ANALISA HARGA SATUAN PEKERJAAN

PERKIRAAN
NO. JENIS PEKERJAAN DAN KOMPONEN KODE ANALISA SATUAN HARGA SATUAN TOTAL HARGA
KUANTITAS
1 PENGUKURAN DAN PEMASANGAN BOUWPLANK 1.1
UPAH Pekerja Oh 0.7800 Rp 72,000.00 Rp. 56,160.00
Tukang Oh 0.3900 Rp 75,000.00 Rp. 29,250.00
Mandor Oh 0.0390 Rp 80,000.00 Rp. 3,120.00
BAHAN papan m3 0.0550 Rp 500,000.00 Rp. 27,500.00
reng m' 0.1000 Rp 15,000.00 Rp. 1,500.00
ALAT Alat Bantu Ls 0.0000 Rp 8,853.00 Rp. -
JUMLAH Rp. 117,530.00
OVERHEAD+PROFIT 1 % Rp. 1,175.30
TOTAL Rp. 118,705.30

2 PEMBERSIHAN LAPANGAN 1.2


UPAH Pekerja Oh 0.8000 Rp 72,000.00 Rp. 57,600.00
Mandor Oh 0.0800 Rp 80,000.00 Rp. 6,400.00
ALAT Alat Bantu Ls 0.0000 Rp 6,400.00 Rp. -
JUMLAH Rp. 64,000.00
OVERHEAD+PROFIT 1 % Rp. 640.00
TOTAL Rp. 64,640.00

3 PAPAN NAMA PROYEK 1.3


UPAH Pekerja Oh 0.0000 Rp 72,000.00 Rp. -
Tukang Oh 0.8000 Rp 75,000.00 Rp. 60,000.00
Mandor Oh 0.6000 Rp 80,000.00 Rp. 48,000.00
BAHAN papan m3 0.0600 Rp 500,000.00 Rp. 30,000.00
reng m' 0.1500 Rp 15,000.00 Rp. 2,250.00
ALAT Alat Bantu Ls 0.0000 Rp 10,800.00 Rp. -
JUMLAH Rp. 140,250.00
OVERHEAD+PROFIT 1 % Rp. 1,402.50
TOTAL Rp. 141,652.50

4 PEKERJAAN K-3 1.4


UPAH Pekerja Oh 0.8700 Rp 72,000.00 Rp. 62,640.00
Mandor Oh 0.0870 Rp 80,000.00 Rp. 6,960.00
ALAT Alat Bantu Ls 0.0000 Rp 6,960.00 Rp. -
JUMLAH Rp. 69,600.00
OVERHEAD+PROFIT 1 % Rp. 696.00
TOTAL Rp. 70,296.00

5 GALIAN TANAH 2.1


UPAH Pekerja Oh 0.2000 Rp 72,000.00 Rp. 14,400.00
Tenaga gali tanah/pondasi Oh 0.1200 Rp 72,000.00 Rp. 8,640.00
Mandor Oh 0.0270 Rp 80,000.00 Rp. 2,160.00
ALAT Alat Bantu Ls 0.0000 Rp 2,520.00 Rp. -
JUMLAH Rp. 25,200.00
OVERHEAD+PROFIT 1 % Rp. 252.00
TOTAL Rp. 25,452.00

6 BUANGAN BEKAS GALIAN 2.2 0.5000


UPAH Pekerja Oh 0.0500 Rp 72,000.00 Rp. 3,600.00
Mandor Oh 0.0000 Rp 80,000.00 Rp. -
ALAT Alat Bantu Ls 0.4000 Rp 360.00 Rp. 144.00
Dump Truck unit 0.0000 Rp - Rp. -
JUMLAH Rp. 3,744.00
OVERHEAD+PROFIT 1 % Rp. 37.44
TOTAL Rp. 3,781.44

7 URUGAN TANAH PILIHAN 2.3


UPAH Pekerja Oh 0.1000 Rp 72,000.00 Rp. 7,200.00
Tenaga gali tanah/pondasi Oh 0.0100 Rp 72,000.00 Rp. 720.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
ALAT Alat Bantu Ls 0.0000 Rp 800.00 Rp. -
JUMLAH Rp. 8,000.00
OVERHEAD+PROFIT 1 % Rp. 80.00
TOTAL Rp. 8,080.00

8 PEMADATAN TANAH 2.4


UPAH Pekerja Oh 0.1500 Rp 72,000.00 Rp. 10,800.00
Tukang Oh 0.0500 Rp 75,000.00 Rp. 3,750.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
ALAT Alat Bantu Ls 0.0000 Rp 1,535.00 Rp. -
Stamper unit 1.0000 Rp - Rp. -
JUMLAH Rp. 15,350.00
OVERHEAD+PROFIT 1 % Rp. 153.50
TOTAL Rp. 15,503.50

9 MEMBUAT LANTAI KERJA BETON MUTU FC = 7,4 MPA (K100), SLUMP (3-6) CM, W/C 2.5
= 0,97
UPAH Pekerja Oh 0.0120 Rp 72,000.00 Rp. 864.00
Tukang Oh 0.0100 Rp 75,000.00 Rp. 750.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
BAHAN pasir beton kg 820.0000 Rp 250.00 Rp. 205,000.00
Semen (PC) kg 180.0000 Rp 1,200.00 Rp. 216,000.00
Split beton kg 920.0000 Rp 250.00 Rp. 230,000.00
Air ltr 200.0000 Rp 40.00 Rp. 8,000.00
ALAT Alat Bantu Ls 0.0000 Rp 169.40 Rp. -
Readi mix unit 0.0000 Rp - Rp. -
JUMLAH Rp. 660,694.00
OVERHEAD+PROFIT 1 % Rp. 6,606.94
TOTAL Rp. 667,300.94

10 PLASTIK COR TEBAL 0,5 MM 2.6


UPAH Pekerja Oh 0.0500 Rp 72,000.00 Rp. 3,600.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN Plastik cor m2 1.0000 Rp 2,000.00 Rp. 2,000.00
ALAT Alat Bantu Ls 0.0000 Rp 440.00 Rp. -
JUMLAH Rp. 6,400.00
OVERHEAD+PROFIT 1 % Rp. 64.00
TOTAL Rp. 6,464.00

11 MEMBUAT BETON MUTU FC = 31,2 MPA (K350), SLUMP (12 2) CM, W/C = 0,48 2.7

UPAH Pekerja Oh 0.0120 Rp 72,000.00 Rp. 864.00


Tukang Oh 0.0100 Rp 75,000.00 Rp. 750.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
BAHAN pasir beton kg 580.0000 Rp 250.00 Rp. 145,000.00
Semen (PC) kg 423.0000 Rp 1,200.00 Rp. 507,600.00
Split beton kg 970.0000 Rp 250.00 Rp. 242,500.00
Air ltr 215.0000 Rp 40.00 Rp. 8,600.00
ALAT Alat Bantu Ls 0.0000 Rp 169.40 Rp. -
Readi mix unit 0.0000 Rp - Rp. -
JUMLAH Rp. 905,394.00
OVERHEAD+PROFIT 1 % Rp. 9,053.94
TOTAL Rp. 914,447.94

12 PENULANGAN BESI 2,8


UPAH Pekerja Oh 0.0100 Rp 72,000.00 Rp. 720.00
Tukang besi Oh 0.0100 Rp 75,000.00 Rp. 750.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
BAHAN Besi beton kg 1.0500 Rp 8,300.00 Rp. 8,715.00
Kawat beton / bendrat kg 0.0100 Rp 15,000.00 Rp. 150.00
ALAT Alat Bantu Ls 0.0000 Rp 155.00 Rp. -
JUMLAH Rp. 10,415.00
OVERHEAD+PROFIT 1 % Rp. 104.15
TOTAL Rp. 10,519.15

13 PEMASANGAN WIREMESH M-10 2.9


UPAH Pekerja Oh 0.0100 Rp 72,000.00 Rp. 720.00
Tukang besi Oh 0.0100 Rp 75,000.00 Rp. 750.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
BAHAN Wiremesh m10 kg 1.0500 Rp 9,500.00 Rp. 9,975.00
ALAT Alat Bantu Ls 0.0000 Rp 155.00 Rp. -
JUMLAH Rp. 11,525.00
OVERHEAD+PROFIT 1 % Rp. 115.25
TOTAL Rp. 11,640.25

14 MEMBUAT BEKISTING 2.10


UPAH Pekerja Oh 0.5200 Rp 72,000.00 Rp. 37,440.00
Tukang kayu Oh 0.2600 Rp 75,000.00 Rp. 19,500.00
Mandor Oh 0.0260 Rp 80,000.00 Rp. 2,080.00
BAHAN kayu begesteng m3 0.0450 Rp 500,000.00 Rp. 22,500.00
ALAT Alat Bantu Ls 0.0000 Rp 5,902.00 Rp. -
JUMLAH Rp. 81,520.00
OVERHEAD+PROFIT 1 % Rp. 815.20
TOTAL Rp. 82,335.20

15 JOINT SEALER 2.11


UPAH Pekerja Oh 0.4000 Rp 72,000.00 Rp. 28,800.00
Tukang Oh 0.0200 Rp 75,000.00 Rp. 1,500.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN sealant tube 0.0000 Rp 38,000.00 Rp. -
ALAT Alat Bantu Ls 0.0000 Rp 3,110.00 Rp. -
JUMLAH Rp. 31,100.00
OVERHEAD+PROFIT 1 % Rp. 311.00
TOTAL Rp. 31,411.00

16 MEMBUAT BETON MUTU FC = 31,2 MPA (K350), SLUMP (12 2) CM, W/C = 0,48 3.1a

UPAH Pekerja Oh 0.0120 Rp 72,000.00 Rp. 864.00


Tukang Oh 0.0100 Rp 75,000.00 Rp. 750.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
BAHAN pasir beton kg 580.0000 Rp 250.00 Rp. 145,000.00
Semen (PC) kg 423.0000 Rp 1,200.00 Rp. 507,600.00
Split beton kg 970.0000 Rp 250.00 Rp. 242,500.00
Air ltr 215.0000 Rp 40.00 Rp. 8,600.00
ALAT Alat Bantu Ls 0.0000 Rp 169.40 Rp. -
Readi mix unit 0.0000 Rp - Rp. -
JUMLAH Rp. 905,394.00
OVERHEAD+PROFIT 1 % Rp. 9,053.94
TOTAL Rp. 914,447.94

