RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : PEMBANGUNAN PAGAR KELILING GEREJA


LOKASI : TIMIKA.

HARGA SAT. JUMLAH HARGA


NO JENIS PEKERJAAN SAT VOLUME
(RP) (RP)
1 2 3 4 5 6

I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi m2 35.00 19,750.00 691,250.00
2 Pengukuran & Pasang Bowplank m1 24.00 66,025.00 1,584,600.00
Sub Total 2,275,850.00

II PEKERJAAN TANAH
1 Galian Tanah Pondasi m3 165.18 86,875.00 14,350,012.50
2 Timbun Kembali Hasil Galian m3 43.34 24,445.00 1,059,446.30
3 Urug Pasir Dibawah Lantai + Pondasi m3 10.32 298,750.00 3,083,100.00
Sub Total 18,492,558.80

III PEKERJAAN PAGAR TEMBOK


1 Pondasi Batu Kali 1 : 4 m3 144.48 1,492,350.00 215,614,728.00
2 Dinding Batu Tela 1 : 3 m2 46.30 248,265.00 11,494,669.50
3 Plesteran Tembok Biasa 1 : 3 m2 588.18 79,869.20 46,977,466.06
4 Sloof Beton 20/40 K.225 m3 27.52 7,082,340.00 194,905,996.80
5 Kolam Estetis tb = 10 cm m3 31.63 10,995,700.00 347,793,991.00
6 Kolam Bentuk Tifa m3 2.36 10,995,700.00 25,949,852.00
Sub Total 842,736,703.36

IV PEKERJAAN PAGAR TRALIS & PINTU


1 Pagar Tralis Pipa Ø 2" & Besi Beton Ø 16 m2 243.00 850,000.00 206,550,000.00
2 Pintu Pagar Unit 3.00 2,900,000.00 8,700,000.00
Sub Total 215,250,000.00

V PEKERJAAN INSTALASI LISTRIK


1 Lampu Pagar bh 54.00 189,250.00 10,219,500.00
2 Pas. Saklar Tunggal bh 2.00 106,500.00 213,000.00
3 Pas. Box Sekring + Arde Set 1.00 1,500,000.00 1,500,000.00
Sub Total 11,932,500.00

VI PEKERJAAN CAT DAN FINISHING


1 Cat Tembok m2 588.18 14,776.50 8,691,241.77
2 Cat Besi m2 241.02 66,791.00 16,097,966.82
Sub Total 24,789,208.59

VII PEKERJAAN AKHIR


1 Pembersihan Akhir ls 1.00 150,000.00 150,000.00
Sub Total 150,000.00
Daftar Harga Bahan
HARGA SATUAN
NO. DAFTAR BAHAN SATUAN
( Rp. )
1 2 3
1 Semen PC Kg 1,700.00
2 Semen Putih Kg 3,250.00
3 Kawat Ikat/Bendrat Kg 35,000.00
4 Kawat Duri Besi Kg 28,000.00
5 Tripleks 3 mm Ukuran 122 x 224 cm Lembar 58,000.00
6 Tripleks 4 mm Ukuran 122 x 224 cm Lembar 70,000.00
7 Tripleks 5 mm Ukuran 122 x 224 cm Lembar 85,000.00
8 Tripleks 6 mm Ukuran 122 x 224 cm Lembar 95,000.00
9 Tripleks 9 mm Ukuran 122 x 224 cm Lembar 135,000.00
10 Tripleks 12 mm Ukuran 122 x 224 cm Lembar 180,000.00
11 Tripleks 18 mm Ukuran 122 x 224 cm Lembar 250,000.00
12 Teakwood Ukuran 122 x 224 cm Lembar 90,000.00
13 Dolken Kayu Dia. 8 - 10 cm/400 cm Batang 25,000.00
14 Farmika Lembar 100,000.00
15 Gypsum Board 9 mm Lembar 90,000.00
16 Akustik 60 x 60 cm Lembar 46,500.00
17 Akustik 30 x 30 cm Lembar 11,625.00
18 List Plafond M 1
20,000.00
19 Paku Biasa Kg 20,000.00
20 Paku Seng Kg 25,000.00
21 Paku Tripleks Kg 25,000.00
22 Paku Asbes Kg 20,500.00
23 Paku Beton Kg 100,000.00
24 Paku Sekrup Kg 75,000.00
25 Mur Baut Dia. 12 - 14 mm Batang 15,000.00
26 Seng Gelombang BJLS 0.30 Lembar 60,000.00
27 Seng Gelombang BJLS 0.20 Lembar 50,000.00
28 Seng Plat BJLS 0.30 Lembar 55,000.00
29 Seng Plat BJLS 0.20 Lembar 45,000.00
30 Genteng Metal Multiroof Polos Lembar 85,000.00
31 Nok Genteng Metal Multiroof Lembar 35,000.00
32 Ardek Gelombang Besar Lembar 50,000.00
33 Ardek Gelombang Kecil Lembar 42,000.00
34 Seng Aluminium lebar 60 cm Lembar 37,500.00
35 Seng Aluminium lebar 55 cm Lembar 35,000.00
36 Genteng Metal Lembar 35,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. DAFTAR BAHAN SATUAN
( Rp. )
1 2 3
37 Bubungan Genteng Metal Buah 45,000.00
38 Polycarbonate M2
300,000.00
39 Lumbersharing @4m Lembar 25,000.00
40 Kaca Bening 3 mm M2
100,000.00
41 Kaca Bening 4 mm M2
150,000.00
42 Kaca Bening 5 mm M2 200,000.00
43 Kaca Bening 8 mm M2 225,000.00
44 Kaca Louvers 5 mm, 8 klip Set 190,000.00
45 Kaca Louvers 5 mm, 7 klip Set 180,000.00
46 Kaca Nako Lembar 15,000.00
47 Kaca Ryben 5 mm M2
170,000.00
48 Batu Kali, ex quarry Mile 32 M3
600,000.00
49 Batu Kali, ex quarry Iwaka M3
600,000.00
50 Kerikil Kali, ex quarry Iwaka M3
450,000.00
51 Kerikil Kali, ex quarry Kilo 7,8,14 M3
450,000.00
52 Kerikil (Batu Pecah) : M3

- Split 1 - 2 cm M3 1,000,000.00
- Split 2 - 3 cm M3
1,000,000.00
- Split 3 - 5 cm M3
850,000.00
53 Sirtu Timbunan, ex quarry Mile 32 M3
220,000.00
54 Sirtu Timbunan, ex quarry Iwaka M3
180,000.00
55 Sirtu Timbunan, ex quarry Kilo 7,8,14 M3
150,000.00
56 Pasir Pasang, ex quarry Mile 32 M3
400,000.00
57 Pasir Pasang, ex quarry Mile Iwaka M3
400,000.00
58 Tanah Timbunan ex quarry Kilo 7,8,14 M3
175,000.00
59 Kayu Kelas I Besi ( Balok ) M3 3,400,000.00
60 Kayu Kelas II Matoa ( Balok ) M3 2,100,000.00
61 Kayu Kelas I Besi ( Papan ) M3 3,750,000.00
62 Kayu Klas II Matoa ( Papan ) M3 2,000,000.00
63 Bambu Dia. 6 - 8 / 600 cm Batang 20,000.00
64 Bilik Bambu M2
65,000.00
65 Batu Tela Buah 1,900.00
66 Batu Batako Buah 2,000.00
67 Batu Berongga Expose Buah 6,000.00
68 Roster/Terawang Buah 6,000.00
69 Batu Bunga/Loster Buah 8,000.00
70 Batu Tempel Hitam M2
66,500.00
71 Marmer ex lokal M2
340,000.00
72 Tegel Keramik 40 x 40 cm Buah 11,600.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. DAFTAR BAHAN SATUAN
( Rp. )
1 2 3
73 Tegel Keramik 30 x 30 cm Buah 6,500.00
74 Tegel Keramik 20 x 25 cm Buah 2,500.00
75 Tegel Keramik 20 x 20 cm Buah 2,000.00
76 Tegel Keramik 10 x 20 cm Buah 1,000.00
77 Tegel Porselin 11 x 11 cm Buah 548.00
78 Tegel Mozaik 30 x 30 cm Buah 6,000.00
79 Tegel Teraso 30 x 30 cm Buah 6,000.00
80 Tegel PC Abu-Abu 20 x 20 cm Buah 2,400.00
81 Plint keramik artistik Buah 4,500.00
82 Batu Alam Palimanan Buah 15,000.00
83 Pipa PVC dia 1/2" - 4m Batang 17,000.00
84 Pipa PVC dia 3/4" - 4m Batang 22,000.00
85 Pipa PVC dia 1" - 4m Batang 27,000.00
86 Pipa PVC dia 2" - 4m Batang 50,000.00
87 Pipa PVC dia 3" - 4m Batang 80,000.00
88 Pipa PVC dia 4" - 4m Batang 115,000.00
89 Pipa PVC dia 5" - 4m Batang 263,958.00
90 Pipa PVC dia 6" - 4m Batang 290,000.00
91 Koppling PVC dia 2" - 4m Buah 15,000.00
92 Koppling PVC dia 4" - 6m Buah 20,000.00
93 Pipa GIV dia 1/2" - 4m Batang 150,000.00
94 Pipa GIV dia 3/4" - 4m Batang 175,000.00
95 Pipa GIV dia 1" - 6m Batang 250,000.00
96 Pipa GIV dia 2" - 6m Batang 450,000.00
97 Pipa GIV dia 3" - 6m Batang 950,000.00
98 Pipa Leding dia 1 1/2" - 6 mtr Batang 12,000.00
99 Kran Leding (Plastik) Buah 15,000.00
100 Kran Leding (Stainles) Buah 75,000.00
101 Ijuk M2 100,000.00
102 Pompa Air Sanyo PH 100 Unit 1,100,000.00
103 Pompa Air Honda (Alkon) Unit 3,500,000.00
104 Permite/Penjaga jarak bekisting/spacer Buah 15,000.00
105 Seal tape Roll 5,000.00
106 Minyak Bekisting Liter 15,000.00
107 Rapidrant Galon 250,000.00
108 Bak Cuci Stainless Steel Buah 450,000.00
109 Water Drain + Acesories Set 150,000.00
110 Floor Drain Buah 55,000.00
111 Tangki Air fibre Kap. 1000 Liter Buah 1,800,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. DAFTAR BAHAN SATUAN
( Rp. )
1 2 3
112 Kloset Jongkok Porselen Putih Buah 250,000.00
113 Kloset Jongkok Biasa Buah 100,000.00
114 Kloset Duduk Keramik KIA Buah 1,800,000.00
115 Kloset Duduk Keramik Biasa Buah 500,000.00
116 Wastafel lengkap TOTO Buah 850,000.00
117 Floor Drain Stainless Steel Buah 75,000.00
118 Lampu TL 2 x 40 Watt Phillips + Mirror inbow Buah 35,000.00
119 Lampu TL 2 x 20 Watt Buah 27,000.00
120 Lampu TL 20 Watt Buah 39,000.00
121 Lampu Down Light + SL 15 Watt Lengkap Buah 80,000.00
122 Lampu Baret SL 18 Watt Buah 25,000.00
123 Lampu Pijar 5 - 100 Watt + Fitting Buah 20,000.00
Kabel Snoor 2 x 0,23 "Supreme" roll 160,200.00
Kabel NYA 2,5 sqmm "Supreme" roll 333,760.00
Kabel NYA 1,5 sqmm "Supreme" roll 211,380.00
Kabel NYA 2,5 sqmm "Supreme" M 1
3,337.60
Kabel NYA 1,5 sqmm "Supreme" M 1
2,113.80
Kabel NYM 2 x 1,5 sqmm "Supreme" M 1
12,000.00
124 Kabel NYM 2 x 2,5 mm (eterna) M 1
7,500.00
Kabel NYM 2 x 4 sqmm "Supreme" M 1
18,750.00
Kabel NYM 3 x 1,5 sqmm "Supreme" M 1
18,000.00
125 Kabel NYM 3 x 2,5 mm M 1
11,000.00
Kabel NYM 4 x 4 mm2 M 1
27,000.00
Kabel NYM 3 x 4 sqmm "Supreme" M 1
25,000.00
Kabel NYY 3 x 1,5 sqmm "Supreme" M 1

Kabel NYY 3 x 2,5 sqmm "Supreme" M1


Kabel NYY 3 x 4 sqmm "Supreme" M1
Kabel NYY 3 x 6 sqmm "Supreme" M1 30,000.00
Kabel NYY 4 x 10 sqmm "Supreme" M1
Kabel NYFGBY 3 x 10 sqmm "Supreme" M1
126 Kabel NYF GbY 4 x 25 mm M1 250,000.00
Kabel ITC 2 x 2 x 0.6 mm2 M 1

Kabel DX 2 x 10 sqmm "Supreme" M1


Kabel DX 2 x 16 sqmm "Supreme" M1
Kabel DX 2 x 25 sqmm "Supreme" M1
Kabel Ties 15 cm "Supreme" M1
Kabel Tis 10 cm "Supreme" M1
Tiang Galvanit cb,1, h=9m, base plate unit
Tiang Galvanit cb,2, h=9m, base plate unit

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. DAFTAR BAHAN SATUAN
( Rp. )
1 2 3
Tiang Galvanit cb,2, h=6m, base plate unit
Tiang Galvanit cb,1, h=7m, base plate unit
Tiang Galvanit cb,1, h=5m, type tanam dia 2" unit
Tiang lampu Highment cb 4, h=20m, hidrolik unit
Tiang lampu Highment cb 2, h=20m, hidrolik unit
Tiang GIP cb 1. 2", 3", 4", 5", h = 9m, tanam unit
Tiang GIP cb 1. 2", 3", 4", h = 7m, tanam unit
Tiang GIP cb 1. 3", 4", 5", h = 9m, tanam unit
127 Vitting Buah 35,000.00
128 Stop Kontak 1000 W Buah 26,396.00
129 Stop Kontak 5000 W Buah 32,000.00
130 Sekring 1 Group Buah 35,000.00
131 Sekring 3 Group Buah 110,000.00
132 Sekring Otomatis Buah 60,000.00
133 Saklar Seri Buah 20,000.00
134 Saklar Tunggal Buah 20,000.00
135 Box Sekring Grup 79,000.00
136 MCB (Miniatur Circuit Breaker) Buah 50,000.00
137 Box MCB Group 50,000.00
138 Plat strip t = 4 mm - 6 m Batang 15,000.00
139 Besi Ø 6 Kg 25,000.00
140 Besi Beton (UK 8 mm x 12) Batang 45,000.00
141 Besi Beton Segala Ukuran ( Polos ) Kg 17,000.00
142 Besi Beton Segala Ukuran ( Ulir ) Kg 19,500.00
143 Besi Ø 10 Kg 66,000.00
144 Besi Ø 12 Kg 93,000.00
145 Besi Siku 20.20-2m Batang 50,000.00
146 Besi Siku 30.30-3m Batang 95,000.00
147 Besi Siku 40.40-3m Batang 100,000.00
148 Besi Siku 40.40-6m Batang 150,000.00
149 Besi Siku 50.50-4m Batang 175,000.00
150 Besi Siku 50.50-6m Batang 225,000.00
151 Besi Siku 60.60-6m Batang 450,000.00
152 Besi Siku 100.100-6m Batang 475,000.00
153 Cat Dasar/Cat Meni Kaleng 20,000.00
154 Melamine IMPRA Liter 45,000.00
155 Cat Kilat Kayu/ Cat besi (Avian) Kaleng 45,000.00
156 Cat Vernis/Politur Kaleng 45,000.00
157 Cat Tembok

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. DAFTAR BAHAN SATUAN
( Rp. )
1 2 3
- Merk Avitex Kg 350,000.00
- Merk Aries Kg 125,000.00
158 Cat Residu Kg 25,000.00
159 Cat Teak oil Kaleng 30,000.00
160 Cat Alluminium Kaleng 55,000.00
161 Soda Api Kg 20,000.00
162 Minyak Cat/Thinner Kg 25,000.00
163 Plamur Tembok Kg 1,600.00
164 Dempul Kg 15,000.00
165 Kuas Biasa Buah 15,000.00
166 Kuas Roll (Besar) Buah 20,000.00
167 Kertas Gosok/Amplas Lembar 3,000.00
168 Lem Kayu Kg 15,000.00
169 Lem Aibon Kaleng 45,000.00
170 Kunci Tanam 2 Slaag SES/Kend Buah 150,000.00
171 Kunci Tanam Silinder 1 Slaag SES/Kend Buah 150,000.00
172 Kunci Kuda Terbang 1 Slaag Buah 60,000.00
173 Kunci Kuda Terbang 2 Slaag Buah 75,000.00
174 Kunci Yale Besar Buah 150,000.00
175 Kunci H Jendela Pasang 18,000.00
176 Kunci H Pintu Pasang 24,000.00
177 Engsel Kupu-Kupu R. Nilon Jendela Pasang 20,000.00
178 Engsel Kupu-Kupu Ring Nilon Pintu Buah 15,000.00
179 Kunci Gembok Besar Buah 50,000.00
180 Kunci Gembok Sedang Buah 25,000.00
181 Kunci Gembok Kecil Buah 15,000.00
182 Grendel Kecil Buah 5,000.00
183 Grendel Sedang Buah 10,000.00
184 Grendel Besar Buah 15,000.00
185 Hak Angin Biasa Buah 8,000.00
186 Hak Angin Lipat Buah 11,500.00

* Harga Sewaktu-waktu dapat mengalami perubahan

Informasi Harga Satuan Pekerjaan Tahun 2012


DAFTAR ANALISA PEKERJAAN
KEGIATAN : PEMBANGUNAN RUMAH IBADAH
PEKERJAAN : PEMBANGUNAN GEDUNG GEREJA GKIP (KINGMI) KLASIS MIMIKA
LOKASI : KOTA TIMIKA
TAHUN ANGG : 2013

HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

I PEKERJAAN PERSIAPAN
I-1 100 M2 Pekerjaan Pengukuran Gedung
- Pekerja 8.0000 org 110,000.00
- Mandor 2.0000 org 175,000.00
- Pengawas / Ahli Teknik 0.5000 org 354,166.67
- Asisten Ahli Ukur 2.0000 org 110,000.00
- Sewa alat ukur 1.0000 hr 275,000.00
JUMLAH :
Untuk 1m2 Pekerjaan Pengukuran 0 m2 1,902,083
I-2 1 M' Pagar Sementara dari Kayu Tinggi 2 M
- Dolken Kayu Dia. 8-10/400 cm 1.2500 Btg 25,000.00
- Semen Portland 2.5000 Kg 1,700.00
- Pasir Beton 0.0050 M3 400,000.00
- Kerikil Koral 0.0090 M3 450,000.00
- Kayu Kelas II Matoa ( Balok ) 0.0720 M3 2,100,000.00
- Paku Biasa 0.0800 Kg 20,000.00
- Meni 0.4500 Kg 20,000.00
- Pekerja 0.4000 Oh 110,000.00
- Tukang Kayu 0.2000 Oh 130,000.00
- Kep. Tukang 0.0200 Oh 155,000.00
- Mandor 0.0200 Oh 175,000.00
JUMLAH :
I-3 1 M' Pagar Sementara Dari Seng Gelombang Tinggi 2 M
- Dolken Kayu Dia. 8-10/400 cm 1.2500 Btg 25,000.00
- Semen Portland 2.5000 Kg 1,700.00
- Seng Gelombang BLJS 20 1.2000 Lbr 50,000.00
- Pasir Beton 0.0050 M3 400,000.00
- Kerikil Koral 0.0090 M3 450,000.00
- Kayu Kelas II Matoa ( Balok ) 0.0720 M3 2,100,000.00
- Paku Biasa 0.0800 Kg 20,000.00
- Cat Residu 0.4500 Kg 25,000.00
- Pekerja 0.4000 Oh 110,000.00
- Tukang Kayu 0.2000 Oh 130,000.00
- Kep. Tukang 0.0200 Oh 155,000.00
- Mandor 0.0200 Oh 175,000.00
JUMLAH :
I-4 1 M' Pagar Sementara Dari Kawat Duri Tinggi 1,8 M
- Dolken Kayu Dia. 8-10/400 cm 1.2500 Btg 25,000.00
- Semen Portland 2.5000 Kg 1,700.00
- Kawat Duri 2.5000 Kg 28,000.00
- Pasir Beton 0.0050 M3 400,000.00
- Kerikil Koral 0.0090 M3 450,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Paku Biasa 0.0800 Kg 20,000.00


- Pekerja 0.4000 Oh 110,000.00
- Tukang Kayu 0.2000 Oh 130,000.00
- Kep. Tukang 0.0200 Oh 155,000.00
- Mandor 0.0200 Oh 175,000.00
JUMLAH :
I-5 1 M' Pengukuran dan Pemasangan Bouwplank
- Kayu Kelas II Matoa ( Balok ) 0.0120 m3 2,100,000.00
- Kayu Kelas II Matoa ( Papan ) 0.0070 m3 2,000,000.00
- Paku Biasa 0.0200 kg 20,000.00
- Pekerja 0.1000 Oh 110,000.00
- Tukang 0.1000 Oh 130,000.00
- Kep. Tukang 0.0100 Oh 155,000.00
- Mandor 0.0050 Oh 175,000.00
JUMLAH :
I-6 1 M2 Pembuatan Kantor Sementara Dengan Lantai Plesteran
- Dolken Kayu Dia. 8-10/400 cm 0.244 m3 25,000.00
- Kayu Kelas II Matoa ( Papan ) 0.180 m3 2,000,000.00
- Kayu Kelas II Matoa ( Balok ) 0.850 m3 2,100,000.00
- Paku Biasa 0.850 Kg 20,000.00
- Semen Portland 5.000 Kg 1,700.00
- Pasir Pasang 0.150 m3 400,000.00
- Kerikil Koral 0.150 m3 450,000.00
- Seng Gelombang BLJS 20 0.417 Lbr 50,000.00
- Jendela Nako 2.000 Bh 175,000.00
- Kaca Polos 0.080 m2 150,000.00
- Kunci Tanam 0.150 Bh 150,000.00
- Plywood 4 mm 3.000 Lmb 70,000.00
- Pekerja 1.500 Oh 110,000.00
- Tukang Kayu 0.750 Oh 130,000.00
- Tukang Batu 0.500 Oh 130,000.00
- Kep. Tukang 0.150 Oh 155,000.00
- Mandor 0.050 Oh 175,000.00
- Perlengkapan Kantor 1.000 Ls 500,000.00
JUMLAH :
I-7 1 M2 Pembuatan Gudang Semen dan Alat-Alat
- Dolken Kayu Dia. 8-10/400 cm 1.700 Btg 25,000.00
- Kayu Kelas II Matoa ( Balok ) 0.210 M3 2,100,000.00
- Paku Biasa 0.300 Kg 20,000.00
- Semen Portland 10.500 Kg 1,700.00
- Pasir Beton 0.030 M3 400,000.00
- Kerikil Koral 0.050 M3 450,000.00
- Seng Gelombang BLJS 20 1.500 Lbr 50,000.00
- Pekerja 1.000 Oh 110,000.00
- Tukang Kayu 2.000 Oh 130,000.00
- Kep. Tukang 0.200 Oh 155,000.00
- Mandor 0.050 Oh 175,000.00
JUMLAH :

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

I-8 1 M2 Pembuatan Rumah Jaga/Konstruksi Kayu


- Dolken Kayu Dia. 8-10/400 cm 3.000 Btg 25,000.00
- Kayu Kelas II Matoa ( Balok ) 0.276 M3 2,100,000.00
- Paku Biasa 0.700 Kg 20,000.00
- Seng Gelombang BLJS 20 1.500 Lbr 50,000.00
- Pekerja 1.000 Oh 110,000.00
- Tukang Kayu 1.500 Oh 130,000.00
- Kep. Tukang 0.150 Oh 155,000.00
- Mandor 0.050 Oh 175,000.00
JUMLAH :
I-9 1 M2 Pembersihan Lapangan dan Peralatan
- Pekerja 0.100 Oh 110,000.00
- Mandor 0.050 Oh 175,000.00
JUMLAH :
I-10 1 M2 Pembuatan Bedeng Buruh
- Dolken Kayu Dia. 8-10/400 cm 1.250 Btg 25,000.00
- Kayu Kelas II Matoa ( Balok ) 0.186 M3 2,100,000.00
- Paku Biasa 0.300 Kg 20,000.00
- Semen Portland 10.500 Kg 1,700.00
- Pasir Beton 0.030 M3 400,000.00
- Kerikil Koral 0.050 M3 450,000.00
- Seng Gelombang BLJS 20 1.500 Lbr 50,000.00
- Plywood 4 mm 1.350 Lmb 70,000.00
- Pekerja 1.000 Oh 110,000.00
- Tukang Kayu 2.000 Oh 130,000.00
- Kep. Tukang 0.200 Oh 155,000.00
- Mandor 0.050 Oh 175,000.00
JUMLAH :
I-11 1 M2 Pembuatan Stegger dari Bambu Ukuran ( 40 x 40 x 20 ) cm
- Bambu Dia. 6 - 8 / 600 cm 1.000 Btg 20,000.00
- Ijuk 0.250 Kg 50,000.00
- Pekerja 0.250 Oh 110,000.00
- Tukang Kayu 0.017 Oh 130,000.00
- Kep. Tukang 0.002 Oh 155,000.00
- Mandor 0.013 Oh 175,000.00
JUMLAH :
I-12 1 M2 Pembuatan Jalan Sementara
- Batu belah 15/20 0.150 M3 650,000.00
- Batu pecah 5/7 0.090 M3 700,000.00
- Pasir pasang 0.010 M3 400,000.00
- Pekerja 1.000 Oh 110,000.00
- Mandor 0.050 Oh 175,000.00
JUMLAH :
I-13 1 M3 Bongkaran Beton Bertulang
- Pekerja 6.667 Oh 110,000.00
- Mandor 0.333 Oh 175,000.00
JUMLAH :
I-14 1 M3 Bongkaran Dinding Tembok Batako

