GCP Punch List & Percent
GCP Punch List & Percent
PROJECT : GAS COMPRESSION PACKAGE FOR GC-16 AND GAS RE-INJECTION SERVICES FOR MINAGISH, KUWAIT. KOC Contract No. 36016
3 Instrument & Plant Air Air chillers - Termination , Glanding , Earthing C 2-Dec SPETCO ELE Open No chiller installed
Welding receptickle (socket) - Power socket to Socket installed. Glanding not done
17 Instrument & Plant Air be fixed , Power cable termination , Glanding & C 2-Dec SPETCO ELE Open 20-Dec due to no reducer. Reducer to be
earthing to be done supplied by SPETCO
19 Instrument & Plant Air All electrical Cable tagging to be done C 2-Dec SPETCO ELE Close 12-Nov
35 Instrument & Plant Air All secondary tray cover to be covered C 2-Dec SPETCO ELE Close 12-Nov
70 Power Generation Tank earthing stub up required B 2-Dec SPETCO ELE Close 4-Dec
87 Power Generation Earthing stub up to be removed behind DG B 2-Dec SPETCO ELE Close 4-Dec
95 Power Generation All electrical Cable tagging to be done B 2-Dec SPETCO ELE Close 4-Dec
116 Power Generation Sealing of cable conduits required for all C 2-Dec SPETCO ELE Close General comment
132 Fuel gas System Electrical stub up to be sealed C 9-Dec SPETCO ELE Close
163 Fuel gas System All electrical cables to be tagged C 9-Dec SPETCO ELE Close General
164 Fuel gas System Cable tray cover to be placed C 9-Dec SPETCO ELE Close General
181 Closed drain Sump earthing to be checked C 9-Dec SPETCO ELE Close 15-Dec
207 Closed drain All electrical cables to be tagged C 9-Dec SPETCO ELE Close General
218 Closed drain KOD vessel earthing conduit to be done C 10-Dec SPETCO ELE Close
292 LP Gas System MOV 7155 ( to be tagged) C 13-Dec SPETCO ELE Close
304 LP Gas System SDV 5002 bottle earthing to be done B 13-Dec SPETCO ELE Close 18-Dec
313 LP Gas System SDV 5110 earthing to be done B 13-Dec SPETCO ELE Close 18-Dec
349 LP Compressor-A Earthing LPA cooler conduit not done C 13-Dec SPETCO ELE Close
04/04/2021 1 of 8
GCP PUNCH LIST CONTROL SHEET
PROJECT : GAS COMPRESSION PACKAGE FOR GC-16 AND GAS RE-INJECTION SERVICES FOR MINAGISH, KUWAIT. KOC Contract No. 36016
352 LP Compressor-A LPA power socket to be given B 13-Dec SPETCO ELE Close
370 LP Compressor-A Earthing to be given for seal pot C 13-Dec SPETCO ELE Close
372 LP Compressor-A Lighting works LPA to be completed B 13-Dec SPETCO ELE Close
378 LP Compressor-A HP scrubber earthing conduit to not given C 13-Dec SPETCO ELE Close
380 LP Compressor-A HP scrubber earthing conduit to not given C 13-Dec SPETCO ELE Close
384 LP Gas System Electrical earthing pits to be done C 13-Dec SPETCO ELE Open After grading
421 Chemical injection stub up conduit to be provided for earthing C 15-Dec SPETCO ELE Close
433 Chemical injection Earthing to be provided on both sides of skid B 15-Dec SPETCO ELE Close
508 HP Compressor-B Trench cleaning & cable to be laid properly C 16-Dec ELE Open SPETCO SCOPE
529 HP Compressor-B Fans start up switch cable tray not supported C 16-Dec ELE Close
545 LP compressor B Trench cleaning & cable to be laid properly C 16-Dec ELE Open SPETCO SCOPE
04/04/2021 2 of 8
SL.NO DISCIPLINE CATEGORY TOTAL COMPLETED
1 A 7 7
2 INSTRUMENTATION B 19 19
3 C 53 49
INSTRUMENT TOTAL ABC 79 75
4 A 2 2
5 ELECTRICAL B 11 11
6 C 43 32
ELECTRICAL TOTAL ABC 56 45
TOTAL E&I ABC 135 120
Condensa
te System
Condensa
te System