17 PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIR 3.1b


UPAH Pekerja Oh 0.0700 Rp 72,000.00 Rp. 5,040.00
Tukang besi Oh 0.0700 Rp 75,000.00 Rp. 5,250.00
Mandor Oh 0.1000 Rp 80,000.00 Rp. 8,000.00
BAHAN Besi beton kg 1.0500 Rp 8,300.00 Rp. 8,715.00
Kawat beton / bendrat kg 0.0100 Rp 15,000.00 Rp. 150.00
ALAT Alat Bantu Ls 0.0000 Rp 1,829.00 Rp. -
JUMLAH Rp. 27,155.00
OVERHEAD+PROFIT 1 % Rp. 271.55
TOTAL Rp. 27,426.55

18 MEMBUAT BEKISTING PONDASI 3.1c


UPAH Pekerja Oh 0.5200 Rp 72,000.00 Rp. 37,440.00
Tukang kayu Oh 0.2600 Rp 75,000.00 Rp. 19,500.00
Mandor Oh 0.0260 Rp 80,000.00 Rp. 2,080.00
BAHAN kayu begesteng m3 0.0450 Rp 500,000.00 Rp. 22,500.00
ALAT Alat Bantu Ls 0.0000 Rp 5,902.00 Rp. -
JUMLAH Rp. 81,520.00
OVERHEAD+PROFIT 1 % Rp. 815.20
TOTAL Rp. 82,335.20
19 GALIAN TANAH 4.1
UPAH Pekerja Oh 0.2000 Rp 72,000.00 Rp. 14,400.00
Mandor Oh 0.1200 Rp 80,000.00 Rp. 9,600.00
ALAT Alat Bantu Ls 0.0000 Rp 2,400.00 Rp. -
JUMLAH Rp. 24,000.00
OVERHEAD+PROFIT 1 % Rp. 240.00
TOTAL Rp. 24,240.00

20 PENGURUGAN DENGAN PASIR URUG 4.2


UPAH Pekerja Oh 0.3000 Rp 72,000.00 Rp. 21,600.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN Pasir urug m3 1.2000 Rp 140,000.00 Rp. 168,000.00
ALAT Alat Bantu Ls 0.0000 Rp 2,240.00 Rp. -
JUMLAH Rp. 190,400.00
OVERHEAD+PROFIT 1 % Rp. 1,904.00
TOTAL Rp. 192,304.00

21 PEMASANGAN 1 M3 PONDASI BATU BELAH (HITAM) CAMPURAN 1SP 6PP 4.3


UPAH Pekerja Oh 1.5000 Rp 72,000.00 Rp. 108,000.00
Tukang Oh 0.6000 Rp 75,000.00 Rp. 45,000.00
Mandor Oh 0.0750 Rp 80,000.00 Rp. 6,000.00
BAHAN Pasir pasang m3 0.5440 Rp 210,000.00 Rp. 114,240.00
Semen (PC) kg 136.0000 Rp 1,200.00 Rp. 163,200.00
Batu belah hitam m3 1.2000 Rp 165,000.00 Rp. 198,000.00
ALAT Alat Bantu Ls 0.0000 Rp 15,900.00 Rp. -
JUMLAH Rp. 634,440.00
OVERHEAD+PROFIT 1 % Rp. 6,344.40
TOTAL Rp. 640,784.40

22 MEMBUAT SLOOF BALOK BETON BERTULANG (10 X 15) CM 4.4


UPAH Pekerja Oh 0.1500 Rp 72,000.00 Rp. 10,800.00
Tukang Oh 0.0900 Rp 75,000.00 Rp. 6,750.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN Besi cor kg 3.0000 Rp 8,300.00 Rp. 24,900.00
kayu begesteng m3 0.1600 Rp 500,000.00 Rp. 80,000.00
ALAT Alat Bantu Ls 0.0000 Rp 1,835.00 Rp. -
JUMLAH Rp. 123,250.00
OVERHEAD+PROFIT 1 % Rp. 1,232.50
TOTAL Rp. 124,482.50

23 MEMBUAT KOLOM PRAKTIS BETON BERTULANG (11 X 11) CM 4,5


UPAH Pekerja Oh 0.1500 Rp 72,000.00 Rp. 10,800.00
Tukang Oh 0.0900 Rp 75,000.00 Rp. 6,750.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN Besi cor kg 3.0000 Rp 8,300.00 Rp. 24,900.00
kayu begesteng m3 0.1600 Rp 500,000.00 Rp. 80,000.00
ALAT Alat Bantu Ls 0.0000 Rp 1,835.00 Rp. -
JUMLAH Rp. 123,250.00
OVERHEAD+PROFIT 1 % Rp. 1,232.50
TOTAL Rp. 124,482.50

24 MEMBUAT RING BALOK BETON BERTULANG (10 X 15) CM 4.6


UPAH Pekerja Oh 0.1500 Rp 72,000.00 Rp. 10,800.00
Tukang Oh 0.0900 Rp 75,000.00 Rp. 6,750.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN Besi cor kg 3.0000 Rp 8,300.00 Rp. 24,900.00
kayu begesteng m3 0.1600 Rp 500,000.00 Rp. 80,000.00
ALAT Alat Bantu Ls 0.0000 Rp 1,835.00 Rp. -
JUMLAH Rp. 123,250.00
OVERHEAD+PROFIT 1 % Rp. 1,232.50
TOTAL Rp. 124,482.50

25 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1/2 BATU, CAMP. 1 SP 4.7
6PP
UPAH Pekerja Oh 0.3000 Rp 72,000.00 Rp. 21,600.00
Tukang Oh 0.1000 Rp 75,000.00 Rp. 7,500.00
Mandor Oh 0.0150 Rp 80,000.00 Rp. 1,200.00
BAHAN Batu bata bj 72.0000 Rp 550.00 Rp. 39,600.00
Semen (PC) kg 9.6800 Rp 1,200.00 Rp. 11,616.00
Pasir pasang m3 0.0450 Rp 210,000.00 Rp. 9,450.00
ALAT Alat Bantu Ls 0.0000 Rp 3,030.00 Rp. -
JUMLAH Rp. 90,966.00
OVERHEAD+PROFIT 1 % Rp. 909.66
TOTAL Rp. 91,875.66

26 PEMASANGAN PLESTERAN 1SP 6PP TEBAL 15 MM 4.8


UPAH Pekerja Oh 0.2700 Rp 72,000.00 Rp. 19,440.00
Tukang Oh 0.2000 Rp 75,000.00 Rp. 15,000.00
Mandor Oh 0.0200 Rp 80,000.00 Rp. 1,600.00
BAHAN Semen (PC) kg 6.9300 Rp 1,200.00 Rp. 8,316.00
Pasir pasang m3 0.0400 Rp 210,000.00 Rp. 8,400.00
ALAT Alat Bantu Ls 0.0000 Rp 3,604.00 Rp. -
JUMLAH Rp. 52,756.00
OVERHEAD+PROFIT 1 % Rp. 527.56
TOTAL Rp. 53,283.56

27 PEMASANGAN ACIAN 4.9


UPAH Pekerja Oh 0.3000 Rp 72,000.00 Rp. 21,600.00
Tukang Oh 0.1400 Rp 75,000.00 Rp. 10,500.00
Mandor Oh 0.0080 Rp 80,000.00 Rp. 640.00
BAHAN Semen (PC) kg 3.2500 Rp 1,200.00 Rp. 3,900.00
ALAT Alat Bantu Ls 0.0000 Rp 3,274.00 Rp. -
JUMLAH Rp. 36,640.00
OVERHEAD+PROFIT 1 % Rp. 366.40
TOTAL Rp. 37,006.40

28 A. MEMBUAT BETON MUTU FC = 19,3 MPA (K225), SLUMP (12 2) CM, W/C = 0,58 5.1a

UPAH Pekerja Oh 0.0120 Rp 72,000.00 Rp. 864.00


Tukang Oh 0.0100 Rp 75,000.00 Rp. 750.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
BAHAN pasir beton kg 540.0000 Rp 250.00 Rp. 135,000.00
Semen (PC) kg 423.0000 Rp 1,200.00 Rp. 507,600.00
Split beton kg 940.0000 Rp 250.00 Rp. 235,000.00
Air ltr 215.0000 Rp 40.00 Rp. 8,600.00
ALAT Alat Bantu Ls 0.0000 Rp 169.40 Rp. -
Readi mix unit 0.0000 Rp - Rp. -
JUMLAH Rp. 887,894.00
OVERHEAD+PROFIT 1 % Rp. 8,878.94
TOTAL Rp. 896,772.94

29 B. PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIR 5.1b


UPAH Pekerja Oh 0.0100 Rp 72,000.00 Rp. 720.00
Tukang besi Oh 0.0100 Rp 75,000.00 Rp. 750.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
BAHAN Besi beton kg 1.0500 Rp 8,300.00 Rp. 8,715.00
Kawat beton / bendrat kg 0.0100 Rp 15,000.00 Rp. 150.00
ALAT Alat Bantu Ls 0.0000 Rp 155.00 Rp. -
JUMLAH Rp. 10,415.00
OVERHEAD+PROFIT 1 % Rp. 104.15
TOTAL Rp. 10,519.15

30 C. MEMBUAT BEKISTING PONDASI 5.1c


UPAH Pekerja Oh 0.5200 Rp 72,000.00 Rp. 37,440.00
Tukang kayu Oh 0.2600 Rp 75,000.00 Rp. 19,500.00
Mandor Oh 0.0260 Rp 80,000.00 Rp. 2,080.00
BAHAN kayu begesteng m3 0.0450 Rp 500,000.00 Rp. 22,500.00
ALAT Alat Bantu Ls 0.0000 Rp 5,902.00 Rp. -
JUMLAH Rp. 81,520.00
OVERHEAD+PROFIT 1 % Rp. 815.20
TOTAL Rp. 82,335.20

