00 l.s 115,000.00 115,000.00 #REF! #REF!
MOVING OUT 150,000.00
TOTAL PHP #REF! #REF! 0
WEEKLY PROGRESS TOTAL #REF! #REF! #REF! #REF! #REF!
COMMULATIVE PROGRESS #REF! #REF! #REF! #REF! #REF!
CASH FLOW AND PAYMENT SCHEDULE #REF! #REF! #REF! #REF! #REF!
29,999,999.68
29,909,999.68
150,139.38
Republic of the Philippines
YOUR PROVINCE
YOUR MUNICIPALITY
LOCATION OF PROJECT
BILL OF QUANTITIES
NAME OF PROJECT:
LOCATION:
TOTAL ESTIMATED
ITEM NO. DESCRIPTION % TOTAL QUANTITY UNIT UNIT COST
COST
I MOVING-IN 0.50% 1.00 l.s 150,000.00 150,000.00
II EARTHWORKS, a.)
Excavation 0.22% 212.77 cu.m 309.34 65,818.16
b.) Backfilling 0.22% 551.20 cu.m 119.41 65,818.16
III CONCRETE WORKS 9.62% 419.27 cu.m 6,865.39 2,878,454.09
IV REINFORCING STEEL 18.08% 58,913.36 kls. 91.79 5,407,566.95
FALSEWORKS,(formworks
V 8,000.00 bdft.
and steel scaffoldings)
3.63% 135.54 1,084,324.48
MASONRY
VI sq.m
a.) 6" CHB 0.81% 61.88 3,908.92 241,883.78
b.) 4" CHB 4.93% 2,058.00 sq.m 717.17 1,475,936.45
FINISHES
VII
A.) Plastering 1.65% 4,177.89 sq.m 118.42 494,763.68
B.) Tileworks,
a.) Ground Floor 2.31% 568.77 sq.m 1,213.31 690,092.03
b.) Second Floor 3.56% 899.69 sq.m 1,181.93 1,063,371.75
c.) Stone Works 0.44% 64.98 sq.m 2,044.03 132,820.80
Submitted By:
No. of
Designation No. of days Daily Rate Amount
Person
A. Labor
MOBILIZATION 1 ls 150,000.00
Mixture( 1 : 2 : 4)
Usage Factor
Portland Cement, 40 kgs. Type 1P 9 bags 3,774 275.00 1,037,850.00
Screened Sand 0.5 load 20.96 15,000.00 314,452.50
3/4"Ø Screened Gravel 1 load 41.93 15,000.00 628,905.00
B. Equipment
F. Materials
Usage Factor
PLASTERING(4,177.89 SQ.M)
Portland Cement, 40 kgs. Type 1P bags 803.00 275.00 220,825.00
Screened Sand loads 10.00 14,000.00 140,000.00
360,825.00
TILEWORKS( GROUND FLOOR)(568.77 sq.m)
0.6m x 0.6m Ceramic Floor Tiles pcs 1580 260.00 410,800.00
Portland Cement, Type I bag 136.00 275.00 37,400.00
fine sand cu.m. 13.00 1,000.00 13,000.00
Tile Grout kg 790.00 72.50 57,275.00
518,475.00
TILEWORKS( SECOND FLOOR)(899.69 sq.m)
0.6m x 0.6m Ceramic Floor Tiles pcs 2500 260.00 650,000.00
Portland Cement, Type I bag 215.00 275.00 59,125.00
fine sand cu.m. 20.00 1,000.00 20,000.00
Tile Grout kg 1250.00 72.50 90,625.00
819,750.00
STONE WORKS(64.98 sq.m)
Mangima Stone(0.6m x 0.6m) pcs 181.00 300.00 54,300.00
Portland Cement, Type I bag 16.00 275.00 4,400.00
fine sand cu.m. 10.00 1,000.00 10,000.00
68,700.00
B. Equipment
F. Materials
Usage Factor
Doors Manufactured
Hardware
Different types Door knob and its Hinges 356 units 700.00 249,200.00
Septic Tank, Catch Basin, Manhole and Drainages 1 lot 300,000.00 300,000.00