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Pekerja 6.667 Oh 110,000.00


- Mandor 0.033 Oh 175,000.00
JUMLAH :
II PEKERJAAN TANAH
II.1 1 M3 Galian Tanah Biasa Sedalam 1 M
- Pekerja 0.750 Oh 110,000.00
- Mandor 0.025 Oh 175,000.00
JUMLAH :
II.2 1 M3 Galian Tanah Biasa Sedalam 2 M
- Pekerja 0.900 Oh 110,000.00
- Mandor 0.045 Oh 175,000.00
JUMLAH :
II.3 1 M3 Galian Tanah Biasa Sedalam 3 M
- Pekerja 1.050 Oh 110,000.00
- Mandor 0.067 Oh 175,000.00
JUMLAH :
II.4 1 M3 Galian Tanah Keras Sedalam 1 M
- Pekerja 1.000 Oh 110,000.00
- Mandor 0.032 Oh 175,000.00
JUMLAH :
II.5 1 M3 Galian Tanah Cadas Sedalam 1 M
- Pekerja 1.500 Oh 110,000.00
- Mandor 0.060 Oh 175,000.00
JUMLAH :
II.6 1 M3 Galian Tanah Lumpur Sedalam 1 M
- Pekerja 1.200 Oh 110,000.00
- Mandor 0.045 Oh 175,000.00
JUMLAH :
II.7 1 M3 Pekerjaan Stripping Setinggi 1 M
- Pekerja 0.050 Oh 110,000.00
- Mandor 0.005 Oh 175,000.00
JUMLAH :
II.8 1 M3 Pembuangan Tanah Sejauh 15 M
- Pekerja 0.330 Oh 110,000.00
- Mandor 0.010 Oh 175,000.00
JUMLAH :
II.9 1 M3 Mengurug Kembali Galian
- Pekerja 0.192 Oh 110,000.00
- Mandor 0.019 Oh 175,000.00
JUMLAH :
II.10 1 M3 Pemadatan Tanah ( per 20 cm)
- Pekerja 0.500 Oh 110,000.00
- Mandor 0.050 Oh 175,000.00
JUMLAH :
II.11 1 M3 Urugan Pasir
- Pasir urug 1.200 M3 220,000.00
- Pekerja 0.300 Oh 110,000.00
- Mandor 0.010 Oh 175,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

JUMLAH :
II.12 1 M3 Urugan Sirtu
- Sirtu Timbunan 1.200 M3 220,000.00
- Pekerja 0.250 Oh 110,000.00
- Mandor 0.025 Oh 175,000.00
JUMLAH :
II.13 1 M3 Pembuatan Jalan Sementara, Tebal 25 cm
- Batu belah 15/20 0.275 M3 650,000.00
- Kerikil 0.030 M3 450,000.00
- Pasir pasang 0.050 M3 400,000.00
- Pekerja 1.000 Oh 110,000.00
- Mandor 0.100 Oh 175,000.00
JUMLAH :
III PEKERJAAN PONDASI
III.1 1 M3 Pasangan Pondasi Batu Belah, Campuran 1 PC : 3 PP
- Pasir Pasang 0.485 M3 400,000.00
- Batu Kali 1.200 M3 600,000.00
- Semen Portland 202.000 Kg 1,700.00
- Pekerja 1.500 Oh 110,000.00
- Tukang Batu 0.750 Oh 130,000.00
- Kep. Tukang 0.075 Oh 155,000.00
- Mandor 0.075 Oh 175,000.00
JUMLAH :
III.2 1 M3 Pasangan Pondasi Batu Belah, Campuran 1 PC : 4 PP
- Pasir Pasang 0.520 M3 400,000.00
- Batu Kali 1.200 M3 600,000.00
- Semen Portland 163.000 Kg 1,700.00
- Pekerja 1.500 Oh 110,000.00
- Tukang Batu 0.750 Oh 130,000.00
- Kep. Tukang 0.075 Oh 155,000.00
- Mandor 0.075 Oh 175,000.00
JUMLAH :
III.3 1 M3 Pasangan Pondasi Batu Belah, Campuran 1 PC : 5 PP
- Pasir Pasang 0.544 M3 400,000.00
- Batu Kali 1.200 M3 600,000.00
- Semen Portland 136.000 Kg 1,700.00
- Pekerja 1.500 Oh 110,000.00
- Tukang Batu 0.750 Oh 130,000.00
- Kep. Tukang 0.075 Oh 155,000.00
- Mandor 0.075 Oh 175,000.00
JUMLAH :
III.4 1 M3 Pasangan Pondasi Batu Belah, Campuran 1 PC : 6 PP
- Pasir Pasang 0.561 M3 400,000.00
- Batu Kali 1.200 M3 600,000.00
- Semen Portland 117.000 Kg 1,700.00
- Pekerja 1.500 Oh 110,000.00
- Tukang Batu 0.750 Oh 130,000.00
- Kep. Tukang 0.075 Oh 155,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Mandor 0.075 Oh 175,000.00


JUMLAH :
III.5 1 M3 Pasangan Pondasi Batu Belah, Campuran 1 PC : 8 PP
- Pasir Pasang 0.584 M3 400,000.00
- Batu Kali 1.200 M3 600,000.00
- Semen Portland 91.000 Kg 1,700.00
- Pekerja 1.500 Oh 110,000.00
- Tukang Batu 0.750 Oh 130,000.00
- Kep. Tukang 0.075 Oh 155,000.00
- Mandor 0.075 Oh 175,000.00
JUMLAH :
III.6 1 M3 Pasangan Batu Kosong (Anstamping)
- Pasir Pasang 0.432 M3 400,000.00
- Batu Kali 1.200 M3 600,000.00
- Pekerja 0.780 Oh 110,000.00
- Tukang Batu 0.390 Oh 130,000.00
- Kep. Tukang 0.039 Oh 155,000.00
- Mandor 0.039 Oh 175,000.00
JUMLAH :
III.7 1 M3 Pasangan Pondasi Siklop, 60% Beton Capuran 1 PC : 2 PB : 3 KR dan 40% Batu Belah
- Batu Kali 0.480 M3 600,000.00
- Besi beton 75.000 Kg 19,500.00
- Semen Portland 202.000 Kg 1,700.00
- Pasir beton 0.320 M3 400,000.00
- Kerikil 0.490 M3 450,000.00
- Kawat beton 0.800 Kg 35,000.00
- Pekerja 3.000 Oh 110,000.00
- Tukang Batu 0.850 Oh 130,000.00
- Kep. Tukang 0.085 Oh 155,000.00
- Mandor 0.150 Oh 175,000.00
JUMLAH :
III.8 1 M3 Pasangan Pondasi Sumuran Diameter 100 cm
- Batu belah 15/20 0.450 M3 650,000.00
- Semen Portland 280.000 Kg 1,700.00
- Pasir beton 0.450 M3 400,000.00
- Kerikil 0.670 M3 450,000.00
- Pekerja 2.380 Oh 110,000.00
- Tukang Batu 0.300 Oh 130,000.00
- Kep. Tukang 0.030 Oh 155,000.00
- Mandor 0.080 Oh 175,000.00
JUMLAH :
III.9 1 M' Pembuatan Tiang Pancang ( 40 x 40 ) Cm, Prestressed Beton
- Pasir Urug 0.019 M3 220,000.00
- Pasir Beton 0.094 M3 400,000.00
- Kerikil 0.150 M3 450,000.00
- Semen Portland 60.500 Kg 1,700.00
- Besi Beton 45.000 Kg 19,500.00
- Kawat Beton 0.900 Kg 35,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Kayu Kelas II Matoa ( Balok ) 0.032 M3 2,100,000.00


- Paku Biasa 0.120 Kg 20,000.00
- Minyak Bekesting 0.090 Ltr 15,000.00
- Plamur tembok 0.240 Kg 28,000.00
- Pekerja 1.000 Oh 110,000.00
- Tukang Batu 0.670 Oh 130,000.00
- Kep. Tukang 0.067 Oh 155,000.00
- Mandor 0.050 Oh 175,000.00
JUMLAH :
III.10 1 M' Pembuatan Tiang Pancang ( 35 x 35 ) Cm, Prestressed Beton
- Pasir Urug 0.016 M3 220,000.00
- Pasir Beton 0.080 M3 400,000.00
- Kerikil 0.125 M3 450,000.00
- Semen Portland 49.000 Kg 1,700.00
- Besi Beton 34.500 Kg 19,500.00
- Kawat Beton 0.700 Kg 35,000.00
- Kayu Kelas II Matoa ( Balok ) 0.027 M3 2,100,000.00
- Paku Biasa 0.120 Kg 20,000.00
- Minyak Bekesting 0.090 Ltr 15,000.00
- Plamur tembok 0.200 Kg 28,000.00
- Pekerja 0.800 Oh 110,000.00
- Tukang Batu 0.500 Oh 130,000.00
- Kep. Tukang 0.050 Oh 155,000.00
- Mandor 0.040 Oh 175,000.00
JUMLAH :
IV PEKERJAAN DINDING
IV.1 1 M2 Pasangan Batu Batako Tebal 1 Batako, 1 PC : 1 PP
- Batu batako 10 x 18 x 24 cm 25.000 Bh 2,000.00
- Semen Portland 64.030 Kg 1,700.00
- Pasir pasang 0.059 M3 400,000.00
- Pekerja 0.650 Oh 110,000.00
- Tukang Batu 0.200 Oh 130,000.00
- Kep. Tukang 0.020 Oh 155,000.00
- Mandor 0.030 Oh 175,000.00
JUMLAH :
IV.2 1 M2 Pasangan Batu Batako Tebal 1 Batako, 1 PC : 2 PP
- Batu batako 10 x 18 x 24 cm 25.000 Bh 2,000.00
- Semen Portland 43.500 Kg 1,700.00
- Pasir pasang 0.080 M3 400,000.00
- Pekerja 0.650 Oh 110,000.00
- Tukang Batu 0.200 Oh 130,000.00
- Kep. Tukang 0.020 Oh 155,000.00
- Mandor 0.030 Oh 175,000.00
JUMLAH :
IV.3 1 M2 Pasangan Batu Batako Tebal 1 Batako, 1 PC : 3 PP
- Batu batako 10 x 18 x 24 cm 25.000 Bh 2,000.00
- Semen Portland 32.950 Kg 1,700.00
- Pasir pasang 0.091 M3 400,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Pekerja 0.650 Oh 110,000.00


- Tukang Batu 0.200 Oh 130,000.00
- Kep. Tukang 0.020 Oh 155,000.00
- Mandor 0.030 Oh 175,000.00
JUMLAH :
1 m3 :
IV.4 1 M2 Pasangan Batu Batako Tebal 1 Batako, 1 PC : 4 PP
- Batu batako 10 x 18 x 24 cm 25.000 Bh 2,000.00
- Semen Portland 26.550 Kg 1,700.00
- Pasir pasang 0.093 M3 400,000.00
- Pekerja 0.650 Oh 110,000.00
- Tukang Batu 0.200 Oh 130,000.00
- Kep. Tukang 0.020 Oh 155,000.00
- Mandor 0.030 Oh 175,000.00
JUMLAH :
IV.5 1 M2 Pasangan Batu Batako Tebal 1 Batako, 1 PC : 5 PP
- Batu batako 10 x 18 x 24 cm 25.000 Bh 2,000.00
- Semen Portland 22.200 Kg 1,700.00
- Pasir pasang 0.102 M3 400,000.00
- Pekerja 0.650 Oh 110,000.00
- Tukang Batu 0.200 Oh 130,000.00
- Kep. Tukang 0.020 Oh 155,000.00
- Mandor 0.030 Oh 175,000.00
JUMLAH :
IV.6 1 M2 Pasangan Dinding Roster/Terawang (12 X 11 X 24) cm, Campuran Spesi 1 PC : 3 PP
- Roster/terawang 30.000 Bh 6,000.00
- Semen Portland 14.000 Kg 1,700.00
- Pasir pasang 0.032 M3 400,000.00
- Pekerja 0.300 Oh 110,000.00
- Tukang Batu 0.100 Oh 130,000.00
- Kep. Tukang 0.010 Oh 155,000.00
- Mandor 0.015 Oh 175,000.00
JUMLAH :
IV.7 1 M2 Pasangan Dinding Roster/Terawang (12 X 11 X 24) cm, Campuran Spesi 1 PC : 4 PP
- Roster/terawang 30.000 Bh 6,000.00
- Semen Portland 11.000 Kg 1,700.00
- Pasir pasang 0.035 M3 400,000.00
- Pekerja 0.300 Oh 110,000.00
- Tukang Batu 0.100 Oh 130,000.00
- Kep. Tukang 0.010 Oh 155,000.00
- Mandor 0.015 Oh 175,000.00
JUMLAH :
IV.8 1 M2 Pasangan Dinding Bata Berongga Ekspose (5 X 11 X 24) cm, Campuran Spesi 1 PC : 3 PP
- Bata berongga ekspose 70.000 Bh 6,000.00
- Semen Portland 14.000 Kg 1,700.00
- Pasir pasang 0.032 M3 400,000.00
- Pekerja 0.300 Oh 110,000.00
- Tukang Batu 0.150 Oh 130,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Kep. Tukang 0.015 Oh 155,000.00


- Mandor 0.015 Oh 175,000.00
JUMLAH :
IV.9 1 PASANG DINDING BATU ALAM
Batu alam Palimanan/Batu Candi 1.060 M2 367,500.00
Paku biasa 3.003 Bh 20,000.00
Semen Portland 12.440 M3 1,700.00
Pasir pasang 0.025 Kg 400,000.00
Semen Warna 0.650 Kg 7,500.00
Pekerja 1.300 o/h 110,000.00
Tukang batu 0.650 o/h 130,000.00
Kep. Tukang 0.065 o/h 155,000.00
Mandor 0.065 o/h 175,000.00
JUMLAH :
IV.10 1 MPASANG DINDING BATU ALAM ANDHESIT
Batu Andhesit 1.050 M2 350,000.00
Semen Portland 11.750 Kg 1,700.00
Pasir Pasang 0.035 M3 400,000.00
Pekerja 0.720 h.o 110,000.00
Tukang Batu 0.380 h.o 130,000.00
Kep. Tukang 0.035 h.o 155,000.00
Mandor 0.030 h.o 175,000.00
JUMLAH :
IV.11 1 MPASANG DINDING BATU ALAM CANDI
Batu Alam Candi 1.050 M2 375,000.00
Semen Portland 11.750 Kg 1,700.00
Pasir Pasang 0.035 M3 400,000.00
Pekerja 0.720 h.o 110,000.00
Tukang Batu 0.380 h.o 130,000.00
Kep. Tukang 0.035 h.o 155,000.00
Mandor 0.030 h.o 175,000.00
JUMLAH :
IV.12 1 MPASANG DINDING BATU ALAM ANDHESIT
Batu Andhesit 1.050 M2 350,000.00
Semen Portland 11.750 Kg 1,700.00
Pasir Pasang 0.035 M3 400,000.00
Pekerja 0.720 h.o 110,000.00
Tukang Batu 0.380 h.o 130,000.00
Kep. Tukang 0.035 h.o 155,000.00
Mandor 0.030 h.o 175,000.00
JUMLAH :
IV.13 1 MPASANG DINDING BATU ALAM LIMESTONE
Batu Alam Limestone 1.050 M2 325,000.00
Semen Portland 11.750 Kg 1,700.00
Pasir Pasang 0.035 M3 400,000.00
Pekerja 0.720 h.o 110,000.00
Tukang Batu 0.380 h.o 130,000.00
Kep. Tukang 0.035 h.o 155,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

Mandor 0.030 h.o 175,000.00


JUMLAH :
IV.14 1 MPASANG DINDING BATU ALAM CANDI
Batu Alam Candi 1.050 M2 375,000.00
Semen Portland 11.750 Kg 1,700.00
Pasir Pasang 0.035 M3 400,000.00
Pekerja 0.720 h.o 110,000.00
Tukang Batu 0.380 h.o 130,000.00
Kep. Tukang 0.035 h.o 155,000.00
Mandor 0.030 h.o 175,000.00
JUMLAH :
IV.15 1 MPASANG DINDING BATU ANDHESIT SUSUN SIRIH
Batu Andhesit Susun Sirih 1.050 M2 380,000.00
Semen Portland 11.750 Kg 1,700.00
Pasir Pasang 0.035 M3 400,000.00
Pekerja 0.720 h.o 110,000.00
Tukang Batu 0.380 h.o 130,000.00
Kep. Tukang 0.035 h.o 155,000.00
Mandor 0.030 h.o 175,000.00
JUMLAH :
IV.16 1 MPASANG BATU KORAL SIKAT
Batu koral sikat 1.050 M2 180,000.00
Semen Portland 11.750 Kg 1,700.00
Pasir Pasang 0.035 M3 400,000.00
Pekerja 0.500 h.o 110,000.00
Tukang Batu 0.380 h.o 130,000.00
Kep. Tukang 0.035 h.o 155,000.00
Mandor 0.030 h.o 175,000.00
JUMLAH :
V PEKERJAAN PLESTERAN
V.1 1 M2 Plesteran, 1 PC : 1 PP, tebal 15 mm
- Semen Portland 15.504 Kg 1,700.00
- Pasir pasang 0.016 M3 400,000.00
- Pekerja 0.300 Oh 110,000.00
- Tukang Batu 0.150 Oh 130,000.00
- Kep. Tukang 0.015 Oh 155,000.00
- Mandor 0.015 Oh 175,000.00
JUMLAH :
V.2 1 M2 Plesteran, 1 PC : 2 PP, tebal 15 mm
- Semen Portland 10.224 Kg 1,700.00
- Pasir pasang 0.020 M3 400,000.00
- Pekerja 0.300 Oh 110,000.00
- Tukang Batu 0.150 Oh 130,000.00
- Kep. Tukang 0.015 Oh 155,000.00
- Mandor 0.015 Oh 175,000.00
JUMLAH :
V.3 1 M2 Plesteran, 1 PC : 3 PP, tebal 15 mm
- Semen Portland 7.776 Kg 1,700.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Pasir pasang 0.023 M3 400,000.00


- Pekerja 0.300 Oh 110,000.00
- Tukang Batu 0.150 Oh 130,000.00
- Kep. Tukang 0.015 Oh 155,000.00
- Mandor 0.015 Oh 175,000.00
JUMLAH :
V.4 1 M2 Plesteran, 1 PC : 4 PP, tebal 15 mm
- Semen Portland 6.240 Kg 1,700.00
- Pasir pasang 0.024 M3 400,000.00
- Pekerja 0.300 Oh 110,000.00
- Tukang Batu 0.150 Oh 130,000.00
- Kep. Tukang 0.015 Oh 155,000.00
- Mandor 0.015 Oh 175,000.00
JUMLAH :
V.5 1 M2 Plesteran, 1 PC : 5 PP, tebal 15 mm
- Semen Portland 5.184 Kg 1,700.00
- Pasir pasang 0.026 M3 400,000.00
- Pekerja 0.300 Oh 110,000.00
- Tukang Batu 0.150 Oh 130,000.00
- Kep. Tukang 0.015 Oh 155,000.00
- Mandor 0.015 Oh 175,000.00
JUMLAH :
V.6 1 M2 Plesteran, 1 PC : 6 PP, tebal 15 mm
- Semen Portland 4.416 Kg 1,700.00
- Pasir pasang 0.027 M3 400,000.00
- Pekerja 0.300 Oh 110,000.00
- Tukang Batu 0.150 Oh 130,000.00
- Kep. Tukang 0.015 Oh 155,000.00
- Mandor 0.015 Oh 175,000.00
JUMLAH :
V.7 1 M2 Plesteran Beton, 1 PC : 2 PP, tebal 15 mm
- Semen Portland 9.300 Kg 1,700.00
- Pasir pasang 0.018 M3 400,000.00
- Pekerja 0.260 Oh 110,000.00
- Tukang Batu 0.200 Oh 130,000.00
- Kep. Tukang 0.020 Oh 155,000.00
- Mandor 0.013 Oh 175,000.00
JUMLAH :
V.8 1 M2 Plesteran Beton, 1 PC : 3 PP, tebal 15 mm
- Semen Portland 7.070 Kg 1,700.00
- Pasir pasang 0.021 M3 400,000.00
- Pekerja 0.260 Oh 110,000.00
- Tukang Batu 0.200 Oh 130,000.00
- Kep. Tukang 0.020 Oh 155,000.00
- Mandor 0.013 Oh 175,000.00
JUMLAH :
V.9 1 M2 Plesteran Skoning, 1 PC : 2 PP, Lebar 10 mm
- Semen Portland 0.500 Kg 1,700.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Pasir pasang 0.013 M3 400,000.00


- Pekerja 0.080 Oh 110,000.00
- Tukang Batu 0.400 Oh 130,000.00
- Kep. Tukang 0.040 Oh 155,000.00
- Mandor 0.004 Oh 175,000.00
JUMLAH :
V.10 1 M2 Plesteran Skoning, 1 PC : 2 PP, Lebar 10 mm
- Semen Portland 3.2500 Kg 1,700.00
- Pekerja 0.2000 M3 110,000.00
- Tukang 0.1000 Oh 130,000.00
- Kep. Tukang 0.0100 Oh 155,000.00
- Mandor 0.0100 Oh 175,000.00
JUMLAH :
V.11 1 ACIAN
Semen Portland 3.2500 Kg 1,700.00
Pekerja 0.2000 o/h 110,000.00
Tukang 0.1000 o/h 130,000.00
Kep. Tukang 0.0100 o/h 155,000.00
Mandor 0.0100 o/h 175,000.00
JUMLAH :
VI PEKERJAAN KAYU
VI.1 1 M3 Membuat dan Memasang Kusen Pintu dan Jendela Kayu Kelas I
- Kayu kelas I (balok) 1.100 M3 3,400,000.00
- Pekerja 7.000 Oh 110,000.00
- Tukang Kayu 21.000 Oh 130,000.00
- Kep. Tukang 2.100 Oh 155,000.00
- Mandor 0.350 Oh 175,000.00
JUMLAH :
VI.2 1 M3 Membuat dan Memasang Kusen Pintu dan Jendela Kayu Kelas II dan III
- Kayu kelas II (balok) 1.200 M3 2,100,000.00
- Pekerja 6.000 Oh 110,000.00
- Tukang Kayu 18.000 Oh 130,000.00
- Kep. Tukang 1.800 Oh 155,000.00
- Mandor 0.300 Oh 175,000.00
JUMLAH :
VI.3 1 M3 Membuat dan Memasang Pintu Klamp Standar, Kayu Kelas II
- Kayu kelas I (papan) 0.040 M3 3,750,000.00
- Paku biasa 0.050 Kg 20,000.00
- Pekerja 0.350 Oh 110,000.00
- Tukang Kayu 1.050 Oh 130,000.00
- Kep. Tukang 0.105 Oh 155,000.00
- Mandor 0.018 Oh 175,000.00
JUMLAH :
VI.4 1 M2 Membuat dan Memasang Daun Pintu Panel Kayu Kelas I
- Kayu kelas I (papan) 0.040 M3 3,750,000.00
- Pekerja 1.000 Oh 110,000.00
- Tukang Kayu 3.000 Oh 130,000.00
- Kep. Tukang 0.300 Oh 155,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Mandor 0.050 Oh 175,000.00


JUMLAH :
VI.5 1 M2 Membuat dan Memasang Pintu dan Jendela Jalusi Kayu Kelas I
- Kayu kelas I (papan) 0.064 M3 3,750,000.00
- Pekerja 1.000 Oh 110,000.00
- Tukang Kayu 3.000 Oh 130,000.00
- Kep. Tukang 0.300 Oh 155,000.00
- Mandor 0.050 Oh 175,000.00
JUMLAH :
VI.6 1 M2 Membuat dan Memasang Daun Pintu dan Jendela Kaca Kayu Kelas I
- Kayu kelas I (papan) 0.024 M3 3,750,000.00
- Lem kayu 0.300 Kg 15,000.00
- Pekerja 0.800 Oh 110,000.00
- Tukang Kayu 2.400 Oh 130,000.00
- Kep. Tukang 0.240 Oh 155,000.00
- Mandor 0.040 Oh 175,000.00
JUMLAH :
VI.7 1 M2 Membuat Pintu Kayu Lapis (Plywood), Rangkap, Rangka Tertutup Kayu Kelas II (Lebar sampai 90cm)
- Kayu kelas II (papan) 0.025 M3 2,000,000.00
- Paku biasa 0.030 Kg 20,000.00
- Lem kayu 0.500 Kg 15,000.00
- Plywood tebal 4 mm ( 90 x 220 ) cm 1.000 Lbr 70,000.00
- Pekerja 0.700 Oh 110,000.00
- Tukang Kayu 2.100 Oh 130,000.00
- Kep. Tukang 0.210 Oh 155,000.00
- Mandor 0.035 Oh 175,000.00
JUMLAH :
VI.8 1 M2 Membuat Pintu Kayu Lapis (Plywood), Rangkap, Rangka Expose Kayu Kelas I dan II
- Kayu kelas II (papan) 0.026 M3 2,000,000.00
- Paku biasa 0.030 Kg 20,000.00
- Lem kayu 0.500 Kg 15,000.00
- Plywood tebal 4 mm ( 90 x 220 ) cm 1.000 Lbr 70,000.00
- Pekerja 0.800 Oh 110,000.00
- Tukang Kayu 2.400 Oh 130,000.00
- Kep. Tukang 0.240 Oh 155,000.00
- Mandor 0.040 Oh 175,000.00
JUMLAH :
VI.9 1 M2 Pasang Jalusi Kusen Kayu Kelas I
- Kayu kelas I (papan) 0.060 M3 3,750,000.00
- Paku biasa 0.150 Kg 20,000.00
- Pekerja 0.670 Oh 110,000.00
- Tukang Kayu 2.000 Oh 130,000.00
- Kep. Tukang 0.200 Oh 155,000.00
- Mandor 0.335 Oh 175,000.00
JUMLAH :
VI.10 1 M2 Pasang Teakwood Rangkap, Rangka Expose Kayu Kelas I
- Kayu kelas I (papan) 0.025 M3 3,750,000.00
- Paku biasa 0.030 Kg 20,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Lem kayu 0.300 Kg 15,000.00