31 BESI PROFIL UNP 100.50.5 5.2


UPAH Pekerja Oh 0.2500 Rp 72,000.00 Rp. 18,000.00
Tukang Las Konstruksi Oh 0.0000 Rp 75,000.00 Rp. -
Mandor Oh 0.0000 Rp 80,000.00 Rp. -
BAHAN Baja UNP kg 0.0000 Rp 9,000.00 Rp. -
JUMLAH Rp. 18,000.00
OVERHEAD+PROFIT 1 % Rp. 180.00
TOTAL Rp. 18,180.00

32 PIPA GIP 4 TEBAL 4,2 MM 5.3


UPAH Pekerja Oh 0.0300 Rp 72,000.00 Rp. 2,160.00
Tukang Oh 0.0600 Rp 75,000.00 Rp. 4,500.00
Mandor Oh 0.0018 Rp 80,000.00 Rp. 144.00
BAHAN galvanis diameter 4" medium A btg 0.1600 Rp 1,300,000.00 Rp. 208,000.00
Perlengkapan 35% Harga Pipa Ls 0.3500
ALAT Alat Bantu Ls 0.0000 Rp 680.40 Rp. -
JUMLAH Rp. 214,804.00
OVERHEAD+PROFIT 1 % Rp. 2,148.04
TOTAL Rp. 216,952.04

33 PIPA GIP 2 TEBAL 2,8 MM


UPAH Pekerja 5.4 Oh 0.0300 Rp 72,000.00 Rp. 2,160.00
Tukang Oh 0.0600 Rp 75,000.00 Rp. 4,500.00
Mandor Oh 0.0018 Rp 80,000.00 Rp. 144.00
BAHAN galvanis diameter 2" medium B btg 0.1600 Rp 400,000.00 Rp. 64,000.00
Perlengkapan 35% Harga Pipa Ls 0.3500
ALAT Alat Bantu Ls 0.0000 Rp 680.40 Rp. -
JUMLAH Rp. 70,804.00
OVERHEAD+PROFIT 1 % Rp. 708.04
TOTAL Rp. 71,512.04

34 PIPA GIP 1 TEBAL 2,8 MM 5.5


UPAH Pekerja Oh 0.0300 Rp 72,000.00 Rp. 2,160.00
Tukang Oh 0.0600 Rp 75,000.00 Rp. 4,500.00
Mandor Oh 0.0018 Rp 80,000.00 Rp. 144.00
BAHAN galvanis diameter 1" medium B btg 0.1600 Rp 350,000.00 Rp. 56,000.00
Perlengkapan 35% Harga Pipa Ls 0.3500
ALAT Alat Bantu Ls 0.0000 Rp 680.40 Rp. -
JUMLAH Rp. 62,804.00
OVERHEAD+PROFIT 1 % Rp. 628.04
TOTAL Rp. 63,432.04

35 TALI TAMBANG PLASTIK 5.6


UPAH Pekerja Oh 0.0050 Rp 72,000.00 Rp. 360.00
Mandor Oh 0.0000 Rp 80,000.00 Rp. -
BAHAN Tali tambang plastik m 0.0451 Rp 5,000.00 Rp. 225.69
ALAT Alat Bantu Ls 0.0000 Rp 36.00 Rp. -
JUMLAH Rp. 585.69
OVERHEAD+PROFIT 1 % Rp. 5.86
TOTAL Rp. 591.55

36 BAUT PANJANG PANJANG 30 CM 5.7


UPAH Tukang Oh 0.0020 Rp 75,000.00 Rp. 150.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
BAHAN Baut 30cm bj 1.0000 Rp 12,000.00 Rp. 12,000.00
ALAT Alat Bantu Ls 0.0000 Rp 23.00 Rp. -
JUMLAH Rp. 12,230.00
OVERHEAD+PROFIT 1 % Rp. 122.30
TOTAL Rp. 12,352.30

37 PEMBUATAN PENGELASAN DENGAN LAS LISTRIK 5.8


UPAH Pekerja Oh 0.0004 Rp 72,000.00 Rp. 28.80
Tukang Las biasa Oh 0.0002 Rp 75,000.00 Rp. 15.00
Mandor Oh 0.0002 Rp 80,000.00 Rp. 16.00
BAHAN Kawat Las kg 0.0400 Rp 35,000.00 Rp. 1,400.00
Solar ltr 0.0300 Rp 9,000.00 Rp. 270.00
ALAT Alat Bantu Ls 0.0000 Rp 5.98 Rp. -
JUMLAH Rp. 1,729.80
OVERHEAD+PROFIT 1 % Rp. 17.30
TOTAL Rp. 1,747.10

38 PEMBERAT BETON+ BESI SIKU 5.9


UPAH Pekerja Oh 0.8250 Rp 72,000.00 Rp. 59,400.00
Tukang Oh 0.1375 Rp 75,000.00 Rp. 10,312.50
Mandor Oh 0.0400 Rp 80,000.00 Rp. 3,200.00
BAHAN pasir beton kg 15.0000 Rp 250.00 Rp. 3,750.00
Semen (PC) kg 85.0000 Rp 1,200.00 Rp. 102,000.00
Split beton kg 23.0000 Rp 250.00 Rp. 5,750.00
Besi Siku m' 15.0000 Rp 18,000.00 Rp. 270,000.00
ALAT Alat Bantu Ls 0.0000 Rp 7,291.25 Rp. -
JUMLAH Rp. 454,412.50
OVERHEAD+PROFIT 1 % Rp. 4,544.13
TOTAL Rp. 458,956.63

39 PEMBUATAN TEMPAT KUNCI DAN GEMBOKNYA 5.10


Tempat Kunci Dan Gembok Ls 1.0000 Rp 99,009.90 Rp. 99,009.90
JUMLAH Rp. 99,009.90
OVERHEAD+PROFIT 1 % Rp. 990.10
TOTAL Rp. 100,000.00

40 PENGECATAN BIDANG BESI 5.11


UPAH Pekerja Oh 0.0200 Rp 72,000.00 Rp. 1,440.00
Tukang cat Oh 0.2000 Rp 75,000.00 Rp. 15,000.00
Mandor Oh 0.0200 Rp 80,000.00 Rp. 1,600.00
BAHAN cat besi kg 0.1000 Rp 60,000.00 Rp. 6,000.00
ALAT Alat Bantu Ls 0.0000 Rp 1,804.00 Rp. -
JUMLAH Rp. 24,040.00
OVERHEAD+PROFIT 1 % Rp. 240.40
TOTAL Rp. 24,280.40

41 CAT TEMBOK BARU (1 LAPIS PLAMUR, 1 LAPIS CAT DASAR, 2 LAPIS CAT 5.12
PENUTUP
UPAH Pekerja Oh 0.0100 Rp 72,000.00 Rp. 720.00
Tukang cat Oh 0.5000 Rp 75,000.00 Rp. 37,500.00
Mandor Oh 0.0030 Rp 80,000.00 Rp. 240.00
BAHAN Dempul/plamir tembok kg 0.0750 Rp 15,000.00 Rp. 1,125.00
cat dasar tembok kg 0.0750 Rp 35,000.00 Rp. 2,625.00
cat tembok (metrolite) kg 0.1500 Rp 40,000.00 Rp. 6,000.00
ALAT Alat Bantu Ls 0.0000 Rp 3,846.00 Rp. -
JUMLAH Rp. 48,210.00
OVERHEAD+PROFIT 1 % Rp. 482.10
TOTAL Rp. 48,692.10

42 GALIAN TANAH 6.1


UPAH Pekerja Oh 0.2000 Rp 72,000.00 Rp. 14,400.00
Tenaga gali tanah/pondasi Oh 0.1200 Rp 72,000.00 Rp. 8,640.00
Mandor Oh 0.0270 Rp 80,000.00 Rp. 2,160.00
ALAT Alat Bantu Ls 0.0000 Rp 2,520.00 Rp. -
JUMLAH Rp. 25,200.00
OVERHEAD+PROFIT 1 % Rp. 252.00
TOTAL Rp. 25,452.00

43 URUGAN KEMBALI GALIAN TANAH BIASA SEDALAM 1 METER 6.2


UPAH Pekerja Oh 0.3000 Rp 72,000.00 Rp. 21,600.00
Tenaga gali tanah/pondasi Oh 0.2000 Rp 72,000.00 Rp. 14,400.00
Mandor Oh 0.0500 Rp 80,000.00 Rp. 4,000.00
ALAT Alat Bantu Ls 0.0000 Rp 4,000.00 Rp. -
JUMLAH Rp. 40,000.00
OVERHEAD+PROFIT 1 % Rp. 400.00
TOTAL Rp. 40,400.00

44 URUGAN PASIR 6.3


UPAH Pekerja Oh 0.0100 Rp 72,000.00 Rp. 720.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN Pasir urug m3 1.0100 Rp 140,000.00 Rp. 141,400.00
ALAT Alat Bantu Ls 0.0000 Rp 152.00 Rp. -
JUMLAH Rp. 142,920.00
OVERHEAD+PROFIT 1 % Rp. 1,429.20
TOTAL Rp. 144,349.20

45 URUGAN TANAH PILIHAN 6.4


UPAH Pekerja Oh 0.1000 Rp 72,000.00 Rp. 7,200.00
Tenaga gali tanah/pondasi Oh 0.0100 Rp 72,000.00 Rp. 720.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
ALAT Alat Bantu Ls 0.0000 Rp 800.00 Rp. -
JUMLAH Rp. 8,000.00
OVERHEAD+PROFIT 1 % Rp. 80.00
TOTAL Rp. 8,080.00

46 PASANG PONDASI BATU BELAH (HITAM) CAMPURAN 1SP 6PP 6.5


UPAH Pekerja Oh 1.5000 Rp 72,000.00 Rp. 108,000.00
Tukang Oh 0.6000 Rp 75,000.00 Rp. 45,000.00
Mandor Oh 0.0750 Rp 80,000.00 Rp. 6,000.00
BAHAN Pasir pasang m3 0.5440 Rp 210,000.00 Rp. 114,240.00
Semen (PC) kg 136.0000 Rp 1,200.00 Rp. 163,200.00
Batu belah hitam m3 1.2000 Rp 165,000.00 Rp. 198,000.00
ALAT Alat Bantu Ls 0.0000 Rp 15,900.00 Rp. -
JUMLAH Rp. 634,440.00
OVERHEAD+PROFIT 1 % Rp. 6,344.40
TOTAL Rp. 640,784.40

