Proyek : Novotel Ibis Kulon Progo

Progress Harian Update


No Tanggal Keterangan Vol Akumulasi Sat Vol Harian Sat
1 Bobok tiang pancang 123 ttk ttk
2 Galian pile cap 80 ttk ttk
3 14 Des 20 Bekisting pile cap 56 ttk ttk
2 2
4 Pembesian lantai 768.74 m m
3 3
5 Pengecoran 551 m m
1 Bobok tiang pancang 154 ttk 31 ttk
2 Galian pile cap 97 ttk 17 ttk
3 15 Des 20 Bekisting pile cap 62 ttk 6 ttk
2 2
4 Pembesian lantai 1059.31 m 290.57 m
3 3
5 Pengecoran 562.5 m 11.5 m