Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)

and current year (2012-13)

Details of ROBs/RUBs Under taken in 2009-2010


State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No
44 ROB at Km373+375 of Completed. No Not Applicable
Nagpur-Hyderabad
1 Andhra Pradesh section.

44 ROB at 261.480 of Completed - -


Hyderabad-Bangalore
2 Andhra Pradesh section.

44 ROB at 300.600 of Completed - -


Hyderabad-Bangalore
3 Andhra Pradesh section.

44 ROB at 351.256 of Completed - -


Hyderabad-Bangalore
4 Andhra Pradesh section.

44 ROB at 397.020 of Completed - -


Hyderabad-Bangalore
5 Andhra Pradesh section.

44 ROB at 397.020 of Completed - -


Hyderabad-Bangalore
6 Andhra Pradesh section.

44 ROB at Km.50.76 of Completed - -


Hyderabad-Bangalore
7 Andhra Pradesh section.

44 ROB at Km.86.94 of Completed - -


Hyderabad-Bangalore
8 Andhra Pradesh section.

44 ROB at Km.196.10 of Completed - -


Hyderabad-Bangalore
9 Andhra Pradesh section.

ROB-I at Ch.79+830 Delay in sanction of drawings & design


10 Assam 31C
(BRPL Gate)
Not commenced Yes
from Rly. authority

ROB-II at Ch. 88+123 Delay in sanction of drawings & design


11 Assam 31C
(SK-48)
Not commenced Yes
from Rly. authority

ROB at Pathsala Delay due to LA, utility shifting &


12 Assam 31
1028+546
work of approaches (viaduct) in progess Yes
sanction / permission of Railway

Page 1 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

ROB at Ghograpara Pilling of ROB & approach work in Delay due to LA, utility shifting &
13 Assam 31
1075+218 progess
Yes
sanction / permission of Railway

ROB at Rangia Pilling Test done & Approach work in Delay due to LA, utility shifting &
14 Assam 31
1082+931 progess
Yes
sanction / permission of Railway

ROB at Changsari Delay due to LA, utility shifting &


15 Assam 31
1113+556
Work in progress. Pile test done Yes
sanction / permission of Railway

GOA 17B Km.1.240 to Km.1.020 _ Yes The matter was in the Hon'ble Supreme
Court
16

Km. 2+800 - Jetpur


17 Gujarat 8D
Byepass
GAD approved by Western Railway NO NA

Km. 23+996 - Junagadh


18 Gujarat 8D
Byepass
GAD approved by Western Railway NO NA

19 Gujarat 8D Km. 112+938 GAD approved by Western Railway NO NA

20 Gujarat 8D Km. 118+374 GAD approved by Western Railway NO NA

Haryana 10 Km. 59+868 Under Construction Due to slow progress of Bahadrugarh-


Rohtak section of NH-10
21 Yes

Haryana 10 Km. 70+012 Under Construction Due to slow progress of Bahadrugarh-


Rohtak section of NH-10
22 Yes

Haryana 10 Km.71+580 Under Construction Due to slow progress of Bahadrugarh-


Rohtak section of NH-10
23 Yes

Haryana 10 Km. 86+108 Under Construction Due to slow progress of Bahadrugarh-


Rohtak section of NH-10
24 Yes

Haryana Km. 199.000 GADs submitted for approval GADs are under scrutiny with Railway
(Ambala city ) Authorities as these GADs involve
25 1 Yes widening of existing structures

Page 2 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

Completed - -

26 Karnataka 7 km 508/014 to 508/184

Completed - -

27 Karnataka 7 km 517/725 to 517/887

Completed - -

28 Karnataka 7 km 524/200 to 524/326

Madhya Pradesh 215 Keonjhar ROB NH- GAD approved No NA


KM.(115.717) & Rly.
Km.(65.262)
29 Tomka-Keonjhar-
Bansapani

Madhya Pradesh 26 322+374 Under Construction Yes Due to delay in execution

30

Madhya Pradesh 3 2+604 completed - -

31

Km 79/600 Completed No NA

32 Maharashtra 9

- -

33 Maharashtra 3 Padali (Km. 445/235) Completed

- -

34 Maharashtra 3 Ghoti (Km. 451/090) Completed

- -

Bortembhe (Km.
35 Maharashtra 3
458/978)
Completed

- -

Umbermali (Km.
36 Maharashtra 3
486/522)
Completed

7 Butibori ROB Completed Yes Initial Delay in approval of drawings


Km.22.865 to for ROB portion by Central Railways,
37 Maharashtra Km.24.650 Non-availability of land to
(Rly Ch.812/26-28) accommodate service road, and utility
shifting.