47 MEMBUAT SLOOF BALOK BETON BERTULANG (10 X 15) CM 6.6


UPAH Pekerja Oh 0.1500 Rp 72,000.00 Rp. 10,800.00
Tukang Oh 0.0900 Rp 75,000.00 Rp. 6,750.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN Besi cor kg 3.0000 Rp 8,300.00 Rp. 24,900.00
kayu begesteng m3 0.1600 Rp 500,000.00 Rp. 80,000.00
ALAT Alat Bantu Ls 0.0000 Rp 1,835.00 Rp. -
JUMLAH Rp. 123,250.00
OVERHEAD+PROFIT 1 % Rp. 1,232.50
TOTAL Rp. 124,482.50

48 MEMBUAT KOLOM PRAKTIS BETON BERTULANG (11 X 11) CM 6.7


UPAH Pekerja Oh 0.1500 Rp 72,000.00 Rp. 10,800.00
Tukang Oh 0.0900 Rp 75,000.00 Rp. 6,750.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN Besi cor kg 3.0000 Rp 8,300.00 Rp. 24,900.00
kayu begesteng m3 0.1600 Rp 500,000.00 Rp. 80,000.00
ALAT Alat Bantu Ls 0.0000 Rp 1,835.00 Rp. -
JUMLAH Rp. 123,250.00
OVERHEAD+PROFIT 1 % Rp. 1,232.50
TOTAL Rp. 124,482.50

49 PASANG DINDING BATA MERAH (5X11X22) CM TEBAL 1/2 BATU, CAMP. 1 SP 6PP 6.8

UPAH Pekerja Oh 0.3000 Rp 72,000.00 Rp. 21,600.00


Tukang Oh 0.1000 Rp 75,000.00 Rp. 7,500.00
Mandor Oh 0.0150 Rp 80,000.00 Rp. 1,200.00
BAHAN Batu bata bj 72.0000 Rp 550.00 Rp. 39,600.00
Semen (PC) kg 9.6800 Rp 1,200.00 Rp. 11,616.00
Pasir pasang m3 0.0450 Rp 210,000.00 Rp. 9,450.00
ALAT Alat Bantu Ls 0.0000 Rp 3,030.00 Rp. -
JUMLAH Rp. 90,966.00
OVERHEAD+PROFIT 1 % Rp. 909.66
TOTAL Rp. 91,875.66

50 PEMASANGAN PLESTERAN 1SP 6PP TEBAL 15 MM 6.9


UPAH Pekerja Oh 0.2700 Rp 72,000.00 Rp. 19,440.00
Tukang Oh 0.2000 Rp 75,000.00 Rp. 15,000.00
Mandor Oh 0.0200 Rp 80,000.00 Rp. 1,600.00
BAHAN Semen (PC) kg 6.9300 Rp 1,200.00 Rp. 8,316.00
Pasir pasang m3 0.0400 Rp 210,000.00 Rp. 8,400.00
ALAT Alat Bantu Ls 0.0000 Rp 3,604.00 Rp. -
JUMLAH Rp. 52,756.00
OVERHEAD+PROFIT 1 % Rp. 527.56
TOTAL Rp. 53,283.56

51 PEMASANGAN ACIAN 6.10


UPAH Pekerja Oh 0.3000 Rp 72,000.00 Rp. 21,600.00
Tukang Oh 0.1400 Rp 75,000.00 Rp. 10,500.00
Mandor Oh 0.0080 Rp 80,000.00 Rp. 640.00
BAHAN Semen (PC) kg 3.2500 Rp 1,200.00 Rp. 3,900.00
ALAT Alat Bantu Ls 0.0000 Rp 3,274.00 Rp. -
JUMLAH Rp. 36,640.00
OVERHEAD+PROFIT 1 % Rp. 366.40
TOTAL Rp. 37,006.40

52 MEMBUAT RINGBALK BETON BERTULANG (10 X 15) CM 6.11


UPAH Pekerja Oh 0.1500 Rp 72,000.00 Rp. 10,800.00
Tukang Oh 0.0900 Rp 75,000.00 Rp. 6,750.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN Besi cor kg 3.0000 Rp 8,300.00 Rp. 24,900.00
kayu begesteng m3 0.1600 Rp 500,000.00 Rp. 80,000.00
ALAT Alat Bantu Ls 0.0000 Rp 1,835.00 Rp. -
JUMLAH Rp. 123,250.00
OVERHEAD+PROFIT 1 % Rp. 1,232.50
TOTAL Rp. 124,482.50

53 MEMBUAT LATIU BALOK BETON BERTULANG (10 X 15) CM 6.12


UPAH Pekerja Oh 0.1500 Rp 72,000.00 Rp. 10,800.00
Tukang Oh 0.0900 Rp 75,000.00 Rp. 6,750.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN Besi cor kg 3.0000 Rp 8,300.00 Rp. 24,900.00
kayu begesteng m3 0.1600 Rp 500,000.00 Rp. 80,000.00
ALAT Alat Bantu Ls 0.0000 Rp 1,835.00 Rp. -
JUMLAH Rp. 123,250.00
OVERHEAD+PROFIT 1 % Rp. 1,232.50
TOTAL Rp. 124,482.50

54 MEMBUAT LANTAI KERJA BETON MUTU FC = 7,4 MPA (K100), SLUMP (3-6) CM, W/C 6.13
UPAH Pekerja Oh 0.0120 Rp 72,000.00 Rp. 864.00
Tukang Oh 0.0100 Rp 75,000.00 Rp. 750.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
BAHAN pasir beton kg 820.0000 Rp 250.00 Rp. 205,000.00
Semen (PC) kg 180.0000 Rp 1,200.00 Rp. 216,000.00
Split beton kg 920.0000 Rp 250.00 Rp. 230,000.00
Air ltr 200.0000 Rp 40.00 Rp. 8,000.00
ALAT Alat Bantu Ls 0.0000 Rp 169.40 Rp. -
JUMLAH Rp. 660,694.00
OVERHEAD+PROFIT 1 % Rp. 6,606.94
TOTAL Rp. 667,300.94

55 PASANG GORDING CANAL C.100.50.20.2,3 6.14


UPAH Pekerja Oh 0.0600 Rp 72,000.00 Rp. 4,320.00
Tukang Oh 0.0060 Rp 75,000.00 Rp. 450.00
Mandor Oh 0.0030 Rp 80,000.00 Rp. 240.00
BAHAN Baja CNP kg 1.1500 Rp 9,000.00 Rp. 10,350.00
ALAT Alat Bantu Ls 0.0000 Rp 501.00 Rp. -
JUMLAH Rp. 15,360.00
OVERHEAD+PROFIT 1 % Rp. 153.60
TOTAL Rp. 15,513.60

56 PEMASANGAN ATAP GALVALUM TEBAL 0,4 MM 6.15


UPAH Pekerja Oh 0.0200 Rp 72,000.00 Rp. 1,440.00
Tukang Oh 0.0800 Rp 75,000.00 Rp. 6,000.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN Atap galvalum 0,4m m2 1.1000 Rp 80,000.00 Rp. 88,000.00
ALAT Alat Bantu Ls 0.0000 Rp 824.00 Rp. -
JUMLAH Rp. 96,240.00
OVERHEAD+PROFIT 1 % Rp. 962.40
TOTAL Rp. 97,202.40

57 PEMASANGAN LANTAI KERAMIK UKURAN 20CM X 20CM 6.16


UPAH Pekerja Oh 0.7000 Rp 72,000.00 Rp. 50,400.00
Tukang Oh 0.3500 Rp 75,000.00 Rp. 26,250.00
Mandor Oh 0.0350 Rp 80,000.00 Rp. 2,800.00
BAHAN keramik 20x20 cm m2 1.2000 Rp 35,000.00 Rp. 42,000.00
Semen (PC) kg 10.4000 Rp 1,200.00 Rp. 12,480.00
Pasir pasang m3 0.0450 Rp 210,000.00 Rp. 9,450.00
Semen warna kg 1.6200 Rp 2,000.00 Rp. 3,240.00
ALAT Alat Bantu Ls 0.0000 Rp 7,945.00 Rp. -
JUMLAH Rp. 146,620.00
OVERHEAD+PROFIT 1 % Rp. 1,466.20
TOTAL Rp. 148,086.20

58 PEMBUATAN SEPTICTANK + PERESAPAN 6.17


Septictank Ls 1.0000 Rp 4,950,495.05 Rp. 4,950,495.05
Peresapan Ls 1.0000 Rp 437,821.78 Rp. 437,821.78
JUMLAH Rp. 5,388,316.83
OVERHEAD+PROFIT 1 % Rp. 53,883.17
TOTAL Rp. 5,442,200.00

59 PEMASANGAN PINTU PVC KAMAR MANDI 6.18


UPAH Pekerja Oh 0.0400 Rp 72,000.00 Rp. 2,880.00
Tukang Oh 0.4000 Rp 75,000.00 Rp. 30,000.00
Mandor Oh 0.0040 Rp 80,000.00 Rp. 320.00
BAHAN Pintu bahan PVC m2 1.0000 Rp 250,000.00 Rp. 250,000.00
ALAT Alat Bantu Ls 0.0000 Rp 3,320.00 Rp. -
JUMLAH Rp. 283,200.00
OVERHEAD+PROFIT 1 % Rp. 2,832.00
TOTAL Rp. 286,032.00

60 PEMASANGAN CLOOSET JONGKOK PORSLIN 6.19


UPAH Pekerja Oh 1.5000 Rp 72,000.00 Rp. 108,000.00
Tukang Oh 1.5000 Rp 75,000.00 Rp. 112,500.00
Mandor Oh 0.1600 Rp 80,000.00 Rp. 12,800.00
BAHAN Kloset jongkok INA bh 1.0000 Rp 120,000.00 Rp. 120,000.00
Semen (PC) kg 6.0000 Rp 1,200.00 Rp. 7,200.00
Pasir pasang m3 0.0100 Rp 210,000.00 Rp. 2,100.00
ALAT Alat Bantu Ls 0.0000 Rp 23,330.00 Rp. -
JUMLAH Rp. 362,600.00
OVERHEAD+PROFIT 1 % Rp. 3,626.00
TOTAL Rp. 366,226.00

