Professional Documents
Culture Documents
Details of Robs/Rubs Undertaken by Nhai During Last Three Years (2009-10, 2010-11, 2011-12) and Current Year (2012-13)
Details of Robs/Rubs Undertaken by Nhai During Last Three Years (2009-10, 2010-11, 2011-12) and Current Year (2012-13)
Page 1 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
ROB at Ghograpara Pilling of ROB & approach work in Delay due to LA, utility shifting &
13 Assam 31
1075+218 progess
Yes
sanction / permission of Railway
ROB at Rangia Pilling Test done & Approach work in Delay due to LA, utility shifting &
14 Assam 31
1082+931 progess
Yes
sanction / permission of Railway
GOA 17B Km.1.240 to Km.1.020 _ Yes The matter was in the Hon'ble Supreme
Court
16
Haryana Km. 199.000 GADs submitted for approval GADs are under scrutiny with Railway
(Ambala city ) Authorities as these GADs involve
25 1 Yes widening of existing structures
Page 2 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
Completed - -
Completed - -
Completed - -
30
31
Km 79/600 Completed No NA
32 Maharashtra 9
- -
- -
- -
Bortembhe (Km.
35 Maharashtra 3
458/978)
Completed
- -
Umbermali (Km.
36 Maharashtra 3
486/522)
Completed
Page 3 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
Yes
Dhanamandal -
39 Odisha 200
Haridaspur
GAD Approved. Due to GAD
40 1
41 1
42 1
43 1
Punjab 230.630 GADs submitted for approval GADs are under scrutiny with Railway
(Rajpura) Authorities as these GADs involve
44 1 Yes widening of existing structures
Punjab 311.850 GADs submitted for approval GADs are under scrutiny with Railway
(Sherpur Chowak) Authorities as these GADs involve
45 1 Yes widening of existing structures
Punjab 326.200 GADs submitted for approval GADs are under scrutiny with Railway
(Hardy World) Authorities as these GADs involve
46 1 Yes widening of existing structures
Punjab 332.050 GADs submitted for approval GADs are under scrutiny with Railway
( Phillaur) Authorities as these GADs involve
47 1 Yes widening of existing structures
Punjab 352.600 (Phagwara Design and drawing under approval GAD under finalization with Railways
Mandhali)
48 1 Yes
Punjab 361.425(Phagwara GADs submitted for approval GADs are under scrutiny with Railway
Chhiherru) Authorities as these GADs involve
49 1 Yes widening of existing structures
Punjab 373.000 (Jalandhar GADs submitted for approval GADs are under scrutiny with Railway
Bypass) Authorities as these GADs involve
50 1 Yes widening of existing structures
Page 4 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
Punjab 374.750 (Jalandhar GADs submitted for approval GADs are under scrutiny with Railway
Bypass) Authorities as these GADs involve
51 1 Yes widening of existing structures
- -
- -
- -
Page 5 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
- -
- -
Two lane ROB completed on LHS and Delay in Land Acquisition and delay by
65 Tamil Nadu 67 Km 129.155
rehabilitation work in progress on RHS
Yes
the Concessionaire
Construction of
- -
Additional 2-lane ROB
to existing Br.No.1449A
67 Tamil Nadu 7
at Km 0+290 between
Completed
Samayanallur -
Sholavandan Stations.
- -
Construction of ROB at
km 8+532, including
68 Tamil Nadu 7
approaches, under pass
Completed
and culverts
- -
Construction of
Additional two lane
ROB to existing Br. No.
69 Tamil Nadu 7
2A at Km 54+139
Completed
between Virudanagar &
Tiruttangal stations.
- -
Construction of four lane
ROB at 66+872 near
70 Tamil Nadu 7
Tulakkapatti in VPE
Completed
–MEJ section.
- -
Construction of ROB at
71 Tamil Nadu 7 km 375+398 of Dindigul Completed
- Samaynallur section.
