ENGINEERING SPECIFICATION
FOR
FABRICATION AND INSTALLATION
OF
CARBON STEEL PIPEWORK
To
ASME B31.3
Fuel Farm Pipework
13.03.2015
First Issue
REV.
DATE
DESCRIPTION
DOCUMENT NO:CPCAVI-BIA-SPEC-M001. PROJECT NO.
03
1 ot28714,
1.2,
CODES, STANDARDS AND TERMINOLOGY
GENERAL
Lia
142
113
The selection of Fabricator shall be subject to the approval of the company, the
basis of the Fabricator’s experience of similar work, shop facilities, production
methods, quality assurance procedures etc
The Fabricator shall not sub-contract any part of the work without the
Company's written approval.
The Fabricator shall submit to the Company for review and approval the
documentation required by the Quality Assurance Data Sheets attached to the
order.The allowable timescale for submission of documentation and the
required approval status prior to release for fabrication shall be as specified in
the QA Data Sheets
TERMINOLOGY
121
1.2.2
123
1.2.4
125
1.2.6
1.2.7
The COMPANY shall be taken to mean -that client identified as such in the
tender enquiry.
‘The PURCHASE is the authority responsible for issuing the relevant enquiry or
order, and will be The Company of the Company's nominated Contractor.
The CONTRACTOR is the organisation appointed by the Company and
responsible for the overall mechanical design and procurement of process plant
for a particular project.
‘The FABRICATOR is the organisation responsible for supplying materials,
carrying out the mechanical design where applicable, fabrication, preparation
for shipment and delivery of equipment in accordance with the Purchaser's order.
The INSPECTOR is the Company employee or duly authorised representative of
the Company, appointed to monitor material quality, workmanship and
conformance to data supplied, Standards and Codes during fabrication, testing
ete.
‘The CERTIFYING AUTHORITY is the independent Inspection Agency or other
body authorised to inspect the equipment through the various stages of
fabrication, examine and approve all documentation including design
calculations, and to certify that the equipment and documentation meet all
requirements,
Where matters have to be agreed or approved, this shall mean agreed or
approved in writing between the Purchaser and the Fabricator. Where the
Purchaser is a Contractor, he must first obtain Company agreement and
approval concerning matters in this document.
2012871.3. CODES AND STANDARDS
1.4. ALL PIPEWORK FABRICATION, TESTING, INSPECTION AND INSTALLATION
‘SHALL MEET, AS A MINIMUM STANDARD, THE REQUIREMENTS OF ANSI
831.3.CHEMICAL PLANT AND PETROLEUM REFINERY PIPING.
2. DESIGN
2.1, WELDING END AND BRANCH ATTACHMENT JOINT DESIGN
2a
Each piping branch reinforcement pad or segment therefore shall be provided
with one hole (at the side and not at the crotch) drilled and tapped 1/4” NPT.
2.2, PROXIMITY OF WELDS
224
2.2.2
The minimum distance between toes of adjacent welds shall be the lesser of
40mm or twice the wall thickness of the thickest pipe/itting
Dimensions less than those specified above are not permitted except where
Company agreement has been obtained and the following additional
requirements met:
(a) Dependent on material, thickness and configuration, the Company may
require an intermediate stress relief to be carried out.
(b) Care shall be taken to minimise stress concentrations. Weld profiles shall be
‘as smooth as possible; at the discretion of the Inspector welds may be
dressed.
() When branch welds cross or are located closer than the allowable to
main seams, such seams shall be radiographed or U/S tested for a distance
on either side of the hole of not less than the opening diameter.
(d) When attachments are located closer than the allowable to main seams
they shall cross the seam completely. The seam shall be radiographed to
the extent which will be covered by the attachment, plus on either side of
the attachment, a distance of twice the pipe wall thickness.
2.3. THERMAL RELIEF PROVISION
23.1
Al protection sections of pipelines where locked in legs of product can exist shall
be protected with thermal relief. Thermal Relief assemblies should straddle the
isolation point closest to storage.it is likely that on one pipeline a series of
thermal relief assemblies will be required. It is essential that the set pressure on
the relief valves are properly selected to ensure the cascade effect valves limits
the maximum line pressure to below the design rating of the pipeline and/or any
underated piece of equipment that may be present on the particular system.
Thermal relief assemblies “cascade” back towards storage. Each thermal relief
assembly shall consist of flanged thermal relief valve. The contractor shall
ensure all pipelines are adequately protected against thermal expansion of
product throughout the phase of the work.
30128734.
32,
4a.
PIPE CUTTING AND WELDING EDGE PREPARATION
METHOD
3.1.1 Pipes shall be cut either by mechanical means or by thermal cutting.
3.1.2 End bevelling shall be done by machining, hand grinding or machine flame cutting.
3.1.3. Where thermal cutting is employed, all slag, oxides and traces of previously
melted metal shall be removed from welding edges by grinding or machining to
sound metal
3.1.4 The preheat level to be used for thermal cutting shall be as required by the
relevant welding procedure.
3.1.5 The bevel geometry shall be the same as and within the tolerances stated
in the approved welding procedure.
INSPECTION
3.2.1 After the material has been prepared for welding it shall be visually examined to
confirm the surface within 25mm of the bevel edge is smooth and uniform,
free from cracks, tears, laminations, gouges and any other discontinuities which
may affect the integrity of the weld. if there is any indication of defects the weld
preparation area shall be subjected to surface crack detection.Where any
defects are found the weld bevel shall be re- prepared and re-examined.
PIPE BENDING
GENERAL
4.1.1 Unless otherwise specified on drawings or Piping Class documents bends in
piping shall be achieved using standard elbows,
4.1.2 Where bending is required this may be performed either in the hot or cold
condition and shall be carried out in accordance with ANSI 831.3 except as
modified below. The bending and heat treatment procedures proposed by the
Fabricator shall be subject to the approval of the Company.