- Teakwood tebal 4 mm ( 90 x 220 ) cm 1.000 Lbr 90,000.00
- Pekerja 0.800 Oh 110,000.00
- Tukang Kayu 2.400 Oh 130,000.00
- Kep. Tukang 0.240 Oh 155,000.00
- Mandor 0.040 Oh 175,000.00
JUMLAH :
VI.11 1 M2 Pasang Teakwood Rangkap Lapis Formika, Rangka Expose Kayu Kelas II
- Kayu kelas II (papan) 0.025 M3 2,000,000.00
- Paku biasa 0.030 Kg 20,000.00
- Lem kayu 0.800 Lt 15,000.00
- Teakwood tebal 4 mm ( 90 x 220 ) cm 1.000 Lbr 90,000.00
- Formika 0.500 Lbr 100,000.00
- Pekerja 0.850 Oh 110,000.00
- Tukang Kayu 2.550 Oh 130,000.00
- Kep. Tukang 0.255 Oh 155,000.00
- Mandor 0.043 Oh 175,000.00
JUMLAH :
VI.12 1 M3 Pasang Konstruksi Kuda-Kuda Konvensional, Kayu Kelas II
- Kayu kelas II (balok) 1.100 M3 2,100,000.00
- Besi strip tebal 5 mm 15.000 Kg 25,000.00
- Paku biasa 5.600 Kg 20,000.00
- Pekerja 4.000 Oh 110,000.00
- Tukang Kayu 12.000 Oh 130,000.00
- Kep. Tukang 1.200 Oh 155,000.00
- Mandor 0.200 Oh 175,000.00
JUMLAH :
VI.13 1 M3 Pasang Konstruksi Kuda-Kuda Expose, Kayu Kelas I
- Kayu kelas I (balok) 1.200 M3 3,400,000.00
- Besi strip tebal 5 mm 15.000 Kg 25,000.00
- Paku biasa 5.600 Kg 20,000.00
- Pekerja 6.700 Oh 110,000.00
- Tukang Kayu 20.100 Oh 130,000.00
- Kep. Tukang 2.010 Oh 155,000.00
- Mandor 0.335 Oh 175,000.00
JUMLAH :
VI.14 1 M3 Pasang Konstruksi Gordeng, Kayu Kelas II
- Kayu kelas II (balok) 1.100 M3 2,100,000.00
- Besi strip tebal 5 mm 15.000 Kg 25,000.00
- Paku biasa 3.000 Kg 20,000.00
- Pekerja 2.400 Oh 110,000.00
- Tukang Kayu 7.200 Oh 130,000.00
- Kep. Tukang 0.720 Oh 155,000.00
- Mandor 0.120 Oh 175,000.00
JUMLAH :
VI.15 1 M2 Pasang Rangka Atap Genteng Keramik, Kayu Kelas II
- Kayu kelas II (balok) 0.014 M3 2,100,000.00
- Reng ( 2 x 3 ) cm 0.004 M3 2,500,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Paku biasa 0.250 Kg 20,000.00


- Pekerja 0.100 Oh 110,000.00
- Tukang Kayu 0.100 Oh 130,000.00
- Kep. Tukang 0.010 Oh 155,000.00
- Mandor 0.005 Oh 175,000.00
JUMLAH :
VI.16 1 M2 Pasang Rangka Atap Genteng Beton, Kayu Kelas II
- Kayu kelas II (balok) 0.014 M3 2,100,000.00
- Reng ( 2 x 3 ) cm 0.007 M3 2,500,000.00
- Paku biasa 0.250 Kg 20,000.00
- Pekerja 0.100 Oh 110,000.00
- Tukang Kayu 0.100 Oh 130,000.00
- Kep. Tukang 0.010 Oh 155,000.00
- Mandor 0.005 Oh 175,000.00
JUMLAH :
VI.17 1 M2 Pasang Rangka Atap Sirap, Kayu Kelas II
- Kayu kelas II (balok) 0.165 M3 2,100,000.00
- Paku biasa 0.200 Kg 20,000.00
- Pekerja 0.120 Oh 110,000.00
- Tukang Kayu 0.120 Oh 130,000.00
- Kep. Tukang 0.012 Oh 155,000.00
- Mandor 0.006 Oh 175,000.00
JUMLAH :
VI.18 1 M2 Pasang Rangka Langit-Langit (50 X 100) cm, Kayu Kelas II atau III
- Kayu kelas II (balok) 0.015 M3 2,100,000.00
- Paku biasa 0.200 Kg 20,000.00
- Pekerja 0.150 Oh 110,000.00
- Tukang Kayu 0.300 Oh 130,000.00
- Kep. Tukang 0.030 Oh 155,000.00
- Mandor 0.075 Oh 175,000.00
JUMLAH :
VI.19 1 M2 Pasang Rangka Langit-Langit (60 X 60) cm, Kayu Kelas II atau III
- Kayu kelas II (balok) 0.016 M3 2,100,000.00
- Paku biasa 0.250 Kg 20,000.00
- Pekerja 0.200 Oh 110,000.00
- Tukang Kayu 0.300 Oh 130,000.00
- Kep. Tukang 0.030 Oh 155,000.00
- Mandor 0.010 Oh 175,000.00
JUMLAH :
VI.20 1 M' Pasang Lisplank Ukuran (3 X 20) cm, Kayu Kelas I atau II
- Kayu kelas I (papan) 0.011 M3 3,750,000.00
- Paku biasa 0.100 Kg 20,000.00
- Pekerja 0.100 Oh 110,000.00
- Tukang Kayu 0.200 Oh 130,000.00
- Kep. Tukang 0.020 Oh 155,000.00
- Mandor 0.005 Oh 175,000.00
JUMLAH :
VI.21 1 M' Pasang List Plafond Kayu Profil

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Kayu profil 1.050 M' 15,000.00


- Pekerja 0.021 Oh 110,000.00
- Tukang Kayu 0.021 Oh 130,000.00
- Kep. Tukang 0.002 Oh 155,000.00
- Mandor 0.001 Oh 175,000.00
JUMLAH :
VI.22 1 M' Pasang Lisplank Ukuran (3 X 30) cm, Kayu Kelas I atau II
- Kayu kelas I (papan) 0.011 M3 3,750,000.00
- Paku biasa 0.050 Kg 20,000.00
- Pekerja 0.100 Oh 110,000.00
- Tukang Kayu 0.200 Oh 130,000.00
- Kep. Tukang 0.020 Oh 155,000.00
- Mandor 0.005 Oh 175,000.00
JUMLAH :
VI.23 1 M2 Pasang Rangka Dinding Pemisah (60 X 120) cm , Kayu Kelas II atau III
- Kayu kelas II (balok) 0.028 M3 2,100,000.00
- Paku biasa 0.150 Kg 20,000.00
- Pekerja 0.150 Oh 110,000.00
- Tukang Kayu 0.450 Oh 130,000.00
- Kep. Tukang 0.045 Oh 155,000.00
- Mandor 0.008 Oh 175,000.00
JUMLAH :
VI.24 1 M2 Pasang Dinding Pemisah Teakwood Rangkap, Rangka Kayu Kelas II
- Kayu kelas II (balok) 0.028 M3 2,100,000.00
- Paku biasa 0.150 Kg 20,000.00
- Teakwood tebal 4 mm ( 120 x 240 ) cm 0.860 Lembar 110,000.00
- Lem kayu 0.560 Kg 15,000.00
- Pekerja 0.150 Oh 110,000.00
- Tukang Kayu 0.450 Oh 130,000.00
- Kep. Tukang 0.045 Oh 155,000.00
- Mandor 0.008 Oh 175,000.00
JUMLAH :
VI.25 1 M2 Pasang Dinding Pemisah Plywood Rangkap, Rangka Kayu Kelas II
- Kayu kelas II (balok) 0.028 M3 2,100,000.00
- Paku biasa 0.150 Kg 20,000.00
- Plywood tebal 4 mm ( 120 x 240 ) cm 0.860 Lembar 75,000.00
- Lem kayu 0.560 Kg 15,000.00
- Pekerja 0.200 Oh 110,000.00
- Tukang Kayu 0.600 Oh 130,000.00
- Kep. Tukang 0.060 Oh 155,000.00
- Mandor 0.010 Oh 175,000.00
JUMLAH :
VI.26 1 M2 Pasang Dinding Lambriziring dari Papan Kayu Kelas I
- Kayu kelas I (papan) 0.007 M3 3,750,000.00
- Paku biasa 0.100 Kg 20,000.00
- Paku sekrup 0.150 Kg 75,000.00
- Pekerja 0.600 Oh 110,000.00
- Tukang Kayu 1.800 Oh 130,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Kep. Tukang 0.180 Oh 155,000.00


- Mandor 0.030 Oh 175,000.00
JUMLAH :
VI.27 1 M2 Pasang Dinding PARTISI dari Plywood ( 120 X 240 ) cm
- Plywood tebal 4 mm ( 120 x 240 ) cm 0.400 lbr 75,000.00
- Paku biasa 0.050 Kg 20,000.00
- Pekerja 0.025 Oh 110,000.00
- Tukang Kayu 0.075 Oh 130,000.00
- Kep. Tukang 0.008 Oh 155,000.00
- Mandor 0.001 Oh 175,000.00
JUMLAH :
VI.28 1 M2 Pasang Dinding Bilik, Rangka Kayu Kelas II
- Bilik bambu 1.500 M3 65,000.00
- Kayu kelas II (balok) 0.014 M3 2,100,000.00
- Paku biasa 0.012 Kg 20,000.00
- Kayu profil 0.003 M3 15,000.00
- Pekerja 0.100 Oh 110,000.00
- Tukang Kayu 0.050 Oh 130,000.00
- Kep. Tukang 0.005 Oh 155,000.00
- Mandor 0.005 Oh 175,000.00
JUMLAH :
VI.29 1 M1 Pekerjaan Railing Kayu kelas 1
- Pekerjaan Kayu Halus 0.126 M3 7,626,750.00
Paku biasa 0.209 Kg 20,000.00
- Pekerjaan Cat Kayu 5.089 m2 35,037.50
JUMLAH :
VII PEKERJAAN BETON (SNI 7394:2008)
VII.1 Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87 (SNI 7394:2008-1)
- Semen Portland 247.000 Kg 1,700.00
- Pasir beton 0.621 M3 400,000.00
- Koral beton 0.740 M3 450,000.00
- Air 215.000 150.00
- Pekerja 1.650 Oh 110,000.00
- Tukang batu 0.275 Oh 130,000.00
- Kep. Tukang 0.028 Oh 155,000.00
- Mandor 0.083 Oh 175,000.00
JUMLAH :
VII.2 Membuat 1 m3 beton mutu f’c = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78
- Semen Portland 276.000 Kg 1,700.00
- Pasir beton 0.591 M3 400,000.00
- Koral beton 0.750 M3 450,000.00
- Air 215.000 150.00
- Pekerja 1.650 Oh 110,000.00
- Tukang batu 0.275 Oh 130,000.00
- Kep. Tukang 0.028 Oh 155,000.00
- Mandor 0.083 Oh 175,000.00
JUMLAH :
VII.3 Membuat 1 m3 beton mutu f’c = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Semen Portland 299.000 Kg 1,700.00


- Pasir beton 0.571 M3 400,000.00
- Koral beton 0.753 M3 450,000.00
- Air 215.000 150.00
- Pekerja 1.650 Oh 110,000.00
- Tukang batu 0.275 Oh 130,000.00
- Kep. Tukang 0.028 Oh 155,000.00
- Mandor 0.083 Oh 175,000.00
JUMLAH :
VII.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
- Semen Portland 230.000 Kg 1,700.00
- Pasir beton 0.638 M3 400,000.00
- Koral beton 0.761 M3 450,000.00
- Air 215.000 150.00
- Pekerja 1.200 Oh 110,000.00
- Tukang batu 0.200 Oh 130,000.00
- Kep. Tukang 0.020 Oh 155,000.00
- Mandor 0.060 Oh 175,000.00
JUMLAH :
VII.5 Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
- Semen Portland 326.000 Kg 1,700.00
- Pasir beton 0.543 M3 400,000.00
- Koral beton 0.762 M3 450,000.00
- Air 215.000 150.00
- Pekerja 1.650 Oh 110,000.00
- Tukang batu 0.275 Oh 130,000.00
- Kep. Tukang 0.028 Oh 155,000.00
- Mandor 0.083 Oh 175,000.00
JUMLAH :
VII.6 Membuat 1 m3 beton mutu f’c = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61
- Semen Portland 352.000 Kg 1,700.00
- Pasir beton 0.522 M3 400,000.00
- Koral beton 0.764 M3 450,000.00
- Air 215.000 150.00
- Pekerja 1.650 Oh 110,000.00
- Tukang batu 0.275 Oh 130,000.00
- Kep. Tukang 0.028 Oh 155,000.00
- Mandor 0.083 Oh 175,000.00
JUMLAH :
VII.7 Membuat 1 m3 beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58
- Semen Portland 371.000 Kg 1,700.00
- Pasir beton 0.499 M3 400,000.00
- Koral beton 0.776 M3 450,000.00
- Air 215.000 150.00
- Pekerja 1.650 Oh 110,000.00
- Tukang batu 0.275 Oh 130,000.00
- Kep. Tukang 0.028 Oh 155,000.00
- Mandor 0.083 Oh 175,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

JUMLAH :
VII.8 Membuat 1 m3 beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
- Semen Portland 384.000 Kg 1,700.00
- Pasir beton 0.494 M3 400,000.00
- Koral beton 0.770 M3 450,000.00
- Air 215.000 150.00
- Pekerja 1.650 Oh 110,000.00
- Tukang batu 0.275 Oh 130,000.00
- Kep. Tukang 0.028 Oh 155,000.00
- Mandor 0.083 Oh 175,000.00
JUMLAH :
VII.9 Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53
- Semen Portland 406.000 Kg 1,700.00
- Pasir beton 0.489 M3 400,000.00
- Koral beton 0.760 M3 450,000.00
- Air 215.000 150.00
- Pekerja 1.650 Oh 110,000.00
- Tukang batu 0.275 Oh 130,000.00
- Kep. Tukang 0.028 Oh 155,000.00
- Mandor 0.083 Oh 175,000.00
JUMLAH :
VII.10 Membuat 1 m3 beton mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52
- Semen Portland 413.000 Kg 1,700.00
- Pasir beton 0.486 M3 400,000.00
- Koral beton 0.756 M3 450,000.00
- Air 215.000 150.00
- Pekerja 1.650 Oh 110,000.00
- Tukang batu 0.275 Oh 130,000.00
- Kep. Tukang 0.028 Oh 155,000.00
- Mandor 0.083 Oh 175,000.00
JUMLAH :
VII.11 Membuat 1 m3 beton mutu f’c = 28,8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,49
- Semen Portland 439.000 Kg 1,700.00
- Pasir beton 0.479 M3 400,000.00
- Koral beton 0.745 M3 450,000.00
- Air 215.000 150.00
- Pekerja 2.100 Oh 110,000.00
- Tukang batu 0.350 Oh 130,000.00
- Kep. Tukang 0.035 Oh 155,000.00
- Mandor 0.106 Oh 175,000.00
JUMLAH :
VII.12 Membuat 1 m3 beton mutu f’c = 31,2 MPa (K 350), slump (12 ± 2) cm, w/c = 0,48
- Semen Portland 448.000 Kg 1,700.00
- Pasir beton 0.476 M3 400,000.00
- Koral beton 0.741 M3 450,000.00
- Air 215.000 150.00
- Pekerja 2.100 Oh 110,000.00
- Tukang batu 0.350 Oh 130,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Kep. Tukang 0.035 Oh 155,000.00


- Mandor 0.106 Oh 175,000.00
JUMLAH :
VII.13 Membuat 1 m3 beton kedap air dengan strorox – 100
- Semen Portland 400.000 Kg 1,700.00
- Pasir beton 0.480 M3 400,000.00
- Koral beton 0.800 M3 450,000.00
- Air 210.000 150.00
- Pekerja 2.100 Oh 110,000.00
- Tukang batu 0.350 Oh 130,000.00
- Kep. Tukang 0.035 Oh 155,000.00
- Mandor 0.106 Oh 175,000.00
JUMLAH :
VII.14 Memasang 1 m’ PVC Waterstop lebar 150 mm
- Waterstop lebar 150 mm 1.050 m’ 15,000.00
- Pekerja 0.060 Oh 110,000.00
- Tukang batu 0.030 Oh 130,000.00
- Kep. Tukang 0.003 Oh 155,000.00
- Mandor 0.003 Oh 175,000.00

VII.15 Memasang 1 m’ PVC Waterstop lebar 200 mm


- Waterstop lebar 200 mm 1.050 m’ 20,000.00
- Pekerja 0.070 Oh 110,000.00
- Tukang batu 0.035 Oh 130,000.00
- Kep. Tukang 0.004 Oh 155,000.00
- Mandor 0.004 Oh 175,000.00

VII.16 Membuat 1 m’ PVC Waterstop lebar 230 mm – 320 mm


- Waterstop lebar 230 mm - 320 mm 1.050 m’ 25,000.00
- Pekerja 0.080 Oh 110,000.00
- Tukang batu 0.040 Oh 130,000.00
- Kep. Tukang 0.004 Oh 155,000.00
- Mandor 0.004 Oh 175,000.00

VII.17 Pembesian 10 Kg dengan Besi polos atau Besi Ulir


- Besi beton 10.500 Kg 19,500.00
- Kawat beton 0.150 Kg 35,000.00
- Pekerja 0.070 Oh 110,000.00
- Tukang besi 0.070 Oh 130,000.00
- Kep. Tukang 0.007 Oh 155,000.00
- Mandor 0.004 Oh 175,000.00
JUMLAH :
JUMLAH : 1 kg

VII.18 Memasang 10 Kg Kabel Presstressed Polos/Strands


- Besi beton 10.500 Kg 19,500.00
- Kawat beton 0.100 Kg 35,000.00
- Pekerja 0.050 Oh 110,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Tukang besi 0.050 Oh 130,000.00


- Kep. Tukang 0.005 Oh 155,000.00
- Mandor 0.003 Oh 175,000.00
JUMLAH :
JUMLAH : 1 kg

VII.19 Memasang 1 Kg jaring kawat baja/wire mesh


Jaring kawat baja dilas 1.020 Kg 25,000.00
Kawat beton 0.050 Kg 35,000.00
Pekerja 0.025 Oh 110,000.00
Tukang besi 0.025 Oh 130,000.00
Kep. Tukang 0.002 Oh 155,000.00
Mandor 0.001 Oh 175,000.00

VII.20 1 M2 Pasang Bekisting untuk Pondasi


- Kayu kelas II (papan) 0.040 M3 2,000,000.00
- Paku biasa 0.300 Kg 20,000.00
- Minyak Bekesting 0.100 Liter 15,000.00
- Pekerja 0.520 Oh 110,000.00
- Tukang Kayu 0.260 Oh 130,000.00
- Kep. Tukang 0.026 Oh 155,000.00
- Mandor 0.026 Oh 175,000.00
JUMLAH :
VII.21 1 M2 Pasang Bekisting untuk Sloof
- Kayu kelas II (papan) 0.045 M3 2,000,000.00
- Paku biasa 0.300 Kg 20,000.00
- Minyak Bekesting 0.100 Liter 15,000.00
- Pekerja 0.520 Oh 110,000.00
- Tukang Kayu 0.260 Oh 130,000.00
- Kep. Tukang 0.026 Oh 155,000.00
- Mandor 0.026 Oh 175,000.00
JUMLAH :
VII.22 1 M2 Pasang Bekisting untuk Kolom
- Kayu kelas II (papan) 0.040 M3 2,000,000.00
- Paku biasa 0.400 Kg 20,000.00
- Minyak Bekesting 0.200 Liter 15,000.00
- Kayu kelas II (balok) 0.015 M3 2,100,000.00
- Tripleks 9 mm 0.350 Lembar 135,000.00
- Dolken Kayu Dia. 8-10/400 cm 2.000 Batang 25,000.00
- Pekerja 0.660 Oh 110,000.00
- Tukang Kayu 0.330 Oh 130,000.00
- Kep. Tukang 0.033 Oh 155,000.00
- Mandor 0.033 Oh 175,000.00
JUMLAH :
VII.23 1 M2 Pasang Bekisting untuk Balok
- Kayu kelas II (papan) 0.040 M3 2,000,000.00
- Paku biasa 0.400 Kg 20,000.00
- Minyak Bekesting 0.200 Liter 15,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Kayu kelas II (balok) 0.018 M3 2,100,000.00


- Tripleks 9 mm 0.350 Lembar 135,000.00
- Dolken Kayu Dia. 8-10/400 cm 2.000 Batang 25,000.00
- Pekerja 0.660 Oh 110,000.00
- Tukang Kayu 0.330 Oh 130,000.00
- Kep. Tukang 0.033 Oh 155,000.00
- Mandor 0.033 Oh 175,000.00
JUMLAH :
VII.24 1 M2 Pasang Bekisting untuk Plat Lantai
- Kayu kelas II (papan) 0.040 M3 2,000,000.00
- Paku biasa 0.400 Kg 20,000.00
- Minyak Bekesting 0.200 Liter 15,000.00
- Kayu kelas II (balok) 0.015 M3 2,100,000.00
- Tripleks 9 mm 0.350 Lembar 135,000.00
- Dolken Kayu Dia. 8-10/400 cm 6.000 Batang 25,000.00
- Pekerja 0.660 Oh 110,000.00
- Tukang Kayu 0.330 Oh 130,000.00
- Kep. Tukang 0.033 Oh 155,000.00
- Mandor 0.033 Oh 175,000.00
JUMLAH :
VII.25 1 M2 Pasang Bekisting untuk Dinding
- Kayu kelas II (papan) 0.040 M3 2,000,000.00
- Paku biasa 0.400 Kg 20,000.00
- Minyak Bekesting 0.200 Liter 15,000.00
- Kayu kelas II (balok) 0.020 M3 2,100,000.00
- Tripleks 9 mm 0.350 Lembar 135,000.00
- Dolken Kayu Dia. 8-10/400 cm 3.000 Batang 25,000.00
- Permite/Penjaga jarak bekisting/spacer 4.000 Buah 15,000.00
- Pekerja 0.660 Oh 110,000.00
- Tukang Kayu 0.330 Oh 130,000.00
- Kep. Tukang 0.033 Oh 155,000.00
- Mandor 0.033 Oh 175,000.00
JUMLAH :
VII.26 1 M2 Pasang Bekisting untuk Tangga
- Kayu kelas II (papan) 0.030 M3 2,000,000.00
- Paku biasa 0.400 Kg 20,000.00
- Minyak Bekesting 0.150 Liter 15,000.00
- Kayu kelas II (balok) 0.015 M3 2,100,000.00
- Tripleks 9 mm 0.350 Lembar 135,000.00
- Dolken Kayu Dia. 8-10/400 cm 2.000 Batang 25,000.00
- Pekerja 0.660 Oh 110,000.00
- Tukang Kayu 0.330 Oh 130,000.00
- Kep. Tukang 0.033 Oh 155,000.00
- Mandor 0.033 Oh 175,000.00
JUMLAH :
VII.27 1 M2 Pasang Jembatan untuk Pengecoran Beton
- Kayu kelas II (papan) 0.026 M3 2,000,000.00
- Paku biasa 0.600 Kg 20,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Dolken Kayu Dia. 8-10/400 cm 0.500 Batang 25,000.00


- Pekerja 0.150 Oh 110,000.00
- Tukang Kayu 0.500 Oh 130,000.00
- Kep. Tukang 0.005 Oh 155,000.00
- Mandor 0.008 Oh 175,000.00
JUMLAH :
VII.28 1 M3 Pekerjaan Pondasi Beton Bertulang P1
- Beton K.300 1.000 m3 1,505,369.76
- Besi beton 165.285 Kg 22,858.50
- Bekisting 3.878 m2 187,080.00
- Tuk.Bongkar Bekisting 0.500 o/h 110,000.00
- JUMLAH :
VII.29 1 M3 PekerjaanPondasi Beton Bertulang P2
- Beton K.300 1.000 m3 1,505,369.76
- Besi beton 173.070 Kg 22,858.50
- Bekisting 4.722 m2 187,080.00
- Tuk.Bongkar Bekisting 0.500 o/h 110,000.00
- JUMLAH :
VII.30 1 M3 Pekerjaan Pondasi Beton Bertulang P3
- Beton K.300 1.000 m3 1,505,369.76
- Besi beton 227.360 Kg 22,858.50
- Bekisting 7.000 m2 187,080.00
- Tuk.Bongkar Bekisting 0.500 o/h 110,000.00
JUMLAH :
VII.31 1 M3 Pekerjaan Kolom Beton Bertulang K1 (dia. 80cm)
- Beton K.300 1.000 m3 1,505,369.76
- Besi beton 126.998 Kg 22,858.50
- Bekisting 8.000 m2 346,140.00
- Tuk.Bongkar Bekisting +siram 1.000 o/h 110,000.00
- JUMLAH :
VII.32 1 M3 Pekerjaan Kolom Beton Bertulang K1 (dia. 70cm)
- Beton K.300 1.000 m3 1,505,369.76
- Besi beton 114.767 Kg 22,858.50
- Bekisting 7.031 m2 346,140.00
- Tuk.Bongkar Bekisting +siram 1.000 o/h 110,000.00
- JUMLAH :
VII.32 1 M3 Pekerjaan Kolom Beton Bertulang K2 (30x35cm)
- Beton K.300 1.000 m3 1,505,369.76
- Besi beton 242.842 Kg 22,858.50
- Bekisting 12.381 m2 346,140.00
- Tuk.Bongkar Bekisting +siram 0.750 o/h 110,000.00
- JUMLAH :
VII.33 1 M3 Pekerjaan Beton Bertulang K3 (20x60 cm)
- Beton K.300 1.000 m3 1,505,369.76
- Besi beton 200.506 Kg 22,858.50
- Bekisting 13.333 m2 346,140.00
- Tuk.Bongkar Bekisting +siram 0.750 o/h 110,000.00
- JUMLAH :

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

VII.34 1 M3 Pekerjaan Kolom Beton Bertulang K4 (15x40 cm)