61 PEMASANGAN FLOOR DRAIN 6.20


UPAH Pekerja Oh 0.0100 Rp 72,000.00 Rp. 720.00
Tukang Oh 0.1000 Rp 75,000.00 Rp. 7,500.00
Mandor Oh 0.0060 Rp 80,000.00 Rp. 480.00
BAHAN Floor Drain stainless bh 1.0000 Rp 20,000.00 Rp. 20,000.00
ALAT Alat Bantu Ls 0.0000 Rp 870.00 Rp. -
JUMLAH Rp. 28,700.00
OVERHEAD+PROFIT 1 % Rp. 287.00
TOTAL Rp. 28,987.00

62 PEMASANGAN PIPA PVC TIPE AW DIAMETER 2 6.21


UPAH Pekerja Oh 0.0360 Rp 72,000.00 Rp. 2,592.00
Tukang Oh 0.0600 Rp 75,000.00 Rp. 4,500.00
Mandor Oh 0.0018 Rp 80,000.00 Rp. 144.00
BAHAN PVC 4 m diameter 2" AW btg 0.2700 Rp 60,000.00 Rp. 16,200.00
Perlengkapan 35% Harga Pipa Ls 0.3500 Rp 59,405.94 Rp. 20,792.08
ALAT Alat Bantu Ls 0.0000 Rp 723.60 Rp. -
JUMLAH Rp. 44,228.08
OVERHEAD+PROFIT 1 % Rp. 442.28
TOTAL Rp. 44,670.36

63 PEMASANGAN PIPA PVC TIPE AW DIAMETER 4 6.22


UPAH Pekerja Oh 0.0360 Rp 72,000.00 Rp. 2,592.00
Tukang Oh 0.0600 Rp 75,000.00 Rp. 4,500.00
Mandor Oh 0.0018 Rp 80,000.00 Rp. 144.00
BAHAN PVC 4 m diameter 4" AW btg 0.2600 Rp 170,000.00 Rp. 44,200.00
Perlengkapan 35% Harga Pipa Ls 0.3500 Rp 168,316.83 Rp. 58,910.89
ALAT Alat Bantu Ls 0.0000 Rp 723.60 Rp. -
JUMLAH Rp. 110,346.89
OVERHEAD+PROFIT 1 % Rp. 1,103.47
TOTAL Rp. 111,450.36

64 PEMASANGAN KRAN DIAMETER 1/2 ATAU 3/4 6.23


UPAH Pekerja Oh 0.0100 Rp 72,000.00 Rp. 720.00
Tukang Oh 0.1000 Rp 75,000.00 Rp. 7,500.00
Mandor Oh 0.0050 Rp 80,000.00 Rp. 400.00
BAHAN Kran Air bh 1.0000 Rp 35,000.00 Rp. 35,000.00
seal tape bh 0.0250 Rp 7,000.00 Rp. 175.00
ALAT Alat Bantu Ls 0.0000 Rp 862.00 Rp. -
JUMLAH Rp. 43,795.00
OVERHEAD+PROFIT 1 % Rp. 437.95
TOTAL Rp. 44,232.95

65 PEMASANGAN PIPA PVC TIPE AW DIAMETER 3/4 6.24


UPAH Pekerja Oh 0.0360 Rp 72,000.00 Rp. 2,592.00
Tukang Oh 0.0600 Rp 75,000.00 Rp. 4,500.00
Mandor Oh 0.0018 Rp 80,000.00 Rp. 144.00
BAHAN PVC 4 m diameter 0,75" AW btg 0.2600 Rp 25,000.00 Rp. 6,500.00
Perlengkapan 35% Harga Pipa Ls 0.3500 Rp 24,752.48 Rp. 8,663.37
ALAT Alat Bantu Ls 0.0000 Rp 723.60 Rp. -
JUMLAH Rp. 22,399.37
OVERHEAD+PROFIT 1 % Rp. 223.99
TOTAL Rp. 22,623.36

66 INSTALASI TITIK LAMPU 6.25


UPAH Pekerja Oh 0.0500 Rp 72,000.00 Rp. 3,600.00
Tukang Erection Oh 0.0100 Rp 75,000.00 Rp. 750.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
JUMLAH Rp. 4,430.00
OVERHEAD+PROFIT 1 % Rp. 44.30
TOTAL Rp. 4,474.30

67 PASANG LAMPU SL 9 WATT 6.26


BAHAN Lampu SL 9 m' 1.0000 Rp 40,000.00 Rp. 40,000.00
JUMLAH Rp. 40,000.00
OVERHEAD+PROFIT 1 % Rp. 400.00
TOTAL Rp. 40,400.00

68 CAT TEMBOK BARU (1 LAPIS PLAMUR, 1 LAPIS CAT DASAR, 2 LAPIS CAT 6.27
PENUTUP
UPAH Pekerja Oh 0.0100 Rp 72,000.00 Rp. 720.00
Tukang cat Oh 0.5000 Rp 75,000.00 Rp. 37,500.00
Mandor Oh 0.0030 Rp 80,000.00 Rp. 240.00
BAHAN Dempul/plamir tembok kg 0.0750 Rp 15,000.00 Rp. 1,125.00
cat dasar tembok kg 0.0750 Rp 35,000.00 Rp. 2,625.00
cat tembok (metrolite) kg 0.1500 Rp 40,000.00 Rp. 6,000.00
ALAT Alat Bantu Ls 0.0000 Rp 3,846.00 Rp. -
JUMLAH Rp. 48,210.00
OVERHEAD+PROFIT 1 % Rp. 482.10
TOTAL Rp. 48,692.10

69 GALIAN TANAH 7.1


UPAH Pekerja Oh 0.2000 Rp 72,000.00 Rp. 14,400.00
Tenaga gali tanah/pondasi Oh 0.1200 Rp 72,000.00 Rp. 8,640.00
Mandor Oh 0.0270 Rp 80,000.00 Rp. 2,160.00
ALAT Alat Bantu Ls 0.0000 Rp 2,520.00 Rp. -
JUMLAH Rp. 25,200.00
OVERHEAD+PROFIT 1 % Rp. 252.00
TOTAL Rp. 25,452.00

70 URUGAN KEMBALI GALIAN TANAH BIASA SEDALAM 1 METER 7.2


UPAH Pekerja Oh 0.3000 Rp 72,000.00 Rp. 21,600.00
Tenaga gali tanah/pondasi Oh 0.2000 Rp 72,000.00 Rp. 14,400.00
Mandor Oh 0.0500 Rp 80,000.00 Rp. 4,000.00
ALAT Alat Bantu Ls 0.0000 Rp 4,000.00 Rp. -
JUMLAH Rp. 40,000.00
OVERHEAD+PROFIT 1 % Rp. 400.00
TOTAL Rp. 40,400.00

71 URUGAN PASIR 7.3


UPAH Pekerja Oh 0.0100 Rp 72,000.00 Rp. 720.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN Pasir urug m3 1.0100 Rp 140,000.00 Rp. 141,400.00
ALAT Alat Bantu Ls 0.0000 Rp 152.00 Rp. -
JUMLAH Rp. 142,920.00
OVERHEAD+PROFIT 1 % Rp. 1,429.20
TOTAL Rp. 144,349.20

72 URUGAN TANAH PILIHAN 7.4


UPAH Pekerja Oh 0.1000 Rp 72,000.00 Rp. 7,200.00
Tenaga gali tanah/pondasi Oh 0.0100 Rp 72,000.00 Rp. 720.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
ALAT Alat Bantu Ls 0.0000 Rp 800.00 Rp. -
JUMLAH Rp. 8,000.00
OVERHEAD+PROFIT 1 % Rp. 80.00
TOTAL Rp. 8,080.00

73 PASANG PONDASI BATU BELAH (HITAM) CAMPURAN 1SP 6PP 7.5


UPAH Pekerja Oh 1.5000 Rp 72,000.00 Rp. 108,000.00
Tukang Oh 0.6000 Rp 75,000.00 Rp. 45,000.00
Mandor Oh 0.0750 Rp 80,000.00 Rp. 6,000.00
BAHAN Pasir pasang m3 0.5440 Rp 210,000.00 Rp. 114,240.00
Semen (PC) kg 136.0000 Rp 1,200.00 Rp. 163,200.00
Batu belah hitam m3 1.2000 Rp 165,000.00 Rp. 198,000.00
ALAT Alat Bantu Ls 0.0000 Rp 15,900.00 Rp. -
JUMLAH Rp. 634,440.00
OVERHEAD+PROFIT 1 % Rp. 6,344.40
TOTAL Rp. 640,784.40

74 MEMBUAT SLOOF BALOK BETON BERTULANG (10 X 15) CM 7.6


UPAH Pekerja Oh 0.1500 Rp 72,000.00 Rp. 10,800.00
Tukang Oh 0.0900 Rp 75,000.00 Rp. 6,750.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN Besi cor kg 3.0000 Rp 8,300.00 Rp. 24,900.00
kayu begesteng m3 0.1600 Rp 500,000.00 Rp. 80,000.00
ALAT Alat Bantu Ls 0.0000 Rp 1,835.00 Rp. -
JUMLAH Rp. 123,250.00
OVERHEAD+PROFIT 1 % Rp. 1,232.50
TOTAL Rp. 124,482.50

75 MEMBUAT KOLOM PRAKTIS BETON BERTULANG (11 X 11) CM 7.7


UPAH Pekerja Oh 0.1500 Rp 72,000.00 Rp. 10,800.00
Tukang Oh 0.0900 Rp 75,000.00 Rp. 6,750.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN Besi cor kg 3.0000 Rp 8,300.00 Rp. 24,900.00
kayu begesteng m3 0.1600 Rp 500,000.00 Rp. 80,000.00
ALAT Alat Bantu Ls 0.0000 Rp 1,835.00 Rp. -
JUMLAH Rp. 123,250.00
OVERHEAD+PROFIT 1 % Rp. 1,232.50
TOTAL Rp. 124,482.50