4.1.3 The bend centre line radius shall be 5 times the nominal pipe diameter unless
otherwise stated on the drawings.
4.1.4 Pipe bends shall be fabricated using seamless pipe and shall have no girth welds.
4.1.5 Bends shall not be wrinkled, cracked, scratched, gouged, die marked or
buckled and shall be in one plane.
4.1.6 Weld repair or pipe bends shall not be permitted.
4.1.7 ‘Cutand shut’, creased or corrugated bends are not permitted.
40128742.
43.
5.1.
HOT BENDING
424
422
423
424
425
426
Hot bending shall be carried out and completed at a metal temperature
above the upper critical point (AC3), within the range 900 degrees celsius.
Heat treatment after bending is not required unless the finished bend
hardness exceeds 225 BHN (237 VPN), or otherwise specified on the drawings
or Piping Class documents, in which case a normalising operation shall be
carried out at 900-950 degrees celsius.
The temperature and furnace atmosphere shall be carefully controlled during
the bending and any subsequent heat treatment cycle to avoid excessive
scaling, carburisation or de- carburisation.
It is recommended that pipes 2” n.b and larger be packed with dry,
sulphur free silica sand before hot bending. The sand shall be completely
removed after bending.
The bore of completed bends shall be visually examined to ensure freedom
from excessive scaling, which may be removed by pickling, blasting or
mechanical means. When pickling is used the procedure shall be subject to
Company approval.
For pipework in sub-zero temperature service hot formed bends shall be
normalised at 900 degrees celsius 950 degrees celsius, unless it can be
demonstrated that the temperature control during hot forming results in the
item having the same mechanical properties as if is was normalised.
MITRE BENDS
43.1
432
Mitre bends shall only be used when specified by the drawings or
piping Class documents.
Mitre bends shall be produced by butt welding together segments cut
from the same length of pipe. The maximum change of direction between
adjacent segments shall be 30 degrees.
FLANGED JOINTS
GENERAL
5.11
Prior to welding on a slip-on flange the bore of the flange and the pipe end
for a distance equal to the flange thickness plus 25mm minimum shall be
cleared free from any protective coating, oil, grease, loose scale or rust. The
difference between the diameter of the flange bore and the outside of the
pipe shall not exceed Smm. Care shall be taken when applying the inside
fillet weld to avoid damaging the facing. The flange shall be positioned such
that the distance from the face to the pipe end is equal to the pipe wall
thickness plus 3mm.
5012876.1.
5.1.2
513
5.1.4
515
Flange bolt holes shall straddle the vertical or NS centre line as applicable,
except where otherwise specified on the piping drawings, and shall match
the orientation of the mating flanges.
Loose flanges shall be bolted to an adjacent flanged piece for shipment or
supplied in hessian or canvas sacks securely attached to that part of the
fabrication.
Flange facing shall be in accordance with the applicable Piping Class
document. Should warping take place during the fabrication the joint
contact surfaces may be restored by machining to their original accuracy
provided the flange thickness dimensions are not reduced below the
minimum required by the relevant ANSI flange specification.
Pipe ends connected to threaded flanges shall not project through to
form part of the gasket surface.
WELDING
GENERAL
611
612
613
614
61s
The Fabricator shall provide adequate and systematic supervision by
competent personnel to ensure that the required quality levels are
maintained. At the discretion of the Inspector, any welder who consistently
fails to meet the standard shall be required to undergo re-training, re-testing
or shall be removed from the job completely.
All welding shall be carried out in accordance with qualified and
approved weld procedures by welders who have been qualified to the
relevant testing code.
The Fabricator shall make maximum effort to ensure that arc strikes outside
the welding groove are avoided. When these occur outside of the finished
weld the arc strike shall be carefully removed by grinding, followed by a
magnetic particle or dye penetrant inspection of the ground area to confirm it
is defect free. Care shall be taken to ensure the ground area ‘blends in’
smoothly with the surrounding material such that no sharp notch results and
the thickness is not reduced below the required minimum wall thickness
shall be carried out in accordance with an approved repair procedure. The
acceptance of arc strikes outside of the welding groove shall be at the sole
discretion of the Inspector who shall be requested to inspect the damage and
approve the repair procedure or reject the damage material as appropriate.
Weld stops and starts shall be staggered by 50mm minimum such that
adjacent passes or layers do not coincide. Weld stops and starts shall be
ground or chipped prior to laying subsequent passes.
The number of weld shall be minimised. Pipe lengths smaller than 1m shall
not normally be welded together.
6 0128762.
63.
6.4,
65.
6.1.6 Internals of inline valves and equipment which may be damaged due to heat
transfer from the welding process shall be removed prior to welding wherever
possible.
BUTT WELDS
6.2.1 All pressure containing butt welds shall be full penetration. Where access
permits consideration shall be given to welding from both sides.
6.2.2 Permanent backing strips shall not be used. Temporary backing strips may be
used only when approved by the Company. The material for temporary steel
backing strips shall be of the same nominal composition as the parent
material. After completion of welding the backing strips shall be removed
and the area dye-penetrant examined to confirm the absence of significant
defects. Alternative types of backing materials shall only be used where
approval has been obtained from the Company.
BRANCH WELDS
6.3.1 All welded branch connection shall be joined to the header with full
penetration welds of comparable quality to, and subject to the same
limitations (fit-up, alignment, welding process etc) as girth welds, unless
otherwise specified.
6.3.2. Piping branch reinforcement pads shall preferably be one piece but when
not practicable pads may be split circumferentially or along the axial
centreline and welded together by full thickness/full penetration welds
6.3.3 Reinforcing pads for branches and structural attachments shall be accurately
shaped and fitted to ensure that the gap between the periphery of the pad
and the pipe outside diameter is not greater than 1.5mm.