Page 3 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

7 Borkhedi ROB work is in progress Yes Launching scheme approval from


Km.37.417 (Rly Railways
38 Maharashtra Ch.798/11-12)

Yes

Dhanamandal -
39 Odisha 200
Haridaspur
GAD Approved. Due to GAD

Punjab 408+465 completed - -

40 1

Punjab 415+250 completed - -

41 1

Punjab 451+275 completed - -

42 1

Punjab 455+690 completed - -

43 1

Punjab 230.630 GADs submitted for approval GADs are under scrutiny with Railway
(Rajpura) Authorities as these GADs involve
44 1 Yes widening of existing structures

Punjab 311.850 GADs submitted for approval GADs are under scrutiny with Railway
(Sherpur Chowak) Authorities as these GADs involve
45 1 Yes widening of existing structures

Punjab 326.200 GADs submitted for approval GADs are under scrutiny with Railway
(Hardy World) Authorities as these GADs involve
46 1 Yes widening of existing structures

Punjab 332.050 GADs submitted for approval GADs are under scrutiny with Railway
( Phillaur) Authorities as these GADs involve
47 1 Yes widening of existing structures

Punjab 352.600 (Phagwara Design and drawing under approval GAD under finalization with Railways
Mandhali)
48 1 Yes

Punjab 361.425(Phagwara GADs submitted for approval GADs are under scrutiny with Railway
Chhiherru) Authorities as these GADs involve
49 1 Yes widening of existing structures

Punjab 373.000 (Jalandhar GADs submitted for approval GADs are under scrutiny with Railway
Bypass) Authorities as these GADs involve
50 1 Yes widening of existing structures

Page 4 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

Punjab 374.750 (Jalandhar GADs submitted for approval GADs are under scrutiny with Railway
Bypass) Authorities as these GADs involve
51 1 Yes widening of existing structures

52 Rajasthan 8 km 368.03 Complete - -

CRS approval of launching


53 Rajasthan 8 km 390.6 3-lane completed & 3-lane in progress Yes
arrangement received on 23.10.12.

CRS approval of launching


54 Rajasthan 8 km 6+250 3-lane completed & 3-lane in progress Yes
arrangement received on 23.10.12.

55 Rajasthan 8 km 48+660 Complete - -

Rajasthan 215 Jajpur Road ROB in By- GAD approved No NA


pass NH-
56 KM.(9.18) & Rly.
Km.(334.886)
Korai-JJKR Block
- -
Two lane ROB at Km
178/775 between
57 Tamil Nadu 7
Nanguneri and Sengulam
Completed
stations

Falls in the proposed alignment of


58 Tamil Nadu 67 Km. 1+758 Work is yet to commence Yes Trichy Bypass, which is involved in
Court Cases.

Due to change in revised schematic


59 Tamil Nadu 67 Km.17+250 Work is yet to commence Yes arrangement, the revised GAD was to
be approved by Southern Railway.

- -

60 Tamil Nadu 67 Km.210+986 Completed

- -

61 Tamil Nadu 7 Km 165/400 Completed

- -

62 Tamil Nadu 7 Km 194/434 Completed

Page 5 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

- -

63 Tamil Nadu 7 Km 221/055 Completed

- -

64 Tamil Nadu 47 Km 20/538 Completed

Two lane ROB completed on LHS and Delay in Land Acquisition and delay by
65 Tamil Nadu 67 Km 129.155
rehabilitation work in progress on RHS
Yes
the Concessionaire

Two lane ROB on RHS is nearing


Delay in Land Acquisition and delay by
66 Tamil Nadu 67 Km 135.705 completion. Rehabilitation work on LHS Yes
the Concessionaire
to be taken up

Construction of
- -
Additional 2-lane ROB
to existing Br.No.1449A
67 Tamil Nadu 7
at Km 0+290 between
Completed
Samayanallur -
Sholavandan Stations.
- -
Construction of ROB at
km 8+532, including
68 Tamil Nadu 7
approaches, under pass
Completed
and culverts

- -

Construction of
Additional two lane
ROB to existing Br. No.
69 Tamil Nadu 7
2A at Km 54+139
Completed
between Virudanagar &
Tiruttangal stations.

- -
Construction of four lane
ROB at 66+872 near
70 Tamil Nadu 7
Tulakkapatti in VPE
Completed
–MEJ section.

- -
Construction of ROB at
71 Tamil Nadu 7 km 375+398 of Dindigul Completed
- Samaynallur section.

- -
Construction of ROB at
72 Tamil Nadu 7 km 394+850 of Dindigul Completed
- Samaynallur section.

Uttar Pradesh Km. 244.200 (Railway Completed - -


Km.527/3-4, LC No.171-
A)
73 28

Page 6 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

Uttar Pradesh 56A &56B ROB at Charbag- Completed - -


Utrathia section. On
74 Lucknow Bypass at NH
km. 14 and Rly. Km.
1061/14-15
Uttar Pradesh 24 Km 181.00 Completed - -

