PERKIRAAN
NO. JENIS PEKERJAAN DAN KOMPONEN KODE ANALISA SATUAN HARGA SATUAN TOTAL HARGA
KUANTITAS
1 PENGUKURAN DAN PEMASANGAN BOUWPLANK 1.1
UPAH Pekerja Oh 0.7800 Rp 72,000.00 Rp. 56,160.00
Tukang Oh 0.3900 Rp 75,000.00 Rp. 29,250.00
Mandor Oh 0.0390 Rp 80,000.00 Rp. 3,120.00
BAHAN papan m3 0.0550 Rp 500,000.00 Rp. 27,500.00
reng m' 0.1000 Rp 15,000.00 Rp. 1,500.00
ALAT Alat Bantu Ls 0.0000 Rp 8,853.00 Rp. -
JUMLAH Rp. 117,530.00
OVERHEAD+PROFIT 1 % Rp. 1,175.30
TOTAL Rp. 118,705.30
9 MEMBUAT LANTAI KERJA BETON MUTU FC = 7,4 MPA (K100), SLUMP (3-6) CM, W/C 2.5
= 0,97
UPAH Pekerja Oh 0.0120 Rp 72,000.00 Rp. 864.00
Tukang Oh 0.0100 Rp 75,000.00 Rp. 750.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
BAHAN pasir beton kg 820.0000 Rp 250.00 Rp. 205,000.00
Semen (PC) kg 180.0000 Rp 1,200.00 Rp. 216,000.00
Split beton kg 920.0000 Rp 250.00 Rp. 230,000.00
Air ltr 200.0000 Rp 40.00 Rp. 8,000.00
ALAT Alat Bantu Ls 0.0000 Rp 169.40 Rp. -
Readi mix unit 0.0000 Rp - Rp. -
JUMLAH Rp. 660,694.00
OVERHEAD+PROFIT 1 % Rp. 6,606.94
TOTAL Rp. 667,300.94
11 MEMBUAT BETON MUTU FC = 31,2 MPA (K350), SLUMP (12 2) CM, W/C = 0,48 2.7
16 MEMBUAT BETON MUTU FC = 31,2 MPA (K350), SLUMP (12 2) CM, W/C = 0,48 3.1a
25 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1/2 BATU, CAMP. 1 SP 4.7
6PP
UPAH Pekerja Oh 0.3000 Rp 72,000.00 Rp. 21,600.00
Tukang Oh 0.1000 Rp 75,000.00 Rp. 7,500.00
Mandor Oh 0.0150 Rp 80,000.00 Rp. 1,200.00
BAHAN Batu bata bj 72.0000 Rp 550.00 Rp. 39,600.00
Semen (PC) kg 9.6800 Rp 1,200.00 Rp. 11,616.00
Pasir pasang m3 0.0450 Rp 210,000.00 Rp. 9,450.00
ALAT Alat Bantu Ls 0.0000 Rp 3,030.00 Rp. -
JUMLAH Rp. 90,966.00
OVERHEAD+PROFIT 1 % Rp. 909.66
TOTAL Rp. 91,875.66
28 A. MEMBUAT BETON MUTU FC = 19,3 MPA (K225), SLUMP (12 2) CM, W/C = 0,58 5.1a
41 CAT TEMBOK BARU (1 LAPIS PLAMUR, 1 LAPIS CAT DASAR, 2 LAPIS CAT 5.12
PENUTUP
UPAH Pekerja Oh 0.0100 Rp 72,000.00 Rp. 720.00
Tukang cat Oh 0.5000 Rp 75,000.00 Rp. 37,500.00
Mandor Oh 0.0030 Rp 80,000.00 Rp. 240.00
BAHAN Dempul/plamir tembok kg 0.0750 Rp 15,000.00 Rp. 1,125.00
cat dasar tembok kg 0.0750 Rp 35,000.00 Rp. 2,625.00
cat tembok (metrolite) kg 0.1500 Rp 40,000.00 Rp. 6,000.00
ALAT Alat Bantu Ls 0.0000 Rp 3,846.00 Rp. -
JUMLAH Rp. 48,210.00
OVERHEAD+PROFIT 1 % Rp. 482.10
TOTAL Rp. 48,692.10
49 PASANG DINDING BATA MERAH (5X11X22) CM TEBAL 1/2 BATU, CAMP. 1 SP 6PP 6.8
54 MEMBUAT LANTAI KERJA BETON MUTU FC = 7,4 MPA (K100), SLUMP (3-6) CM, W/C 6.13
UPAH Pekerja Oh 0.0120 Rp 72,000.00 Rp. 864.00
Tukang Oh 0.0100 Rp 75,000.00 Rp. 750.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
BAHAN pasir beton kg 820.0000 Rp 250.00 Rp. 205,000.00
Semen (PC) kg 180.0000 Rp 1,200.00 Rp. 216,000.00
Split beton kg 920.0000 Rp 250.00 Rp. 230,000.00
Air ltr 200.0000 Rp 40.00 Rp. 8,000.00
ALAT Alat Bantu Ls 0.0000 Rp 169.40 Rp. -
JUMLAH Rp. 660,694.00
OVERHEAD+PROFIT 1 % Rp. 6,606.94
TOTAL Rp. 667,300.94