- -
Construction of ROB at
72 Tamil Nadu 7 km 394+850 of Dindigul Completed
- Samaynallur section.
Page 6 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
75
- -
Page 7 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
- -
Bhotaigaon 14.092 Km
10 Assam 37
of Nagaon Bypass
Completed
Bihar Yes
Bihar Yes
Bihar Yes
Bihar -
14 19 142.361 In Progress No
Bihar -
15 19 149.371 In Progress No
Bihar -
16 19 156.3 In Progress No
Bihar -
17 19 175.517 In Progress No
Bihar -
18 19 207.249 In Progress No
Bihar -
19 19 188.237 In Progress No
Bihar
- -
Km 353.08 -
21 Gujarat 8 Near Udwada Completed
(LC no. 87)
Page 8 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
Haryana 71 Km 434.857 on Rewari deck slab laid. 80% of the work No N.A
bypass completed.
31
Haryana 71 Km 436.643 on Rewari deck slab laid. 80% of the work No N.A
bypass completed.
32
- -
Page 9 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
- -
- -
- -
- -
Orissa 215 Joda ROB/RUB at GAD under process for approval Yes Intiallly proposal for 2-lane ROB & 2-
NH.Km. 182.579 lane RUB submitted. Further 4-lane
Padapahar-Banspani Rly. RUB proposed as suggested by
40 Block Raiways, requiring 6 months of block
period. GAD approval is in process in
Railways
Page 10 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
46
47
48
49
- -
At Km 150/180 near
54 Tamil Nadu 7 Talaiyuthu (Tirunelveli Completed
Bypass)
- -
ROB near Palayamkottai
55 Tamil Nadu 7 and Seydunganallur at Completed
Km 161/135
- -
ROB between
Aralvaimozhi, Panagudi
56 Tamil Nadu 7
and Valliyoor stations at
Completed
Km 210/400
Page 11 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
- -
- -
- -
60
61
62
Page 12 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
67
Uttar Pradesh - -
Uttar Pradesh - -
Uttar Pradesh - -
Uttar Pradesh -
Between EP No. 8/11 &
72 91 8/12 NTPC feeder line Pier cap are under construction No
NCR, Allahabad
Uttar Pradesh -
Between EP no. 1343/15
73 91 & 1343/18 NCR Pile work under process No
Allahabad
Uttar Pradesh -
Between EP No. 1321/17
74 91 & 1321/18 NCR, Pier cap are under construction No
Allahabad
75 NO
Page 13 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
Uttar Pradesh 24 ROB In lieu of Level GAD approved Structural design uner approval with
crossing no. 343E at km Railways
81 289+620 and Railway Yes
km 1269+500 between
Katra and Beelpur
Uttar Pradesh 24 ROB In lieu of Level GAD uner approval GAD uner approval with Railway
crossing no. 318E at
82 331+300 and Railway Yes
km 1231.18 km between
Rauza and Shahjahanpur
Uttar Pradesh 24 ROB In lieu of Level GAD approved Structural design under approval with
crossing no. 45A at Railways
83 399+300 and Railway Yes
km 67 km between
Maholi and Hempur
Uttar Pradesh 24 Extension of 2 lane ROB GAD approved Structural design under approval with
at 4 lane ROB at Sitapur Railways
84 Bypass at km 409+000 Yes
and Railway km 56
km+200 km between
4-lane ROB over
Krishnagar-Lalgola line
in between station New
Detail design and drawing is under
85 West Bengal 34 Balrampur halt and
approval
No N.A
Berharampore on
Berharampore bypass at
Km.192.891.
4-lane ROB over Katwa-
Azimganj line between
stn. Jibanti halt-
86 West Bengal 34
Khagraghat road on
Work in progress No N.A
Berharampore bypass at
Km.199.159
2-lane ROB over Nalhati-
Azimganj line between
87 West Bengal 34 stn. Moregram- Work in progress No N.A
Sagardighi at
Km.229.734
Page 14 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
16 ROB at 3+450 of GADs approval is in progress Yes Construction of ROB is delayed due to
Chilakaluripet-Nellore pending approval of GADs from
section. Railways.