75

Details of ROBs/RUBs Under taken in 2010-2011


State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No

44 ROB at Km.189+456 of Completed - -


Nagpur-Hyderabad
1 Andhra Pradesh section

44 ROB at Km.195+991 of Completed - -


Nagpur-Hyderabad
2 Andhra Pradesh section

ROB-I at Ch.79+830 Delay in Land Acquisition by State


3 Assam 31C
(BRPL gate)
Under progress Yes
Govt. and Delay in Utility shifting

ROB-II at Ch. 88+123 Delay in Land Acquisition


4 Assam 31C
(SK- 48)
Under progress Yes
and Utility shifting

ROB at Pathsala Delay due to LA, utility shifting &


5 Assam 31
1028+546
Under progress Yes
sanction / permission of Railway

ROB at Ghograpara Delay due to LA, utility shifting &


6 Assam 31
1075+218
Under progress Yes
sanction / permission of Railway

ROB at Rangia Delay due to LA, utility shifting &


7 Assam 31
1082+931
Under progress Yes
sanction / permission of Railway

ROB at Changsari Delay due to LA, utility shifting &


8 Assam 31
1113+556
Under progress Yes
sanction / permission of Railway

- -

Dino Village 0.078 Km


9 Assam 37
of Nagaon Bypass
Completed

Page 7 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

- -

Bhotaigaon 14.092 Km
10 Assam 37
of Nagaon Bypass
Completed

Bihar Yes

11 77 0.45 In Progress Land availability problem

Bihar Yes

12 77 6.157 In Progress Land availability problem

Bihar Yes

13 77 15.350 (Bypass) In Progress Land availability problem

Bihar -

14 19 142.361 In Progress No

Bihar -

15 19 149.371 In Progress No

Bihar -

16 19 156.3 In Progress No

Bihar -

17 19 175.517 In Progress No

Bihar -

18 19 207.249 In Progress No

Bihar -

19 19 188.237 In Progress No

Bihar

20 57A 8.2093 Yet to commence Yes Design under finalization

- -
Km 353.08 -
21 Gujarat 8 Near Udwada Completed
(LC no. 87)

Page 8 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

NH-6 (New Km.4.066


22 Gujarat
NH-53) (Existing LC)
40% Completed No

NH-6 (New Km.19.597


23 Gujarat
NH-53) (Existing 2 Lane RUB)
70% Completed No

NH-6 (New Km.40.822


24 Gujarat
NH-53) (Existing LC)
60% Completed No

NH-6 (New Km.96.373


25 Gujarat
NH-53) (Existing 2 Lane ROB)
90% Completed No

NH-6 (New Km. 116.714


26 Gujarat
NH-53) (Existing LC)
40% Completed No

NH-6 (New Km.119.252


27 Gujarat
NH-53) (Existing LC)
10% Completed No

Km 356.930 of NH-8A work in progress


(Rly Km1/12-13 LC
Delay in obtaining the approval from
28 Gujarat 8A No.1-A SPL at North Yes
the Railway Authorities.
end entrance of
Gandhidham Town,
Km 10.021 of NH-8A work in progress
(Extn) (Rly Km 12/16-
8A Delay in obtaining the approval from
29 Gujarat
(Extn)
17 LC No.8B/20 Yes
the Railway Authorities.
between Adipur-Anjar
on GIM-BVJ Section)
Haryana 71 Km 386.988 on Gudda deck slab laid. 80% of the work No N.A
Bypass completed.
30

Haryana 71 Km 434.857 on Rewari deck slab laid. 80% of the work No N.A
bypass completed.
31

Haryana 71 Km 436.643 on Rewari deck slab laid. 80% of the work No N.A
bypass completed.
32

- -

33 Karnataka 13 286+317 Completed

Page 9 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

34 Karnataka 13 296+700 Under progress No

- -

35 Maharashtra 3 Khardi (Km. 494/767) Completed

- -

36 Maharashtra 3 Asangaon (Km. 514/488) Completed

- -

37 Maharashtra 3 Dhule (Km. 265/A) Completed

- -

38 Maharashtra 3 Nardana (Km. 225/800) Completed

7 Hinganghat ROB work is in progeess Yes Shifting of level crossing by Railway


Km.76.380 and Change of superstructure type from
39 Maharashtra (Rly Ch.792/2-3) PSC girder to composite girder.

Orissa 215 Joda ROB/RUB at GAD under process for approval Yes Intiallly proposal for 2-lane ROB & 2-
NH.Km. 182.579 lane RUB submitted. Further 4-lane
Padapahar-Banspani Rly. RUB proposed as suggested by
40 Block Raiways, requiring 6 months of block
period. GAD approval is in process in
Railways

Orissa 215 Roxy ROB at NH Km. GAD approved on dt. 27/01/2011 No -


234.770 Km.
Bondamunda-Kiribur
41 Rly. Section.

Orissa 215 Bimalgarh ROB NH Ch. GAD approved on dt. 27/01/2011 No -


246.258
Bondamunda-Barsuan
42 section

Orissa 6 ROB at Hirakud & GAD approved on dt.22/11/2011. Design No -


Godbhaga NH Km.11.40 submitted. Scrutiny under progress
43 & Rly. Km.571/7-8
Sambalpur- Bargarh Rly
Dvisi.