FILLET WELDS
6.4.1 A minimum of two runs shall be deposited for all permanent attachments
to pressure parts where strength requirements permit, one weld run shall be
acceptable for weld to non-pressure containing parts.
6.4.2 All fillet welds shall be continuous and their surfaces shall be free from
marked irregularities.All fillet welds shall be overlapped at the stop-start
position by at least 10mm
SOCKET WELDS
6.5.1 Care shall be taken during the assemble of socket weld joints to ensure there
isa 1.5mm gap between the pipe end and root face of the fitting.
6.5.2. Welds shall be fillet welds deposited by the MMA or TIG process, with a
minimum of two runs. The weld surface shall be free from marked
irregularities.
70128766.
67.
68.
ATTACHMENTS TO THIN WALL PIPES.
6.6.1 Where attachments are to be made thin walled piping ie. less than Smm
thick, care shall be taken to avoid excessive oxidation or burn through.
An inert gas purge shall be applied to the bore necessary. Where access
to the bore surface for cleaning and inspection is not possible the inert gas
purge is mandatory.
6.6.2 In order to demonstrate the suitability of the weld procedure the Company
may require a test weld to be made on pipe of the minimum contract
thickness. Similarly the Company may require Welders to be tested on their
ability to weld attachments to the thin wall pipes even if their qualification
range apparently covers the thin wall situation.
ALIGNMENT
6.7.1. The ends of piping components to be butt welded shall be accurately
aligned in accordance with the requirements on ANSI 831.3. The maximum
internal misalignment shall be 1.5mm except that where the pipe wall
thickness is less than 6mm the internal misalignment shall not exceed 25% of
the wall thickness.
6.7.2. Where mis-match of the bores results in misalignment greater than that
permitted above, this shall preferably be corrected by taper or
counterboring in accordance with ANS! B31.3. Permitted alternatives to
machining are:
(a) Roller expanding for pipes up to 4” nb.
() Cold drifting with a slow taper drift provided the diameter is not
increased more than 3%.
6.7.3. Care shall be taken to ensure that the wall thickness after machining,
expanding or drifting is not reduced below 87.5% of the nominal thickness.
FIT-UP & TEMPORARY ATTACHMENTS.
6.8.1 Parts to be welded shall be carefully aligned and held securely in
position by clamps, tack welds in the welding groove, bridge pieces or
wedges.
6.8.2 All welding of fit-up tacks and temporary attachments shall be
performed by qualified welders using qualified procedures and the
preheat level specified by the procedure.
6.8.3 Where tack welds are to be incorporated into the main welds they
shall be of a length such that they become part of the proposed root
pass and their ends shall be ground. Defective tack welds, and those
which are not to be incorporated into the root pass, shall be
completely removed by grinding, following completion of welding
8 0128769.
6.10.
6.11.
6.8.4. Temporary attachments shall be of the same nominal composition as
the parent material. They shall be removed by cutting 3mm above the
surface followed by grinding flush. The area shall then be surface
crack detected to confirm the absence of defects.
PROTECTION FROM WEATHER
6.9.1 The welder and welding area shall always be adequately protected from the
weather so that the weld integrity is not detrimentally affected by wind,
rain or snow or from the decline of the welder’s ability when working at
low temperatures or other adverse conditions. The continuation of welding
indoor weather conditions shall be at the discretion of the inspector.
6.9.2. Weld areas shall be kept dry throughout the complete welding cycle until
after the weld has cooled. Metal surfaces which are damp or below 5
degrees the commencement for a minimum of 100mm on either side of the
weld, taking care to avoid hot spots.
6.3.3 Where gas shielded welding is employed, special care shall be taken to
protect the welding area from draughts
WELD CLEANING, BACK GOUGING AND REPAIR
6.10.1 After each welding pass the weld shall be thoroughly cleaned and all slag
and foreign matter removed before the next run is deposited
6.10.2 Peening of weld runs or the finished welds shall not be permitted,
6.10.3 The removal of weld defects shall preferably be carried out by grinding,
machining or chipping. Arc or oxygen gouging may also be used, provided
all slag and oxidation is removed by grinding from the gouged surfaces.
6.10.4 Welds which have been repaired and remain defective shall be cut out
completely and re- welded in accordance with the original procedure, except
where the Inspector authorises one further repair attempt. In no case shall
more than 2 repair attempts be permitted
6.10.5 All weld repairs shall be performed by qualified welders using an approved
repair procedure.
WELDED PROCESSES
6.11.1 Except where otherwise agreed, welds shall be made by the manual
metal arc (MMA), tungsten inert gas (TIG), metal inert gas (MIG) or
submerged arc welding (SAW) processes.
6.11.2 The oxyacetylene process is permitted only for joints in pipe sizes
6.11.3 Where root runs are made by the MMA process, the electrode shall not
be larger than 2.5mm diameter.
9012877A.
72.
8.1.
6114
611s
6116
If the TIG process is proposed, a high frequency arc initiation unit and
crater eliminating device shall be used. The electrode shall be 2% thoriated
tungsten, 2.5 to 3.0mm diameter.
The MIG process may be used where the Fabricator can demonstrate he is.
capable of reliably producing full penetration, full fusion welds.
The SAW process may be used for circumferential joint filler runs onto root
runs made by some other acceptable process/method. Recycling of flux
shall only be permitted after Company approval of the Fabricators
WELDING CONSUMABLES
SPECIFICATION & SELECTION
Tad
712
743
All consumables such as coated electrodes, bare wire, fluxes and gases
shall comply with the applicable AWS of British Standard. Other
consumables may also be used provided full details of chemical and
mechanical properties, and service experience are submitted and approval
obtained from the Company.
