VALE MALAYSIA

MANUFACTURING PROJECT
(VMMP)
TÍTLE VALE Nº PAGE
VMMP
CR-3060ML-F-20000 1/2
PORT & MARINE
REV.
MATERIAL HANDLING QUAY 1
MILESTONE SCHEDULE

REVISIONS
IT: ISSUE A - PRELIMINARY C - FOR INFORMATION E - FOR CONSTRUCTION G - AS BUILT
TYPE H - CANCELED
B - FOR APPROVAL D - FOR QUOTATION F - AS PURCHASED

Rev. IT Description By Chec Appr. Aut. Date

0 D Issue for Enquiry ET KH 29/10/10

1 D Updated for Enquiry ET PJW 20/12/10

PE-G-606E - Rev. 5
VALE MALAYSIA
MANUFACTURING PROJECT
(VMMP)
TÍTLE VALE Nº PAGE
VMMP
CR-3060ML-F-20000 2/2
PORT & MARINE
REV.
MATERIAL HANDLING QUAY 1
MILESTONE SCHEDULE

MILESTONE SCHEDULE

The forecast durations for Material Handling Quay enquiry process are summarized below.
The dates detailed below for the tender process have been based on the notification date of
22nd December, 2010. Should this date be delayed for any reason then all subsequent dates
will be amended by a corresponding number of days.

Activity
Description Milestone Date
No.
1 Issue Complete Request for Quotation to Bidders 22/12/2010
2 Bidders Technical Clarification Meetings 10 to
14/01/2011
3 Technical and Commercial Proposal 31/01/2011
4 Bidders Presentations 07/02/2011 to
11/02/2011
5 Technical & Commercial Evaluation and Issue of 18/02/2011
Clarifications Requests to Tenderers.
6 Technical/Clarification Replies by Tenderers 28/02/2011
7 Selection and Negotiation of Contract for MHQ 15-30/03/2011

The tenderer is to confirm that they are able to meet these submission dates based on their
detailed review of the enquiry documentation. If the compliance with any date is not possible
an alternative proposed time schedule is to be defined.