PPR
G.I Pipe & Polypropylene(PPR) length 241 1,000.00 241,000.00
and Composite Water Line
Fixtures
Waterline and Fixtures W/ COMPLETE INSTALLATIONS sets 86 1,000.00 86,000.00
Steel (904.20sq.m)
primer( red oxide)( 1st coat) gals 46 550.00 25,300.00
topcoat( Quick dry Enamel) gals 73 608.00 44,384.00
Thinner gals 30 239.00 7,170.00
76,854.00
Finish Carpentry and ceiling(1083.61sq.m)
primer( Flatwall Enamel)( 1st coating) gals 55 662.00 36,410.00
Putty( glazing putty) gals 91 590.00 53,690.00
Topcoat(Quick dry Enamel) gals 87 608.00 52,896.00
Thinner gals 47 239.00 11,233.00
Sand paper # 120 pcs 30 30.00 900.00
Paint roller w/ pan(# 9) unit 10 250.00 2,500.00
157,629.00
Masonry(4177.89sq.m)
Neutralizer (Premium Welcoat) gals 12 752.00 9,024.00
Skim Coat bags 523 600.00 313,800.00
Wall Primer( 1st coat) gals 120 681.00 81,720.00
topcoat( Gloss latex) gals 120 730.00 87,600.00
Sand paper # 120 pcs 40 30.00 1,200.00
Paint roller w/ pan(# 9) unit 15 250.00 3,750.00
497,094.00
Electrical Works
a. Pipes
STRUCTURE CABLING
No. of
Designation No. of days Daily Rate Amount
Person
A. Labor
BUILDING PERMIT
L W d S.A
ITEM 804a: Backfilling and Compaction
1. Earth soil (20% Shrinkage Allowance)
Volumeroom(interior)
= 10 x 14 x 0.4
= 15 x 20 x 0.4
13.5 X 0.4
Volumeseptec tank= 13.5 x 0.4
on stock
Vol unit
= 420 cu.m.
= 900 cu.m.
= 40.5 cu.m.
= 20.25 cu.m.
1380.75 cu.m.
Vol unit
= 56.00 cu.m.
= 120.00 cu.m.
5.40
= 5.40 cu.m.
Gross 186.80 cu.m.
Less 1380.75 cu.m.
Net 1193.95 cu.m.
FOUNDATION
FOOTINGS L W D #
F1 2.3 1.9 0.4 17
F2
F3 1.9 1.8 0.4 19
F4
TOTAL VOLUME:
assume: 6m
1 2.79069767442 2
2 -40 -40
3 3.42857142857 3
4 -40 -40
TIE WIRES 1 2 3 4
alignment 361 256 256 0
total ties 6137 7607.296 4096 0
meter/ ties 1841.1 2282.1888 1228.8 0
total kg of ties 34.7377358491 43.0601660377358 23.1849056604 0
SAY(kgs) 35 44 24 0
FOUNDATION
FOUNDATION
STIRRUPS
NET LENGTH = 2(A + B) + 20d
1.08 m
Number of Stirrups( end spans) = {(total length(2D)/spacing 2D) +1} x (# of 2D)
= 9
Number of Stirrups( mid. spans) = {(total clear span(L) - total length of 2D /spacing Mid.) - 1}
= 1087
assume 6m Total Stirrups
Total bar length
367.166666666667 says 368 pcs
Tie Wires
LT x pcs of Stirrups
578067.2
173420.16
3272.07849056604
says 3273 kg
says 130 roll
COLUMNS L W H #
C1 0.4 0.35 5.5 19
C2
C3
C4
TOTAL VOLUME:
LATERA TIES
NET LENGTH (outer) = 2(A + B) + 20d
1.38 m
Number of Ties( end zones) = {(total length(end Z)/spacing stirrups) +1}
= 1046
Number of Ties( mid. spans) = {(total clear hieght(H) - total length of EZ /spacing Mid.) - 1}
-1
assume 6m
Total bar length
174.166666666667 says 175 pcs