Shielding gases shall normally be one of the following, depending on the
particular application
(a) Argon to BS 4365
(b) Argon/oxygen mixtures consisting of argon to BS 4365 with up to 5%
oxygen to BS 4365. Total impurities 0.07% maximum.
(c)_Argon/carbon dioxide mixtures consisting of argon to BS 4365 with
up to 25% carbon dioxide to BS 4105 type 1 and up to 5% oxygen (if
required) to BS 4363,
Other gases may also be considered where they have been proved
satisfactory by the weld procedure qualification tests and any other tests
deemed necessary by the Company.
Gases for back purging shall be argon as specified above or nitrogen to BS
4366 type 1.
STORAGE, PROTECTION AND BAKING
724
The Storage, protection and baking of all welding electrodes, filler wires
and fluxes shall be in accordance with the Manufacturer's recommendations.
WELDING PROCEDURE & WELDER QUALIFICATION
GENERAL
g11
All pressure containing welds and welds made onto pressure parts shall be
made in accordance with a procedure written and qualified in accordance
with the ASME Boiler & Pressure Vessel Code Section IX. No welding shall
be carried out until the procedure have been approved and the test results
accepted by the Company.
100126782.
10.
B12
813
B14
Each welding procedure shall be given a reference number and shall be cross
referenced to construction drawing and to the applicable qualification
records,
All welders shall be qualified in accordance with the requirements of the
ASME Boller and pressure Vessel Code Section IX.
Each Welder shall be assigned an identification number, letter or symbol,
and a complete circumference of 5% of above ground welds shall be
radiographed. The radiographs shall be retained for examination and
approval by the Company.
REPAIR PROCEDURES
821
All weld repairs shall be carried out in accordance with written procedures
which shall be submitted to the Company for approval.
FABRICATION TOLERANCES
94
9.2
93
94
Fabrication tolerances shall be in accordance with the specified codes and
standards, supplemented by the requirements given below.
Flattening of a bend, as measured by the difference between the maximum
and minimum outside diameter at any cross section shall not exceed 8% of
the original outside
diameter of the pipe for internal pressure and 3% for external.
Flange alignment tolerances shall be as stated in Appendix A figure 1.
The tolerances on linear dimensions involved in the relative positions of
branches, bosses, flanged ends, flow instrument tappings and changes of
direction shall be as stated in Appendix A figure 2. Also given in this figure
are tolerances on pipe bending and across the land of prepared welding ends.
INSPECTION AND TESTING
GENERAL
10.1.1
10.1.2
The Inspector shall have free access to all parts of the Fabricator’s Works
engaged in the manufacture of pipework and shall have the right to inspect
any aspect of the work during fabrication, installation, testing or an
completion. The Fabricator shall afford the Inspector all reasonable facilities
to allow these inspection functions to be fulfilled. All tests and
inspections shall be conducted at the place of fabrication unless otherwise
stated.
The Fabricator is required to have an identification system such that each
component part can be identified against the Mill Test Certificates and that
all weld seems can be identified with the welder or welding operator and
welding procedure specification.
110126710.2, INSPECTION CLASSES
10.2.1 Piping Systems are classified on the basis of service and material. The
applicable inspection class shall be as specified on the Piping Class document.
10.2.2 The extent of inspection to be carried out for each inspection class is
shown in table 14.2.2.
10.2.3 In addition to the requirements of table 14.2.2, the following welds shall
be subject to 100% radiographic examination unless otherwise agreed with
the Company.
(a) Mitre bends
{b) Underground Welds
TABLE 14.2.2 EXTENT OF INSPECTION
NozzLE | ATTACHMENT | SOCKET
cuass | metHoD | uTTweLDs | Wein, WELDS WELDS
Visual 100% 100% 100% 100%
Radiographic 100%
Ultrasonic 100%
Magnetic 100% 100% 100% 100%
Particie
Visual 100% 100% 100% 100%
100% Exposure
| Radiographic | “256. crjoints
Magnetic
Particie
Visual 100% 100% 100% 100%
100% Exposure
ur [Ragieeraphiec | 2086 of Joints
Magnetic
Particie
Visual 100% 100% 100% 100%
iy _ [Radiographic
Magnetic
Particie
1201267a
PRESSURE TESTING
11.1 All flanged piping assemblies shall be hydrostatically tested in the
Fabricator’s works prior to shipment. The test medium shall be potable
water, unless otherwise specified. The water temperature shall be
maintained above 7 degrees celsius or the ductle/brittle transition
temperature, whichever is the higher, throughout the test.
11.2 _ Other piping assemblies, such as those with Welding ends, do not require to
be hydrostatically tested at the Fabricator’s works. In this case however the
Fabricator remains responsible for any defects causing leakage or failure in
his fabrication found during the site test of the erected pipework
11.3. Erected pipework shall be pressure tested in accordance with ANSI 831.3
Chemical Plant and Petroleum Refinery Piping,
11.4 All pressure tests shall be carried out in the pressure of the Inspector and
shall be to his satisfaction. The test pressure shall be maintained for a
sufficient time to enable a thorough examination to be made for leakage
and defects, with a minimum of 30 minutes.
11.5 _ Prior to pressure testing being carried out the inside of the pipework shall be
clean and free from loose millscale and foreign matter.
12. QUALITY CONTROL
12.1 GENERAL
12.1.1 The Fabricator shall afford the Company and/or the Certifying Authority
adequate opportunity and facility to verify that the design, material,
construction and performance of the equipment is in accordance with
Company requirements.
12.1.2 Any verification of quality carried out by the Company and/or the Certifying
Authority shall not relieve the Fabricator of his obligations under the
contract nor shall it preclude any subsequent rejection of items.
13, TREATMENT AFTER FABRICATION
13.1. CLEANING AND PROTECTION
13.1.2 On completion of the fabrication, prior to shipment, the Fabricator shall
clean the inside and outside of all fabricated assemblies of loose scale, dirt,
sand, weld spatter and swarf using any suitable method. The assembly shall
then be blown out with compressed air, dried and the inside inspected for
cleanliness.