68 CAT TEMBOK BARU (1 LAPIS PLAMUR, 1 LAPIS CAT DASAR, 2 LAPIS CAT 6.27
PENUTUP
UPAH Pekerja Oh 0.0100 Rp 72,000.00 Rp. 720.00
Tukang cat Oh 0.5000 Rp 75,000.00 Rp. 37,500.00
Mandor Oh 0.0030 Rp 80,000.00 Rp. 240.00
BAHAN Dempul/plamir tembok kg 0.0750 Rp 15,000.00 Rp. 1,125.00
cat dasar tembok kg 0.0750 Rp 35,000.00 Rp. 2,625.00
cat tembok (metrolite) kg 0.1500 Rp 40,000.00 Rp. 6,000.00
ALAT Alat Bantu Ls 0.0000 Rp 3,846.00 Rp. -
JUMLAH Rp. 48,210.00
OVERHEAD+PROFIT 1 % Rp. 482.10
TOTAL Rp. 48,692.10
76 PASANG DINDING BATA MERAH (5X11X22) CM TEBAL 1/2 BATU, CAMP. 1 SP 6PP 7.8
80 A. MEMBUAT BETON MUTU FC = 19,3 MPA (K225), SLUMP (12 2) CM, W/C = 0,58 8.1a
86 PEMASANGAN RANGKA HOLLOW METAL FURING GALVANIS 0,4 MM, MODUL 60 X 8.7
UPAH Pekerja Oh 0.1100 Rp 72,000.00 Rp. 7,920.00
Tukang Oh 0.0500 Rp 75,000.00 Rp. 3,750.00
Mandor Oh 0.0050 Rp 80,000.00 Rp. 400.00
BAHAN hollow metal furing galvanis 0,4 mm m 1.1000 Rp 6,500.00 Rp. 7,150.00
Paku skrup kg 0.1100 Rp 60,000.00 Rp. 6,600.00
ALAT Alat Bantu Ls 0.0000 Rp 1,207.00 Rp. -
JUMLAH Rp. 25,820.00
OVERHEAD+PROFIT 1 % Rp. 258.20
TOTAL Rp. 26,078.20
95 INSTALASI STOPKONTAK
UPAH Pekerja Oh 0.0500 Rp 72,000.00 Rp. 3,600.00
Tukang Erection Oh 0.0100 Rp 75,000.00 Rp. 750.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
JUMLAH Rp. 4,430.00
OVERHEAD+PROFIT 1 % Rp. 44.30
TOTAL Rp. 4,474.30
101 CAT TEMBOK BARU (1 LAPIS PLAMUR, 1 LAPIS CAT DASAR, 2 LAPIS CAT 8.21
PENUTUP
UPAH Pekerja Oh 0.0100 Rp 72,000.00 Rp. 720.00
Tukang cat Oh 0.5000 Rp 75,000.00 Rp. 37,500.00
Mandor Oh 0.0030 Rp 80,000.00 Rp. 240.00
BAHAN Dempul/plamir tembok kg 0.0750 Rp 15,000.00 Rp. 1,125.00
cat dasar tembok kg 0.0750 Rp 35,000.00 Rp. 2,625.00
cat tembok (metrolite) kg 0.1500 Rp 40,000.00 Rp. 6,000.00
ALAT Alat Bantu Ls 0.0000 Rp 3,846.00 Rp. -
JUMLAH Rp. 48,210.00
OVERHEAD+PROFIT 1 % Rp. 482.10
TOTAL Rp. 48,692.10
110 PASANG DINDING BATA MERAH (5X11X22) CM TEBAL 1/2 BATU, CAMP. 1 SP 6PP 9.8
114 MEMBUAT LANTAI KERJA BETON MUTU FC = 7,4 MPA (K100), SLUMP (3-6) CM, W/C 9.13
= 0,97
UPAH Pekerja Oh 0.0120 Rp 72,000.00 Rp. 864.00
Tukang Oh 0.0100 Rp 75,000.00 Rp. 750.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
BAHAN pasir beton kg 820.0000 Rp 250.00 Rp. 205,000.00
Semen (PC) kg 180.0000 Rp 1,200.00 Rp. 216,000.00
Split beton kg 920.0000 Rp 250.00 Rp. 230,000.00
Air ltr 200.0000 Rp 40.00 Rp. 8,000.00
ALAT Alat Bantu Ls 0.0000 Rp 169.40 Rp. -
JUMLAH Rp. 660,694.00
OVERHEAD+PROFIT 1 % Rp. 6,606.94
TOTAL Rp. 667,300.94
117 CAT TEMBOK BARU (1 LAPIS PLAMUR, 1 LAPIS CAT DASAR, 2 LAPIS CAT 9.16
PENUTUP
UPAH Pekerja Oh 0.0100 Rp 72,000.00 Rp. 720.00
Tukang cat Oh 0.5000 Rp 75,000.00 Rp. 37,500.00
Mandor Oh 0.0030 Rp 80,000.00 Rp. 240.00
JUMLAH Rp. 38,460.00
OVERHEAD+PROFIT 1 % Rp. 384.60
TOTAL Rp. 38,844.60
NOTE:
1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah
kecuali terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN yang dibayar dari kontrak) dan biaya-biaya lainnya.