Page 10 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

Orissa 6 Bargarh By-pass GAD approved on dt.22/11/2011. Design No -


ROB(Between Attabira submitted. Scrutiny under progress
44 & Bargarh)NH
Ch.44.46(0.454 on
Bargarh By-pass) Rly
Orissa 6 Bargarh By-pass ROB GAD approved on dt.25/05/2012. Design No -
NH Km. 46.60(Km. 2.8 submitted. Scrutiny under progress
45 on Bargarh Bypass) &
Rly. Km.604.594
ACC Pvt.siding
Punjab 1A 29+756, completed - -

46

Punjab 1A 83+100 completed - -

47

Punjab 1A 111+444 completed - -

48

Punjab 22 km. 39.000 completed - -

49

Punjab 21 km. 41.000 completed - -


( Ropar)
50

Due to delay in issuance of demand


51 Rajasthan 11 Km296.665 Work in progress for approaches Yes note for super vision charges & utility
shifting estimates from Railway .

Formalities from Railway department


52 Rajasthan 12 Km25+525 Under Construction Yes i.e demand note, shifting of existing
level crossing, CRS clearance etc.

Formalities from Railway department


53 Rajasthan 12 Km68+950 Yes i.e demand note, shifting of existing
level crossing, CRS clearance etc.

- -
At Km 150/180 near
54 Tamil Nadu 7 Talaiyuthu (Tirunelveli Completed
Bypass)

- -
ROB near Palayamkottai
55 Tamil Nadu 7 and Seydunganallur at Completed
Km 161/135

- -
ROB between
Aralvaimozhi, Panagudi
56 Tamil Nadu 7
and Valliyoor stations at
Completed
Km 210/400

Page 11 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

- -

57 Tamil Nadu 47 Km 1/061 Completed

- -

58 Tamil Nadu 47 Km 22/800 Completed

- -

59 Tamil Nadu 68 Km 83/250 Completed

Uttar Pradesh 25 KM 96.339 Completed - -

60

Uttar Pradesh 25 KM 101.491 Completed - -

61

Uttar Pradesh 25 KM 119.600 Completed - -

62

Uttar Pradesh ROB in Km. 200.836 Completed - -


(Railway Km.570/7-8,
63 LC No.201-A) LMNHP-
5 in Basti district of NH-
28
Uttar Pradesh 28 ROB At km 20.42 on completed - -
Barabanki Bypass
on NH-28 Rly. Km.
1073.72
64

Uttar Pradesh 28 ROB At km 83.275 at completed - -


Rauzagaon
on NH-28 Rly. Km.
65 1010.864

Uttar Pradesh 28 ROB At km 1.250 on completed - -


Faizabad bypass
on NH-28 Rly km.
969.68
66

Page 12 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

Uttar Pradesh 28 ROB At km 1.975 on completed - -


Faizabad bypass
on NH-28 Rly km. 1.15

67

Uttar Pradesh 28 ROB At km 11.600 on completed - -


Faizabad bypass
68 on NH-28 Rly. Km.
957.69

Uttar Pradesh - -

69 58 Km. 69.489 Completed

Uttar Pradesh - -

70 58 Km. 87.600 Completed

Uttar Pradesh - -

71 58 Km. 114.289 Completed

Uttar Pradesh -
Between EP No. 8/11 &
72 91 8/12 NTPC feeder line Pier cap are under construction No
NCR, Allahabad

Uttar Pradesh -
Between EP no. 1343/15
73 91 & 1343/18 NCR Pile work under process No
Allahabad

Uttar Pradesh -
Between EP No. 1321/17
74 91 & 1321/18 NCR, Pier cap are under construction No
Allahabad

Uttar Pradesh 24 Km 159.772 Completed -

75 NO

Uttar Pradesh 24 Km 165.402 96% -


(In progress)
76 NO

Uttar Pradesh 24 Km 186.138 80% -


(In progress)
77 NO

Uttar Pradesh 24 Km 216.695 75% -


(In progress)
78 NO

Page 13 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

Uttar Pradesh 24 Km 234.812 89% -


(In progress)
79 NO

Uttar Pradesh 24 Km 246.000 60% -


(In progress)
80 NO

Uttar Pradesh 24 ROB In lieu of Level GAD approved Structural design uner approval with
crossing no. 343E at km Railways
81 289+620 and Railway Yes
km 1269+500 between
Katra and Beelpur
Uttar Pradesh 24 ROB In lieu of Level GAD uner approval GAD uner approval with Railway
crossing no. 318E at
82 331+300 and Railway Yes
km 1231.18 km between
Rauza and Shahjahanpur
Uttar Pradesh 24 ROB In lieu of Level GAD approved Structural design under approval with
crossing no. 45A at Railways
83 399+300 and Railway Yes
km 67 km between
Maholi and Hempur
Uttar Pradesh 24 Extension of 2 lane ROB GAD approved Structural design under approval with
at 4 lane ROB at Sitapur Railways
84 Bypass at km 409+000 Yes
and Railway km 56
km+200 km between
4-lane ROB over
Krishnagar-Lalgola line
in between station New
Detail design and drawing is under
85 West Bengal 34 Balrampur halt and
approval
No N.A
Berharampore on
Berharampore bypass at
Km.192.891.
4-lane ROB over Katwa-
Azimganj line between
stn. Jibanti halt-
86 West Bengal 34
Khagraghat road on
Work in progress No N.A
Berharampore bypass at
Km.199.159
2-lane ROB over Nalhati-
Azimganj line between
87 West Bengal 34 stn. Moregram- Work in progress No N.A
Sagardighi at
Km.229.734