- Beton K.300 1.000 m3 1,505,369.76
- Besi beton 223.450 Kg 22,858.50
- Bekisting 15.000 m2 346,140.00
- Tuk.Bongkar Bekisting +siram 0.750 o/h 110,000.00
- JUMLAH :
VII.35 1 M3 Pekerjaan Kolom Beton Bertulang K5 (20x20 cm)
- Beton K.300 1.000 m3 1,505,369.76
- Besi beton 173.606 Kg 22,858.50
- Bekisting 20.000 m2 346,140.00
- Tuk.Bongkar Bekisting +siram 0.750 o/h 110,000.00
- JUMLAH :
VII.36 1 M3 PekerjaanKolom Praktis Kp (12x12 cm)
- Beton K.175 1.000 m3 1,382,707.86
- Besi beton 385.792 Kg 22,858.50
- Bekisting 33.333 m2 346,140.00
- Tuk.Bongkar Bekisting +siram 0.750 o/h 110,000.00
- JUMLAH :
VII.36 1 M3 Pekerjaan Slof Beton Bertulang S1 (30x60 cm)
- Beton K.275 1.000 m3 1,505,369.76
- Besi beton 326.733 Kg 22,858.50
- Bekisting 6.667 m2 197,080.00
- Tuk.Bongkar Bekisting +siram 0.750 o/h 110,000.00
- JUMLAH :
VII.37 1 M3 Pekerjaan Slof Beton Bertulang S1 (25x40 cm)
- Beton K.275 1.000 m3 1,505,369.76
- Besi beton 272.277 Kg 22,858.50
- Bekisting 8.000 m2 197,080.00
- Tuk.Bongkar Bekisting +siram 0.750 o/h 110,000.00
- JUMLAH :
VII.38 1 M3 PekerjaanSlof Beton Bertulang S2 (20x35 cm)
- Beton K.275 1.000 m3 1,505,369.76
- Besi beton 223.983 Kg 22,858.50
- Bekisting 10.000 m2 197,080.00
- Tuk.Bongkar Bekisting +siram 0.750 o/h 110,000.00
- JUMLAH :
VII.39 1 M3 Pekerjaan Slof Beton Bertulang S3 (15x20 cm)
- Beton K.175 1.000 m3 1,382,707.86
- Besi beton 126.998 Kg 22,858.50
- Bekisting 8.000 m2 197,080.00
- Tuk.Bongkar Bekisting +siram 0.750 o/h 110,000.00
- JUMLAH :
VII.40 1 M3 Pekerjaan Balok Lantai Beton Bertulang B1 (30 x 45 cm)
- Beton K.275 1.000 m3 1,505,369.76
- Besi beton 248.002 Kg 22,858.50
- Bekisting 8.889 m2 352,440.00
- Tuk.Bongkar Bekisting +siram 1.000 o/h 110,000.00
- JUMLAH :

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

VII.41 1 M3 Pekerjaan Balok Lantai Beton Bertulang B2 (20 x 30 cm)


- Beton K.275 1.000 m3 1,505,369.76
- Besi beton 220.022 Kg 22,858.50
- Bekisting 13.333 m2 352,440.00
- Tuk.Bongkar Bekisting +siram 1.000 o/h 110,000.00
- JUMLAH :
VII.42 1 M3 Pekerjaan Ring Balok Beton Bertulang RB1 (30 x 45 cm)
- Beton K.275 1.000 m3 1,505,369.76
- Besi beton 187.672 Kg 22,858.50
- Bekisting 8.889 m2 352,440.00
- Tuk.Bongkar Bekisting +siram 1.000 o/h 110,000.00
- JUMLAH :
VII.43 1 M3 Pekerjaan Ring Balok Beton Bertulang RB1a (20 x 50 cm)
- Beton K.275 1.000 m3 1,505,369.76
- Besi beton 238.166 Kg 22,858.50
- Bekisting 12.000 m2 352,440.00
- Tuk.Bongkar Bekisting +siram 1.000 o/h 110,000.00
- JUMLAH :
VII.44 1 M3 Pekerjaan Ring Balok Beton Bertulang RB2 (20 x 30 cm)
- Beton K.275 1.000 m3 1,505,369.76
- Besi beton 227.557 Kg 22,858.50
- Bekisting 13.333 m2 352,440.00
- Tuk.Bongkar Bekisting +siram 1.000 o/h 110,000.00
- JUMLAH :
VII.45 1 M3 Pekerjaan Ring Balok Beton Bertulang RB3 (15 x 50 cm)
- Beton K.275 1.000 m3 1,505,369.76
- Besi beton 244.134 Kg 22,858.50
- Bekisting 15.333 m2 352,440.00
- Tuk.Bongkar Bekisting +siram 1.000 o/h 110,000.00
- JUMLAH :
VII.46 1 M3 Pekerjaan Ring Balok Beton Bertulang RB4 (20 x 40 cm)
- Beton K.275 1.000 m3 1,505,369.76
- Besi beton 173.380 Kg 22,858.50
- Bekisting 12.500 m2 352,440.00
- Tuk.Bongkar Bekisting +siram 1.000 o/h 110,000.00
- JUMLAH :
VII.47 1 M3 Pekerjaan Konsol Beton Bertulang KB
- Beton K.275 1.000 m3 1,505,369.76
- Besi beton 554.739 Kg 22,858.50
- Bekisting 20.235 m2 352,440.00
- Tuk.Bongkar Bekisting +siram 1.000 o/h 110,000.00
- JUMLAH :
VII.48 1 M3 Pekerjaan Lisplan Beton Bertulang LB
- Beton K.275 1.000 m3 1,505,369.76
- Besi beton 174.884 Kg 22,858.50
- Bekisting 26.923 m2 441,640.00
- Tuk.Bongkar Bekisting +siram 1.000 o/h 110,000.00
- JUMLAH :

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

VII.49 1 M3 Pekerjaan Ring Beton Bertulang RBD


- Beton K.275 1.000 m3 1,505,369.76
- Besi beton 162.756 Kg 22,858.50
- Bekisting 10.000 m2 441,640.00
- Tuk.Bongkar Bekisting +siram 1.000 o/h 110,000.00
- JUMLAH :
VII.50 1 M3 Pekerjaan Plat Lantai Beton Bertulang
- Beton K.275 1.000 m3 1,505,369.76
- Besi beton 226.050 Kg 22,858.50
- Bekisting 8.333 m2 441,640.00
- Tuk.Bongkar Bekisting +siram 1.000 o/h 110,000.00
- JUMLAH :
VII.51 1 M3 Membuat Pondasi Beton Bertulang (150 kg besi + bekisting )
- Kayu kelas II (papan) 0.200 M3 2,000,000.00
- Paku biasa 1.500 Kg 20,000.00
- Minyak Bekesting 0.400 Liter 15,000.00
- Besi beton 150.000 Kg 19,500.00
- Kawat beton 2.250 Kg 35,000.00
- Semen Portland 336.000 Kg 1,700.00
- Pasir Beton 0.540 M3 400,000.00
- Koral beton 0.810 M3 450,000.00
- Pekerja 5.300 Oh 110,000.00
- Tukang Batu 0.275 Oh 130,000.00
- Tukang Kayu 1.300 Oh 130,000.00
- Tukang besi 1.050 Oh 130,000.00
- Kep. Tukang 0.262 Oh 155,000.00
- Mandor 0.265 Oh 175,000.00
JUMLAH :
VII.52 1 M3 Membuat Sloof Beton Bertulang (200 kg besi + bekisting )
- Kayu kelas II (papan) 0.270 M3 2,000,000.00
- Paku biasa 2.000 Kg 20,000.00
- Minyak Bekesting 0.600 Liter 15,000.00
- Besi beton 210.000 Kg 19,500.00
- Kawat beton 3.000 Kg 35,000.00
- Semen Portland 336.000 Kg 1,700.00
- Pasir Beton 0.540 M3 400,000.00
- Koral beton 0.810 M3 450,000.00
- Pekerja 5.650 Oh 110,000.00
- Tukang Batu 0.275 Oh 130,000.00
- Tukang Kayu 1.560 Oh 130,000.00
- Tukang besi 1.400 Oh 130,000.00
- Kep. Tukang 0.323 Oh 155,000.00
- Mandor 0.283 Oh 175,000.00
JUMLAH :
VII.53 1 M3 Membuat Kolom Beton Bertulang (300 kg besi + bekisting )
- Kayu kelas II (papan) 0.400 M3 2,000,000.00
- Paku biasa 4.000 Kg 20,000.00
- Minyak Bekesting 2.000 Liter 15,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Besi beton 300.000 Kg 19,500.00


- Kawat beton 4.500 Kg 35,000.00
- Semen Portland 323.000 Kg 1,700.00
- Pasir Beton 0.520 M3 400,000.00
- Koral beton 0.780 M3 450,000.00
- Kayu kelas II (balok) 0.150 M3 2,100,000.00
- Tripleks 9 mm 3.500 Lembar 135,000.00
- Dolken Kayu Dia. 8-10/400 cm 20.000 Batang 25,000.00
- Pekerja 7.300 Oh 110,000.00
- Tukang Batu 0.350 Oh 130,000.00
- Tukang Kayu 3.300 Oh 130,000.00
- Tukang besi 2.100 Oh 130,000.00
- Kep. Tukang 0.570 Oh 155,000.00
- Mandor 0.250 Oh 175,000.00
JUMLAH :
VII.54 1 M3 Membuat Plat Beton Bertulang (150 kg besi + bekisting )
- Kayu kelas II (papan) 0.320 M3 2,000,000.00
- Paku biasa 3.200 Kg 20,000.00
- Minyak Bekesting 1.600 Liter 15,000.00
- Besi beton 150.000 Kg 19,500.00
- Kawat beton 2.250 Kg 35,000.00
- Semen Portland 336.000 Kg 1,700.00
- Pasir Beton 0.540 M3 400,000.00
- Koral beton 0.810 M3 450,000.00
- Kayu kelas II (balok) 0.120 M3 2,100,000.00
- Tripleks 9 mm 2.800 Lembar 135,000.00
- Dolken Kayu Dia. 8-10/400 cm 32.000 Batang 25,000.00
- Pekerja 5.300 Oh 110,000.00
- Tukang Batu 0.275 Oh 130,000.00
- Tukang Kayu 1.300 Oh 130,000.00
- Tukang besi 1.050 Oh 130,000.00
- Kep. Tukang 0.265 Oh 155,000.00
- Mandor 0.265 Oh 175,000.00
JUMLAH :
VII.55 1 M3 Membuat Balok Beton Bertulang ( 200 Kg Besi + Bekisting )
- Kayu kelas II (papan) 0.250 M3 2,000,000.00
- Paku biasa 3.200 Kg 20,000.00
- Minyak Bekesting 1.600 Liter 15,000.00
- Besi beton 200.000 Kg 19,500.00
- Kawat Beton 3.000 Kg 35,000.00
- Semen Portland 323.000 Kg 1,700.00
- Pasir Beton 0.520 M3 400,000.00
- Koral Beton 0.780 M3 450,000.00
- Kayu kelas II (balok) 0.140 M3 2,100,000.00
- Tripleks 9 mm 2.800 Ltr 135,000.00
- Dolken Kayu Dia. 8-10/400 cm 16.000 Btg 25,000.00
- Pekerja 5.960 Oh 110,000.00
- Tukang Batu 0.350 Oh 130,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Tukang Kayu 2.800 Oh 130,000.00


- Tukang Besi 1.400 Oh 130,000.00
- Kep. Tukang 0.550 Oh 155,000.00
- Mandor 0.208 Oh 175,000.00
JUMLAH :
VII.56 1 M3 Membuat Balok Beton Bertulang ( 150 Kg Besi + Bekisting )
- Kayu kelas II (papan) 0.240 M3 2,000,000.00
- Paku biasa 3.200 Kg 20,000.00
- Minyak Bekesting 1.600 Liter 15,000.00
- Besi beton 150.000 Kg 19,500.00
- Kawat Beton 2.250 Kg 35,000.00
- Semen Portland 323.000 Kg 1,700.00
- Pasir Beton 0.520 M3 400,000.00
- Koral Beton 0.780 M3 450,000.00
- Kayu kelas II (balok) 0.120 M3 2,100,000.00
- Tripleks 9 mm 2.800 Lbr 135,000.00
- Dolken Kayu Dia. 8-10/400 cm 32.000 Btg 25,000.00
- Pekerja 5.800 Oh 110,000.00
- Tukang Batu 0.350 Oh 130,000.00
- Tukang Kayu 2.800 Oh 130,000.00
- Tukang Besi 1.050 Oh 130,000.00
- Kep. Tukang 0.420 Oh 155,000.00
- Mandor 0.185 Oh 175,000.00
JUMLAH :
VII.57 1 M3 Membuat Dinding Beton Bertulang (150 kg besi + bekisting )
- Kayu kelas II (papan) 0.240 M3 2,000,000.00
- Paku biasa 3.200 Kg 20,000.00
- Minyak Bekesting 1.600 Liter 15,000.00
- Besi beton 150.000 Kg 19,500.00
- Kawat beton 2.250 Kg 35,000.00
- Semen Portland 323.000 Kg 1,700.00
- Pasir Beton 0.540 M3 400,000.00
- Kerikil 0.810 M3 450,000.00
- Kayu kelas II (balok) 0.160 M3 2,100,000.00
- Tripleks 9 mm 2.800 Lembar 135,000.00
- Dolken Kayu Dia. 8-10/400 cm 24.000 Batang 25,000.00
- Pekerja 5.300 Oh 110,000.00
- Tukang Batu 0.275 Oh 130,000.00
- Tukang Kayu 1.300 Oh 130,000.00
- Tukang Besi 1.050 Oh 130,000.00
- Kep. Tukang 0.262 Oh 155,000.00
- Mandor 0.265 Oh 175,000.00
JUMLAH :
VII.58 1 M3 Membuat Dinding Beton Bertulang (200 kg besi + bekisting )
- Kayu kelas II (papan) 0.250 M3 2,000,000.00
- Paku biasa 3.000 Kg 20,000.00
- Minyak Bekesting 1.200 Liter 15,000.00
- Besi beton 200.000 Kg 19,500.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Kawat beton 3.000 Kg 35,000.00


- Semen Portland 323.000 Kg 1,700.00
- Pasir Beton 0.540 M3 400,000.00
- Kerikil 0.810 M3 450,000.00
- Kayu kelas II (balok) 0.105 M3 2,100,000.00
- Tripleks 9 mm 2.500 Lembar 135,000.00
- Dolken Kayu Dia. 8-10/400 cm 14.000 Batang 25,000.00
- Pekerja 5.650 Oh 110,000.00
- Tukang Batu 0.275 Oh 130,000.00
- Tukang Kayu 1.560 Oh 130,000.00
- Tukang Besi 1.400 Oh 130,000.00
- Kep. Tukang 0.323 Oh 155,000.00
- Mandor 0.283 Oh 175,000.00
JUMLAH :
VII.59 1 M' Membuat Kolom Praktis Beton Bertulang (11 x 11 ) cm
- Kayu kelas II (papan) 0.002 M3 2,000,000.00
- Besi beton 0.010 Kg 19,500.00
- Minyak Bekesting 3.000 Kg 15,000.00
- Kawat beton 0.045 Kg 35,000.00
- Semen Portland 4.000 Kg 1,700.00
- Pasir Beton 0.006 M3 400,000.00
- Kerikil 0.009 M3 450,000.00
- Pekerja 0.180 Oh 110,000.00
- Tukang Batu 0.020 Oh 130,000.00
- Tukang Kayu 0.020 Oh 130,000.00
- Tukang Besi 0.020 Oh 130,000.00
- Kep. Tukang 0.006 Oh 155,000.00
- Mandor 0.009 Oh 175,000.00
JUMLAH :
VII.60 1 M' Membuat Ring Balok Beton Bertulang (10 x 15 ) cm
- Kayu kelas II (papan) 0.003 M3 2,000,000.00
- Besi beton 0.020 Kg 19,500.00
- Minyak Bekesting 3.600 Kg 15,000.00
- Kawat beton 0.050 Kg 35,000.00
- Semen Portland 5.500 Kg 1,700.00
- Pasir Beton 0.009 M3 400,000.00
- Kerikil 0.015 M3 450,000.00
- Pekerja 0.297 Oh 110,000.00
- Tukang Batu 0.033 Oh 130,000.00
- Tukang Kayu 0.033 Oh 130,000.00
- Tukang Besi 0.033 Oh 130,000.00
- Kep. Tukang 0.010 Oh 155,000.00
- Mandor 0.015 Oh 175,000.00
JUMLAH :
VIII PEKERJAAN PENUTUP ATAP
VIII.1 1 M2 Pasang Atap Seng Gelombang
- Seng Gelombang BJLS 30' 0.700 Lembar 55,000.00
- Paku biasa 0.020 Kg 20,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Pekerja 0.120 Oh 110,000.00


- Tukang Kayu 0.060 Oh 130,000.00
- Kep. Tukang 0.006 Oh 155,000.00
- Mandor 0.006 Oh 175,000.00
JUMLAH :
VIII.2 1 M2 Pasang Atap Genteng Metal
- Genteng Metal 2.250 Lembar 35,000.00
- Paku Atap 0.200 Kg 20,500.00
- Pekerja 0.200 Oh 110,000.00
- Tukang Kayu 0.200 Oh 130,000.00
- Kep. Tukang 0.020 Oh 155,000.00
- Mandor 0.075 Oh 175,000.00
JUMLAH :
VIII.3 1 M1 Pasang Bubungan Genteng Metal
- Bubungan Genteng Metal 5.000 M1 45,000.00
- Kayu kelas II (papan) 0.020 M3 2,000,000.00
- Paku Atap 0.015 Kg 20,500.00
- Pekerja 0.100 Oh 110,000.00
- Tukang Kayu 0.100 Oh 130,000.00
- Kep. Tukang 0.010 Oh 155,000.00
- Mandor 0.005 Oh 175,000.00
JUMLAH :
VIII.4 1 M2 Pasang Atap Nok Seng
- Seng Plat 3' x 6 " bjls 30 0.300 M1 50,000.00
- Paku biasa 0.040 Kg 20,000.00
- Pekerja 0.150 Oh 110,000.00
- Tukang Kayu 0.070 Oh 130,000.00
- Kep. Tukang 0.008 Oh 155,000.00
- Mandor 0.006 Oh 175,000.00
JUMLAH :
IX PEKERJAAN LANGIT - LANGIT

IX.1 1 PEKERJAAN RANGKA PLAFON 60/60


Kayu kelas II (balok) 0.016 M3 2,100,000.00
Paku campur 0.250 Kg 20,000.00
Pekerja 0.200 o/h 110,000.00
Tukang Kayu 0.300 o/h 130,000.00
Kep. Tukang 0.030 o/h 155,000.00
Mandor 0.010 o/h 175,000.00
Jumlah
IX.2 1 M2 Pasang Langit-Langit Akustik Ukuran (30 x 30) cm
- Akustik 30 x 30 cm 12.000 Lembar 11,625.00
- Paku tripleks 0.050 Kg 25,000.00
- Pekerja 0.120 Oh 110,000.00
- Tukang Kayu 0.120 Oh 130,000.00
- Kep. Tukang 0.012 Oh 155,000.00
- Mandor 0.006 Oh 175,000.00
JUMLAH :

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

IX.3 1 M2 Pasang Langit-Langit Akustik Ukuran (30 x 60) cm


- Akustik 60 x 60 cm 5.800 Lembar 46,500.00
- Paku tripleks 0.050 Kg 25,000.00
- Pekerja 0.100 Oh 110,000.00
- Tukang Kayu 0.100 Oh 130,000.00
- Kep. Tukang 0.010 Oh 155,000.00
- Mandor 0.005 Oh 175,000.00
JUMLAH :
IX.4 1 M2 Pasang Langit-Langit Akustik Ukuran (60 x 120) cm
- Akustik 60 x 120 cm 1.500 Lembar 58,125.00
- Paku tripleks 0.050 Kg 25,000.00
- Pekerja 0.100 Oh 110,000.00
- Tukang Kayu 0.100 Oh 130,000.00
- Kep. Tukang 0.010 Oh 155,000.00
- Mandor 0.005 Oh 175,000.00
JUMLAH :
IX.5 1 M2 Pasang Langit-Langit Tripleks Ukuran (120 x 240) cm, tebal 4 mm
- Tripleks 4 mm Ukuran 122 x 244 cm 0.375 Lembar 75,000.00
- Paku tripleks 0.030 Kg 25,000.00
- Pekerja 0.100 Oh 110,000.00
- Tukang Kayu 0.100 Oh 130,000.00
- Kep. Tukang 0.010 Oh 155,000.00
- Mandor 0.005 Oh 175,000.00
JUMLAH :
IX.6 1 M2 Pasang Plafond Lambriziring
- Lumbersharing @4m 12.000 Lbr 25,000.00
- Paku biasa 0.100 Kg 20,000.00
- Pekerja 0.100 Oh 110,000.00
- Tukang Kayu 0.500 Oh 130,000.00
- Kep. Tukang 0.030 Oh 155,000.00
- Mandor 0.010 Oh 175,000.00
JUMLAH :
IX.7 1 M2 Pasang Langit-Langit Gypsum Board, Ukuran (1200 x 2400 x 9) mm
- Gypsum Board 9 mm 0.364 Lembar 90,000.00
- Paku sekrup 0.110 Kg 75,000.00
- Pekerja 0.100 Oh 110,000.00
- Tukang Kayu 0.050 Oh 130,000.00
- Kep. Tukang 0.005 Oh 155,000.00
- Mandor 0.005 Oh 175,000.00
JUMLAH :
IX.8 1 M2 Pasang Langit-Langit Teakwood (60 x 120) cm, tebal 4 mm
- Tripleks 4 mm Ukuran 122 x 244 cm 0.375 Lembar 75,000.00
- Paku biasa 0.030 Kg 20,000.00
- Pekerja 0.070 Oh 110,000.00
- Tukang Kayu 0.100 Oh 130,000.00
- Kep. Tukang 0.010 Oh 155,000.00
- Mandor 0.004 Oh 175,000.00
JUMLAH :

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

IX.9 1 M2 Pasang Langit-Langit Lat Kayu Kelas I


- Kayu Kelas I (papan) 0.024 M3 3,750,000.00
- Paku biasa 0.010 Kg 20,000.00
- Paku sekrup 0.050 Kg 75,000.00
- Pekerja 0.200 Oh 110,000.00
- Tukang Kayu 0.600 Oh 130,000.00
- Kep. Tukang 0.060 Oh 155,000.00
- Mandor 0.010 Oh 175,000.00
JUMLAH :
IX.10 1 M2 Pasang Langit-Langit Lat Kayu Kelas II
- Kayu Kelas II (papan) 0.024 M3 2,000,000.00
- Paku biasa 0.010 Kg 20,000.00
- Paku sekrup 0.050 Kg 75,000.00
- Pekerja 0.200 Oh 110,000.00
- Tukang Kayu 0.600 Oh 130,000.00
- Kep. Tukang 0.060 Oh 155,000.00
- Mandor 0.010 Oh 175,000.00
JUMLAH :
IX.11 1 M' Pasang List Langit-Langit Kayu Profil
- kayu profil 1.050 M' 15,000.00
- Paku biasa 0.010 Kg 20,000.00
- Pekerja 0.050 Oh 110,000.00
- Tukang Kayu 0.050 Oh 130,000.00
- Kep. Tukang 0.005 Oh 155,000.00
- Mandor 0.003 Oh 175,000.00
JUMLAH :
IX.12 1 MPEKERJAAN RANGKA PLAFOND 1,00X1,00 M2, HOLLOW 40X40X1,2 MM
Hollow 40x40x3,2 mm 2.936 Kg 23,500.00
assessories 1.000 set 1,000.00
Pekerja 0.090 o/h 110,000.00
Tukang Kayu 0.015 o/h 130,000.00
Kep. Tukang 0.009 o/h 155,000.00
Mandor 0.000 o/h 175,000.00
JUMLAH :
IX.13 1 PEKERJAAN PLAFON GYPSUM
Hollow Plafon - Btg 25,000.00
Penggantung - Ls 10,000.00
Gypsum Board 9 mm 0.364 Lbr 90,000.00
Paku sekrup 0.070 Doz 75,000.00
Pekerja 0.330 o/h 110,000.00
Tukang 0.419 o/h 130,000.00
Kep. Tukang 0.047 o/h 155,000.00
Mandor 0.016 o/h 175,000.00
Jumlah
X PEKERJAAN SANITASI
X.1 Memasang 1 Buah Kloset Duduk/Monoblok
- Kloset duduk / monoblok 1.000 Buah 1,850,000.00
- Perlengkapan ( 6 % Harga Kloset ) 1.000 Ls 111,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Pekerja 3.300 Oh 110,000.00


- Tukang batu 1.100 Oh 130,000.00
- Kep. Tukang 0.001 Oh 155,000.00
- Mandor 0.160 Oh 175,000.00
JUMLAH :
X.2 Memasang 1 Buah Kloset Jongkok Porselen
- Kloset jongkok porselen 1.000 Buah 250,000.00
- Semen Portland 6.000 Kg 1,700.00
- Pasir Pasang 0.010 M3 400,000.00
- Pekerja 1.000 Oh 110,000.00
- Tukang batu 1.500 Oh 130,000.00
- Kep. Tukang 1.500 Oh 155,000.00
- Mandor 0.160 Oh 175,000.00
JUMLAH :
X.3 Memasang 1 Buah Wastafel
- Wastafel lengkap TOTO 1.000 Buah 850,000.00
- Perlengkapan ( 12 % Harga ) 1.000 Ls 102,000.00
- Semen Warna 6.000 Kg 5,000.00
- Pasir Pasang 0.010 M3 400,000.00
- Pekerja 1.200 Oh 110,000.00
- Tukang batu 1.450 Oh 130,000.00
- Kep. Tukang 0.150 Oh 155,000.00
- Mandor 0.100 Oh 175,000.00
JUMLAH :
X.4 Memasang 1 Buah Bak Mandi Batu Batako Volume 0,30 M3
- Batu batako 10 x 18 x 24 cm 21.000 Bh 2,000.00
- Semen portland 120.000 Kg 1,700.00
- Pasir pasang 0.300 M3 400,000.00
- Tegel Porselin 11 x 11 cm 360.000 Buah 548.00
Semen Warna 6.000 Kg 5,000.00
- Pekerja 6.000 Oh 110,000.00
- Tukang batu 3.000 Oh 130,000.00
- Kep. Tukang 0.300 Oh 155,000.00
- Mandor 0.300 Oh 175,000.00
JUMLAH :
X.5 1 M' Pasang Pipa Tanah Penyalur Air Limbah Diameter 15 cm
- Pipa tanah 1.600 Buah -
- Semen portland 0.680 Kg 1,700.00
- Pasir pasang 0.013 M3 400,000.00
- Pasir urug 0.011 M3 220,000.00
- Pekerja 0.060 Oh 110,000.00
- Tukang batu 0.030 Oh 130,000.00
- Kep. Tukang 0.003 Oh 155,000.00
- Mandor 0.003 Oh 175,000.00
JUMLAH :
X.6 1 M' Pasang Pipa Galvanis Diameter 1/2"
- Pipa GIV Dia 1/2" - 4 m 1.200 Buah #N/A
- Perlengkapan 0.350 Hp #N/A