76 PASANG DINDING BATA MERAH (5X11X22) CM TEBAL 1/2 BATU, CAMP. 1 SP 6PP 7.8

UPAH Pekerja Oh 0.3000 Rp 72,000.00 Rp. 21,600.00


Tukang Oh 0.1000 Rp 75,000.00 Rp. 7,500.00
Mandor Oh 0.0150 Rp 80,000.00 Rp. 1,200.00
BAHAN Batu bata bj 72.0000 Rp 550.00 Rp. 39,600.00
Semen (PC) kg 9.6800 Rp 1,200.00 Rp. 11,616.00
Pasir pasang m3 0.0450 Rp 210,000.00 Rp. 9,450.00
ALAT Alat Bantu Ls 0.0000 Rp 3,030.00 Rp. -
JUMLAH Rp. 90,966.00
OVERHEAD+PROFIT 1 % Rp. 909.66
TOTAL Rp. 91,875.66

77 PEMASANGAN PLESTERAN 1SP 6PP TEBAL 15 MM


UPAH Pekerja 7.9 Oh 0.2700 Rp 72,000.00 Rp. 19,440.00
Tukang Oh 0.2000 Rp 75,000.00 Rp. 15,000.00
Mandor Oh 0.0200 Rp 80,000.00 Rp. 1,600.00
BAHAN Semen (PC) kg 6.9300 Rp 1,200.00 Rp. 8,316.00
Pasir pasang m3 0.0400 Rp 210,000.00 Rp. 8,400.00
ALAT Alat Bantu Ls 0.0000 Rp 3,604.00 Rp. -
JUMLAH Rp. 52,756.00
OVERHEAD+PROFIT 1 % Rp. 527.56
TOTAL Rp. 53,283.56
78 PEMASANGAN ACIAN 7.10
UPAH Pekerja Oh 0.3000 Rp 72,000.00 Rp. 21,600.00
Tukang Oh 0.1400 Rp 75,000.00 Rp. 10,500.00
Mandor Oh 0.0080 Rp 80,000.00 Rp. 640.00
BAHAN Semen (PC) kg 3.2500 Rp 1,200.00 Rp. 3,900.00
ALAT Alat Bantu Ls 0.0000 Rp 3,274.00 Rp. -
JUMLAH Rp. 36,640.00
OVERHEAD+PROFIT 1 % Rp. 366.40
TOTAL Rp. 37,006.40

79 MEMBUAT RINGBALK BETON BERTULANG (10 X 15) CM 7.11


UPAH Pekerja Oh 0.1500 Rp 72,000.00 Rp. 10,800.00
Tukang Oh 0.0900 Rp 75,000.00 Rp. 6,750.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN Besi cor kg 3.0000 Rp 8,300.00 Rp. 24,900.00
kayu begesteng m3 0.1600 Rp 500,000.00 Rp. 80,000.00
ALAT Alat Bantu Ls 0.0000 Rp 1,835.00 Rp. -
JUMLAH Rp. 123,250.00
OVERHEAD+PROFIT 1 % Rp. 1,232.50
TOTAL Rp. 124,482.50

80 A. MEMBUAT BETON MUTU FC = 19,3 MPA (K225), SLUMP (12 2) CM, W/C = 0,58 8.1a

UPAH Pekerja Oh 0.0120 Rp 72,000.00 Rp. 864.00


Tukang Oh 0.0100 Rp 75,000.00 Rp. 750.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
BAHAN pasir beton kg 540.0000 Rp 250.00 Rp. 135,000.00
Semen (PC) kg 423.0000 Rp 1,200.00 Rp. 507,600.00
Split beton kg 940.0000 Rp 250.00 Rp. 235,000.00
Air ltr 215.0000 Rp 40.00 Rp. 8,600.00
ALAT Alat Bantu Ls 0.0000 Rp 169.40 Rp. -
Readi mix unit 0.0000 Rp - Rp. -
JUMLAH Rp. 887,894.00
OVERHEAD+PROFIT 1 % Rp. 8,878.94
TOTAL Rp. 896,772.94

81 B. PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIR 8.2


UPAH Pekerja Oh 0.0100 Rp 72,000.00 Rp. 720.00
Tukang besi Oh 0.0100 Rp 75,000.00 Rp. 750.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
BAHAN Besi beton kg 1.0500 Rp 8,300.00 Rp. 8,715.00
Kawat beton / bendrat kg 0.0100 Rp 15,000.00 Rp. 150.00
ALAT Alat Bantu Ls 0.0000 Rp 155.00 Rp. -
JUMLAH Rp. 10,415.00
OVERHEAD+PROFIT 1 % Rp. 104.15
TOTAL Rp. 10,519.15

82 C. MEMBUAT BEKISTING PONDASI 8.3


UPAH Pekerja Oh 0.5200 Rp 72,000.00 Rp. 37,440.00
Tukang kayu Oh 0.2600 Rp 75,000.00 Rp. 19,500.00
Mandor Oh 0.0260 Rp 80,000.00 Rp. 2,080.00
BAHAN kayu begesteng m3 0.0450 Rp 500,000.00 Rp. 22,500.00
ALAT Alat Bantu Ls 0.0000 Rp 5,902.00 Rp. -
JUMLAH Rp. 81,520.00
OVERHEAD+PROFIT 1 % Rp. 815.20
TOTAL Rp. 82,335.20

83 PEMBUATAN BALOK LATIU 8.4


UPAH Pekerja Oh 0.1500 Rp 72,000.00 Rp. 10,800.00
Tukang Oh 0.0900 Rp 75,000.00 Rp. 6,750.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN Besi cor kg 12.4100 Rp 8,300.00 Rp. 103,003.00
kayu begesteng m3 0.1600 Rp 500,000.00 Rp. 80,000.00
ALAT Alat Bantu Ls 0.0000 Rp 1,835.00 Rp. -
JUMLAH Rp. 201,353.00
OVERHEAD+PROFIT 1 % Rp. 2,013.53
TOTAL Rp. 203,366.53

84 PASANG GORDING CANAL C.100.50.20.2,3 8.5


UPAH Pekerja Oh 0.0600 Rp 72,000.00 Rp. 4,320.00
Tukang Oh 0.0060 Rp 75,000.00 Rp. 450.00
Mandor Oh 0.0030 Rp 80,000.00 Rp. 240.00
BAHAN Baja CNP kg 1.1500 Rp 9,000.00 Rp. 10,350.00
ALAT Alat Bantu Ls 0.0000 Rp 501.00 Rp. -
JUMLAH Rp. 15,360.00
OVERHEAD+PROFIT 1 % Rp. 153.60
TOTAL Rp. 15,513.60

85 PEMASANGAN 1 M2 ATAP ASBES GELOMBANG 1,05M X 3,00M X 4MM 8.6


UPAH Pekerja Oh 0.1400 Rp 72,000.00 Rp. 10,080.00
Tukang Oh 0.0750 Rp 75,000.00 Rp. 5,625.00
Mandor Oh 0.0080 Rp 80,000.00 Rp. 640.00
BAHAN Asbes gelombang 3000x1050x4 mm lbr 0.6000 Rp 76,000.00 Rp. 45,600.00
Paku payung kg 0.1200 Rp 35,000.00 Rp. 4,200.00
ALAT Alat Bantu Ls 0.0000 Rp 1,634.50 Rp. -
JUMLAH Rp. 66,145.00
OVERHEAD+PROFIT 1 % Rp. 661.45
TOTAL Rp. 66,806.45

86 PEMASANGAN RANGKA HOLLOW METAL FURING GALVANIS 0,4 MM, MODUL 60 X 8.7
UPAH Pekerja Oh 0.1100 Rp 72,000.00 Rp. 7,920.00
Tukang Oh 0.0500 Rp 75,000.00 Rp. 3,750.00
Mandor Oh 0.0050 Rp 80,000.00 Rp. 400.00
BAHAN hollow metal furing galvanis 0,4 mm m 1.1000 Rp 6,500.00 Rp. 7,150.00
Paku skrup kg 0.1100 Rp 60,000.00 Rp. 6,600.00
ALAT Alat Bantu Ls 0.0000 Rp 1,207.00 Rp. -
JUMLAH Rp. 25,820.00
OVERHEAD+PROFIT 1 % Rp. 258.20
TOTAL Rp. 26,078.20

87 PEMASANGAN LANGIT-LANGIT CALCYBOARD UKURAN ( 120X240X9 )CM, TEBAL 8.8


9MM
UPAH Pekerja Oh 0.1000 Rp 72,000.00 Rp. 7,200.00
Tukang Oh 0.0500 Rp 75,000.00 Rp. 3,750.00
Mandor Oh 0.0050 Rp 80,000.00 Rp. 400.00
BAHAN Kalsiboard (240x120) cm tebal 9 mm lbr 0.3640 Rp 120,000.00 Rp. 43,680.00
Paku skrup kg 0.1100 Rp 60,000.00 Rp. 6,600.00
ALAT Alat Bantu Ls 0.0000 Rp 1,135.00 Rp. -
JUMLAH Rp. 61,630.00
OVERHEAD+PROFIT 1 % Rp. 616.30
TOTAL Rp. 62,246.30

88 PEMASANGAN LANTAI KERAMIK WARNA UKURAN 40CM X 40CM 8.9


UPAH Pekerja Oh 0.7000 Rp 72,000.00 Rp. 50,400.00
Tukang Oh 0.3500 Rp 75,000.00 Rp. 26,250.00
Mandor Oh 0.0350 Rp 80,000.00 Rp. 2,800.00
BAHAN keramik 40x40 cm m2 1.2000 Rp 65,000.00 Rp. 78,000.00
Semen (PC) kg 10.4000 Rp 1,200.00 Rp. 12,480.00
Pasir pasang m3 0.0450 Rp 210,000.00 Rp. 9,450.00
Semen warna kg 1.6200 Rp 2,000.00 Rp. 3,240.00
ALAT Alat Bantu Ls 0.0000 Rp 7,945.00 Rp. -
JUMLAH Rp. 182,620.00
OVERHEAD+PROFIT 1 % Rp. 1,826.20
TOTAL Rp. 184,446.20