2-lane ROB over


Azimganj-New Farakka
Detail design and drawing is under
88 West Bengal 34 line between stn.
approval
No N.A
Ballalpur Halt-Sakopara
halt at km.285.391

4-lane ROB over Malda -


Singabad Railway line
89 West Bengal 34
on Malda By-pass at Km.
Work under mobiliztion No N.A
330.843

Page 14 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

4-lane ROB over Barsoi -


Work of ROB is yet to be started as detail
Raiganj Railway line on
90 West Bengal 34
Raiganj By-pass at
design and drawing is under approval by No N.A
Railway
Km.405.802

Details of ROBs/RUBs Under taken in 2011-2012


State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No.

44 ROB at Km.310.750 of Completed. No


Nagpur-Hyderabad
1 Andhra Pradesh section. --

44 ROB at Km.336.023 of Completed. Yes Delay in obtaining the approval by


Nagpur-Hyderabad Concessionaire for the design &
2 Andhra Pradesh section. drawings from Railway Authorities.

44 ROB at Km.471.70 of Completed No


Hyderabad-Bangalore
section.
3 Andhra Pradesh --

16 ROB at 3+450 of GADs approval is in progress Yes Construction of ROB is delayed due to
Chilakaluripet-Nellore pending approval of GADs from
section. Railways.
4 Andhra Pradesh

16 ROB at 8+970 of GADs approval is in progress Yes GAD under approval with Railways
Chilakaluripet-Nellore
5 Andhra Pradesh section.

16 ROB at 1341+971 of GADs approval is in progress Yes GAD under approval with Railways
Chilakaluripet-Nellore
6 Andhra Pradesh section.

work is in progress Yes

ROB-I at Ch.79+830
7 Assam 31C
(BRPL Gate)
Delay in Utility shifting

work is in progress Yes

ROB-II at Ch. 88+123


8 Assam 31C
(SK-48)
Delay in Utility shifting

work is in progress Yes

ROB at Pathsala Delay due to LA, utility shifting &


9 Assam 31
1028+546 sanction / permission of Railway

Page 15 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

work is in progress Yes

ROB at Ghograpara Delay due to LA, utility shifting &


10 Assam 31
1075+218 sanction / permission of Railway

work is in progress Yes

ROB at Rangia Delay due to LA, utility shifting &


11 Assam 31
1082+931 sanction / permission of Railway

work is in progress Yes

ROB at Changsari Delay due to LA, utility shifting &


12 Assam 31
1113+556 sanction / permission of Railway

13 Bihar 2 km 788.65 Yet to commence No -

14 Bihar 2 km 809.05 Yet to commence No -

15 Bihar 2 km 940.8 Yet to commence No -

16 Bihar 30 km 182.57 In Progress No -

17 Bihar 30 km 207.62 In Progress No -

18 Bihar 85 km 14.217 In Progress No -

19 Bihar 85 km 27.501 In Progress No -

20 Bihar 85 km 58.421 In Progress No -

21 Bihar 85 km 91.604 Construction work to start No -

22 Bihar 77 km 6.004 In Progress No -

Page 16 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

23 Bihar 77 km 46.25 In Progress No -

24 Bihar 77 km 52.75 In Progress No -

25 Bihar 28A km 18.172 In Progress No -

26 Bihar 28A km 53.632 In Progress No -

Km. 306.67
Near Billimora
27 Gujarat 8
(LC no. 17)
Completed No NA

28 Karnataka NH-48 79/690 Completed No --

29 Karnataka 4 264/175 Completed No --

4 Km 256+732 No NA

30 Karnataka Completed

4 Km 311 No NA

31 Karnataka Completed

4 Km 328 No NA

32 Karnataka Completed

Preparation of GAD is held up for want of


handing over of land due to which soil
33 Karnataka 4A 7+100
investigation at the location is also
No --
pending.

GAD Submitted to SWR on 08.12.12.


34 Karnataka 4A 23+568
Approval awaited
No --

Page 17 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

ROB falls in the Forest area. Preparation


35 Karnataka 4A 48+430 of GAD is pending for want of clearance No --
of Forest Diversion Proposal.

ROB falls in the Forest area. Preparation


36 Karnataka 4A 65+640 of GAD is pending for want of clearance No --
of Forest Diversion Proposal.

17 ROB 4/972 Construction of substructure work of ROB Yes Due to delay in mobilization of
commenced. 13 piles out of 30 nos. have Concessionaire.
been completed.
37 Karnataka

75 & 3
(Gwalior
38 Madhya Pradesh
Bypass New
km 1+279 Completed - -
Alignment )

75 & 3
(Gwalior
39 Madhya Pradesh
Bypass New
km 7+790 Completed - -
Alignment )

Modnimb Railway Km. CRS application submitted to Railways Yes The CRS approval is awaited.
398/5-6 Authorities
40 Maharashtra 9

Mohol Railway CRS application submitted to Railways Yes The CRS approval is awaited.
Km.423/3-4 Authorities
41 Maharashtra 9

NH-17 Kharpada GAD approved

42 Maharashtra No -

NH-17 Pen GAD approved

43 Maharashtra No -

NH-17 Wadkhal GAD approval awaited from Railways

44 Maharashtra No -

7 Pimpalkutti ROB Work is in progress Yes


Km.173.450 (Rly.
Approval of structural design and
45 Maharashtra Ch.181/14-15)
drawing for staging by Railway.