Tie Wires
HT x pcs of ties
109202.5
32760.75
618.127358490566
says 619 kg
says 24 roll
MAIN BEAMS
total c.c total 9d 9d
0.08 0.288 0.144 0.016
BEAMS L W D VOLUME
B1 45 0.2 0.4 3.6
B2 0
B3 0
total 3.6
STIRRUPS
NET LENGTH = 2(A + B) + 20d
1.08 m
Number of Stirrups( end spans) = {(total length(2D)/spacing 2D) +1} x (# of 2D)
= 9
Number of Stirrups( mid. spans) = {(total clear span(L) - total length of 2D /spacing Mid.) - 1}
= -21
assume 6m Total Stirrups
Total bar length
86.5 says 87 pcs
Tie Wires
LT x pcs of Stirrups
23355
7006.5
132.198113207547
says 133 kg
says 4 roll
MAIN BEAMS
total c.c total 9d 9d
0.08 0.45 0.225 0.025
STIRRUPS
NET LENGTH = 2(A + B) + 20d
0.88 m
Number of Stirrups( end spans) = {(total length(2D)/spacing 2D) +1} x (# of 2D)
= 7
Number of Stirrups( mid. spans) = {(total clear span(L) - total length of 2D /spacing Mid.) - 1}
= 332.333333333333
assume 6m Total Stirrups
Total bar length
90.5 says 91 pcs
Tie Wires
LT x pcs of Stirrups
36924
11077.2
209.003773584906
says 210 kg
says 8 roll
ASSUME 6m
537.092361111
say 538 pcs of main bars 6 m
tie wire use
224.2068 kg says 225
7.50 roll
TOTAL 1.975
ASSUME 6m
166.666666667
say 167 pcs of main bars 6 m
SEPTIC TANK
L W D N
3 1.5 0.1 2 0.9
2 1.5 0.1 2 0.6
1.5
volume bar dia. TOTAL BARS ( ONE WAY) GRAVEL BEDDING
29.716 16 19
0 16 16
25.992 16 16
0 10
55.708 cu.m TOTAL
29.92
24.92
bags
cu.m
cu.m
0.9 1744.2 kg
bags
cu.m
cu.m
Tie wire
L x pcs of cross bars
1224
367.2
6.92830188679245
says 7 kg
says 0 roll
length 10 bar
0.9 54
0.62 11.16
m
6 m length 10 bar
Total length of 2D
99.2
bags
cu.m
cu.m
length 25 dia bar
of 6m 10mm bar
volume # OF MAIN BARS end zone total # end zone total length (end zones)
14.63 12 1.375 76 104.5
0
0
0
14.63 CU.M
bags
cu.m
cu.m
length of 20 mm dia. bar
Total length of 2D
48
bags
cu.m
cu.m
+ extra bars
157.212
length 16 mm bar
of 6m 10mm bar
Total length of 2D
18
bags
cu.m
cu.m
+ extra bars
135.94
length 25 mm bar
of 6m 10mm bar
GRAVEL BEDDING
SPACING 0
0.125 mm TOTAL 0 cu.m
0.125 mm
0.6 mm 0
CU.M
bags
cu.m
cu.m
main bar dia.
12 mm
6m of 12 mm dia. bar
kg
6m of 12 mm dia. bar
kg
mm
L LENGTH LONGITUDINAL/ CLEAR SPACING + 1
41 of 24 m long
TOTAL LENGTH CROSS SECTIONAL/ CLEAR SPACING + 1
61.5833333333333 of 36.35 m long
102.58333333333 m
VOLUME
0.375
cu.m
bags
cu.m
cu.m
mm
L LENGTH LONGITUDINAL/ CLEAR SPACING + 1
71 of 14 m long
TOTAL LENGTH CROSS SECTIONAL/ CLEAR SPACING + 1
6 of 1m long
77 m
kg
GRAVEL BEDDING
3.7145
0
3.249
0
6.9635 cu.m
ne way) x 2 x #
646
0
608
0
6 m of 16 dia. bar
6 m of 16 dia. bar
6 m of 16 dia. bar
6 m of 10 dia. bar
Spacing Mid.