13.1.2 Where there are any special requirements, such as wire brushing, spot or
gritblasting, then these shall be specified on the fabrication drawings and
purchase orders.
130126714.
14.1
1313
B14
B15
13.1.6
13.7
Welding ends shall be clean and ready for welding. Unless otherwise
specified, the welding end shall be blanked off and protected from
corrosion or mechanical damage. Rigid plugs or discs of non-absorbent
material securely held in position shall be provided and the pipe ends, discs
or plugs shall be sealed off using ‘Denso’ paste and tape or an approved
alternative.
flanged ends shall be blanked off using 10mm thick plywood or 3mm thick
steel covers secured by a minimum of four bolts after the faces have been
protected with a hard film coating to BS 1133, Section 6, Type T.P.la or
agreed alternative.
Threaded connections shall be sealed using distinctively colour-identified
screwed plastic plugs or caps.
Piping and components shall be stored under cover out of contact with the
ground and shall be regularly examined to ensure the materials do not
deteriorate. Corrosion protection shall be renewed as necessary. Pipe or
piping components shall be protected from exposure to salt water or salt
spray.
The external surfaces of carbon steel pipework shall be coated with
temporary corrosion preventative or base primed when specific in the
fabrication drawings or purchase orders.
13.2. MARKING
13.2.1 All fabrication spool pieces shall be clearly marked and identified prior to
shipment in accordance with the following paragraphs or as otherwise
specified in the purchase order. All markings shall be applied after the
application of any permanent protective coatings which have been called for.
13.2.2 Fabricated spools requiring trial shop assembly shall be match marked with
scribed lines in white paint to facilitate erection,
INSTALLATION
GENERAL
14.1.1 All pipework shall be inspected prior to erection to ensure it is free from
dirt, scale, weld spatter and other foreign matter.
14.1.2 Except where cold springing is specified on the piping drawings, all
piping shall be installed in place without springing or forcing,
14.1.3 Field run piping is restricted to line sizes below 50 ns. It shall be run
generally in accordance with the routing indicated on the piping drawings, in
a neat and orderly manner consistent with good operation, safety of
personnel and economy of material, with adequate provisions for
expansion and flexibility.
140126714.2
14.3
14.4
FLANGED JOINTS
14.2.1
14.2.2
142.3
14.2.4
14.2.5
14.2.6
14.2.7
Flanged faces shall be cleaned of all dirt, grease and protective coating
and shall be inspected for defects such as scratches or dents prior to
installation,
Flanges shall be properly aligned prior to the insertation of gaskets and
bolts to avoid stresses or uneven gasket loads. See Appendix A figure 1 for
flange alignment tolerance,
Where specified by the Company, bolts shall be tightened by means of
suitable torque wrenches or tensioning devices to ensure the correct bolt
stress is obtained and the gasket is properly compressed in accordance with
the design principals applicable to the gasket type.
All bolts shall extend completely though their nuts. The use of washers
or spacers to take up excess bolt length shall not be permitted.
Stud bolts cut from length of studding shall have the material grade
stamped on the cut ends.
Steel to cast iron flanged joints shall be assembled with care to prevent
damage to the cast iron flange.
Joint Rings shall be non-asbestos 1.6m thick in accordance with the
general specification.
EQUIPMENT FLANGE CONNECTIONS
143.1
14.3.2
Flange covers shall not be removed from equipment flange connections
until ready to connect the mating piping,
Connections to strain sensitive equipment shall not be made until the
mating piping has been fully erected complete with permanent supports.
Prior to bolting up to the equipment flange the connection shall be
checked for correct alignment.
‘SCREWED PIPEWORK
14.4.1
Pipe ends cut shall be cut square, threaded, reamed and cleaned to
remove cuttings from internal and external surfaces. All threading shall be
carried out after bending, forging or heat treatment but where this is not
possible suitable thread protection must be provided. All screwed
connections shall have taper threads in accordance with API unless
otherwise stated.
1501267148
15
14.4.2 All joints shall be tightened using a suitable wrench; connection 50 ns and
larger shall be tightened using a ‘RIGID compound leverage pipe wrench’
cr equivalent. Excessive wrench markings on pipe and fittings shall be
cause for rejection of the fabrication at the discretion of the Inspector.
14.4.3 The joints shall be assembled using a suitable Petroleum resistant pipe
jointing compound which shall be applied to the male thread only, taking
care to ensure the compound does not reach the inside of the pipe. PTFE
tape shall not be used.
PIPE SUPPORTS.
14.5.1 Where pipe supports are required to be welded to the pipe, as specif
the drawings, this shall be carried out during the fabrication of the pipe
spool, with the exception of pipe support shoes which are generally welded
during installation,
14.5.2 The Fabricator shall ensure there is adequate field fit margin in the pipe
supports to allow the piping to be installed without forcing,
14.5.3. The burning of holes in structural steelwork or component parts shall not be
permitted.
14.5.4 Adjacent structures or equipment shall not be used as temporary
supporting or lifting attachments without the permission of the Company.
14.5.5 Metallic surfaces of supports which will be inaccessible after erection shall
receive a protective coating before assembly in accordance with Company
Standard Surface Coatings.
14.5.6 Pipe reinforcement pads on supports, anchors, etc shall be provided with one
hole (at the side and not at the crotch) drilled and tapped 1/4" N.P.T.
ADDENDUM TO GENERAL PIPEWORK SPECIFICATION,
15.1 CLEANING
All flanges of pipes, valves, fittings, filters, pumps etc are to be thoroughly
cleaned of all rust, protective coatings etc, before assembly.