Page 18 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

NH-7 Ch. 1.397 Completed No


(Nagpur &
46 Maharashtra Kamptee
Kanhan
Bypass)
NH-7 Ch. 4.973 Completed No
(Nagpur &
47 Maharashtra Kamptee
Kanhan
Bypass)
NH-7 Ch. 21.9 Completed No
(Nagpur &
48 Maharashtra Kamptee
Kanhan
Bypass)
Punjab NH-1A 115+910 completed No -

49

50 Rajasthan 14 14.64 Work in progress No -

51 Rajasthan 14 103.919 Work in progress No -

Construction of ROB at -
Km.125/605 between
Revised GAD approved on 26.11.2012.
52 Tamil Nadu 67 Tiruchirappalli and
Work to be commenced.
NO
Kumaramangalam
Stations
-
Construction of ROB at
Sub-structure design approved on
Km.22/020 between
53 Tamil Nadu 210
Kumaramangalam and
31.08.2012. NO
Sub Structure work in progress.
Keeranur Stations

Construction of four
lane ROB at Km 233/890 Due to delay in obtaining clearance
54 Tamil Nadu 7
between kanniyakumari
Completed Yes
from Southern Railway for line block.
and Suchindram stations

Due to delay in obtaining approval


55 Tamil Nadu 68 Km 68/073 Completed Yes from Southern Railway and clearance
from CRS.

Delay in obtaining clearance


Construction of ROB at
56 Tamil Nadu 45B
km 174+645
Completed Yes from Railways and
LA

Delay in obtaining clearance


Construction of ROB at
57 Tamil Nadu 45B
km 262+185
Completed Yes from Railways and
LA

Uttar Pradesh ROB in Km. 278.70 Completed _ _


(Railway Km.492/13-
58 28 14, LC No.: NA, new
alignment) Gorakhpur
Bypass Project in

Page 19 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

Uttar Pradesh Level Xing no. 8A/E3 Pile work under process NO NA
NR, New Delhi
59 91

Uttar Pradesh 275/2-3

60 91 in progress No -

Uttar Pradesh 100/13-14

61 91 in progress No -

Uttar Pradesh 45/11-12


These ROBs are part of Aligarh - Kanpur
62 91 stretch where work is yet to be started due No
to forest clearance
-
Uttar Pradesh 41/3-4
These ROBs are part of Aligarh - Kanpur
63 91 stretch where work is yet to be started due No -
to forest clearance

Details of ROBs/RUBs Under taken in 2012-2013 (Current year)


State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No

40 ROB at 290.783 of Under progress No


Kadapa-Kurnool section.
1 Andhra Pradesh -

40 ROB at 290.986 of Under progress No


Kadapa-Kurnool section.
2 Andhra Pradesh -

40 ROB at 355.839 of Under progress No


Kadapa-Kurnool section.
3 Andhra Pradesh -

163 ROB at Km.24.320 of Completed No


Hyderabad-Yadagiri
4 Andhra Pradesh -
section.

163 ROB at Km.41.843 of Completed No


Hyderabad-Yadagiri
5 Andhra Pradesh section. -

44 ROB at Km.21.640 of Under progress Yes Delayed due to poor Progress


Hyderabad-Bangalore
6 Andhra Pradesh section.

Under progress Yes


ROB-I at Ch.79+830 Few stretches affected due to utility
7 Assam 31C
(BRPL Gate) shifting

Under progress Yes


ROB-II at Ch. 88+123 Ground improvement for RE wall of
8 Assam 31C
(SK-48) ROBs in progress

Page 20 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No

Under progress Yes


ROB at Pathsala Delay due to LA, utility shifting &
9 Assam 31
1028+546 sanction / permission of Railway

Under progress Yes


ROB at Ghograpara Delay due to LA, utility shifting &
10 Assam 31
1075+218 sanction / permission of Railway

Under progress Yes


Delay due to LA, utility shifting &
11 Assam 31 At Rangia 1082+931
sanction / permission of Railway

Under progress Yes


Delay due to LA, utility shifting &
12 Assam 31 At Changsari 1113+556
sanction / permission of Railway

13 Assam 37 Thekraguri 240.110 Km Completed _ _

14 Assam 54E 58.720 Km Lumding Work in progess No NA

15 Assam 54E 122.750 Km Kalachand Work in progess No NA

Km. 179.283 between


16 Assam 54E Railway station Jatinga Yet to commenced No NA
Lampur and Ditokchera

Km. 169.617 near


17 Assam 54E
Jatinga
Yet to commenced No NA

18 Bihar 28A km 37.085 In Progress No _

19 Bihar 28A km 66.454 In Progress No _

Page 21 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No

8 km 54.865 GAD Approved No


Detailed design submitted to Railways
20 Gujarat NA

8 km 65.545 GAD under approval with Railways Yes GAD under approval with Railways