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Pekerja 0.054 Oh 110,000.00


- Tukang batu 0.090 Oh 130,000.00
- Kep. Tukang 0.009 Oh 155,000.00
- Mandor 0.027 Oh 175,000.00
JUMLAH :
X.7 1 M' Pasang Pipa Galvanis Diameter 3/4"
- Pipa GIV Dia 3/4" - 4 m 1.200 Buah #N/A
- Perlengkapan 0.350 Hp #N/A
- Pekerja 0.054 Oh 110,000.00
- Tukang batu 0.090 Oh 130,000.00
- Kep. Tukang 0.009 Oh 155,000.00
- Mandor 0.027 Oh 175,000.00
JUMLAH :
X.8 1 M' Pasang Pipa Galvanis Diameter 1"
- Pipa GIV dia 1" - 6m 1.200 Buah #N/A
- Perlengkapan 0.350 Hp #N/A
- Pekerja 0.054 Oh 110,000.00
- Tukang batu 0.090 Oh 130,000.00
- Kep. Tukang 0.009 Oh 155,000.00
- Mandor 0.027 Oh 175,000.00
JUMLAH :
X.9 1 M' Pasang Pipa Galvanis Diameter 2"
- Pipa GIV Dia 2" - 6 m 1.200 Buah #N/A
- Perlengkapan 0.350 Hp #N/A
- Pekerja 0.108 Oh 110,000.00
- Tukang batu 0.180 Oh 130,000.00
- Kep. Tukang 0.018 Oh 155,000.00
- Mandor 0.005 Oh 175,000.00
JUMLAH :
X.10 1 M' Pasang Pipa Galvanis Diameter 3"
- Pipa GIV dia 3" - 6m 1.200 Buah #N/A
- Perlengkapan 0.350 Hp #N/A
- Pekerja 0.108 Oh 110,000.00
- Tukang batu 0.180 Oh 130,000.00
- Kep. Tukang 0.018 Oh 155,000.00
- Mandor 0.005 Oh 175,000.00
JUMLAH :
X.11 Memasang 1 Buah Bak Kontrol Pasangan Batu Bata ukuran ( 30 x 30 ) cm Tinggi 35 cm
- Batu Tela (m3) 0.145 M3 659,722.22
- Semen portland 44.000 Kg 1,700.00
- Pasir pasang 0.070 M3 400,000.00
- kerikil 0.070 M3 450,000.00
- Besi beton 1.600 Kg 19,500.00
- Pasir beton 0.060 M3 400,000.00
- Pekerja 3.200 Oh 110,000.00
- Tukang batu 1.015 Oh 130,000.00
- Kep. Tukang 0.002 Oh 155,000.00
- Mandor 0.016 Oh 175,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

JUMLAH :
X.12 Memasang 1 Buah Bak Kontrol Pasangan Batu Bata ukuran ( 45 x 45 ) cm Tinggi 50 cm
- Batu Tela (m3) 0.250 M3 659,722.22
- Semen portland 77.000 Kg 1,700.00
- Pasir pasang 0.130 M3 400,000.00
- Kerikil 0.020 M3 450,000.00
- Besi beton 2.600 Kg 19,500.00
- Pasir beton 0.090 M3 400,000.00
- Pekerja 3.200 Oh 110,000.00
- Tukang batu 1.015 Oh 130,000.00
- Kep. Tukang 0.002 Oh 155,000.00
- Mandor 0.016 Oh 175,000.00
JUMLAH :
X.13 Memasang 1 Buah Bak Kontrol Pasangan Batu Bata ukuran ( 60 x 60 ) cm Tinggi 65 cm
- Batu Tela (m3) 0.371 Buah 659,722.22
- Semen portland 114.000 Kg 1,700.00
- Pasir pasang 0.184 M3 400,000.00
- Kerikil 0.033 M3 450,000.00
- Besi beton 4.850 Kg 19,500.00
- Pasir beton 0.120 M3 400,000.00
- Pekerja 3.200 Oh 110,000.00
- Tukang batu 1.015 Oh 130,000.00
- Kep. Tukang 0.002 Oh 155,000.00
- Mandor 0.016 Oh 175,000.00
- Tukang gali 0.100 Oh 110,000.00
JUMLAH :
X.14 Memasang 1 Buah Cuci Piring Stainles Steel
- Bak cuci stainless steel 1.000 Bh 450,000.00
- Water drain + asesories 1.000 Set 50,000.00
- Pekerja 0.030 Oh 110,000.00
- Tukang Batu 0.300 Oh 130,000.00
- Kep. Tukang 0.030 Oh 155,000.00
- Mandor 0.002 Oh 175,000.00
JUMLAH :
X.15 Memasang 1 Buah Kran Diameter 3/4" atau 1/2"
- Kran Air Stainless 1.000 Buah 35,000.00
- Seal tape 0.025 Buah 5,000.00
- Pekerja 0.010 Oh 110,000.00
- Tukang Batu 0.100 Oh 130,000.00
- Kep. Tukang 0.010 Oh 155,000.00
- Mandor 0.005 Oh 175,000.00
JUMLAH :
X.16 Memasang 1 Buah Floor Drain
- Floor drain 1.000 Buah 55,000.00
- Pekerja 0.010 Oh 110,000.00
- Tukang Batu 0.100 Oh 130,000.00
- Kep. Tukang 0.010 Oh 155,000.00
- Mandor 0.005 Oh 175,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

JUMLAH :
X.17 1 UPEKERJAAN SEPTICTANK & REMBESAN
Galian tanah 21.365 M3 127,225.00
Urugan tanah kembali 6.410 M3 24,445.00
Urugan Pasir 0.380 M3 298,750.00
Pasangan Pondasi Batu Kali 1 : 4 1.219 M3 1,492,350.00
Pasangan Tembok 1 pc : 4 psr 2.224 M3 238,185.00
Cor rabat 1 pc : 3 psr : 5 krl 0.218 M3 1,269,550.71
Sloof, Kolom, Ringbalk 0.550 M3 7,082,340.00
Beton Plat Penutup 0.420 M3 10,462,867.02
Plesteran 1 pc : 2 psr 25.000 M2 82,830.80
Urugan Kerikil 0.448 M3 295,875.00
Pekerjaan Ijuk 0.522 M3 1,250,000.00
Pipa PVC Ø 4 " 4.000 M' 73,832.50
Pipa Udara Gip. Ø 2 " 1.000 m 155,265.00
JUMLAH :
X.18 1 MPEKERJAAN SALURAN KELILING BANGUNAN
Cor Rabat 1 Pc : 3 Psr : 5 Krl 0.1000 m3 1,269,550.71
Plesteran 1 Pc : 3 Psr 2.2000 m2 82,830.80
Acian 2.2000 m2 43,825.00
Jumlah
X.19 1 MPEKERJAAN PIPA GIP Ø ½ "
Pipa Gip Ø ½ " 1.200 M' 25,000.00
Perlengkapan (35 % Harga Pipa) 1.000 Ls 8,750.00
Pekerja 0.054 o/h 110,000.00
Tukang 0.090 o/h 130,000.00
Kep. Tukang 0.009 o/h 155,000.00
Mandor 0.027 o/h 175,000.00
JUMLAH :
X.20 1 MPEKERJAAN PIPA GIP Ø ¾ "
Pipa Gip Ø ¾ " 1.200 M' 29,166.67
Perlengkapan (35 % Harga Pipa) 1.000 Ls 10,208.33
Pekerja 0.054 o/h 110,000.00
Tukang 0.090 o/h 130,000.00
Kep. Tukang 0.009 o/h 155,000.00
Mandor 0.027 o/h 175,000.00
JUMLAH :
X.21 1 MPEKERJAAN PIPA GIP Ø 1 "
Pipa Gip Ø 1 " 1.200 M' 37,500.00
Perlengkapan (35 % Harga Pipa) 1.000 Ls 13,125.00
Pekerja 0.054 o/h 110,000.00
Tukang 0.090 o/h 130,000.00
Kep. Tukang 0.009 o/h 155,000.00
Mandor 0.027 o/h 175,000.00
JUMLAH :
X.22 1 MPEKERJAAN PIPA GIP Ø 1 ¼ "
Pipa Gip Ø 1 ¼ " 1.200 M' 41,666.67
Perlengkapan (35 % Harga Pipa) 1.000 Ls 14,583.33

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

Pekerja 0.108 o/h 110,000.00


Tukang 0.180 o/h 130,000.00
Kep. Tukang 0.018 o/h 155,000.00
Mandor 0.005 o/h 175,000.00
JUMLAH :
X.23 1 MPEKERJAAN PIPA GIP Ø 1 ½ "
Pipa Gip Ø 1 ½ " 1.200 M' 45,833.33
Perlengkapan (35 % Harga Pipa) 1.000 Ls 16,041.67
Pekerja 0.108 o/h 110,000.00
Tukang 0.180 o/h 130,000.00
Kep. Tukang 0.018 o/h 155,000.00
Mandor 0.005 o/h 175,000.00
JUMLAH :
X.24 1 MPEKERJAAN PIPA GIP Ø 2 "
Pipa Gip Ø 2 " 1.200 M' 75,000.00
Perlengkapan (35 % Harga Pipa) 1.000 Ls 26,250.00
Pekerja 0.108 o/h 110,000.00
Tukang 0.180 o/h 130,000.00
Kep. Tukang 0.018 o/h 155,000.00
Mandor 0.005 o/h 175,000.00
JUMLAH :
X.25 1 MPEKERJAAN PIPA GIP Ø 3 "
Pipa Gip Ø 3 " 1.200 M' 158,333.33
Perlengkapan (35 % Harga Pipa) 1.000 Ls 55,416.67
Pekerja 0.108 o/h 110,000.00
Tukang 0.180 o/h 130,000.00
Kep. Tukang 0.018 o/h 155,000.00
Mandor 0.005 o/h 175,000.00
JUMLAH :
X.26 1 MPEKERJAAN PIPA GIP Ø 4 "
Pipa Gip Ø 4 " 1.200 M' 200,000.00
Perlengkapan (35 % Harga Pipa) 1.000 Ls 70,000.00
Pekerja 0.135 o/h 110,000.00
Tukang 0.225 o/h 130,000.00
Kep. Tukang 0.023 o/h 155,000.00
Mandor 0.007 o/h 175,000.00
JUMLAH :
X.27 1 MPEKERJAAN PIPA PVC Ø 6 "
Pipa PVC Ø 6 " 1.200 M' 72,500.00
Perlengkapan (35 % Harga Pipa) 1.000 Ls 25,375.00
Pekerja 0.081 o/h 110,000.00
Tukang 0.135 o/h 130,000.00
Kep. Tukang 0.014 o/h 155,000.00
Mandor 0.004 o/h 175,000.00
JUMLAH :
X.28 1 MPEKERJAAN PIPA PVC Ø 4 "
Pipa PVC Ø 4 " 1.200 M' 28,750.00
Perlengkapan (35 % Harga Pipa) 1.000 Ls 10,062.50

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

Pekerja 0.081 o/h 110,000.00


Tukang 0.135 o/h 130,000.00
Kep. Tukang 0.014 o/h 155,000.00
Mandor 0.004 o/h 175,000.00
JUMLAH :
X.29 1 MPEKERJAAN PIPA PVC Ø 3 "
Pipa PVC Ø 3 " 1.200 M' 20,000.00
Perlengkapan (35 % Harga Pipa) 1.000 Ls 7,000.00
Pekerja 0.081 o/h 110,000.00
Tukang 0.135 o/h 130,000.00
Kep. Tukang 0.014 o/h 155,000.00
Mandor 0.004 o/h 175,000.00
JUMLAH :
X.30 1 MPEKERJAAN PIPA PVC Ø 2 "
Pipa PVC Ø 2 " 1.200 M' 12,500.00
Perlengkapan (35 % Harga Pipa) 1.000 Ls 4,375.00
Pekerja 0.054 o/h 110,000.00
Tukang 0.090 o/h 130,000.00
Kep. Tukang 0.009 o/h 155,000.00
Mandor 0.003 o/h 175,000.00
JUMLAH :
X.31 1 MPEKERJAAN PIPA PVC Ø 1 ½ "
Pipa PVC Ø 1 ½ " 1.200 M' 8,000.00
Perlengkapan (35 % Harga Pipa) 1.000 Ls 2,800.00
Pekerja 0.036 o/h 110,000.00
Tukang 0.066 o/h 130,000.00
Kep. Tukang 0.006 o/h 155,000.00
Mandor 0.002 o/h 175,000.00
JUMLAH :
X.32 1 MPEKERJAAN PIPA PVC Ø 1 "
Pipa PVC Ø 1 " 1.200 M' 6,750.00
Perlengkapan (35 % Harga Pipa) 1.000 Ls 2,362.50
Pekerja 0.036 o/h 110,000.00
Tukang 0.060 o/h 130,000.00
Kep. Tukang 0.006 o/h 155,000.00
Mandor 0.002 o/h 175,000.00
JUMLAH :
XI PEKERJAAN BESI
XI.1 1 M2 Pasang Jendela Nako 7 klip & Tralis
- Jendela Nako 1.100 M2 175,000.00
- Paku Biasa 0.020 Kg 20,000.00
- Besi strip tebal 5 mm 4.000 M2 25,000.00
- Pekerja 0.200 Oh 110,000.00
- Tukang Kayu 0.200 Oh 130,000.00
- Kep. Tukang 0.020 Oh 155,000.00
- Mandor 0.001 Oh 175,000.00
JUMLAH :
XI.2 1 M' Pasang Talang Datar, Seng BJLS 30"

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Seng Plat 3' x 6 " bjls 30 0.500 Lembar 50,000.00


- Paku Biasa 0.015 Kg 20,000.00
- Kayu Kelas II (Papan) 0.010 M3 2,000,000.00
- Meni 0.250 Kg 20,000.00
- Pekerja 0.150 Oh 110,000.00
- Tukang Kayu 0.400 Oh 130,000.00
- Kep. Tukang 0.025 Oh 155,000.00
- Mandor 0.001 Oh 175,000.00
JUMLAH :
XI.3 1 M' Pasang Talang Miring, Seng BJLS 30"
- Seng Plat 3' x 6 " bjls 30 0.500 Lembar 50,000.00
- Paku Biasa 0.015 Kg 20,000.00
- Kayu Kelas II (Papan) 0.019 M3 2,000,000.00
- Meni 0.300 Kg 20,000.00
- Pekerja 0.040 Oh 110,000.00
- Tukang Kayu 0.400 Oh 130,000.00
- Kep. Tukang 0.025 Oh 155,000.00
- Mandor 0.001 Oh 175,000.00
JUMLAH :
XI.4 1 M' Pasang Talang 1/2 Lingkaran D - 10 cm, Seng BJLS 30"
- Seng Plat 3' x 6 " bjls 30 0.300 Lembar 50,000.00
- Paku Biasa 0.100 Kg 20,000.00
- Kayu Kelas II (Papan) 0.019 M3 2,000,000.00
- Besi strip tebal 5 mm 0.500 Kg 25,000.00
- Pekerja 0.150 Oh 110,000.00
- Tukang Kayu 0.250 Oh 130,000.00
- Kep. Tukang 0.025 Oh 155,000.00
- Mandor 0.001 Oh 175,000.00
JUMLAH :
XII PEKERJAAN KUNCI DAN KACA
XII.1 1 Buah Pasang Kunci Tanam Antik
- Kunci Tanam 2 Slaag SES/Kend 1.000 Buah 150,000.00
- Pekerja 0.060 Oh 110,000.00
- Tukang Kayu 0.600 Oh 130,000.00
- Kep. Tukang 0.060 Oh 155,000.00
- Mandor 0.003 Oh 175,000.00
JUMLAH :
XII.2 1 Buah Pasang Kunci Tanam Biasa
- Kunci tanam 1.000 Buah 150,000.00
- Pekerja 0.010 Oh 110,000.00
- Tukang Kayu 0.500 Oh 130,000.00
- Kep. Tukang 0.010 Oh 155,000.00
- Mandor 0.005 Oh 175,000.00
JUMLAH :
XII.3 1 Ps Pasang Engsel Pintu
- Engsel Pintu 0.500 Psg 45,000.00
- Pekerja 0.015 Oh 110,000.00
- Tukang Kayu 0.150 Oh 130,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Kep. Tukang 0.015 Oh 155,000.00


- Mandor 0.001 Oh 175,000.00
JUMLAH :
XII.4 1 Buah Pasang Engsel Jendela Kupu-Kupu
- Engsel jendela 1.000 Psg 25,000.00
- Pekerja 0.010 Oh 110,000.00
- Tukang Kayu 0.100 Oh 130,000.00
- Kep. Tukang 0.010 Oh 155,000.00
- Mandor 0.001 Oh 175,000.00
JUMLAH :
XII.5 1 Buah Pasang Kait Angin
- Hak Angin Biasa 1.000 Psg 8,000.00
- Pekerja 0.015 Oh 110,000.00
- Tukang Kayu 0.150 Oh 130,000.00
- Kep. Tukang 0.015 Oh 155,000.00
- Mandor 0.001 Oh 175,000.00
JUMLAH :
XII.6 1 Buah Pasang Pegangan Pintu/Door Holder
- Door holder 1.000 Buah 55,000.00
- Pekerja 0.050 Oh 110,000.00
- Tukang Kayu 0.500 Oh 130,000.00
- Kep. Tukang 0.050 Oh 155,000.00
- Mandor 0.003 Oh 175,000.00
JUMLAH :
XII.7 1 Buah Pasang Kunci Lemari
- Kunci lemari 1.000 Buah 35,000.00
- Pekerja 0.025 Oh 110,000.00
- Tukang Kayu 0.250 Oh 130,000.00
- Kep. Tukang 0.025 Oh 155,000.00
- Mandor 0.001 Oh 175,000.00
JUMLAH :
XII.8 1 M2 Pasang Kaca, Tebal 3 mm
- Kaca Bening 3 mm 1.100 M2 100,000.00
- Pekerja 0.015 Oh 110,000.00
- Tukang Kayu 0.150 Oh 130,000.00
- Kep. Tukang 0.015 Oh 155,000.00
- Mandor 0.001 Oh 175,000.00
JUMLAH :
XII.9 1 M2 Pasang Kaca, Tebal 5 mm
- Kaca Bening 5 mm 1.000 M2 200,000.00
- Pekerja 0.015 Oh 110,000.00
- Tukang Kayu 0.150 Oh 130,000.00
- Kep. Tukang 0.015 Oh 155,000.00
- Mandor 0.001 Oh 175,000.00
JUMLAH :
XII.10 1 M2 Pasang Kaca, Tebal 8 mm
- Kaca Bening 8 mm 1.000 M2 225,000.00
- Pekerja 0.017 Oh 110,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Tukang Kayu 0.165 Oh 130,000.00


- Kep. Tukang 0.017 Oh 155,000.00
- Mandor 0.001 Oh 175,000.00
JUMLAH :
XIII PEKERJAAN PENUTUP LANTAI DAN DINDING (SNI 7395-2008-lantai)
XIII.2 Memasang 1 m2 lantai keramik ukuran (60x60) cm
- Tegel keramik 60x60 3.100 Buah 73,333.33
- Semen portland 9.600 Kg 1,700.00
- Pasir pasang 0.045 M3 400,000.00
- Semen Warna 1.500 Kg 5,000.00
- Pekerja 0.250 Oh 110,000.00
- Tukang batu 0.125 Oh 130,000.00
- Kep. Tukang 0.013 Oh 155,000.00
- Mandor 0.013 Oh 175,000.00
JUMLAH :
XIII.2 Memasang 1 m2 lantai ubin PC abu-abu ukuran (40 x 40) cm
- Ubin abu-abu 40 x 40 cm 6.630 Buah #N/A
- Semen portland 9.800 Kg 1,700.00
- Pasir pasang 0.045 M3 400,000.00
- Semen Warna Kg 5,000.00
- Pekerja 0.250 Oh 110,000.00
- Tukang batu 0.125 Oh 130,000.00
- Kep. Tukang 0.013 Oh 155,000.00
- Mandor 0.013 Oh 175,000.00
JUMLAH :
XIII.2 1 M2 Pasang Lantai Ubin Teraso Ukuran (30 x 30) cm
- Tegel Teraso 30 x 30 cm 11.870 Buah 6,000.00
- Semen portland 10.000 Kg 1,700.00
- Pasir pasang 0.045 M3 400,000.00
- Semen Warna 1.500 Kg 5,000.00
- Pekerja 0.260 Oh 110,000.00
- Tukang batu 0.130 Oh 130,000.00
- Kep. Tukang 0.013 Oh 155,000.00
- Mandor 0.013 Oh 175,000.00
JUMLAH :
XIII.4 1 M2 Pasang Lantai Keramik Ukuran (30 x 30 ) cm
- Tegel Keramik 30 x 30 cm 11.870 Buah 6,500.00
- Semen portland 10.000 Kg 1,700.00
- Pasir pasang 0.045 M3 400,000.00
- Semen Warna 1.500 Kg 5,000.00
- Pekerja 0.700 Oh 110,000.00
- Tukang batu 0.350 Oh 130,000.00
- Kep. Tukang 0.035 Oh 155,000.00
- Mandor 0.035 Oh 175,000.00
JUMLAH :
XIII.5 1 M2 Pasang Lantai Keramik Ukuran (20 x 20 ) cm
- Tegel Keramik 20 x 20 cm 26.500 Buah 2,000.00
- Semen portland 10.400 Kg 1,700.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Pasir pasang 0.045 M3 400,000.00


- Semen Warna 1.620 Kg 5,000.00
- Pekerja 0.700 Oh 110,000.00
- Tukang batu 0.350 Oh 130,000.00
- Kep. Tukang 0.035 Oh 155,000.00
- Mandor 0.035 Oh 175,000.00
JUMLAH :
XIII.6 1 M2 Pasang Lantai Keramik Ukuran (10 x 20 ) cm, Variasi/Border
- Tegel Keramik 10 x 20 cm 33.000 Buah 1,000.00
- Semen portland 9.800 Kg 1,700.00
- Pasir pasang 0.045 M3 400,000.00
- Semen Warna 4.370 Kg 5,000.00
- Pekerja 1.050 Oh 110,000.00
- Tukang batu 0.525 Oh 130,000.00
- Kep. Tukang 0.053 Oh 155,000.00
- Mandor 0.053 Oh 175,000.00
JUMLAH :
XIII.7 1 M2 Pasang Lantai Mosaik Ukuran (30 x 30 ) cm, Campuran Spesi 1 pc : 3 PP
- Tegel Mozaik 30 x 30 cm 11.870 Buah 6,000.00
- Semen portland 14.150 Kg 1,700.00
- Pasir pasang 0.039 M3 400,000.00
- Semen Warna 2.000 Kg 5,000.00
- Pekerja 0.700 Oh 110,000.00
- Tukang batu 0.350 Oh 130,000.00
- Kep. Tukang 0.035 Oh 155,000.00
- Mandor 0.035 Oh 175,000.00
JUMLAH :
XIII.11 1 M2 Pasang Dinding Porselen Ukuran (11 x 11) cm
- Tegel Porselin 11 x 11 cm 86.000 Buah 548.00
- Semen portland 9.300 Kg 1,700.00
- Pasir pasang 0.018 M3 400,000.00
- Semen Warna 1.500 Kg 5,000.00
- Pekerja 1.000 Oh 110,000.00
- Tukang batu 0.500 Oh 130,000.00
- Kep. Tukang 0.050 Oh 155,000.00
- Mandor 0.050 Oh 175,000.00
JUMLAH :
XIII.12 1 M2 Pasang Dinding Keramik Ukuran (10 x 20) cm
- Tegel Keramik 10 x 20 cm 53.000 Buah 1,000.00
- Semen portland 9.300 Kg 1,700.00
- Pasir pasang 0.018 M3 400,000.00
- Semen Warna 2.750 Kg 5,000.00
- Pekerja 0.900 Oh 110,000.00
- Tukang batu 0.450 Oh 130,000.00
- Kep. Tukang 0.045 Oh 155,000.00
- Mandor 0.045 Oh 175,000.00
JUMLAH :
XIII.13 1 M2 Pasang Dinding Keramik Ukuran (20 x 20) cm

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Tegel Keramik 20 x 20 cm 26.500 Buah 2,000.00


- Semen portland 9.300 Kg 1,700.00
- Pasir pasang 0.018 M3 400,000.00
- Semen Warna 1.940 Kg 5,000.00
- Pekerja 0.900 Oh 110,000.00
- Tukang batu 0.450 Oh 130,000.00
- Kep. Tukang 0.045 Oh 155,000.00
- Mandor 0.045 Oh 175,000.00
JUMLAH :
XIII.13 1 M2 Pasang Dinding Keramik Ukuran (20 x 25) cm
- Tegel Keramik 20 x 25 cm 20.000 Buah 4,000.00
- Semen portland 10.400 Kg 1,700.00
- Pasir pasang 0.045 M3 400,000.00
- Semen Warna 1.620 Kg 5,000.00
- Pekerja 0.700 Oh 110,000.00
- Tukang batu 0.350 Oh 130,000.00
- Kep. Tukang 0.035 Oh 155,000.00
- Mandor 0.035 Oh 175,000.00
JUMLAH :
XIII.14 1 M2 Pasang Lantai Keramik Ukuran (10 x 20) cm
- Tegel Keramik 10 x 20 cm 50.000 Buah 1,000.00
- Semen portland 11.380 Kg 1,700.00
- Pasir pasang 0.042 M3 400,000.00
- Semen Warna 1.500 Kg 5,000.00
- Pekerja 0.620 Oh 110,000.00
- Tukang batu 0.350 Oh 130,000.00
- Kep. Tukang 0.035 Oh 155,000.00
- Mandor 0.030 Oh 175,000.00
JUMLAH :
XIII.15 1 M' Pasang Plint Kayu Kelas II Tebal 2 cm, Lebar 10 cm
- Kayu kelas II (papan) 0.003 M3 2,000,000.00
- Paku biasa 0.050 Kg 20,000.00
- Pekerja 0.120 Oh 110,000.00
- Tukang kayu 0.120 Oh 130,000.00
- Kep. Tukang 0.012 Oh 155,000.00
- Mandor 0.006 Oh 175,000.00
JUMLAH :
XIV PEKERJAAN PENGECATAN
1 1 M2 CAT DASAR
Meni 0.030 Ltr 20,000.00
Kuas biasa 0.010 Bh 10,000.00
Pekerja 0.020 o/h 110,000.00
Tukang cat 0.200 o/h 130,000.00
Kep. Tukang 0.020 o/h 155,000.00
Mandor 0.010 o/h 175,000.00
JUMLAH :
XIV.1 1 M2 Mengikis Bidang Permukaan Cat Tembok Lama
- Soda Api 0.050 Kg 20,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Pekerja 0.150 Oh 110,000.00