89 PEMASANGAN LANTAI KERAMIK UKURAN 20CM X 20CM 8.10


UPAH Pekerja Oh 0.7000 Rp 72,000.00 Rp. 50,400.00
Tukang Oh 0.3500 Rp 75,000.00 Rp. 26,250.00
Mandor Oh 0.0350 Rp 80,000.00 Rp. 2,800.00
BAHAN keramik 20x20 cm m2 1.2000 Rp 35,000.00 Rp. 42,000.00
Semen (PC) kg 10.4000 Rp 1,200.00 Rp. 12,480.00
Pasir pasang m3 0.0450 Rp 210,000.00 Rp. 9,450.00
Semen warna kg 1.6200 Rp 2,000.00 Rp. 3,240.00
ALAT Alat Bantu Ls 0.0000 Rp 7,945.00 Rp. -
JUMLAH Rp. 146,620.00
OVERHEAD+PROFIT 1 % Rp. 1,466.20
TOTAL Rp. 148,086.20

90 PEMASANGAN DINDING KERAMIK 25CMX 40CM 8.11


UPAH Pekerja Oh 0.7000 Rp 72,000.00 Rp. 50,400.00
Tukang Oh 0.3500 Rp 75,000.00 Rp. 26,250.00
Mandor Oh 0.0350 Rp 80,000.00 Rp. 2,800.00
BAHAN keramik dinding 25/40 m2 1.2000 Rp 50,000.00 Rp. 60,000.00
Semen (PC) kg 10.4000 Rp 1,200.00 Rp. 12,480.00
Pasir pasang m3 0.0450 Rp 210,000.00 Rp. 9,450.00
Semen warna kg 1.6200 Rp 2,000.00 Rp. 3,240.00
ALAT Alat Bantu Ls 0.0000 Rp 7,945.00 Rp. -
JUMLAH Rp. 164,620.00
OVERHEAD+PROFIT 1 % Rp. 1,646.20
TOTAL Rp. 166,266.20

91 PEMASANGAN PINTU PVC KAMAR MANDI 8.12


UPAH Pekerja Oh 0.0400 Rp 72,000.00 Rp. 2,880.00
Tukang Oh 0.4000 Rp 75,000.00 Rp. 30,000.00
Mandor Oh 0.0040 Rp 80,000.00 Rp. 320.00
BAHAN Pintu bahan PVC m2 1.0000 Rp 250,000.00 Rp. 250,000.00
ALAT Alat Bantu Ls 0.0000 Rp 3,320.00 Rp. -
JUMLAH Rp. 283,200.00
OVERHEAD+PROFIT 1 % Rp. 2,832.00
TOTAL Rp. 286,032.00

92 PEMASANGAN CLOOSET JONGKOK PORSLIN 8.13


UPAH Pekerja Oh 1.5000 Rp 72,000.00 Rp. 108,000.00
Tukang Oh 1.5000 Rp 75,000.00 Rp. 112,500.00
Mandor Oh 0.1600 Rp 80,000.00 Rp. 12,800.00
BAHAN Kloset jongkok INA bh 1.0000 Rp 120,000.00 Rp. 120,000.00
Semen (PC) kg 6.0000 Rp 1,200.00 Rp. 7,200.00
Pasir pasang m3 0.0100 Rp 210,000.00 Rp. 2,100.00
ALAT Alat Bantu Ls 0.0000 Rp 23,330.00 Rp. -
JUMLAH Rp. 362,600.00
OVERHEAD+PROFIT 1 % Rp. 3,626.00
TOTAL Rp. 366,226.00

93 PEMASANGAN FLOOR DRAIN 8.14


UPAH Pekerja Oh 0.0100 Rp 72,000.00 Rp. 720.00
Tukang Oh 0.1000 Rp 75,000.00 Rp. 7,500.00
Mandor Oh 0.0060 Rp 80,000.00 Rp. 480.00
BAHAN Floor Drain stainless bh 1.0000 Rp 20,000.00 Rp. 20,000.00
ALAT Alat Bantu Ls 0.0000 Rp 870.00 Rp. -
JUMLAH Rp. 28,700.00
OVERHEAD+PROFIT 1 % Rp. 287.00
TOTAL Rp. 28,987.00

94 INSTALASI TITIK LAMPU 8.15


UPAH Pekerja Oh 0.0500 Rp 72,000.00 Rp. 3,600.00
Tukang Erection Oh 0.0100 Rp 75,000.00 Rp. 750.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
JUMLAH Rp. 4,430.00
OVERHEAD+PROFIT 1 % Rp. 44.30
TOTAL Rp. 4,474.30

95 INSTALASI STOPKONTAK
UPAH Pekerja Oh 0.0500 Rp 72,000.00 Rp. 3,600.00
Tukang Erection Oh 0.0100 Rp 75,000.00 Rp. 750.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
JUMLAH Rp. 4,430.00
OVERHEAD+PROFIT 1 % Rp. 44.30
TOTAL Rp. 4,474.30

96 PASANG LAMPU SL 9 WATT 8.16


BAHAN Lampu SL 9 m' 1.0000 Rp 40,000.00 Rp. 40,000.00
JUMLAH Rp. 40,000.00
OVERHEAD+PROFIT 1 % Rp. 400.00
TOTAL Rp. 40,400.00

97 PEMASANGAN PIPA PVC TIPE AW DIAMETER 2 8.17


UPAH Pekerja Oh 0.0360 Rp 72,000.00 Rp. 2,592.00
Tukang Oh 0.0600 Rp 75,000.00 Rp. 4,500.00
Mandor Oh 0.0018 Rp 80,000.00 Rp. 144.00
BAHAN PVC 4 m diameter 2" AW btg 0.2600 Rp 60,000.00 Rp. 15,600.00
Perlengkapan 35% Harga Pipa Ls 0.3500 Rp 59,405.94 Rp. 20,792.08
ALAT Alat Bantu Ls 0.0000 Rp 723.60 Rp. -
JUMLAH Rp. 43,628.08
OVERHEAD+PROFIT 1 % Rp. 436.28
TOTAL Rp. 44,064.36

98 PEMASANGAN PIPA PVC TIPE AW DIAMETER 4 8.18


UPAH Pekerja Oh 0.0360 Rp 72,000.00 Rp. 2,592.00
Tukang Oh 0.0600 Rp 75,000.00 Rp. 4,500.00
Mandor Oh 0.0018 Rp 80,000.00 Rp. 144.00
BAHAN PVC 4 m diameter 4" AW btg 0.2600 Rp 170,000.00 Rp. 44,200.00
Perlengkapan 35% Harga Pipa Ls 0.3500 Rp 168,316.83 Rp. 58,910.89
ALAT Alat Bantu Ls 0.0000 Rp 723.60 Rp. -
JUMLAH Rp. 110,346.89
OVERHEAD+PROFIT 1 % Rp. 1,103.47
TOTAL Rp. 111,450.36

99 PEMASANGAN KRAN DIAMETER 1/2 ATAU 3/4 8.19


UPAH Pekerja Oh 0.0100 Rp 72,000.00 Rp. 720.00
Tukang Oh 0.1000 Rp 75,000.00 Rp. 7,500.00
Mandor Oh 0.0050 Rp 80,000.00 Rp. 400.00
BAHAN Kran Air bh 1.0000 Rp 35,000.00 Rp. 35,000.00
seal tape bh 0.0250 Rp 7,000.00 Rp. 175.00
ALAT Alat Bantu Ls 0.0000 Rp 862.00 Rp. -
JUMLAH Rp. 43,795.00
OVERHEAD+PROFIT 1 % Rp. 437.95
TOTAL Rp. 44,232.95

100 PEMASANGAN PIPA PVC TIPE AW DIAMETER 3/4 8.20


UPAH Pekerja Oh 0.0360 Rp 72,000.00 Rp. 2,592.00
Tukang Oh 0.0600 Rp 75,000.00 Rp. 4,500.00
Mandor Oh 0.0018 Rp 80,000.00 Rp. 144.00
BAHAN PVC 4 m diameter 0,75" AW btg 0.2600 Rp 25,000.00 Rp. 6,500.00
Perlengkapan 35% Harga Pipa Ls 0.3500 Rp 24,752.48 Rp. 8,663.37
ALAT Alat Bantu Ls 0.0000 Rp 723.60 Rp. -
JUMLAH Rp. 22,399.37
OVERHEAD+PROFIT 1 % Rp. 223.99
TOTAL Rp. 22,623.36

101 CAT TEMBOK BARU (1 LAPIS PLAMUR, 1 LAPIS CAT DASAR, 2 LAPIS CAT 8.21
PENUTUP
UPAH Pekerja Oh 0.0100 Rp 72,000.00 Rp. 720.00
Tukang cat Oh 0.5000 Rp 75,000.00 Rp. 37,500.00
Mandor Oh 0.0030 Rp 80,000.00 Rp. 240.00
BAHAN Dempul/plamir tembok kg 0.0750 Rp 15,000.00 Rp. 1,125.00
cat dasar tembok kg 0.0750 Rp 35,000.00 Rp. 2,625.00
cat tembok (metrolite) kg 0.1500 Rp 40,000.00 Rp. 6,000.00
ALAT Alat Bantu Ls 0.0000 Rp 3,846.00 Rp. -
JUMLAH Rp. 48,210.00
OVERHEAD+PROFIT 1 % Rp. 482.10
TOTAL Rp. 48,692.10

102 CAT PLAFOND 8.22


UPAH Pekerja Oh 0.0200 Rp 72,000.00 Rp. 1,440.00
Tukang cat Oh 0.0600 Rp 75,000.00 Rp. 4,500.00
Mandor Oh 0.0030 Rp 80,000.00 Rp. 240.00
BAHAN Dempul/plamir tembok kg 0.1000 Rp 15,000.00 Rp. 1,500.00
cat dasar tembok kg 0.1000 Rp 35,000.00 Rp. 3,500.00
cat tembok (metrolite) kg 0.2600 Rp 40,000.00 Rp. 10,400.00
ALAT Alat Bantu Ls 0.0000 Rp 618.00 Rp. -
JUMLAH Rp. 21,580.00
OVERHEAD+PROFIT 1 % Rp. 215.80
TOTAL Rp. 21,795.80

103 GALIAN TANAH 9.1


UPAH Pekerja Oh 0.2000 Rp 72,000.00 Rp. 14,400.00
Tenaga gali tanah/pondasi Oh 0.1200 Rp 72,000.00 Rp. 8,640.00
Mandor Oh 0.0270 Rp 80,000.00 Rp. 2,160.00
ALAT Alat Bantu Ls 0.0000 Rp 2,520.00 Rp. -
JUMLAH Rp. 25,200.00
OVERHEAD+PROFIT 1 % Rp. 252.00
TOTAL Rp. 25,452.00