At the completion of a days work and at any time when the end of a pipeline
is left unattached, the end of the pipe shall be closed by a suitable protector
in the form of a wooden blank. All piping after hydrostatic testing shall be
thoroughly dried internally
15.2 PIPE OFFCUTS
Wherever possible and economic the Contractor shall make use of short
lengths of pipe.
180126715.3
15.4
15.5
16.1
BENDING
All bends shall be true to radius and the bore of the pipe at any point after
bending shall not vary be more than plus or minus 1/8” from the bore of the
pipe before bending,
Lobster back or gusseted bends will not be accepted. The bend centreline
radius shall be 5 times the normal pipe diameter unless stated otherwise.
BOLTING
The contractor shall include in his supply for all studbolts, bolts, nuts etc. All
bolts shall be the correct length to ensure that all thread on nuts are engaged
and that the end of the bolt does not project more than 3mm from the upper
face of the nut when tightened.
TESTING
Test pressures shall be held steady at the required pressure for a period of
four hours, without further use of the test pressurising pump,
Testing shall not be carried out when there is any likelihood of the water
freezing in the pipework, the Contractor shall be responsible for repairing and
re-testing the damaged pipework and fittings.
For all tests, vents shall be located at the high points in the system, or of the
section to be tested, in order to ensure compete displacement of air from the
system.
All equipment likely to sustain damage during the test is to be removed from
the pipeline, control valves are to be left in the open position.
Records are to be kept of each test. The information to be recorded is to be
as follows:
i) Pipeline or system tested
ii) Testing Medium
iil) Test Pressure
iii) Temperature of Testing Medium
iv) Date of Test
vi) Signature of the Company's Engineer
vil) Signature of Agent or Contractors Supervisor
16. STAINLESS STEEL PIPING AND FITTINGS
Design
‘The design of piping systems shall comply the following:
All pipework fabrication, testing, inspection and installation shall meet as a
minimum standard the requirements of ANSI 831.4 ‘Chemical Plant and
Petroleum Refinery Piping’.
70126716.2
16.3
16.4
16.5
16.6
16.7
16.8
PIPES
Materials shall be in accordance with ANSI Type 316 Grade 18/8. Austenitic
Stainless Steel, clean smooth and free from scratches to ASTM A-269 or
equivalent,
General
Field run piping shall be run generally in accordance with the routing
indicated on the piping drawings, in neat and orderly manner consistent
with good operation safety of personnel and economy of material
Connections
All joints except where butt welded to change from tube, in nominal pipe
size shall be gauge cable double ferrule compression tube fittings in 316
stainless steel Swagelok or approved equivalent, complete with gap
inspection gauge. A thread sealant shall be applied when assembling
threaded fittings, Liquid PTFE or approved equivalent.
Flanges shall be drilled to ANSI class 150 to match existing. Flange bolts
shall straddle the vertical or NS centreline as applicable.
Joint rings shall be non asbestos 1.6mm thick in accordance with
the General Specification.
Supports
Pipework shall be adequately supported in trays. Pipework shall be fixed to
horizontal trays with Stauff polypropelene clamps or equivalent. Pipework
shall be adequately supported and securely fixed immediately before and
after a bend or offset and at 0.5m maximum pitch.
All carbon steel supports shall be isolated from pipe to prevent electrolytic
corrosion.
Identification
Each pipe shall be clearly identified; labels shall be fitted during erection or
pipework
Snubbers or Pulsation Dampers
Where conditions for steady instrument readings are required due to
pulsations a snubber or pulsation damper shall be provided.
Testing-
A pressure and operating test shall be applied to the complete assembled
system. Testing shall be by pneumatic test to 20 PSI and a soap solution
applied to all joints in accordance with the General Pipework Specification.
All leaks shall be rectified and all connections proved fully leak proof before
the system is considered acceptable.
180126716.9
16.10
Flushing of the system
The injection system shall be final flushed using a suitable medium. During
flushing, all injector cubicles, control valves and flow meters shall be
removed, where practical, or by- passed using hoses.
Installation Stainless Steel ipework
The use of elbows shall be kept to a minimum, bends and offsets shall be cold
formed wherever possible. Bends shall not be wrinkled, cracked, scratched,
gouged or die- marked or buckled and shall be in one plane.
Where connections are required in multi-line pipework, pipe connections
shall be staggered to allow for maintenance.
Welding
‘The Fabricator shall provide adequate and systematic supervision by
competent personnel to ensure that the required quality levels are
maintained. At the discretion of the Engineer, any welder who consistently
fails to meet the standard shall be required to undergo re-training, re-testing
of shall be removed from the job completely.
All welding shall be carried out in accordance with the qualified and approved
weld procedure by welders who have been qualified to the relevant testing
code.
‘The Contractor shall make maximum effort to ensure that arc strikes outside
the welding groove are avoided. When these occur outside of the finished
weld the arc strike shall be carefully removed by grinding, followed by a dye
penetrant inspection of the ground area to confirm it is defect free. Care
shall be taken to ensure the ground is ‘blends in’
smoothly with the surrounding material such that no sharp notch results and
the thickness is not reduced with an approved repair procedure. The
acceptance of arc strikes outside of the welding groove shall be at the sole
discretion of the Engineer, who shall be requested to inspect the damage and
approved the repair procedure or reject the damaged material as
appropriate.
‘The number of welds shall be minimised. Pipe lengths smaller than 1m shall
not normally be welded together.
Butt Welds
All pressure containing butt welds shall be full penetration. Where access
permits consideration shall be given to welding both sides.
1901267Fillet Welds
‘A minimum of two runs shall be deposited for all permanent attachments to
pressure parts
All fillet welds shall be continuous and their surfaces free from marked
irregularities.
Socket Welds
Care shall be taken during the assembly of socket weld joints to ensure there
isa 1.5mm gap between pipe end and the root face of the fitting.