- Tukang Cat - Oh 130,000.00
- Kep. Tukang - Oh 155,000.00
- Mandor 0.0025 Oh 175,000.00
JUMLAH :
XIV.2 1 M2 Mencuci Bidang Permukaan Cat Tembok Lama
- Sabun 0.050 Kg 1,800.00
- Pekerja 0.150 Oh 110,000.00
- Tukang Cat - Oh 130,000.00
- Kep. Tukang - Oh 155,000.00
- Mandor 0.0025 Oh 175,000.00
JUMLAH :
XIV.3 1 M2 Mendempul dan Menggosok Kayu
- Dempul 0.080 Kg 15,000.00
- Minyak Cat 0.020 Kg 25,000.00
- Batu Apung 0.010 Kg 25,000.00
- Pekerja 0.040 Oh 110,000.00
- Tukang Cat 0.040 Oh 130,000.00
- Kep. Tukang 0.004 Oh 155,000.00
- Mandor 0.0025 Oh 175,000.00
JUMLAH :
XIV.4 1 M2 Pengecatan Bidang Kayu Lama
- Plamur Kayu 0.150 Kg 38,000.00
- Cat Dasar 0.170 Kg 20,000.00
- Cat Kilat Kayu 0.170 Kg 45,000.00
- Pekerja 0.070 Oh 110,000.00
- Tukang Cat 0.075 Oh 130,000.00
- Kep. Tukang 0.0075 Oh 155,000.00
- Mandor 0.0025 Oh 175,000.00
JUMLAH :
XIV.5 1 M2 Pengecatan Bidang Kayu Baru ( 1 Lapisan Plamir ), 1 Lapis Cat Dasar, 2 Lapis Cat Penutup
- Meni Kayu 0.200 Kg 20,000.00
- Plamur Kayu 0.150 Kg 38,000.00
- Cat Dasar 0.170 Kg 20,000.00
- Cat Kilat Kayu 0.260 Kg 45,000.00
- Pekerja 0.070 Oh 110,000.00
- Tukang Cat 0.009 Oh 130,000.00
- Kep. Tukang 0.006 Oh 155,000.00
- Mandor 0.0025 Oh 175,000.00
JUMLAH :
XIV.6 1 M2 Pengecatan Bidang Kayu Baru ( 1 Lapisan Plamir ), 1 Lapis Cat Dasar, 3 Lapis Cat Penutup
- Meni Kayu 0.200 Kg 20,000.00
- Plamur Kayu 0.150 Kg 38,000.00
- Cat Dasar 0.170 Kg 20,000.00
- Cat Kilat Kayu 0.350 Kg 45,000.00
- Pekerja 0.070 Oh 110,000.00
- Tukang Cat 0.105 Oh 130,000.00
- Kep. Tukang 0.004 Oh 155,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Mandor 0.0025 Oh 175,000.00


JUMLAH :
XIV.7 1 M2 Pelaburan Bidang Kayu Dengan Teak Oil
- Cat Teak oil 0.360 Liter 30,000.00
- Pekerja 0.040 Oh 110,000.00
- Tukang Cat 0.063 Oh 130,000.00
- Kep. Tukang 0.063 Oh 155,000.00
- Mandor 0.0025 Oh 175,000.00
JUMLAH :
XIV.8 1 M2 Pelaburan Bidang Kayu Dengan Politur
- Politur Dasar 0.150 Liter 25,000.00
- Cat Vernis/Politur 0.372 Liter 45,000.00
- Ampelas 2.000 Lembar 3,000.00
- Pekerja - Oh 110,000.00
- Tukang Cat 0.060 Oh 130,000.00
- Kep. Tukang 0.016 Oh 155,000.00
- Mandor 0.0025 Oh 175,000.00
JUMLAH :
XIV.9 1 M2 Pelaburan Bidang Kayu Dengan Cat Residu dan Ter
- Cat Residu 0.350 Liter 25,000.00
- Pekerja 0.100 Oh 110,000.00
- Tukang Cat - Oh 130,000.00
- Kep. Tukang - Oh 155,000.00
- Mandor 0.006 Oh 175,000.00
JUMLAH :
XIV.10 1 M2 Pelaburan Bidang Kayu Dengan Vernis
- Cat Vernis/Politur 0.150 Liter 45,000.00
- Dempul 0.050 Kg 15,000.00
- Ampelas 0.100 Lembar 3,000.00
- Kuas Biasa 0.010 Buah 10,000.00
- Pekerja 0.160 Oh 110,000.00
- Tukang Cat 0.160 Oh 130,000.00
- Kep. Tukang 0.016 Oh 155,000.00
- Mandor 0.0025 Oh 175,000.00
JUMLAH :
XIV.11 1 M2 Pengecatan Tembok Baru ( 1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup )
- Plamur Tembok 0.100 Kg 28,000.00
- Cat Dasar Tembok 0.100 Kg 25,000.00
- Cat Tembok 0.260 Kg 50,000.00
- Pekerja 0.020 Oh 110,000.00
- Tukang Cat 0.063 Oh 130,000.00
- Kep. Tukang 0.0063 Oh 155,000.00
- Mandor 0.0025 Oh 175,000.00
JUMLAH :
XIV.12 1 M2 Pengecatan Tembok Lama ( 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
- Cat Dasar Tembok 0.120 Kg 25,000.00
- Cat Tembok 0.180 Kg 50,000.00
- Pekerja 0.028 Oh 110,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


HARGA SATUAN
NO. HARGA SATUAN PEKERJAAN KOEFISIEN SATUAN
(Rp)

- Tukang Cat 0.042 Oh 130,000.00


- Kep. Tukang 0.0042 Oh 155,000.00
- Mandor 0.0025 Oh 175,000.00
JUMLAH :
XIV.13 1 M2 Pengecatan Permukaan Baja dengan Meni Besi
- Meni 0.100 Kg 20,000.00
- Kuas Biasa 0.010 Buah 10,000.00
- Pekerja 0.020 Oh 110,000.00
- Tukang Cat 0.200 Oh 130,000.00
- Kep. Tukang 0.020 Oh 155,000.00
- Mandor 0.010 Oh 175,000.00
JUMLAH :
XIV.15 1 M2 Duco Melamine Clear Dof
- Melamine IMPRA 0.250 Liter 45,000.00
- Minyak Cat 0.250 Liter 25,000.00
- Ampelas 0.500 Lembar 3,000.00
- Pekerja 0.010 Oh 110,000.00
- Tukang Cat 0.100 Oh 130,000.00
- Kep. Tukang 0.025 Oh 155,000.00
- Mandor 0.005 Oh 175,000.00
- Alat bantu 1.0000 Unit 5,000.00
JUMLAH :

Informasi Harga Satuan Pekerjaan Tahun 2012


R ANALISA PEKERJAAN

JUMLAH HARGA (Rp)

1,902,083.33
880,000.00
350,000.00
177,083.33
220,000.00
275,000.00
1,902,083.33
19,020.83
279,950.00
31,250.00
4,250.00
2,000.00
4,050.00
151,200.00
1,600.00
9,000.00
44,000.00
26,000.00
3,100.00
3,500.00
279,950.00
342,200.00
31,250.00
4,250.00
60,000.00
2,000.00
4,050.00
151,200.00
1,600.00
11,250.00
44,000.00
26,000.00
3,100.00
3,500.00
342,200.00
189,750.00
31,250.00
4,250.00
70,000.00
2,000.00
4,050.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

1,600.00
44,000.00
26,000.00
3,100.00
3,500.00
189,750.00
66,025.00
25,200.00
14,000.00
400.00
11,000.00
13,000.00
1,550.00
875.00
66,025.00
3,778,923.33
6,090.00
360,000.00
1,785,000.00
17,000.00
8,500.00
60,000.00
67,500.00
20,833.33
350,000.00
12,000.00
22,500.00
210,000.00
165,000.00
97,500.00
65,000.00
23,250.00
8,750.00
500,000.00
3,778,923.33
1,026,600.00
42,500.00
441,000.00
6,000.00
17,850.00
12,000.00
22,500.00
75,000.00
110,000.00
260,000.00
31,000.00
8,750.00
1,026,600.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

1,080,600.00
75,000.00
579,600.00
14,000.00
75,000.00
110,000.00
195,000.00
23,250.00
8,750.00
1,080,600.00
19,750.00
11,000.00
8,750.00
19,750.00
1,059,450.00
31,250.00
390,600.00
6,000.00
17,850.00
12,000.00
22,500.00
75,000.00
94,500.00
110,000.00
260,000.00
31,000.00
8,750.00
1,059,450.00
64,795.00
20,000.00
12,500.00
27,500.00
2,210.00
310.00
2,275.00
64,795.00
283,250.00
97,500.00
63,000.00
4,000.00
110,000.00
8,750.00
283,250.00
791,645.00
733,370.00
58,275.00
791,645.00
739,145.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

733,370.00
5,775.00
739,145.00

86,875.00
82,500.00
4,375.00
86,875.00
106,875.00
99,000.00
7,875.00
106,875.00
127,225.00
115,500.00
11,725.00
127,225.00
115,600.00
110,000.00
5,600.00
115,600.00
175,500.00
165,000.00
10,500.00
175,500.00
139,875.00
132,000.00
7,875.00
139,875.00
6,375.00
5,500.00
875.00
6,375.00
38,050.00
36,300.00
1,750.00
38,050.00
24,445.00
21,120.00
3,325.00
24,445.00
63,750.00
55,000.00
8,750.00
63,750.00
298,750.00
264,000.00
33,000.00
1,750.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

298,750.00
295,875.00
264,000.00
27,500.00
4,375.00
295,875.00
339,750.00
178,750.00
13,500.00
20,000.00
110,000.00
17,500.00
339,750.00

1,544,650.00
194,000.00
720,000.00
343,400.00
165,000.00
97,500.00
11,625.00
13,125.00
1,544,650.00
1,492,350.00
208,000.00
720,000.00
277,100.00
165,000.00
97,500.00
11,625.00
13,125.00
1,492,350.00
1,456,050.00
217,600.00
720,000.00
231,200.00
165,000.00
97,500.00
11,625.00
13,125.00
1,456,050.00
1,430,550.00
224,400.00
720,000.00
198,900.00
165,000.00
97,500.00
11,625.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

13,125.00
1,430,550.00
1,395,550.00
233,600.00
720,000.00
154,700.00
165,000.00
97,500.00
11,625.00
13,125.00
1,395,550.00
1,042,170.00
172,800.00
720,000.00
85,800.00
50,700.00
6,045.00
6,825.00
1,042,170.00
2,950,325.00
288,000.00
1,462,500.00
343,400.00
128,000.00
220,500.00
28,000.00
330,000.00
110,500.00
13,175.00
26,250.00
2,950,325.00
1,569,450.00
292,500.00
476,000.00
180,000.00
301,500.00
261,800.00
39,000.00
4,650.00
14,000.00
1,569,450.00
1,415,035.00
4,180.00
37,600.00
67,500.00
102,850.00
877,500.00
31,500.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

67,200.00
2,400.00
1,350.00
6,720.00
110,000.00
87,100.00
10,385.00
8,750.00
1,415,035.00
1,106,120.00
3,520.00
32,000.00
56,250.00
83,300.00
672,750.00
24,500.00
56,700.00
2,400.00
1,350.00
5,600.00
88,000.00
65,000.00
7,750.00
7,000.00
1,106,120.00

288,301.00
50,000.00
108,851.00
23,600.00
71,500.00
26,000.00
3,100.00
5,250.00
288,301.00
261,800.00
50,000.00
73,950.00
32,000.00
71,500.00
26,000.00
3,100.00
5,250.00
261,800.00
248,265.00
50,000.00
56,015.00
36,400.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

71,500.00
26,000.00
3,100.00
5,250.00
248,265.00
2,482,650.00
238,185.00
50,000.00
45,135.00
37,200.00
71,500.00
26,000.00
3,100.00
5,250.00
238,185.00
234,390.00
50,000.00
37,740.00
40,800.00
71,500.00
26,000.00
3,100.00
5,250.00
234,390.00
266,775.00
180,000.00
23,800.00
12,800.00
33,000.00
13,000.00
1,550.00
2,625.00
266,775.00
262,875.00
180,000.00
18,700.00
14,000.00
33,000.00
13,000.00
1,550.00
2,625.00
262,875.00
514,050.00
420,000.00
23,800.00
12,800.00
33,000.00
19,500.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

2,325.00
2,625.00
514,050.00

389,550.00
60,060.00
21,148.00
10,000.00
4,875.00
143,000.00
84,500.00
10,075.00
11,375.00
734,583.00

367,500.00
19,975.00
14,000.00
79,200.00
49,400.00
5,425.00
5,250.00
540,750.00

393,750.00
19,975.00
14,000.00
79,200.00
49,400.00
5,425.00
5,250.00
567,000.00

367,500.00
19,975.00
14,000.00
79,200.00
49,400.00
5,425.00
5,250.00
540,750.00

341,250.00
19,975.00
14,000.00
79,200.00
49,400.00
5,425.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

5,250.00
514,500.00

393,750.00
19,975.00
14,000.00
79,200.00
49,400.00
5,425.00
5,250.00
567,000.00

399,000.00
19,975.00
14,000.00
79,200.00
49,400.00
5,425.00
5,250.00
572,250.00

189,000.00
19,975.00
14,000.00
55,000.00
49,400.00
5,425.00
5,250.00
338,050.00

90,206.80
26,356.80
6,400.00
33,000.00
19,500.00
2,325.00
2,625.00
90,206.80
82,830.80
17,380.80
8,000.00
33,000.00
19,500.00
2,325.00
2,625.00
82,830.80
79,869.20
13,219.20

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

9,200.00
33,000.00
19,500.00
2,325.00
2,625.00
79,869.20
77,658.00
10,608.00
9,600.00
33,000.00
19,500.00
2,325.00
2,625.00
77,658.00
76,662.80
8,812.80
10,400.00
33,000.00
19,500.00
2,325.00
2,625.00
76,662.80
75,757.20
7,507.20
10,800.00
33,000.00
19,500.00
2,325.00
2,625.00
75,757.20
82,985.00
15,810.00
7,200.00
28,600.00
26,000.00
3,100.00
2,275.00
82,985.00
80,394.00
12,019.00
8,400.00
28,600.00
26,000.00
3,100.00
2,275.00
80,394.00
73,750.00
850.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

5,200.00
8,800.00
52,000.00
6,200.00
700.00
73,750.00
43,825.00
5,525.00
22,000.00
13,000.00
1,550.00
1,750.00
43,825.00

5,525.00
22,000.00
13,000.00
1,550.00
1,750.00
43,825.00

7,626,750.00
3,740,000.00
770,000.00
2,730,000.00
325,500.00
61,250.00
7,626,750.00
5,851,500.00
2,520,000.00
660,000.00
2,340,000.00
279,000.00
52,500.00
5,851,500.00
345,425.00
150,000.00
1,000.00
38,500.00
136,500.00
16,275.00
3,150.00
345,425.00
705,250.00
150,000.00
110,000.00
390,000.00
46,500.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

8,750.00
705,250.00
795,250.00
240,000.00
110,000.00
390,000.00
46,500.00
8,750.00
795,250.00
538,700.00
90,000.00
4,500.00
88,000.00
312,000.00
37,200.00
7,000.00
538,700.00
516,775.00
50,000.00
600.00
7,500.00
70,000.00
77,000.00
273,000.00
32,550.00
6,125.00
516,775.00
573,500.00
51,200.00
600.00
7,500.00
70,000.00
88,000.00
312,000.00
37,200.00
7,000.00
573,500.00
651,325.00
225,000.00
3,000.00
73,700.00
260,000.00
31,000.00
58,625.00
651,325.00
633,050.00
93,750.00
600.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

4,500.00
90,000.00
88,000.00
312,000.00
37,200.00
7,000.00
633,050.00
674,650.00
50,000.00
600.00
12,000.00
90,000.00
50,000.00
93,500.00
331,500.00
39,525.00
7,525.00
674,650.00
5,018,000.00
2,310,000.00
375,000.00
112,000.00
440,000.00
1,560,000.00
186,000.00
35,000.00
5,018,000.00
8,287,175.00
4,080,000.00
375,000.00
112,000.00
737,000.00
2,613,000.00
311,550.00
58,625.00
8,287,175.00
4,077,600.00
2,310,000.00
375,000.00
60,000.00
264,000.00
936,000.00
111,600.00
21,000.00
4,077,600.00
69,825.00
29,400.00
9,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

5,000.00
11,000.00
13,000.00
1,550.00
875.00
69,825.00
78,825.00
29,400.00
18,000.00
5,000.00
11,000.00
13,000.00
1,550.00
875.00
78,825.00
382,210.00
346,500.00
4,000.00
13,200.00
15,600.00
1,860.00
1,050.00
382,210.00
109,615.00
32,340.00
4,000.00
16,500.00
39,000.00
4,650.00
13,125.00
109,615.00
106,630.00
34,230.00
5,000.00
22,000.00
39,000.00
4,650.00
1,750.00
106,630.00
83,475.00
40,500.00
2,000.00
11,000.00
26,000.00
3,100.00
875.00
83,475.00
21,275.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

15,750.00
2,310.00
2,730.00
310.00
175.00
21,275.00
82,475.00
40,500.00
1,000.00
11,000.00
26,000.00
3,100.00
875.00
82,475.00
145,175.00
58,800.00
3,000.00
16,500.00
58,500.00
6,975.00
1,400.00
145,175.00
248,175.00
58,800.00
3,000.00
94,600.00
8,400.00
16,500.00
58,500.00
6,975.00
1,400.00
248,175.00
245,750.00
58,800.00
3,000.00
64,500.00
8,400.00
22,000.00
78,000.00
9,300.00
1,750.00
245,750.00
372,650.00
26,250.00
2,000.00
11,250.00
66,000.00
234,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

27,900.00
5,250.00
372,650.00
44,915.00
30,000.00
1,000.00
2,750.00
9,750.00
1,240.00
175.00
44,915.00
146,335.00
97,500.00
29,400.00
240.00
45.00
11,000.00
6,500.00
775.00
875.00
146,335.00
1,144,871.71
962,374.59
4,184.10
178,313.02
1,144,871.71

419,900.00
248,285.71
333,000.00
32,250.00
181,500.00
35,750.00
4,340.00
14,525.00
1,269,550.71

469,200.00
236,571.43
337,333.33
32,250.00
181,500.00
35,750.00
4,340.00
14,525.00
1,311,469.76
1,343,950.71

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

508,300.00
228,285.71
339,000.00
32,250.00
181,500.00
35,750.00
4,340.00
14,525.00
1,343,950.71
1,192,326.19
391,000.00
255,142.86
342,333.33
32,250.00
132,000.00
26,000.00
3,100.00
10,500.00
1,192,326.19
1,382,707.86
554,200.00
217,142.86
343,000.00
32,250.00
181,500.00
35,750.00
4,340.00
14,525.00
1,382,707.86
1,419,288.81
598,400.00
208,857.14
343,666.67
32,250.00
181,500.00
35,750.00
4,340.00
14,525.00
1,419,288.81
1,447,493.57
630,700.00
199,428.57
349,000.00
32,250.00
181,500.00
35,750.00
4,340.00
14,525.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

1,447,493.57
1,465,212.62
652,800.00
197,714.29
346,333.33
32,250.00
181,500.00
35,750.00
4,340.00
14,525.00
1,465,212.62
1,495,993.57
690,200.00
195,428.57
342,000.00
32,250.00
181,500.00
35,750.00
4,340.00
14,525.00
1,495,993.57
1,505,369.76
702,100.00
194,571.43
340,333.33
32,250.00
181,500.00
35,750.00
4,340.00
14,525.00
1,505,369.76
1,605,786.90
746,300.00
191,428.57
335,333.33
32,250.00
231,000.00
45,500.00
5,425.00
18,550.00
1,605,786.90
1,618,229.76
761,600.00
190,571.43
333,333.33
32,250.00
231,000.00
45,500.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

5,425.00
18,550.00
1,618,229.76
1,563,975.00
680,000.00
192,000.00
360,000.00
31,500.00
231,000.00
45,500.00
5,425.00
18,550.00
1,563,975.00

15,750.00
6,600.00
3,900.00
465.00
525.00
11,490.00

21,000.00
7,700.00
4,550.00
542.50
612.50
34,405.00

26,250.00
8,800.00
5,200.00
620.00
700.00
41,570.00
228,585.00
204,750.00
5,250.00
7,700.00
9,100.00
1,085.00
700.00
228,585.00
22,858.50

221,550.00
204,750.00
3,500.00
5,500.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

6,500.00
775.00
525.00
221,550.00
22,155.00

25,500.00
1,750.00
2,750.00
3,250.00
310.00
175.00
33,735.00
187,080.00
80,000.00
6,000.00
1,500.00
57,200.00
33,800.00
4,030.00
4,550.00
187,080.00
197,080.00
90,000.00
6,000.00
1,500.00
57,200.00
33,800.00
4,030.00
4,550.00
197,080.00
346,140.00
80,000.00
8,000.00
3,000.00
31,500.00
47,250.00
50,000.00
72,600.00
42,900.00
5,115.00
5,775.00
346,140.00
352,440.00
80,000.00
8,000.00
3,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

37,800.00
47,250.00
50,000.00
72,600.00
42,900.00
5,115.00
5,775.00
352,440.00
446,140.00
80,000.00
8,000.00
3,000.00
31,500.00
47,250.00
150,000.00
72,600.00
42,900.00
5,115.00
5,775.00
446,140.00
441,640.00
80,000.00
8,000.00
3,000.00
42,000.00
47,250.00
75,000.00
60,000.00
72,600.00
42,900.00
5,115.00
5,775.00
441,640.00
325,390.00
60,000.00
8,000.00
2,250.00
31,500.00
47,250.00
50,000.00
72,600.00
42,900.00
5,115.00
5,775.00
325,390.00
160,975.00
52,800.00
12,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

12,500.00
16,500.00
65,000.00
775.00
1,400.00
160,975.00

1,505,369.76
3,778,158.34
725,412.24
55,000.00
6,063,940.35

1,505,369.76
3,956,112.75
883,433.33
55,000.00
6,399,915.85

1,505,369.76
5,197,115.39
1,309,560.00
55,000.00
8,067,045.15

1,505,369.76
2,902,981.40
2,769,120.00
110,000.00
7,287,471.16

1,505,369.76
2,623,392.99
2,433,796.88
110,000.00
6,672,559.62

1,505,369.76
5,551,010.39
4,285,542.86
82,500.00
11,424,423.01

1,505,369.76
4,583,274.40
4,615,200.00
82,500.00
10,786,344.16

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

1,505,369.76
5,107,741.54
5,192,100.00
82,500.00
11,887,711.30

1,505,369.76
3,968,381.89
6,922,800.00
82,500.00
12,479,051.66

1,382,707.86
8,818,626.43
11,538,000.00
82,500.00
21,821,834.29

1,505,369.76
7,468,618.74
1,313,866.67
82,500.00
10,370,355.17

1,505,369.76
6,223,848.95
1,576,640.00
82,500.00
9,388,358.71

1,505,369.76
5,119,921.28
1,970,800.00
82,500.00
8,678,591.05

1,382,707.86
2,902,981.40
1,576,640.00
82,500.00
5,944,829.25

1,505,369.76
5,668,952.96
3,132,800.00
110,000.00
10,417,122.72

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

1,505,369.76
5,029,372.89
4,699,200.00
110,000.00
11,343,942.65

1,505,369.76
4,289,894.32
3,132,800.00
110,000.00
9,038,064.08

1,505,369.76
5,444,123.91
4,229,280.00
110,000.00
11,288,773.67

1,505,369.76
5,201,611.68
4,699,200.00
110,000.00
11,516,181.45

1,505,369.76
5,580,537.04
5,404,080.00
110,000.00
12,599,986.80

1,505,369.76
3,963,214.73
4,405,500.00
110,000.00
9,984,084.49

1,505,369.76
12,680,502.95
7,131,727.06
110,000.00
21,427,599.77

1,505,369.76
3,997,596.24
11,890,307.69
110,000.00
17,503,273.70

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

1,505,369.76
3,720,358.03
4,416,400.00
110,000.00
9,752,127.79

1,505,369.76
5,167,163.93
3,680,333.33
110,000.00
10,462,867.02

400,000.00
30,000.00
6,000.00
2,925,000.00
78,750.00
571,200.00
216,000.00
364,500.00
583,000.00
35,750.00
169,000.00
136,500.00
40,610.00
46,375.00
5,602,685.00
7,082,340.00
540,000.00
40,000.00
9,000.00
4,095,000.00
105,000.00
571,200.00
216,000.00
364,500.00
621,500.00
35,750.00
202,800.00
182,000.00
50,065.00
49,525.00
7,082,340.00
10,995,700.00
800,000.00
80,000.00
30,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

5,850,000.00
157,500.00
549,100.00
208,000.00
351,000.00
315,000.00
472,500.00
500,000.00
803,000.00
45,500.00
429,000.00
273,000.00
88,350.00
43,750.00
10,995,700.00
7,325,150.00
640,000.00
64,000.00
24,000.00
2,925,000.00
78,750.00
571,200.00
216,000.00
364,500.00
252,000.00
378,000.00
800,000.00
583,000.00
35,750.00
169,000.00
136,500.00
41,075.00
46,375.00
7,325,150.00
8,141,850.00
500,000.00
64,000.00
24,000.00
3,900,000.00
105,000.00
549,100.00
208,000.00
351,000.00
294,000.00
378,000.00
400,000.00
655,600.00
45,500.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

364,000.00
182,000.00
85,250.00
36,400.00
8,141,850.00
7,391,325.00
480,000.00
64,000.00
24,000.00
2,925,000.00
78,750.00
549,100.00
208,000.00
351,000.00
252,000.00
378,000.00
800,000.00
638,000.00
45,500.00
364,000.00
136,500.00
65,100.00
32,375.00
7,391,325.00
7,026,585.00
480,000.00
64,000.00
24,000.00
2,925,000.00
78,750.00
549,100.00
216,000.00
364,500.00
336,000.00
378,000.00
600,000.00
583,000.00
35,750.00
169,000.00
136,500.00
40,610.00
46,375.00
7,026,585.00
7,762,240.00
500,000.00
60,000.00
18,000.00
3,900,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

105,000.00
549,100.00
216,000.00
364,500.00
220,500.00
337,500.00
350,000.00
621,500.00
35,750.00
202,800.00
182,000.00
50,065.00
49,525.00
7,762,240.00
94,125.00
4,000.00
195.00
45,000.00
1,575.00
6,800.00
2,400.00
4,050.00
19,800.00
2,600.00
2,600.00
2,600.00
930.00
1,575.00
94,125.00
131,555.00
6,000.00
390.00
54,000.00
1,750.00
9,350.00
3,600.00
6,750.00
32,670.00
4,290.00
4,290.00
4,290.00
1,550.00
2,625.00
131,555.00