4 Andhra Pradesh
16 ROB at 8+970 of GADs approval is in progress Yes GAD under approval with Railways
Chilakaluripet-Nellore
5 Andhra Pradesh section.
16 ROB at 1341+971 of GADs approval is in progress Yes GAD under approval with Railways
Chilakaluripet-Nellore
6 Andhra Pradesh section.
ROB-I at Ch.79+830
7 Assam 31C
(BRPL Gate)
Delay in Utility shifting
Page 15 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
Page 16 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
Km. 306.67
Near Billimora
27 Gujarat 8
(LC no. 17)
Completed No NA
4 Km 256+732 No NA
30 Karnataka Completed
4 Km 311 No NA
31 Karnataka Completed
4 Km 328 No NA
32 Karnataka Completed
Page 17 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
17 ROB 4/972 Construction of substructure work of ROB Yes Due to delay in mobilization of
commenced. 13 piles out of 30 nos. have Concessionaire.
been completed.
37 Karnataka
75 & 3
(Gwalior
38 Madhya Pradesh
Bypass New
km 1+279 Completed - -
Alignment )
75 & 3
(Gwalior
39 Madhya Pradesh
Bypass New
km 7+790 Completed - -
Alignment )
Modnimb Railway Km. CRS application submitted to Railways Yes The CRS approval is awaited.
398/5-6 Authorities
40 Maharashtra 9
Mohol Railway CRS application submitted to Railways Yes The CRS approval is awaited.
Km.423/3-4 Authorities
41 Maharashtra 9
42 Maharashtra No -
43 Maharashtra No -
44 Maharashtra No -
Page 18 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
49
Construction of ROB at -
Km.125/605 between
Revised GAD approved on 26.11.2012.
52 Tamil Nadu 67 Tiruchirappalli and
Work to be commenced.
NO
Kumaramangalam
Stations
-
Construction of ROB at
Sub-structure design approved on
Km.22/020 between
53 Tamil Nadu 210
Kumaramangalam and
31.08.2012. NO
Sub Structure work in progress.
Keeranur Stations
Construction of four
lane ROB at Km 233/890 Due to delay in obtaining clearance
54 Tamil Nadu 7
between kanniyakumari
Completed Yes
from Southern Railway for line block.
and Suchindram stations
Page 19 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
Uttar Pradesh Level Xing no. 8A/E3 Pile work under process NO NA
NR, New Delhi
59 91
60 91 in progress No -
61 91 in progress No -
Page 20 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No
Page 21 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No
8 km 65.545 GAD under approval with Railways Yes GAD under approval with Railways
21 Gujarat
8 km 75.425 GAD under approval of Railways Yes GAD under approval of Railways
22 Gujarat
24 -
25 -
Km.22+745
Haryana NH -71A Under Construction No
26 -
Km.79+875
Haryana 73 Km.88.692 GAD approval in process Yes GAD of ROB under processing in
Railways
27
69 Work is in Progress No
Ch. 204/800
31 Madhya Pradesh
(Chichonda)
_
Page 22 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No
3 -
3 -
GAD approved
3
GAD approved
3
GAD approved
69 -
GAD approved
69 -
69
69
40 Madhya Pradesh 88+100 Modified GAD resubmitted No
26
206+111 (old km) Delay in approval of TAD drawing
41 Madhya Pradesh
211+004 (New km)
Completed Yes
from Railway
3
Delay in land acquision, delay in tree
42 Madhya Pradesh 53+145 99% completed Yes
cutting and delay in approval of CRS
Solapur Railway Km. GAD approval in process with Railways Yes The alignment is changed due to