Welds shall be fillet welds deposited by MMA or TIG process with a minimum
of two runs,
‘Attachments te Thin Wall Pipes
Where attachments are to be made to thin walled piping i.e. less than Smm
thick, care shall be taken to avoid excessive oxidation or burn through. An
inert gas purge shall be applied to the bore surface.
In order to demonstrate the suitability of the weld procedure the Company
may require a test weld to be made on pipe of the minimum contract
thickness. Similarly the Company requires Welders to be tested on their
ability to weld attachments to the thin wall pipes even if their qualification
range apparently covers the thin wall situation,
Alignment
‘The ends of piping components to be butt welded shall accurately aligned in
accordance with the requirements of ANS! B31.1. The maximum internal
misalignment shall be
1.5mm except that where the pipe wall thickness is less than 6mm, the
internal misalignment shall not exceed 25% of the wall thickness.
Weld Cleaning, Back Gouging and Repair
Aiter each welding pass the weld shall be thoroughly cleaned and all slag and
foreign matter removed before the next run is deposited. Peening of weld
runs or the finished welds shall not be permitted.
The removal of weld defects shall be carried out by grinding, machining or
chipping. Arc or oxygen gouging shall not be used.
Welds which have been repaired and remain defective shall be cut out
completely and re- welded in accordance with the original procedure, except
where the Inspector authorises one further attempt. In no case shall more
than 2 repair attempts be permitted.
2o0f20716.10.1
16.10.2
16.103
All weld repairs shall be performed by qualified welders using an approved
repair procedure.
Welding Processes
Except where otherwise agreed, welds shall be made by the manual metal arc
(MMA), tungsten inert gas (MIG) or submerged arc welding (SAW) processes.
Where root runs are made by the MMA process, the electrode shall not be
larger than 2.5mm diameter.
if the TIG processes, a high frequency arc initiation unit and crater eliminating
device with a 10 second minimum delay sequence shall be used. The electrode
shall be 2% thoriated tungten, 1.5 to 3.0mm diameter.
Welding Consumables Specification and Selection
All consumables such as coated electrodes, bare wire, fluxes and gases shall
comply with the applicable AWS or British Standard. Other consumable may
also be used provided full details of chemical and mechanical properties, and
service experience are submitted, and approval obtained from the Company.
Welding electrodes and filler wires shall be selected to give a deposited weld
metal similar in composition to the parent metal. Unless otherwise specified
austenitic welds have a ferrite content of between 3% and 10%.
Filler metal for welds between austenitic stainless steels and ferritic or ferritic
alloy steels shall be subject to agreement but shall normally be of the £309,
Incoweld A or Inconel 182 type or equivalent. Where Post Weld Heat
Treatment is required, the Incoweld A or Inconel 182 type shall be used.
Preheat and PWHT shall be required by the ferritic material.
‘The shielding gas for the TIG process shall be argon to BS 4365. The purge gas
shall be argon to BS 4365 or dry nitrogen to BS 4366, type 1. No other gas or
gas mixture shall be used without prior approval of the Company.
‘Storage, protection and Baking
‘The storage, protection and baking of all welding electrodes, filler wires and
fluxes shall be in accordance with the Manufacturer's recommendations.
Protection from Weather
‘The welder and welding area shall always be adequately protected from the
Weather so that the integrity is not detrimentally affected by wind, rain or snow
or from the decline of the welder’s ability when working at low temperature or
other adverse conditions.
2 of20717 BLANK
18 MATERIAL SPECIFICATIONS.
Maximum Pressure
Maximum Temperature
Piping Design Code
Line Pipe
Si e Range (NPS)
15-40
50-150
200-350
Flanges — Forged
Butt Weld Fittings
Reinforced Branch Fittir
Gaskets
Bolting
19.2 Bar for class 150 systems
soc
‘ASME B31.3
Seamless A.P.I. SL Gr B (Carbon Content 0.23% Max)
Description
Schedule 80 P.E,
Schedule 40 B.E.
Schedule 40 B.E.
MAT ASTM A105 N (Carbon Content 0.23% Max)
DIMN ANSI 8 16.55 CLASS 150,
Finish — MSS SP 44
incl
Welding Neck — Note: To Match Pipe Wall Thickness
Slip-on
Blind
Matt ASTM A234 WPB (Carbon Content 0.23% Max)
DIM ANSI B16.9
Incl
Eccentric Weld Reducer
Concentric Weld Reducer
Equal Tee
90% Long Radius Weld Elbow
45% Long Radius Weld Elbow
NOTE — All To Match Pipe Wall Thickness
mat! ASTM A105 N (Carbon Content 0.25% Max)
‘Spec Bonney Forge Or Equal
Incl
Weldolet
Sockolet
Elbolet
Thredolet
Latrolet
NOTE- Weight / Rating To Match Pipe Wall Thickness
Non Asbestos Klingersil C4400 (OR EQUAL)
1.6 Mm Thk Flat Ring - Richard Klinger
Stud Bolts ASTM A193 Gr B7
Nuts ASTM A194 Gr 2H
mot2e7NoTEs:
Minimum pipe size 15nps
All forgings shall be normalised & tempered
Carbon content shall be limited to 0.23% max for pipe & 0.25% max for other items
(carbon equivalent shall be limited to 0.45% max)
Where flanges mate with cast iron equipment the mating flange face shall be a smooth
1
2
3
finish
Allunconnected branches 40 nps and below shall be class 6000 1b / schedule 160
For selection of reinforced branch connections see detail drgs
Buried lines shall be coated & wrapped in accordance with specification. All aviation
product pipes lines shall be internally lined in accordance with the specification 3326-
0025.
Material test certificates to din 50049.3.1b
Branch Connection Chart
Header Si e
350 300 250 200 150 100 80
RB RB
RB RB
RB RB
RB RB
BB
BB
BB
BB
a ow
wor
t
RB.