61,880.00
38,500.00
400.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

13,200.00
7,800.00
930.00
1,050.00
61,880.00
147,075.00
78,750.00
4,100.00
22,000.00
26,000.00
3,100.00
13,125.00
147,075.00
291,732.50
225,000.00
40,000.00
307.50
11,000.00
13,000.00
1,550.00
875.00
291,732.50
43,690.00
15,000.00
800.00
16,500.00
9,100.00
1,240.00
1,050.00
43,690.00

34,230.00
5,000.00
22,000.00
39,000.00
4,650.00
1,750.00
106,630.00
172,460.00
139,500.00
1,250.00
13,200.00
15,600.00
1,860.00
1,050.00
172,460.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

297,375.00
269,700.00
1,250.00
11,000.00
13,000.00
1,550.00
875.00
297,375.00
114,862.50
87,187.50
1,250.00
11,000.00
13,000.00
1,550.00
875.00
114,862.50
55,300.00
28,125.00
750.00
11,000.00
13,000.00
1,550.00
875.00
55,300.00
384,400.00
300,000.00
2,000.00
11,000.00
65,000.00
4,650.00
1,750.00
384,400.00
60,160.00
32,760.00
8,250.00
11,000.00
6,500.00
775.00
875.00
60,160.00
51,587.50
28,125.00
600.00
7,700.00
13,000.00
1,550.00
612.50
51,587.50

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

205,000.00
90,000.00
200.00
3,750.00
22,000.00
78,000.00
9,300.00
1,750.00
205,000.00
163,000.00
48,000.00
200.00
3,750.00
22,000.00
78,000.00
9,300.00
1,750.00
163,000.00
29,250.00
15,750.00
200.00
5,500.00
6,500.00
775.00
525.00
29,250.00

68,996.00
1,000.00
9,900.00
1,950.00
1,395.00
78.75
83,319.75

-
-
32,760.00
5,250.00
36,300.00
54,418.00
7,285.00
2,712.50
138,725.50

1,850,000.00
111,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

363,000.00
143,000.00
155.00
28,000.00
2,495,155.00
829,700.00
250,000.00
10,200.00
4,000.00
110,000.00
195,000.00
232,500.00
28,000.00
829,700.00
1,347,250.00
850,000.00
102,000.00
30,000.00
4,000.00
132,000.00
188,500.00
23,250.00
17,500.00
1,347,250.00
1,742,280.00
42,000.00
204,000.00
120,000.00
197,280.00
30,000.00
660,000.00
390,000.00
46,500.00
52,500.00
1,742,280.00
20,178.50
-
1,156.00
5,200.00
2,420.00
6,600.00
3,900.00
465.00
437.50
20,178.50
#N/A
#N/A
#N/A

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

5,940.00
11,700.00
1,395.00
4,725.00
#N/A
#N/A
#N/A
#N/A
5,940.00
11,700.00
1,395.00
4,725.00
#N/A
#N/A
#N/A
#N/A
5,940.00
11,700.00
1,395.00
4,725.00
#N/A
#N/A
#N/A
#N/A
11,880.00
23,400.00
2,790.00
945.00
#N/A
#N/A
#N/A
#N/A
11,880.00
23,400.00
2,790.00
945.00
#N/A
772,219.72
95,659.72
74,800.00
28,000.00
31,500.00
31,200.00
24,000.00
352,000.00
131,950.00
310.00
2,800.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

772,219.72
930,590.56
164,930.56
130,900.00
52,000.00
9,000.00
50,700.00
36,000.00
352,000.00
131,950.00
310.00
2,800.00
930,590.56
1,167,641.94
244,756.94
193,800.00
73,600.00
14,850.00
94,575.00
48,000.00
352,000.00
131,950.00
310.00
2,800.00
11,000.00
1,167,641.94
547,212.50
450,000.00
50,000.00
3,300.00
39,000.00
4,650.00
262.50
547,212.50
51,650.00
35,000.00
125.00
1,100.00
13,000.00
1,550.00
875.00
51,650.00
71,525.00
55,000.00
1,100.00
13,000.00
1,550.00
875.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

71,525.00

2,718,162.13
156,680.23
113,525.00
1,819,174.65
529,723.44
276,762.06
3,895,287.00
4,394,404.15
2,070,770.00
132,552.00
652,500.00
295,330.00
155,265.00
17,210,135.65

126,955.07
182,227.76
96,415.00
405,597.83

30,000.00
8,750.00
5,940.00
11,700.00
1,395.00
4,725.00
62,510.00

35,000.00
10,208.33
5,940.00
11,700.00
1,395.00
4,725.00
68,968.33

45,000.00
13,125.00
5,940.00
11,700.00
1,395.00
4,725.00
81,885.00

50,000.00
14,583.33

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

11,880.00
23,400.00
2,790.00
945.00
103,598.33

55,000.00
16,041.67
11,880.00
23,400.00
2,790.00
945.00
110,056.67
-
90,000.00
26,250.00
11,880.00
23,400.00
2,790.00
945.00
155,265.00

190,000.00
55,416.67
11,880.00
23,400.00
2,790.00
945.00
284,431.67

240,000.00
70,000.00
14,850.00
29,250.00
3,487.50
1,190.00
358,777.50

87,000.00
25,375.00
8,910.00
17,550.00
2,092.50
717.50
141,645.00

34,500.00
10,062.50

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

8,910.00
17,550.00
2,092.50
717.50
73,832.50

24,000.00
7,000.00
8,910.00
17,550.00
2,092.50
717.50
60,270.00

15,000.00
4,375.00
5,940.00
11,700.00
1,395.00
472.50
38,882.50

9,600.00
2,800.00
3,960.00
8,580.00
930.00
315.00
26,185.00

8,100.00
2,362.50
3,960.00
7,800.00
930.00
315.00
23,467.50

344,175.00
192,500.00
400.00
100,000.00
22,000.00
26,000.00
3,100.00
175.00
344,175.00
122,093.75

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

25,000.00
300.00
19,200.00
5,000.00
16,500.00
52,000.00
3,875.00
218.75
122,093.75

25,000.00
300.00
38,000.00
6,000.00
4,400.00
52,000.00
3,875.00
218.75
129,793.75
120,593.75
15,000.00
2,000.00
38,000.00
12,500.00
16,500.00
32,500.00
3,875.00
218.75
120,593.75

244,425.00
150,000.00
6,600.00
78,000.00
9,300.00
525.00
244,425.00
218,525.00
150,000.00
1,100.00
65,000.00
1,550.00
875.00
218,525.00
46,106.25
22,500.00
1,650.00
19,500.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

2,325.00
131.25
46,106.25
40,737.50
25,000.00
1,100.00
13,000.00
1,550.00
87.50
40,737.50
31,606.25
8,000.00
1,650.00
19,500.00
2,325.00
131.25
31,606.25
133,687.50
55,000.00
5,500.00
65,000.00
7,750.00
437.50
133,687.50
74,343.75
35,000.00
2,750.00
32,500.00
3,875.00
218.75
74,343.75
133,606.25
110,000.00
1,650.00
19,500.00
2,325.00
131.25
133,606.25
223,606.25
200,000.00
1,650.00
19,500.00
2,325.00
131.25
223,606.25
250,962.50
225,000.00
1,815.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

21,450.00
2,557.50
140.00
250,962.50

317,193.33
227,333.33
16,320.00
18,000.00
7,500.00
27,500.00
16,250.00
2,015.00
2,275.00
317,193.33

#N/A
16,660.00
18,000.00
-
27,500.00
16,250.00
2,015.00
2,275.00
#N/A
163,510.00
71,220.00
17,000.00
18,000.00
7,500.00
28,600.00
16,900.00
2,015.00
2,275.00
163,510.00
253,705.00
77,155.00
17,000.00
18,000.00
7,500.00
77,000.00
45,500.00
5,425.00
6,125.00
253,705.00
230,830.00
53,000.00
17,680.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

18,000.00
8,100.00
77,000.00
45,500.00
5,425.00
6,125.00
230,830.00
290,750.00
33,000.00
16,660.00
18,000.00
21,850.00
115,500.00
68,250.00
8,215.00
9,275.00
290,750.00
254,925.00
71,220.00
24,055.00
15,600.00
10,000.00
77,000.00
45,500.00
5,425.00
6,125.00
254,925.00
269,138.00
47,128.00
15,810.00
7,200.00
7,500.00
110,000.00
65,000.00
7,750.00
8,750.00
269,138.00
262,110.00
53,000.00
15,810.00
7,200.00
13,750.00
99,000.00
58,500.00
6,975.00
7,875.00
262,110.00
258,060.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

53,000.00
15,810.00
7,200.00
9,700.00
99,000.00
58,500.00
6,975.00
7,875.00
258,060.00

80,000.00
17,680.00
18,000.00
8,100.00
77,000.00
45,500.00
5,425.00
6,125.00
257,830.00
218,021.00
50,000.00
19,346.00
16,800.00
7,500.00
68,200.00
45,500.00
5,425.00
5,250.00
218,021.00
38,710.00
6,000.00
1,000.00
13,200.00
15,600.00
1,860.00
1,050.00
38,710.00

600.00
100.00
2,200.00
26,000.00
3,100.00
1,750.00
33,750.00
17,937.50
1,000.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

16,500.00
-
-
437.50
17,937.50
17,027.50
90.00
16,500.00
-
-
437.50
17,027.50
12,607.50
1,200.00
500.00
250.00
4,400.00
5,200.00
620.00
437.50
12,607.50
35,800.00
5,700.00
3,400.00
7,650.00
7,700.00
9,750.00
1,162.50
437.50
35,800.00
35,037.50
4,000.00
5,700.00
3,400.00
11,700.00
7,700.00
1,170.00
930.00
437.50
35,037.50
51,257.50
4,000.00
5,700.00
3,400.00
15,750.00
7,700.00
13,650.00
620.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

437.50
51,257.50
33,592.50
10,800.00
4,400.00
8,190.00
9,765.00
437.50
33,592.50
37,207.50
3,750.00
16,740.00
6,000.00
-
7,800.00
2,480.00
437.50
37,207.50
20,800.00
8,750.00
11,000.00
-
-
1,050.00
20,800.00
49,217.50
6,750.00
750.00
300.00
100.00
17,600.00
20,800.00
2,480.00
437.50
49,217.50
30,104.00
2,800.00
2,500.00
13,000.00
2,200.00
8,190.00
976.50
437.50
30,104.00
21,628.50
3,000.00
9,000.00
3,080.00

Informasi Harga Satuan Pekerjaan Tahun 2012


JUMLAH HARGA (Rp)

5,460.00
651.00
437.50
21,628.50
35,150.00
2,000.00
100.00
2,200.00
26,000.00
3,100.00
1,750.00
35,150.00
42,850.00
11,250.00
6,250.00
1,500.00
1,100.00
13,000.00
3,875.00
875.00
5,000.00
42,850.00

Informasi Harga Satuan Pekerjaan Tahun 2012


DAFTAR UPAH DAN BAHAN
HARGA SATUAN
NO. NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)

Semen Portland Kg 1,700.00


Semen Putih Kg 3,250.00
Semen Warna Kg 5,000.00
Kawat beton Kg 35,000.00
Kawat Duri Kg 28,000.00
Kawat Las Doz 75,000.00
Jaring kawat baja dilas Kg 25,000.00
Air M3 150.00
Tripleks 3 mm Ukuran 122 x 224 cm Lembar 58,000.00
Plywood tebal 4 mm ( 90 x 220 ) cm Lembar 70,000.00
Plywood tebal 4 mm ( 120 x 240 ) cm Lembar 75,000.00
Tripleks 4 mm Ukuran 122 x 244 cm Lembar 75,000.00
Tripleks 5 mm Ukuran 122 x 224 cm Lembar 85,000.00
Tripleks 6 mm Ukuran 122 x 224 cm Lembar 95,000.00
Tripleks 9 mm Lembar 135,000.00
Tripleks 12 mm Ukuran 122 x 224 cm Lembar 180,000.00
Tripleks 18 mm Ukuran 122 x 224 cm Lembar 250,000.00
Teakwood tebal 4 mm ( 90 x 220 ) cm Lembar 90,000.00
Teakwood tebal 4 mm ( 120 x 240 ) cm Lembar 110,000.00
Plywood 4 mm Lembar 70,000.00
Dolken Kayu Dia. 8-10/400 cm Batang 25,000.00
Waterstop lebar 150 mm M 15,000.00
Waterstop lebar 200 mm M 20,000.00
Waterstop lebar 230 mm - 320 mm M 25,000.00
Formika Lembar 100,000.00
Gypsum Board 9 mm Lembar 90,000.00
Akustik 60 x 60 cm Lembar 46,500.00
Akustik 30 x 30 cm Lembar 11,625.00
Akustik 60 x 120 cm Lembar 58,125.00
List Plafond M1 20,000.00
Paku Biasa Kg 20,000.00
Paku campur Kg 20,000.00
Paku Seng Kg 25,000.00
Paku tripleks Kg 25,000.00
Paku Atap Kg 20,500.00
Paku Beton Kg 100,000.00
Paku sekrup Kg 75,000.00
Hollow 40x40x3,2 mm Kg 23,500.00
Besi strip tebal 5 mm Kg 25,000.00
Mur Baut Dia. 12 - 14 mm Batang 15,000.00
Seng Gelombang BJLS 0.30 Lembar 60,000.00
Seng Gelombang BLJS 20 Lembar 50,000.00
Seng Gelombang BJLS 30' Lembar 55,000.00
Seng Plat BJLS 0.20 Lembar 45,000.00
Seng Plat 3' x 6 " bjls 30 Lembar 50,000.00
Genteng Metal Multiroof Polos Lembar 85,000.00
Nok Genteng Metal Multiroof Lembar 35,000.00
Ardek Gelombang Besar Lembar 50,000.00
Ardek Gelombang Kecil Lembar 42,000.00
Seng Aluminium lebar 60 cm Lembar 37,500.00
Seng Aluminium lebar 55 cm Lembar 35,000.00
Genteng Metal Lembar 35,000.00
Bubungan Genteng Metal Buah 45,000.00
Polycarbonate M2 300,000.00
Lumbersharing @4m Lembar 25,000.00
Kaca Polos M2 150,000.00
Kaca Bening 3 mm M2 100,000.00
Kaca Bening 4 mm M2
150,000.00
HARGA SATUAN
NO. NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
Kaca Bening 5 mm M2 200,000.00
Kaca Bening 8 mm M2 225,000.00
Kaca Louvers 5 mm, 8 klip Set 190,000.00
Kaca Louvers 5 mm, 7 klip Set 180,000.00
Jendela Nako Ser 175,000.00
Kaca Ryben 5 mm M2 170,000.00
Batu belah 15/20 650,000.00
Batu Kali 600,000.00
Batu pecah 5/7 700,000.00
Batu Kali, ex quarry Mile 32 M3 600,000.00
Batu Kali, ex quarry Iwaka M 3
600,000.00
Kerikil M3 450,000.00
Kerikil Koral 450,000.00
Koral beton 450,000.00
Kerikil Kali, ex quarry Kilo 7,8,14 M3 450,000.00
Kerikil (Batu Pecah) : M 3

- Split 1 - 2 cm M3 1,000,000.00
- Split 2 - 3 cm M3 1,000,000.00
- Split 3 - 5 cm M3 850,000.00
Sirtu Timbunan 220,000.00
Sirtu Timbunan, ex quarry Mile 32 M3 220,000.00
Sirtu Timbunan, ex quarry Iwaka M3 180,000.00
Sirtu Timbunan, ex quarry Kilo 7,8,14 M3 150,000.00
Pasir Pasang M 3
400,000.00
Pasir Beton M3 400,000.00
Pasir Urug 220,000.00
Tanah Timbunan ex quarry Kilo 7,8,14 M3 175,000.00
Kayu kelas I (balok) M3 3,400,000.00
Kayu kelas II (balok) 2,100,000.00
Kayu kelas II (papan) 2,000,000.00
Kayu Kelas II Matoa ( Balok ) M3 2,100,000.00
Kayu kelas I (papan) 3,750,000.00
Kayu Kelas I Besi ( Papan ) M3 3,750,000.00
Kayu Kelas II Matoa ( Papan ) M3 2,000,000.00
Kayu profil m 15,000.00
Reng ( 2 x 3 ) cm M3 2,500,000.00
Bambu Dia. 6 - 8 / 600 cm Batang 20,000.00
Bilik Bambu M2 65,000.00
Batu Tela Buah 1,900.00
Batu Tela (m3) M3 659,722.22
Batu batako 10 x 18 x 24 cm Buah 2,000.00
Bata berongga ekspose Buah 6,000.00
Roster/terawang Buah 6,000.00
Batu Bunga/Loster Buah 8,000.00
Batu Tempel Hitam M2 66,500.00
Batu Apung Kg 25,000.00
Marmer ex lokal M2 340,000.00
Batu alam Palimanan/Batu Candi M2 367,500.00
Batu Andhesit M2 350,000.00
Batu Alam Candi M2 375,000.00
Batu Andhesit M2 350,000.00
Batu Alam Limestone M2 325,000.00
Batu Alam Candi M2 375,000.00
Batu Andhesit Susun Sirih M2 380,000.00
Batu koral sikat M2 180,000.00
Tegel keramik 60x60 Buah 73,333.33
HARGA SATUAN
NO. NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
Tegel Keramik 40 x 40 cm Buah 11,600.00
Tegel Keramik 30 x 30 cm Buah 6,500.00
Tegel Keramik 20 x 25 cm Buah 4,000.00
Tegel Keramik 20 x 20 cm Buah 2,000.00
Tegel Keramik 10 x 20 cm Buah 1,000.00
Tegel Porselin 11 x 11 cm Buah 548.00
Tegel Mozaik 30 x 30 cm Buah 6,000.00
Tegel Teraso 30 x 30 cm Buah 6,000.00
Tegel PC Abu-Abu 20 x 20 cm Buah 2,400.00
Plint keramik artistik Buah 4,500.00
Batu Alam Palimanan Buah 15,000.00
Pipa PVC Ø 1/2 " Batang 17,000.00
Pipa PVC Ø 3/4 " Batang 22,000.00
Pipa PVC Ø 1 " Batang 27,000.00
Pipa PVC Ø 1 ½ " Batang 32,000.00
Pipa PVC Ø 2 " Batang 50,000.00
Pipa PVC Ø 3 " Batang 80,000.00
Pipa PVC Ø 4 " Batang 115,000.00
Pipa PVC dia 5" - 4m Batang 263,958.00
Pipa PVC Ø 6 " Batang 290,000.00
Koppling PVC dia 2" Buah 15,000.00
Koppling PVC dia 4" Buah 20,000.00
Pipa Gip Ø ½ " Batang 150,000.00
Pipa Gip Ø ¾ " Batang 175,000.00
Pipa Gip Ø 1 " Batang 225,000.00
Pipa Gip Ø 1 ¼ " Batang 250,000.00
Pipa Gip Ø 1 ½ " Batang 275,000.00
Pipa Gip Ø 2 " Batang 450,000.00
Pipa Gip Ø 3 " Batang 950,000.00
Pipa Gip Ø 4 " Batang 1,200,000.00
Kabel ITC 2 x 2 x 0.6 mm2 m 2,500.00
Kabel NYM 2 X 2,5 mm2 m 6,240.00
Kabel NYM 3 X 2,5 mm2 m 10,800.00
Kabel NYM 3 x 4 mm2 m 29,000.00
Kabel NYM 4 x 4 mm2 m 45,000.00
Kabel NYM HY 3 X 2,5 mm2 m 10,800.00
Klem PVC Clipsal m 675.00
Las Dop Legrand 4 mm2 Bh 1,800.00
Pipa Clipsal PVC 3/4 Bh 3,750.00
Pipa PVC Maspion 5/8 Bh 2,800.00
T.Doos PVC 3/4 Bh 5,000.00
Elbo Clipsal PVC 3/4 Bh 5,000.00
Sock PVC Clipsal 3/4 5,000.00
Isolasi Unibel Bh 12,000.00
Kran Leding (Plastik) Buah 15,000.00
Kran Leding (Stainles) Buah 75,000.00
Ijuk Kg 50,000.00
Pompa Air Sanyo PH 100 Unit 1,100,000.00
Pompa Air Honda (Alkon) Unit 3,500,000.00
Permite/Penjaga jarak bekisting/spacer Buah 15,000.00
Seal tape Roll 5,000.00
Minyak Bekesting Liter 15,000.00
Rapidrant Galon 250,000.00
Bak Cuci Stainless Steel Buah 450,000.00
Water Drain + Acesories Set 150,000.00
Floor Drain Buah 55,000.00
Tangki Air fibre Kap. 1000 Liter Buah 1,800,000.00
Kloset jongkok porselen Buah 250,000.00
Kloset Jongkok Biasa Buah 100,000.00
Kloset Duduk Keramik KIA Buah 1,800,000.00
Kloset Duduk Keramik Biasa Buah 500,000.00
Kloset duduk / monoblok 1,850,000.00
HARGA SATUAN
NO. NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
Wastafel lengkap TOTO Buah 850,000.00
Floor Drain Stainless Steel Buah 75,000.00
Kran Air Stainless 35,000.00
Lampu TL 2 x 40 Watt Phillips + Mirror inbow Buah 35,000.00
Lampu TL 2 x 20 Watt Buah 27,000.00
Lampu TL 20 Watt Buah 39,000.00
Lampu Down Light + SL 15 Watt Lengkap Buah 80,000.00
Lampu Baret SL 18 Watt Buah 25,000.00
Lampu Pijar 5 - 100 Watt + Fitting Buah 20,000.00
Kabel Snoor 2 x 0,23 "Supreme" roll 160,200.00
Kabel NYA 2,5 sqmm "Supreme" roll 333,760.00
Kabel NYA 1,5 sqmm "Supreme" roll 211,380.00
Kabel NYA 2,5 sqmm "Supreme" M1 3,337.60
Kabel NYA 1,5 sqmm "Supreme" M1 2,113.80
Kabel NYM 2 x 1,5 sqmm "Supreme" M 1
12,000.00
Kabel NYM 2 x 2,5 mm (eterna) M1 7,500.00
Kabel NYM 2 x 4 sqmm "Supreme" M1 18,750.00
Kabel NYM 3 x 1,5 sqmm "Supreme" M1 18,000.00
Kabel NYM 3 x 2,5 mm M 1
11,000.00
Kabel NYM 4 x 4 mm2 M1 27,000.00
Kabel NYM 3 x 4 sqmm "Supreme" M1 25,000.00
Kabel NYY 3 x 1,5 sqmm "Supreme" M 1

Kabel NYY 3 x 2,5 sqmm "Supreme" M1


Kabel NYY 3 x 4 sqmm "Supreme" M1
Kabel NYY 3 x 6 sqmm "Supreme" M1 30,000.00
Kabel NYY 4 x 10 sqmm "Supreme" M 1

Kabel NYFGBY 3 x 10 sqmm "Supreme" M1


Kabel NYF GbY 4 x 25 mm M1 250,000.00
Kabel ITC 2 x 2 x 0.6 mm2 M 1

Kabel DX 2 x 10 sqmm "Supreme" M1


Kabel DX 2 x 16 sqmm "Supreme" M1
Kabel DX 2 x 25 sqmm "Supreme" M1
Kabel Ties 15 cm "Supreme" M1
Kabel Tis 10 cm "Supreme" M1
Tiang Galvanit cb,1, h=9m, base plate unit
Tiang Galvanit cb,2, h=9m, base plate unit
Tiang Galvanit cb,2, h=6m, base plate unit
Tiang Galvanit cb,1, h=7m, base plate unit
Tiang Galvanit cb,1, h=5m, type tanam dia 2" unit
Tiang lampu Highment cb 4, h=20m, hidrolik unit
Tiang lampu Highment cb 2, h=20m, hidrolik unit
Tiang GIP cb 1. 2", 3", 4", 5", h = 9m, tanam unit
Tiang GIP cb 1. 2", 3", 4", h = 7m, tanam unit
Tiang GIP cb 1. 3", 4", 5", h = 9m, tanam unit
Vitting Buah 35,000.00
Stop Kontak 1000 W Buah 26,396.00
Stop Kontak 5000 W Buah 32,000.00
Sekring 1 Group Buah 35,000.00
Sekring 3 Group Buah 110,000.00
Sekring Otomatis Buah 60,000.00
Saklar Seri Buah 20,000.00
Saklar Tunggal Buah 20,000.00
Box Sekring Grup 79,000.00
MCB (Miniatur Circuit Breaker) Buah 50,000.00
Box MCB Group 50,000.00
Plat strip t = 4 mm - 6 m Batang 15,000.00
Besi Ø 6 Kg 25,000.00
Besi Beton (UK 8 mm x 12) Batang 45,000.00
Besi Beton Segala Ukuran ( Polos ) Kg 17,000.00
HARGA SATUAN
NO. NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
Besi beton Kg 19,500.00
Besi Ø 10 Batang 66,000.00
Besi Ø 12 Batang 93,000.00
Besi Siku 20.20-2m Batang 50,000.00
Besi Siku 30.30-3m Batang 95,000.00
Besi Siku 40.40-3m Batang 100,000.00
Besi Siku 40.40-6m Batang 150,000.00
Besi Siku 50.50-4m Batang 175,000.00
Besi Siku 50.50-6m Batang 225,000.00
Besi Siku 60.60-6mm Batang 450,000.00
Besi Siku 70.70-7 mm Batang 475,000.00
Hollow Plafon Batang 25,000.00
Cat Dasar Kaleng 20,000.00
Cat Dasar Tembok Kg 25,000.00
Meni Kayu Kg 20,000.00
Melamine IMPRA Liter 45,000.00
Cat Kilat Kayu Kaleng 45,000.00
Politur Dasar Kaleng 25,000.00
Cat Vernis/Politur Kaleng 45,000.00
Cat Tembok Kg 50,000.00
- Merk Avitex Klg 350,000.00
- Merk Aries Klg 125,000.00
-Merk mowilex Klg 1,250,000.00
Cat Residu Kg 25,000.00
Meni Kg 20,000.00
Cat Teak oil Kaleng 30,000.00
Cat Alluminium Kaleng 55,000.00
Soda Api Kg 20,000.00
Minyak Cat Kg 25,000.00
Sabun 1,800.00
Plamur Tembok Kg 28,000.00
Plamur Kayu Kg 38,000.00
Dempul Kg 15,000.00
Kuas Biasa Buah 10,000.00
Kuas Roll (Besar) Buah 20,000.00
Ampelas Lembar 3,000.00
Lem kayu Kg 15,000.00
Lem Aibon Kaleng 45,000.00
Plester "Cotton Tape" roll 15,000.00
Compound kg 15,000.00
Kunci Tanam Buah 150,000.00
Kunci Tanam 2 Slaag SES/Kend Buah 150,000.00
Kunci Tanam Silinder 1 Slaag SES/Kend Buah 150,000.00
Kunci Kuda Terbang 1 Slaag Buah 60,000.00
Kunci Kuda Terbang 2 Slaag Buah 75,000.00
Kunci lemari Buah 35,000.00
Kunci Yale Besar Buah 150,000.00
Kunci H Jendela Pasang 18,000.00
Kunci H Pintu Pasang 24,000.00
Engsel jendela Pasang 25,000.00
Engsel Pintu Pasang 45,000.00
Kunci Gembok Besar Buah 50,000.00
Kunci Gembok Sedang Buah 25,000.00
Kunci Gembok Kecil Buah 15,000.00
Grendel Kecil Buah 5,000.00
Grendel Sedang Buah 10,000.00
Grendel Besar Buah 15,000.00
Door holder 55,000.00
Hak Angin Biasa Buah 8,000.00
Hak Angin Lipat Buah 11,500.00