0.15
m
ties spacing(mid)
0.15
1.2
# of c.c
1
Spacing Mid.
0.15
m
# of c.c
1
Spacing Mid.
0.15
m
m
FORMWORKS AND SCAFFOLDINGS
FORMWORKS(Columns)
FORMULA
P = 2(a + b) + 0.20
P = lateral perimeter
a = shorter side of column total column height
b = longer side of column 197.5
0.20 = constant value
P = 1.9 m perimeter
Area for forms = P x column height x number of columns
= 198.55 sq.m
P = 2(d) + b + 0.10
P = perimeter of two sides form
d = the two sides form total beam length
b = the bottom form 110
0.10 = constant value
GRADE beams
P = 1.1 m Perimeter
Beams
P = 1.7 m Perimeter
Roof Beams
P = 1.1 m Perimeter
TYPES
SCAFFOLDING AND STAGING
LUMBER SIZE
2" x 2"
SCAFFOLDING(COLUMNS) 2" x 3"
2" x 4"
34 kg
12 kg
Total areas
Tied beams
125.07 sq.m
Beams
663.17 sq.m
Roof Beams
359.425 sq.m
399 pcs of plywood 1/2" x 4' x 8'
399 pcs of 2" x 3"
19 kg
68 kg
31 kg
2" x 2"
2" x 2"
2" x 3"
2" x 2"
2" x 3"
145 kg
# of plywood x 29.67
2047.23 bdft. of 2" x 2" lumber
MORTAR
CEMENT USE = NET AREA x 0.522
1074.276
SAND USE = NET AREA x 0.0435
89.523
PLASTERING
CEMENT USE = NET AREA x 0.192
= 395.136
SAND USE = NET AREA x 0.016
32.928
assume: 6m
1469 pcs 6 m length 12mm
SLOPE PROTECTIONS
GROUTED RIPRAP
CLASS B STONE CLASS C MIXTURE
TOTAL AREA(sq.m) L V
0
0
0
216
Sq.m 144
F WALL) x 12.5
725 SAYS 25725 pcs of 4" x 8" x 16"
EA x 0.522 Cement
4.276 bags says 1075 bags Cement
A x 0.0435 sand
.523 cu.m says 90 cu.m sand
EA x 0.192 Cement
5.136 bags says 396 bags Cement
EA x 0.016 Fine sand
.928 cu.m says 33 cu.m Fine sand
AREA METHOD
dia. Bar
0 Total Tiles
PAINTING WORKS
119.4 gals.
Topcoat(PERMACOAT LATEX) 35 sq.m/gallon
119.368285714286 gals.
PAINTING WORKS
10 gals.
PAINT THINNER
2.3 gals.
Topcoat(QUICK DRY ENAMEL) 40 sq.m/gallon
8.75 gals.
PAINTING WORKS
2.85714285714286 gals.
PAINT THINNER
0.7 gals.
Topcoat(QUICK DRY ENAMEL) 40 sq.m/gallon
2.5 gals.
PAINTING WORKS
5.71428571428571 gals.
PAINT THINNER
1.3 gals.
Topcoat(ROOF GUARD) 40 sq.m/gallon
5 gals.
total areas
0
Tile area
0.36
0.36
0.36
STEEL TRUSSES
RAILINGS
D. Ramp Railings
2"Ø x 6m Stainless Steel 14 x 1.22 = 17.08
1 1/2"Ø x 6m Stainless Steel 8.2 x 1.22 = 10.00
total kls 881.7748
Base
12mmplates
thick and Bolts
x 250mm units # of Units
x250mm base plate pcs 7
15.51 16
14.13 15
3.80 4
3.90 4
2.33 3
1.37 2
DETAILED UNIT PRICE ANALYSIS (DUPA)