Between 447/7 to 447/8 declaration of Rationalization of GIBS
43 Maharashtra 13 Boundary.
Page 23 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No
46 Maharashtra 6 No.
47 Maharashtra 6 No.
km 630.791
GAD yet to be approved -
48 Maharashtra 6 No.
640.146
49 Maharashtra 6 396+885 GAD Approved Yes Land and required clearances delayed
50 Maharashtra 6 405+603 GAD Approved Yes Land and required clearances delayed
51 Maharashtra 6 414+900 GAD Approved Yes Land and required clearances delayed
52 Maharashtra 6 426+781 GAD Approved Yes Land and required clearances delayed
53 Maharashtra 6 440+218 GAD Approved Yes Land and required clearances delayed
Page 24 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No
69 Work is in Progress No
69 Work is in Progress No
Ch. 29/540
56 Maharashtra
(Khaperkheda)
_
69 Work is in Progress No
69 Work is in Progress No
Page 25 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No
66 Orissa No _
Sakhigopal -
67 Orissa 203
Janakideipur
GAD Approved. Work in progress Yes Due to local site constraints
5 297.154 Completed and opened to traffic w.e.f. New contractor had to be appointed
Nov 12
69 Orissa Yes
Page 26 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No
At Km 38/986 in
76 Tamil Nadu 66
Tindivanam Bypass
Work in progress. NO -
At Km 174/832 near
77 Tamil Nadu 66
Samalpatti
Work to be commenced. NO -
Yes
Additional 2-lane ROB
at KM.293+150 between Due to delay in obtaining approval
78 Tamil Nadu 205
Pudi - Renigunta
Foundation work is in progress
drawings from Southern Railway.
Stations.
Yes
Due to delay in obtaining approval
79 Tamil Nadu 68 At Km 31/500 Completed from Southern Railway and clearance
from CRS.
Uttar Pradesh 2 Km. 219 of NH-2 Completed Yes The work of Tundla ROB was delayed
due to delayed approval from Railways
80 on account of construction of 3rd track
by the Railways
Uttar Pradesh 25 KM 218.986 Completed No NA
81
Uttar Pradesh 26 KM 10.481 ROB Work is in advanced stage of Yes Delay in approval and implementation
completion
82
Uttar Pradesh 56A & 56B ROB between Dilkhusha- Completed Yes Due to delay in getting approval from
Malhour section at railways. Due to change in
83 1086/18-19 on Lucknow- methodology for launching of girder
Faizable section NH- and termination of contractor.
56A&56B Lucknow
Uttar Pradesh 25 ROB Bhighapur-Unnao under progress Yes Due to delay in getting approval from
section at NH km. 60 railway and due to this the ROB was
84 and Rly. Km. 182/6-7 deleted from his scope of work. Non
availability of soil presently hampering
Uttar Pradesh 24B Lucknow-Raebarailly, under progress No the work -
NH-24B ROB at km.
85 Rly. Km. 1026/7-8 and
NH km. 78.72
Uttar Pradesh No -
86 Lucknow-Raebarailly,
NH-24B Rly km. 993/11-
24B 12 and NH km. 81.27 under progress
Uttar Pradesh GAD Approved No -
87 2 788.650
88 2 809.050
Page 27 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No
At Jwalapur Km.21/13-
94 Uttarakhand 58
14
In progress Yes GAD approval from Railways
At Raiwala, in lieu of
96 Uttarakhand 58
existing Raiwala RUB
In progress Yes GAD approval from Railways
km 75.955 (ROB) GAD Approved. Design under approval No. Not Applicable
from Railways
97 West Bengal 34
km 90.640 (ROB) GAD Approved. Design under approval No. Not Applicable
from Railways
98 West Bengal 34
km 95.350 (ROB) GAD Approved. Design under approval No. Not Applicable
from Railways
99 West Bengal 34
Page 28 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)
State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No
Page 29 of 29