RB.
RB.
RB.
201207
RB
RB
RB
RB
RB
RB
RB
RB
65 50 40 25 20 15
RB RB RB RB RB OT
RB RB RB ORB OT
RB ORB RB OT
RBOW oT
wot
t
LEGEND
RB ~ RE-INFORCED BRANCH
B— UN RE-INFORCED BRANCH
W- WELDOLET
T- BUTT WELD EQUAL TEE‘Appendix A — Schedule of Rates
‘Al DEFINITION OF TERMS USED IN THESE SCHEDULES OF RATES
‘ALI The terms ‘erect, ‘install’ and ‘set-up’ shall mean taking delivery, off-loading,
loading, handling, storing, transporting to and from the fabrication area to the
final position and fixing to correct levels including lining up all pipework
described including the taking of all necessary measurements.
Pipework shall be measured nett and all specials, elbows, valves, flanges, jointing
and cutting etc have been measured separately.
‘AL.2__ The term ‘supply’ shall mean the cost of purchase, delivery and transporting to
score on site and storing,
AL.3_ Where items have been described as ‘extra over’ the Contractor is to include for
making such labours as described.
AL.4 The term ‘cut pipe’ shall mean the unit of measurement per cut for the cutting of
a square end to both sides of the cut to receive bevelled ends, screwed ends or
slip-on flanges.
ALS The term ‘bevel end’ shall mean the unit of measurement per end for preparing
ends of pipe for welding,
AL.6 The term ‘make flanged joint’ shall mean to include for all fitting work and the
supply and fixing of all gaskets, studbolts, nuts and washers.
‘Schedule of bolts for flanged ioints
Pipe Diameter | Number of Bolts| Dia Stud Length | Bolt Length
{mm) {mm)
15mm 4 a2" 55 44
20mm 4 yo" 55 51
25mm 4 yr" 65 51
40mm 4 a2" 70 57
50mm 4 5/8” 75 70
80mm 4 5/8” 90 76
100mm 8 5/8” 90 76
1somm 8 3/4" 95 83
200mm 8 3/4" 100 89
250mm R 78" 1s 85
300mm 2 78" 115 102
350mm R v 25 108
400mm 16 v 130 a4
450mm 16 11/8" 150 aa
24 of 207AL?
ALB
AL9
a2
Ada
A22
a3
ABA
03.2
03.3
034
Aas
A36
The term ‘make screwed joint’ shall mean the unit of measurement per end of
pipe or fitting for making a screwed joint, including all fitting work and preparing
ends with specified jointing material.
The term ‘make 90 degrees branch’ shall mean to include for the cutting of holes
in the main pipe, shaping of branch ends, fitting, bevelling tacking and the
finished welding of the branch
No distinction has been made in the description between main pipes of differing
diameter. Only the branch diameter has been stated. The Contractor should
make any allowance necessary in his prices for this lack of distinction,
The term ‘make weld joint’ shall mean the unit of measurement per end of pipe
or fitting for making a socket weld joint. To include all cutting of pipe end,
preparing pipe end, all fitting work and finished welding of the joint.
SCHEDULE OF RATE FOR MECHANICAL WORKS,
The Contractor should enter a rate against all items. Items with no rate shall be
deemed to have been included in rates for other items.
This schedule of rates is to be used in the costing of the works or variations to
the works deemed necessary by the Engineer, and in accordance with the
General Conditions of Contract.
RATESTO INCLUDE
For all handling and distribution costs, insurances, subsistence allowances, non
productive overtime in accordance with the working week which forms the basis
of this schedule, supervision, overheads, etc
Non-productive overtime charges will only be allowed if specific instructions have
been given to carry out extra work during overtime hours.
Normal Working hours are as stated in Section 2, Form of Tender.
Handling and distribution costs shall be deemed to be inclusive of taking from
allocated safe working area to erection site and all necessary double handling as
a result of NO hot work being allowed in erection areas.
For all work up to a height of 2.00m and all depths in all locations on the site.
Any safe working platform required for any work over 2.00m will be reimbursed
at cost. Any air supplied breathing apparatus for work below 1.3m under ground
level will be reimbursed at cost.
Provision of all consumables and sundry materials such as, but not limited to:-
i) Welding rods and electrodes.
ii) Cutting discs.
iii) Oxygen and Acetylene.
iv) Inert Gas,
v) Pipe jointing material other than gaskets.
vi) Nuts, bolts and studbolts.
2501207A37
A3.8
03.9
vii) Fuel for generators and welding sets.
viii) Fuel for Contractor's plant and transport.
ix) Provision of all necessary plant and equipment such as, but not
limited to:
x) Temporary lighting and power.
xi) Temporary screens, fencing and guard rails.
xii) Welding plant and associated equipment.
Small hand tools, air operated or manual.
xvi) Temporary supports.
Provision of all non structural steelwork supports (bottom of pipe to be
supported less than 1.5 meters above grade) including levelling and aligning
before erection and final bolting down on prepared foundations (foundations
and bolts by others); for pipe-lines at any level below 2 meters above ground
level.
For site checking of dimensions before fabrication for proper execution of work.
All working platform above 2.00m will be provided by the contractor. he shall
use the terminals nominated specialist contractor, the cost of which shall be
reimbursed on a cost plus basis as nominated in the Form of Tender, Section 2.
‘A3.10 All powered lifting equipment shall be provided by the contractors as deemed
necessary to execute the works safely and efficientiy. He shall use the terminals
nominated specialist contractor, the cost of which shall be reimbursed on a cost
plus basis as nominated in the Form of Tender.
‘A3.11 All water used on site for the purposes of wetting down during hazardous work
and hydrostatic testing shall be provided by the company unless otherwise
stated.
201207