PROJECT NAME : PROPOSE 2 STOREY RESIDENTIAL BUILDING W/ BASEMENT
LOCATION : P-1, BRGY. VIOLETA, MALAYBALAY CITY
Item No./Description : 803 EXCAVATION
Output per day. : Excavation: cu.m/MD Quantity: 1,100.00
No. Of day/s : day/s Unit: cu.m
Say - day/s
No. of
Designation No. of days Daily Rate Amount
Person
A. Labor
FOREMAN 1 15 -
SKILLED 1 15
HELPER 3 15
Sub - Total for A -
No. of
Name and Capacity No of Units Daily Rate Amount
day/s
B. Equipment
SELF LOADER 1
1CU.M BACKHOE 1
20CU.M DUMP TRUCK( CHINA TYPE) 1
Sub - Total for B -
C. Total (A + B) -
D. Quantity = 1100.00 cu.m.
E. Direct Cost (A+B) -
Name and Specification Unit Quantity Unit Cost Amount
F. Materials
Surplus Common Excavation W/ Clearing and grubbing cu.m 1193.95 230.00 274,608.50
Mixture( 1 : 2 : 4)
Usage Factor
Portland Cement, 40 kgs. Type 1P 9 bags #REF! 250.00 #REF!
Screened Sand 0.5 cu.m #REF! 1,000.00 #REF!
3/4"Ø Screened Gravel 1 cu.m #REF! 1,000.00 #REF!
10mmØ def. bars length 2,581 175.00 451,675.00
16mmØ def. bars length 72 400.00 28,800.00
20mmØ def. bars length 217 750.00 162,750.00
25mmØ def. bars length 393 980.00 385,140.00
Tie wire #18 roll 100 1,700.00 170,000.00
Sub - Total for F #REF!
G. Direct Unit Cost (E + F) #REF!
H. OCM 5% #REF!
I. CP 10% #REF!
J.
K. Total Item Cost (G + H + I + J) #REF!
DETAILED UNIT PRICE ANALYSIS (DUPA)
PROJECT NAME : PROPOSE 2 STOREY RESIDENTIAL BUILDING W/ BASEMENT
LOCATION : P-1, BRGY. VIOLETA, MALAYBALAY CITY
Item No./Description : Formworks and Scaffoldings
Output per day : Quantity: 6,000.00
unit bdft
6" x 8" x 16" CHB standard - Machine made pcs 3,160 18.00 56,880.00
Screened Sand cu.m 20 1,000.00 20,000.00
Portland Cement, 40 kgs. Type 1P bags 132 250.00 33,000.00
#18 G.I tie wire roll 1 1,800.00 1,800.00
12mmØ x 6.0m def. bars length 200 250.00 50,000.00
a. Construction Foreman
b. Mason/Carpenter/Painter
c. Unskilled Laborer
B. Equipment
Usage Factor
100,000.00
G. Direct Unit Cost (E + F) 100,000.00
H. - 5,000.00
I. 10,000.00
J. -
K. Total Unit Cost (G + H + I + J) 115,000.00
CEILING WORKS
Ordinary/Marine 2.88
7 shts
Hardi Flex 2.88
7 shts
Acoustic/Gypsom 0.36
Board(0.6m x 0.6) 50 pcs
Fiber cement Board 0.36 50 pcs
36 scrw/board
ROOFING WORKS
ROOFING SHEETS
Effective WIDTH Effective WIDTH
SIZES OF SHEETS
6'
8'
1.1 0.76
sheets in a row
sheets
bar length bar diameter (mm) bar spacing:
6 10 10 cm
7.5 12 12.5 cm
9 16 15 cm
10.5 20 20 cm
12 25
bar spacing
floor dept 10 cm
0.1 12.5 cm
0.125 15 cm
0.15 20 cm
0.2 25 cm
BAR SPACING
6m: 7.5m: 9m:
3.763 2.937 2.421
3.062 2.381 1.934
2.584 2.004 1.636
1.98 1.528 1.258
6m 7.5m 9m
4.369 3.337 2.772
3.603 2.662 2.245
3.221 2.296 1.921
2.36 1.775 1.461
1.977 1.466 1.217
CHB
VALUE/ SQ.M