21 Gujarat

8 km 75.425 GAD under approval of Railways Yes GAD under approval of Railways

22 Gujarat

8 km 106.475 GAD approved No -----


Detailed design under preparation
23 Gujarat

Haryana NH -71A Km.11+640 Under Construction No

24 -

Haryana NH -71A Under Construction No

25 -

Km.22+745
Haryana NH -71A Under Construction No

26 -

Km.79+875
Haryana 73 Km.88.692 GAD approval in process Yes GAD of ROB under processing in
Railways
27

17 364-365 Work awarded. Preliminary works are in


progress
28 Karnataka - -

48 Km.329/1 Work awarded. Preliminary works are in


progress
29 Karnataka - -

Bijapur Railway Km. GAD approved .submission of structural No -


191/100-200 drawings and design in process
30 Karnataka 13

69 Work is in Progress No

Ch. 204/800
31 Madhya Pradesh
(Chichonda)
_

Page 22 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No

3 -

32 Madhya Pradesh Km. 492.70 GAD approved No

3 -

33 Madhya Pradesh Km.536.00 GAD approved No

34 Madhya Pradesh Km.2.09 Yes Design under preperation

GAD approved
3

35 Madhya Pradesh Km.109.9 Yes Design under preparation

GAD approved
3

36 Madhya Pradesh Km. 121.4 Yes Design under preparation

GAD approved
69 -

37 Madhya Pradesh Km.53.5 No

GAD approved
69 -

38 Madhya Pradesh 66+400 In progress No

69

39 Madhya Pradesh 66+400 Modified GAD resubmitted No

69
40 Madhya Pradesh 88+100 Modified GAD resubmitted No

26
206+111 (old km) Delay in approval of TAD drawing
41 Madhya Pradesh
211+004 (New km)
Completed Yes
from Railway

3
Delay in land acquision, delay in tree
42 Madhya Pradesh 53+145 99% completed Yes
cutting and delay in approval of CRS

Solapur Railway Km. GAD approval in process with Railways Yes The alignment is changed due to
Between 447/7 to 447/8 declaration of Rationalization of GIBS
43 Maharashtra 13 Boundary.

Page 23 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No

Solapur ROB at Km. Two lane ROB already constructed on NH - -


78+602 211 by PWD / Railways. The 4 laning
44 Maharashtra 211 project is at RFQ Stage.

45 Maharashtra 6 km. 162.907 Under completion stages No. _

km 522.293 GAD Approved -

46 Maharashtra 6 No.

GAD yet to be approved -

47 Maharashtra 6 No.

km 630.791
GAD yet to be approved -

48 Maharashtra 6 No.

640.146

49 Maharashtra 6 396+885 GAD Approved Yes Land and required clearances delayed

50 Maharashtra 6 405+603 GAD Approved Yes Land and required clearances delayed

51 Maharashtra 6 414+900 GAD Approved Yes Land and required clearances delayed

52 Maharashtra 6 426+781 GAD Approved Yes Land and required clearances delayed

53 Maharashtra 6 440+218 GAD Approved Yes Land and required clearances delayed

Ch. 5/200 (Mankapur)


54 Maharashtra 69
ROB
Work is in Progress No _

Page 24 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No

69 Work is in Progress No

55 Maharashtra Ch. 7/485 (Godhani) _

69 Work is in Progress No

Ch. 29/540
56 Maharashtra
(Khaperkheda)
_

69 Work is in Progress No

57 Maharashtra Ch. 33/350 _

69 Work is in Progress No

58 Maharashtra Ch. 38/367 _

42 km 20/950 Modified GAD complying with Rly.


Observation submitted to ECoR Khurda
59 Orissa No _

42 km 147/300 Modified GAD complying with Rly.


Observation submitted
60 Orissa No _

6 km 350/240 GAD has been approved by SEN/Bridge,


E.Co. Rly, Bhubaneswar
61 Orissa No _

6 km 561/723 GAD has been approved by Sr. Divl. Engr,


Sambalpur
62 Orissa No _

6 km 566/240 GAD has been approved by Sr. Divl. Engr,


Sambalpur
63 Orissa No _

Page 25 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No

23 km 261/281 Modified GAD has been submitted to CE,


SE.Rly
64 Orissa No _

23 km 266/500 modified GAD submitted to Dy.CE,


Rourkela
65 Orissa No _

23 km 236/718 GAD has submitted to SE. Rly, Kolkata

66 Orissa No _

Sakhigopal -
67 Orissa 203
Janakideipur
GAD Approved. Work in progress Yes Due to local site constraints

Project cost for LHS to be deposited by


Vani Vihar - the Railway Agency . Detailed
68 Orissa 5
Mancheswar
GAD Approved Yes
structural design to be approved by
Railway for RHS

5 297.154 Completed and opened to traffic w.e.f. New contractor had to be appointed
Nov 12
69 Orissa Yes