104 URUGAN KEMBALI GALIAN TANAH BIASA SEDALAM 1 METER 9.2


UPAH Pekerja Oh 0.3000 Rp 72,000.00 Rp. 21,600.00
Tenaga gali tanah/pondasi Oh 0.2000 Rp 72,000.00 Rp. 14,400.00
Mandor Oh 0.0500 Rp 80,000.00 Rp. 4,000.00
ALAT Alat Bantu Ls 0.0000 Rp 4,000.00 Rp. -
JUMLAH Rp. 40,000.00
OVERHEAD+PROFIT 1 % Rp. 400.00
TOTAL Rp. 40,400.00

105 URUGAN PASIR 9.3


UPAH Pekerja Oh 0.0100 Rp 72,000.00 Rp. 720.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN Pasir urug m3 1.0100 Rp 140,000.00 Rp. 141,400.00
ALAT Alat Bantu Ls 0.0000 Rp 152.00 Rp. -
JUMLAH Rp. 142,920.00
OVERHEAD+PROFIT 1 % Rp. 1,429.20
TOTAL Rp. 144,349.20

106 URUGAN TANAH PILIHAN 9.4


UPAH Pekerja Oh 0.1000 Rp 72,000.00 Rp. 7,200.00
Tenaga gali tanah/pondasi Oh 0.0100 Rp 72,000.00 Rp. 720.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
ALAT Alat Bantu Ls 0.0000 Rp 800.00 Rp. -
JUMLAH Rp. 8,000.00
OVERHEAD+PROFIT 1 % Rp. 80.00
TOTAL Rp. 8,080.00
107 PASANG PONDASI BATU BELAH (HITAM) CAMPURAN 1SP 6PP 9.5
UPAH Pekerja Oh 1.5000 Rp 72,000.00 Rp. 108,000.00
Tukang Oh 0.6000 Rp 75,000.00 Rp. 45,000.00
Mandor Oh 0.0750 Rp 80,000.00 Rp. 6,000.00
BAHAN Pasir pasang m3 0.5440 Rp 210,000.00 Rp. 114,240.00
Semen (PC) kg 136.0000 Rp 1,200.00 Rp. 163,200.00
Batu belah hitam m3 1.2000 Rp 165,000.00 Rp. 198,000.00
ALAT Alat Bantu Ls 0.0000 Rp 15,900.00 Rp. -
JUMLAH Rp. 634,440.00
OVERHEAD+PROFIT 1 % Rp. 6,344.40
TOTAL Rp. 640,784.40

108 MEMBUAT SLOOF BALOK BETON BERTULANG (10 X 15) CM 9.6


UPAH Pekerja Oh 0.1500 Rp 72,000.00 Rp. 10,800.00
Tukang Oh 0.0900 Rp 75,000.00 Rp. 6,750.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN Besi cor kg 3.0000 Rp 8,300.00 Rp. 24,900.00
kayu begesteng m3 0.1600 Rp 500,000.00 Rp. 80,000.00
ALAT Alat Bantu Ls 0.0000 Rp 1,835.00 Rp. -
JUMLAH Rp. 123,250.00
OVERHEAD+PROFIT 1 % Rp. 1,232.50
TOTAL Rp. 124,482.50

109 MEMBUAT KOLOM PRAKTIS BETON BERTULANG (11 X 11) CM 9.7


UPAH Pekerja Oh 0.1500 Rp 72,000.00 Rp. 10,800.00
Tukang Oh 0.0900 Rp 75,000.00 Rp. 6,750.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN Besi cor kg 3.0000 Rp 8,300.00 Rp. 24,900.00
kayu begesteng m3 0.1600 Rp 500,000.00 Rp. 80,000.00
ALAT Alat Bantu Ls 0.0000 Rp 1,835.00 Rp. -
JUMLAH Rp. 123,250.00
OVERHEAD+PROFIT 1 % Rp. 1,232.50
TOTAL Rp. 124,482.50

110 PASANG DINDING BATA MERAH (5X11X22) CM TEBAL 1/2 BATU, CAMP. 1 SP 6PP 9.8

UPAH Pekerja Oh 0.3000 Rp 72,000.00 Rp. 21,600.00


Tukang Oh 0.1000 Rp 75,000.00 Rp. 7,500.00
Mandor Oh 0.0150 Rp 80,000.00 Rp. 1,200.00
BAHAN Batu bata bj 72.0000 Rp 550.00 Rp. 39,600.00
Semen (PC) kg 9.6800 Rp 1,200.00 Rp. 11,616.00
Pasir pasang m3 0.0450 Rp 210,000.00 Rp. 9,450.00
ALAT Alat Bantu Ls 0.0000 Rp 3,030.00 Rp. -
JUMLAH Rp. 90,966.00
OVERHEAD+PROFIT 1 % Rp. 909.66
TOTAL Rp. 91,875.66

111 PEMASANGAN PLESTERAN 1SP 6PP TEBAL 15 MM 9.9


UPAH Pekerja Oh 0.2700 Rp 72,000.00 Rp. 19,440.00
Tukang Oh 0.2000 Rp 75,000.00 Rp. 15,000.00
Mandor Oh 0.0200 Rp 80,000.00 Rp. 1,600.00
BAHAN Semen (PC) kg 6.9300 Rp 1,200.00 Rp. 8,316.00
Pasir pasang m3 0.0400 Rp 210,000.00 Rp. 8,400.00
ALAT Alat Bantu Ls 0.0000 Rp 3,604.00 Rp. -
JUMLAH Rp. 52,756.00
OVERHEAD+PROFIT 1 % Rp. 527.56
TOTAL Rp. 53,283.56

112 PEMASANGAN ACIAN 9.10


UPAH Pekerja Oh 0.3000 Rp 72,000.00 Rp. 21,600.00
Tukang Oh 0.1400 Rp 75,000.00 Rp. 10,500.00
Mandor Oh 0.0080 Rp 80,000.00 Rp. 640.00
BAHAN Semen (PC) kg 3.2500 Rp 1,200.00 Rp. 3,900.00
ALAT Alat Bantu Ls 0.0000 Rp 3,274.00 Rp. -
JUMLAH Rp. 36,640.00
OVERHEAD+PROFIT 1 % Rp. 366.40
TOTAL Rp. 37,006.40

113 MEMBUAT RINGBALK BETON BERTULANG (10 X 15) CM 9.11


UPAH Pekerja Oh 0.1500 Rp 72,000.00 Rp. 10,800.00
Tukang Oh 0.0900 Rp 75,000.00 Rp. 6,750.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN Besi cor kg 3.0000 Rp 8,300.00 Rp. 24,900.00
kayu begesteng m3 0.1600 Rp 500,000.00 Rp. 80,000.00
ALAT Alat Bantu Ls 0.0000 Rp 1,835.00 Rp. -
JUMLAH Rp. 123,250.00
OVERHEAD+PROFIT 1 % Rp. 1,232.50
TOTAL Rp. 124,482.50

114 MEMBUAT LANTAI KERJA BETON MUTU FC = 7,4 MPA (K100), SLUMP (3-6) CM, W/C 9.13
= 0,97
UPAH Pekerja Oh 0.0120 Rp 72,000.00 Rp. 864.00
Tukang Oh 0.0100 Rp 75,000.00 Rp. 750.00
Mandor Oh 0.0010 Rp 80,000.00 Rp. 80.00
BAHAN pasir beton kg 820.0000 Rp 250.00 Rp. 205,000.00
Semen (PC) kg 180.0000 Rp 1,200.00 Rp. 216,000.00
Split beton kg 920.0000 Rp 250.00 Rp. 230,000.00
Air ltr 200.0000 Rp 40.00 Rp. 8,000.00
ALAT Alat Bantu Ls 0.0000 Rp 169.40 Rp. -
JUMLAH Rp. 660,694.00
OVERHEAD+PROFIT 1 % Rp. 6,606.94
TOTAL Rp. 667,300.94

115 PASANG RANGKA ATAP BAJA RINGAN TEBAL 1MM 9.14


UPAH Pekerja Oh 0.2500 Rp 72,000.00 Rp. 18,000.00
Tukang Oh 0.1700 Rp 75,000.00 Rp. 12,750.00
Mandor Oh 0.1000 Rp 80,000.00 Rp. 8,000.00
BAHAN Baja ringan truss C75.70 btg 2.8000 Rp 65,000.00 Rp. 182,000.00
Reng baja ringan 30.45 btg 5.1000 Rp 30,000.00 Rp. 153,000.00
Paku skrup kg 0.5000 Rp 60,000.00 Rp. 30,000.00
ALAT Alat Bantu Ls 0.0000 Rp 3,875.00 Rp. -
JUMLAH Rp. 403,750.00
OVERHEAD+PROFIT 1 % Rp. 4,037.50
TOTAL Rp. 407,787.50

116 PEMASANGAN ATAP GALVALUM TEBAL 0,4 MM 9.15


UPAH Pekerja Oh 0.0200 Rp 72,000.00 Rp. 1,440.00
Tukang Oh 0.0800 Rp 75,000.00 Rp. 6,000.00
Mandor Oh 0.0100 Rp 80,000.00 Rp. 800.00
BAHAN Atap galvalum 0,4m m2 1.1000 Rp 80,000.00 Rp. 88,000.00
ALAT Alat Bantu Ls 0.0000 Rp 824.00 Rp. -
JUMLAH Rp. 96,240.00
OVERHEAD+PROFIT 1 % Rp. 962.40
TOTAL Rp. 97,202.40

117 CAT TEMBOK BARU (1 LAPIS PLAMUR, 1 LAPIS CAT DASAR, 2 LAPIS CAT 9.16
PENUTUP
UPAH Pekerja Oh 0.0100 Rp 72,000.00 Rp. 720.00
Tukang cat Oh 0.5000 Rp 75,000.00 Rp. 37,500.00
Mandor Oh 0.0030 Rp 80,000.00 Rp. 240.00
JUMLAH Rp. 38,460.00
OVERHEAD+PROFIT 1 % Rp. 384.60
TOTAL Rp. 38,844.60

HIDE BARIS INI

NOTE:
1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah
kecuali terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN yang dibayar dari kontrak) dan biaya-biaya lainnya.