Punjab 15 14+409 Under Progress in project of Four laning No


project from Km6..082 to 108.502 of NH-
70 15 on BOT(Toll) Basis] -

Punjab 15 42+467 Under Progress in project of Four laning No


project from Km6..082 to 108.502 of NH-
71 15 on BOT(Toll) Basis] -

Punjab 15 51+533 Under Progress in project of Four laning No


project from Km6..082 to 108.502 of NH-
72 15 on BOT(Toll) Basis] -

Punjab 15 70+178, Under Progress in project of Four laning No


project from Km6..082 to 108.502 of NH-
73 15 on BOT(Toll) Basis] -

Punjab 15 78+492 Under Progress in project of Four laning No


project from Km6..082 to 108.502 of NH-
74 15 on BOT(Toll) Basis] -

Punjab 95 156+953 under on going project of Four No


Laning project from
75 Km92.00 to 170.00 of -
NH-95 on BOT(Toll) Basis

Page 26 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No

At Km 38/986 in
76 Tamil Nadu 66
Tindivanam Bypass
Work in progress. NO -

At Km 174/832 near
77 Tamil Nadu 66
Samalpatti
Work to be commenced. NO -

Yes
Additional 2-lane ROB
at KM.293+150 between Due to delay in obtaining approval
78 Tamil Nadu 205
Pudi - Renigunta
Foundation work is in progress
drawings from Southern Railway.
Stations.

Yes
Due to delay in obtaining approval
79 Tamil Nadu 68 At Km 31/500 Completed from Southern Railway and clearance
from CRS.
Uttar Pradesh 2 Km. 219 of NH-2 Completed Yes The work of Tundla ROB was delayed
due to delayed approval from Railways
80 on account of construction of 3rd track
by the Railways
Uttar Pradesh 25 KM 218.986 Completed No NA

81

Uttar Pradesh 26 KM 10.481 ROB Work is in advanced stage of Yes Delay in approval and implementation
completion
82

Uttar Pradesh 56A & 56B ROB between Dilkhusha- Completed Yes Due to delay in getting approval from
Malhour section at railways. Due to change in
83 1086/18-19 on Lucknow- methodology for launching of girder
Faizable section NH- and termination of contractor.
56A&56B Lucknow
Uttar Pradesh 25 ROB Bhighapur-Unnao under progress Yes Due to delay in getting approval from
section at NH km. 60 railway and due to this the ROB was
84 and Rly. Km. 182/6-7 deleted from his scope of work. Non
availability of soil presently hampering
Uttar Pradesh 24B Lucknow-Raebarailly, under progress No the work -
NH-24B ROB at km.
85 Rly. Km. 1026/7-8 and
NH km. 78.72
Uttar Pradesh No -

86 Lucknow-Raebarailly,
NH-24B Rly km. 993/11-
24B 12 and NH km. 81.27 under progress
Uttar Pradesh GAD Approved No -
87 2 788.650

Uttar Pradesh GAD Approved No -

88 2 809.050

Page 27 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No

Uttar Pradesh Work is yet to be srated due to forest No


clearance
89 91 1274/1-2

Uttar Pradesh At LC No. 44A (Near In progress No -


Unchahar of NH-24B
90 24B (Raebareilly-Allahabad)

Uttar Pradesh At LC No. 54A (Near GAD approval in process in Railways No -


Bhupiamu) & At LC no.
91 231 72B (Near Ramapur) of
NH-231 (Raebareilly-
Jaunpur Section)

Uttar Pradesh At LC No. NIL GAD approval in process in Railways No -


(Akbarpur Bypass), At
92 232 LC No. 73B (Near
Loharamau-Sultanpur),
At LC No. 147A (Near

Roorkee bypass, Vill.


93 Uttarakhand 58
Nagla Imarti
In progress Yes GAD approval from Railways

At Jwalapur Km.21/13-
94 Uttarakhand 58
14
In progress Yes GAD approval from Railways

At Motichur, in lieu of L.-


95 Uttarakhand 58
Xing no. 19A
In progress Yes GAD approval from Railways

At Raiwala, in lieu of
96 Uttarakhand 58
existing Raiwala RUB
In progress Yes GAD approval from Railways

km 75.955 (ROB) GAD Approved. Design under approval No. Not Applicable
from Railways
97 West Bengal 34

km 90.640 (ROB) GAD Approved. Design under approval No. Not Applicable
from Railways
98 West Bengal 34

km 95.350 (ROB) GAD Approved. Design under approval No. Not Applicable
from Railways
99 West Bengal 34

km 111.345 (ROB) GAD approved No. Not Applicable


Detailed design under preparation
100 West Bengal 34

Page 28 of 29
Details of ROBs/RUBs undertaken by NHAI during last three years (2009-10, 2010-11, 2011-12)
and current year (2012-13)

State NH. No. Location (Km) Present Status Wheather Reason for delay
delayed or Not
S No

112.215 (RUB) GAD approved No. Not Applicable


Detailed design under preparation
101 West Bengal 34

Mecheda ROB from Km Non availability of Power cum Traffic


102 West Bengal 41
1.580 to Km 2.485
In progress Yes
Block from S.E.Rly

Page 29 of 29