Pekerja O/h 110,000.00


HARGA SATUAN
NO. NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
Pekerja Tukang Aspal O/h 110,000.00
Tukang O/h 130,000.00
Tukang Kayu O/h 130,000.00
Tukang Batu O/h 130,000.00
Tukang besi 130,000.00
Tukang gali 110,000.00
Tukang Cat O/h 130,000.00
Tukang Bongkar O/h 110,000.00
Tukang Listrik O/h 130,000.00
Tukang Pipa O/h 130,000.00
Tukang Aspal O/h 130,000.00
Kep. Tukang O/h 155,000.00
Mandor O/h 175,000.00
Pengawas / Ahli Teknik O/h 354,166.67
Ahli ukur O/h 155,000.00
Asisten ahli ukur O/h 110,000.00

Mesin penyaring 8 HP jam 50,000.00


Chip Spreader jam 50,000.00
Mesin penghampar 1820 MM 30 HP jam 181,000.00
Thriller gandeng 1 ton jam 184,000.00
Dump Truck 3,5 ton 44 HP jam 118,000.00
Pompa air (D 5 cm) 30 m3 / jam jam 11,000.00
Thriller 1ton jam 15,000.00
Traktor jam 15,000.00
Alat Bor jam 150,000.00
Sewa Alat Ukur Hr 275,000.00
Beton Molen jam 25,000.00
Mata Cutter bh 1,000,000.00
Mesin Cutter jam 60,000.00
Motor Walls jam 20,000.00
Peralatan Las jam 75,000.00
Sprayer jam 48,000.00
Alat bantu untuk pekerjaan analisa - E ls 500.00
ENGINEERING ESTIMATE (EE)
KEGIATAN : PERENCANAAN RUMAH IBADAH
PEKERJAAN : PERENCANAAN CENTRAL MONUMENT KRISTUS ALLAH NOL PAPUA
LOKASI : AGIMUGA- MIMIKA
TAHUN ANGG : 2014

HARGA SATUAN
NO. URAIAN JENIS PEKERJAAN SAT VOLUME JUMLAH HARGA (Rp) KETERANGAN
(Rp.)
1 2 3 4 5 6 7
A PEKERJAAN SITE DEVELOBMENT
1 Pek. Pembersihan Lokasi M2 250,000.00 19,750 4,937,500,000
2 Pek. Penimbunan Lokasi (area Bangunan Utama) m3 10,000.00 275,000 2,750,000,000
3 Pek. Pembuatan Pagar Kelilng m 2,000.00 2,200,000 4,400,000,000
TOTAL. A 12,087,500,000
B. BANGUNAN UTAMA
I PEKERJAAN PERSIAPAN
1 Pek. Mobilisasi/Demobilisasi Ls 1.00 2,550,000,000 2,550,000,000
2 Pek. Gudang / Direksi keet M2 32.00 1,026,600 32,851,200
3 Pek. Pengukuran & Pasang Bowplank M1 200.00 66,025 13,205,000
4 Quality Control Ls 1.00 250,000,000 250,000,000
TOTAL. B1 2,846,056,200
II PEKERJAAN TANAH
1 Pek. Galian Tanah Pondasi M3 735.87 127,225 93,620,773
2 Pek. Timbun Kembali Hasil Galian M3 245.29 24,445 5,996,096
3 Pek. Urug Sirtu Peninggian Peil Lantai M3 1,554.00 295,875 459,789,750
4 Pek. Urug Pasir dibawah Pondasi M3 53.44 298,750 15,966,236
TOTAL. B2 575,372,854
III PEKERJAAN PONDASI
a Pekerjaan pondasi tiang Pancang
1 Pengadaan Spun Piles Ø 45 : Ttk 105 5,744,108 603,131,288
2 Pemancangan Spun Piles : m 1,260 448,632 565,275,690
3 Sambungan Pemancangan Ttk 105 553,697 58,138,185
4 Pengupasan Kepala Tiang Pancang Ttk 105 1,601,875 168,196,875
Sub Total B3.a 1,394,742,037.50
b Pekerjaan Pondasi Struktur
1 Pek. Pondasi Beton Pile Cap (K300) M3 148.75 6,063,940.35 902,011,127.10
2 Pek. Pondasi Beton Foot Plat (K300) M3 10.24 6,399,915.85 65,535,138.26
3 Pek. Pondasi Beton Tangga (K300) M3 46.52 6,399,915.85 297,724,085.15
4 Pek. Beton Lantai Kerja Pondasi (K125) m3 149.77 1,311,470 196,424,072.12
5 Pek. Beton Lantai Kerja Slof (K125) m3 8.02 1,311,470 10,520,173.27
Sub Total B3.b 1,472,214,595.91
TOTAL. B3 2,866,956,633.41
IV PEKERJAAN BETON
a Pekerjaan Lantai 1
1 Pek. Beton Slof utama uk. 30x60 M3 48.13 10,370,355.17 499,125,194.13
2 Pek. Beton Slof uk. 25x40 M3 12.31 9,388,358.71 115,570,695.71
3 Pek. Beton Slof Praktis uk. 15x20 M3 1.16 5,944,829.25 6,916,655.03
4 Pek. Beton Kolom Utama uk. Ø80 M3 11.29 10,995,700.00 124,093,930.39
5 Pek. Beton Kolom Utama uk. Ø70 M3 30.20 10,995,700.00 332,116,142.42
6 Pek. Beton Kolom Utama uk. 60x60 M3 16.07 10,995,700.00 176,700,899.00
7 Pek. Beton Kolom uk. 40x40 M3 8.34 10,995,700.00 91,704,138.00
8 Pek. Beton Kolom uk. 30x30 M3 2.16 10,995,700.00 23,750,712.00
9 Pek. Beton Kolom Praktis M3 1.39 11,424,423.01 15,834,250.29
10 Pek. Beton Ring Balk Praktis Praktis M3 0.45 11,887,711.30 5,349,470.09
Pek. Beton Tangga Ke Lantai 2 m3 53.16 8,141,850.00 432,820,746.00
Sub Total B4.a 1,823,982,833.05
b Pekerjaan Lantai 2
1 Pek. Beton Balok Utama uk 40x80 M3 120.89 10,417,123 1,259,325,965.25
2 Pek. Beton Balok anak uk30x60 M3 4.50 10,417,123 46,877,052.23
3 Pek. Lisplan Beton M3 2.24 17,503,274 39,207,333.08
4 Pek. Beton Plat Lantai 2 T=15cm M3 87.00 10,462,867 910,269,430.76
5 Pek. Beton Kolom Utama uk. Ø80 M3 7.99 12,095,270.00 96,639,521.01
6 Pek. Beton Kolom Utama uk. Ø70 M3 12.45 12,095,270.00 150,573,769.39
7 Pek. Beton Kolom uk. 30x30 M3 1.44 12,095,270.00 17,417,188.80
8 Pek. Beton Kolom Praktis M3 0.26 12,566,865.31 3,317,652.44
9 Pek. Beton Tangga Ke Lantai 3 M3 2.37 8,956,035.00 21,225,802.95
10 Pek. Beton Tangga luar dari lantai 2 ke Top flour M3 8.53 10,177,312.50 86,832,830.25
Sub Total B4.b 2,631,686,546.17

517211341.xlsx/Nas
1 2 3 4 5 6 7
c Pekerjaan Lantai 3
1 Pek. Beton Balok anak uk30x60 M3 25.50 11,458,835 292,200,292.21
2 Pek. Lisplan Beton M3 0.28 19,253,601 5,391,008.30
3 Pek. Beton Plat Lantai 2 T=12cm M3 12.42 11,509,154 142,932,180.08
4 Pek. Beton Kolom Utama uk. Ø80 M3 7.99 12,095,270.00 96,639,521.01
5 Pek. Beton Kolom Utama uk. Ø70 M3 12.45 12,095,270.00 150,573,769.39
6 Pek. Beton Kolom uk. 30x30 M3 1.44 12,095,270.00 17,417,188.80
7 Pek. Beton Kolom Praktis M3 0.26 12,566,865.31 3,317,652.44
Sub Total B4.c 708,471,612.23
d Pekerjaan Lantai 4
1 Pek. Beton Balok Utama uk 40x80 M3 50.44 12,500,547 630,527,603.81
2 Pek. Beton Balok anak uk30x60 M3 20.88 12,500,547 261,011,426.80
3 Pek. Lisplan Beton M3 15.89 21,003,928 333,752,422.88
4 Pek. Beton Plat Lantai 2 T=12cm M3 32.25 12,555,440 404,912,953.68
5 Pek. Beton Kolom Utama uk. Ø80 M3 3.99 12,095,270.00 48,319,760.51
6 Pek. Beton Kolom Utama uk. Ø70 M3 6.22 12,095,270.00 75,286,884.69
7 Pek. Beton Kolom uk. 30x30 M3 1.44 12,095,270.00 17,417,188.80
8 Pek. Beton Kolom Praktis M3 0.13 12,566,865.31 1,658,826.22
Sub Total B4.d 1,772,887,067.40
e Pekerjaan Top Flour
1 Pek. Beton Balok Utama uk 40x80 M3 13.69 13,021,403 178,263,012.49
2 Pek. Lisplan Beton M3 3.00 21,879,092 65,637,276.37
3 Pek. Beton Plat Lantai 2 T=12cm M3 12.74 13,078,584 166,621,157.30
4 Pek. Beton atap tangga M3 6.56 13,078,584 85,795,509.57
Sub Total B4.e 496,316,955.73
TOTAL. B4 7,433,345,015
V. PEKERJAAN PASANGAN DAN PLESTERAN
a Pekerjaan Lantai I
1 Pek. Pasangan Pondasi Batu Kali 1 :4 M3 8.14 1,544,650.00 12,580,122.17
2 Pek. Batu Kosong M3 6.98 1,042,170.00 7,274,763.47
3 Pek. Pasangan Pondasi Trassraam 1:3 M3 6.87 2,482,650.00 17,064,743.04
4 Pek. Pasangan Dinding Batu Tela 1 :4 m2 467.38 238,185 111,321,714.38
5 Pek. Plesteran Dinding 1:4 M2 934.75 77,658 72,590,815.50
6 Pek. Plesteran Beton 1 : 3 M2 184.66 79,869 14,748,593.43
7 Pek. Acian Dinding Dan Beton M2 1,119.41 43,825 49,058,114.14
8 Pek. Pasangan Keramik Lantai (60x60) M2 937.74 317,193 297,444,876.40
9 Pek. Pasangan Keramik Tangga (60x60) M2 330.54 333,053 110,086,387.04
10 Pek. Pas. Plin Keramik 10x60 m1 746.27 66,611 49,709,685.01
11 Pek. Pasangan Keramik Lantai Km/WC (20x20) M2 26.32 230,830 6,075,445.60
12 Pek. Pasangan Keramik Dinding Km/WC (20x25) M2 30.90 257,830 7,966,947.00
13 Pek. Profilan Kolom Bulat Lot 20.00 1,200,000 24,000,000.00
14 Pek. Penebalan Kaki Kolom Bulat Bh 20.00 850,000 17,000,000.00
Sub Total B5.a 796,922,207.17
b Pekerjaan Lantai 2
1 Pek. Pasangan Dinding Batu Tela 1 :4 m3 111.48 85,424 9,523,045.22
2 Pek. Plesteran Dinding 1:4 M2 222.96 85,424 19,046,090.45
3 Pek. Plesteran Beton 1 : 3 M2 86.69 87,856 7,615,912.67
4 Pek. Acian Dinding Dan Beton M2 309.65 48,208 14,927,268.90
5 Pek. Pasangan Keramik Lantai (60x60) M2 572.36 348,913 199,703,653.89
6 Pek. Pas. Plin Keramik 10x60 m1 57.24 76,761 4,393,480.39
7 Pek. Profilan Kolom Lot 12.00 500,000 6,000,000.00
8 Biaya Lansiran material Ls 1.00 26,120,945 26,120,945.15
Sub Total B5.b 287,330,396.67
c Pekerjaan Lantai 3
1 Pek. Pasangan Dinding Batu Tela 1 :4 m3 126.50 93,190 11,788,484.40
2 Pek. Plesteran Dinding 1:4 M2 253.00 93,190 23,576,968.80
3 Pek. Plesteran Beton 1 : 3 M2 24.14 95,843 2,313,338.16
4 Pek. Acian Dinding Dan Beton M2 277.14 52,590 14,574,620.95
5 Pek. Pasangan Keramik Lantai (60x60) M2 89.38 380,632 34,020,888.16
6 Pek. Pas. Plin Keramik 10x60 m1 55.00 83,739 4,605,647.20
7 Pek. Profilan Kolom Lot 12.00 650,000 7,800,000.00
8 Biaya Lansiran material Ls 1.00 9,867,995 9,867,994.77
Sub Total B5.c 108,547,942.44

517211341.xlsx/Nas
1 2 3 4 5 6 7
d Pekerjaan Lantai 4 dan Top Flour
1 Pek. Pasangan Dinding Batu Tela 1 :4 m3 89.40 97,073 8,678,281.50
2 Pek. Plesteran Dinding 1:4 M2 178.80 97,073 17,356,563.00
3 Pek. Plesteran Beton 1 : 3 M2 35.99 99,837 3,593,115.64
4 Pek. Acian Dinding Dan Beton M2 214.79 54,781 11,766,464.69
5 Pek. Pasangan Keramik Lantai (60x60) M2 251.41 396,492 99,681,969.92
6 Pek. Pas. Plin Keramik 10x60 m1 154.71 87,228 13,494,650.21
7 Pek. Profilan Kolom Lot 12.00 780,000 9,360,000.00
8 Biaya Lansiran material Ls 1.00 16,393,104 16,393,104.50
Sub Total B5.d 180,324,149.45
TOTAL. B5 1,373,124,696
VI. PEKERJAAN KOSEN, PINTU DAN JENDELA (Lantai 1,2 ,3 & 4)
1 Pek. Kosen Pintu Dan Jendela Kayu Kelas I M3 3.21 7,626,750 24,454,411.20
2 Pek. Pintu Panil Kelas I m2 42.56 705,250 30,014,029.50
3 Pek. Daun Pintu Tripleks Lapis Formika m2 3.02 516,775 1,562,727.60
4 Pek. Daun Jendela Kaca Buka m2 62.35 538,700 33,586,436.64
5 Pek. Daun Vetilasi Kaca Buka m2 18.61 538,700 10,026,284.40
6 Pek. Daun Jendela Kaca Mati m2 34.96 223,606 7,817,095.62
TOTAL. B6 107,460,985
VII PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 Pek. Kunci Pintu Tanan dobel Set 4.00 244,425 977,700.00
2 Pek. Kunci Tanam Set 4.00 218,525 874,100.00
3 Pek. Kunci cilinder Set 4.00 218,525 874,100.00
4 Pek. Tarikan Pintu Dobel Set 4.00 133,688 534,750.00
5 Pek. Engsel Pintu Ps 19.00 46,106 876,018.75
6 Pek. Engsel Jendela Ps 26.00 40,738 1,059,175.00
7 Pek. Grendel Jendela Set 26.00 31,606 821,762.50
8 Pek. Hak Angin jendela dan ventilasi Set 26.00 31,606 821,762.50
TOTAL. B7 6,839,369
VIII. PEKERJAAN PLAFON DAN INTERIOR/EXTERIOR
a Pekerjaan Plafon
1 Pek. Plafon Gysum + Rangka, Lantai 1 m2 629.60 222,045 139,798,801.22
2 Pek. Plafon Triplex + Rangka, Lantai 1 m2 26.32 161,930 4,261,997.60
3 Pek. List Plafon Profil Gysum, Lantai 1 m 944.39 28,685 27,089,941.89
4 Pek. List Plafon Profil Kayu, Lantai 1 m 52.64 34,685 1,825,818.40
5 Pek. Plafon Gysum + Rangka, Lantai 2 m2 80.44 222,045 17,861,764.00
6 Pek. List Plafon Profil Gysum, Lantai 2 m 96.53 28,685 2,768,974.52
Sub Total B8.a 193,607,297.63
b Pekerjaan Exterior dan Interior
1 Pek. Railing tangga Lantai m 273.00 1,144,871.71 312,549,976.61
2 Pek. Railing Selasar Lantai m 135.00 1,144,871.71 154,557,680.74
3 Pek. Dinding Pembukus dan assessoris m2 469.06 594,737.50 278,965,192.80
4 Pek. Pasangan Batu Tempel m2 57.00 567,000.00 32,319,000.00
5 Pek. Saluran Keliling Bangunan m 220.00 405,597.83 89,231,522.91
Sub Total B8.b 867,623,373.07
TOTAL.B 8 1,061,230,671
IX PEKERJAAN MECANIKAL ELECTRICAL
a PEKERJAAN ELECTRICAL
1 Pek. Panel BH 2.00 2,500,000.00 5,000,000.00
2 Pek. Intralasi Penerangan + Armatur Ttk 135.00 515,607.50 69,607,012.50
Pek Instalasi Power Ac Ttk 8.00 1,219,750.00 9,758,000.00
3 Pek. Istalasi Stop Kontak Ttk 30.00 387,500.00 11,625,000.00
Sub Total B9.a 95,990,012.50
b PEKERJAAN MECANIKAL
1 Pek. Intalasi Pipa Air Bersih m 50.00 68,968.33 3,448,416.67
2 Pek. Intalasi Pipa Pembuangan Air Kotor m 24.00 60,270.00 1,446,480.00
3 Pek. Intalasi Pipa Pembuangan Air Hujan Pvc 4 Inc m 65.00 73,832.50 4,799,112.50
4 Pek. Intalasi Pipa Pembuangan Air Tinja Pvc 4 Inc m 24.00 73,832.50 1,771,980.00
5 Pek. Septiptank dan peresapan Unit 1.00 17,210,135.65 17,210,135.65
6 Pek. Klosed Jongkok Bh 4.00 829,700.00 3,318,800.00
7 Pek. Wastaffel Dinding Bh 4.00 1,347,250.00 5,389,000.00
8 Pek. Kran Air bh 4.00 51,650.00 206,600.00
9 Pek. Flour Drain bh 3.00 71,525.00 214,575.00
Pek. Orinoir bh 3.00 1,347,250.00 4,041,750.00
Sub Total B9.b 41,846,849.81
TOTAL B. 9 137,836,862

517211341.xlsx/Nas
1 2 3 4 5 6 7
X PEKERJAAN PENGECATAN
a Cat Tembok :
1 Pek. Cat Bagian Dalam dengan Interior m2 960.49 32,604.00 31,315,852.90
2 Pek. Cat Bagian Luar dengan Exterior (Mowilex) m2 1,200.61 45,604.00 54,752,797.04
3 Pek. Cat Plafon Gysum dan Plafon Triplex m2 736.36 40,907.00 30,122,196.71
Sub Total B10.a 116,190,846.64
b Cat Kayu dan Besi :
1 Pek. Cat Kusen Pintu dan jendela m2 64.13 51,257.50 3,287,040.96
2 Pek. Cat Daun Pintu m2 85.12 51,257.50 4,362,833.37
3 Pek. Cat Daun Jendela m2 80.96 51,257.50 4,149,766.19
4 Pek. Cat Lisplan kayu m2 1.60 51,257.50 82,012.00
5 Pek. Cat List Plafon profil kayu m2 80.96 5,126 414,976.62
6 Pek. Cat Meni Rangka Plafon Kayu m2 52.64 33,750 1,776,600.00
Sub Total B10.b 14,073,229.14
TOTAL. B10 130,264,076
XI PEKERJAAN KHUSUS PATUNG KRISTUS
a Pekerjaan Rangka Baja
1 Pek. Kolom baja HB 400x400 Kg 16,137.92 40,065 646,560,842.73
2 Pek. Balok Baja HB 600X200 Kg 12,122.29 40,065 485,675,700.45
3 Pek. Plat Simpul Aneka Ukuran Kg 1,500.00 40,065 60,097,042.50
4 Pek. Best Plat + Anchor Bolt Set 4.00 5,000,000 20,000,000.00
Sub Total B11.a 1,212,333,585.68
a Pembuatan Patung dengan Material dan Tenaga Khusus
1 Badan Patung m2 839.39 1,500,000 1,259,082,000.00
2 Kepala Patung m2 59.32 1,650,000 97,871,400.00
3 Assesories Ls 1.00 250,000,000 250,000,000.00
Alat Bantu Ls 1.00 250,000,000 250,000,000.00
Sub Total B11.b 1,856,953,400.00
TOTAL. B11 3,069,286,986
XII PEKERJAAN AKHIR
1 Biaya Pelaporan dan dokumentasi Ls 1.00 7,500,000.00 7,500,000.00
2 Biaya Pembersihan Akhir Ls 1.00 5,000,000.00 5,000,000.00
TOTAL. B12 12,500,000
TOTAL. B 19,620,274,346
C. BANGUNAN PENUNJANG
1 Kantor Permanen m2 400.00 8,500,000.00 3,400,000,000.00
2 Pengadaan Tenaga Listrik Ls 1.00 1,500,000,000.00 1,500,000,000.00
3 Pengadaan Air Bersih Ls 1.00 950,000,000.00 950,000,000.00
4 Sarana Olah Raga dan Pendidikan ls 1.00 2,885,000,000 2,885,000,000.00
5 Jalan dan Pelataran Ls 1.00 2,497,269,381 2,497,269,380.93
6 Lanscape ls 1.00 350,000,000 350,000,000.00
TOTAL. C 11,582,269,381

PENANGGUNG JAWAB

AGUSTINUS ANGGAIBAK

517211341.xlsx/Nas
perhitungan Panjang Lebar

1 Galian Pondasi
P1 2 2
P2 1.8 1.8
P3 1.6 1.6

Batu Kali 165 1


Galian slof luar 187.509341 0.5

Urugan Pasir
Bawah Bawah Pondasi
P1 2 2
P2 1.8 1.8
P3 1.6 1.6

Batu Kali 165 1


slof luar 187.509341 0.5

Urugan Pasir Bawah Lantai 55.5 35


Urugan Tanah bawah Lantai 55.5 35

Pek. Beton
PEKERJAAN PADA ELEVASI (BOC -3,15 S/D TOC. -0,05)
Lantai Kerja
Bawah Bawah Pondasi
P1 2 2
P2 1.8 1.8
P3 1.6 1.6

slof luar 187.509341 0.5

Beton rabat 55.5 35

Pondasi Poot Plat


P1
P2
P3

Pedestal Kolom
K1. Ø 50 (-2,60 s/d. -1,10) 1.5 0.19625
K1. Ø 50 (-2,60 s/d. -0,05) 2.45 0.19625

K2. 30/35 (-2,60 s/d. -1,10) 1.5 0.3


K2. 30/35 (-2,60 s/d. -0,05) 2.45 0.3

K3. 20/60 (-2,60 s/d. -1,10) 1.5 0.2


K3. 20/60 (-2,60 s/d. -0,05) 2.45 0.2

K4.15/30 (-2,60 s/d. -1,10) 1.5 0.2

Slof
S1 (-0,05 & -1,10) 0.25 0.4
S2 (-1,10) 0.2 0.35

S3 0.15 0.2

PEKERJAAN PADA ELEVASI (BOC -5,05 - S/D TOC.3,92)


Kolom
K1. Ø 50 (-1,1 s/d. +3,92) 5.02 0.19625
K1. Ø 50 (-0,05 s/d. -3,92) 3.97 0.19625

K2. 30/35 (-1,1 s/d. +3,92) 5.02 0.3


K2. 30/35 (-0,05 s/d. -3,92) 3.97 0.3

K3. 20/60 (-1,1 s/d. +3,92) 5.02 0.2


K3. 20/60 (-0,05 s/d. -3,92) 3.97 0.2

5.55 K4.20/40 (-1,1 s/d. +3,92) 5.55 0.2

K5.20/20 (-1,1 s/d. +4,45) 5.02 0.2


K5.20/20 (-0,05 s/d. -3,92) 3.97 0.2

Tangga beton
Tangga Dalam 2 Unit
Tangga Luar 2 Unit

Balok Lantai B1 .30/45 +3,92 239.14814815 0.3


Balok Lantai B2. 20/30 +3,93 109.7 0.2
Konsol Beton (kb)
Lisplan Beton Pembatas Plafond
Ring Balk Rb1. 30/45 +3,92 83.681481481 0.3
Ring Balk Rb1a. 25/50 +3,93 37.136 0.25
Ring Balk Rbd.
Rbs (20/30)
Ring Balk Rb3. 15/50 +2,92 107.12 0.15
Plat Lantai 2 (+3.92)

PEKERJAAN PADA ELEVASI (TOC.3,92 S/D +22.25 )


Kolom
K2. 30/35 (3.92 s/d. +7.00) 3.0798534799 0.3
K5.20/20 (7.00 s/d. +12.03 dan +22,25) 5.5583333333 0.2
K3. 20/60 (+3,92 s/d 16.93) var 0.2
Ring Balk Rb4. 20/40 +7.0 29.495833333 0.2
Ring Balk Rb2. 20/30 +7.0 3.9166666667 0.2
Ring Balok Sopy2 Depan RBS
Ring Balok Sopy2 Samping RB1
Konsol Beton KB3,KB4
Lisplan Beton Besar

Kanopy Depan (+6.80)


Balok Lantai B1 .30/45 +6.80 Kanopy
Konsol Kanopy (Kb2)
Plat Kanopy
Lisplan Kanopy

PEKERJAAN BETON MENARA BESAR PADA ELEVASI (TOC.7.00 S/D +27.92)


K1. Ø 50)
K6.25/25
Balok Lantai 25/35
Balok lantai 15/25
RingbalkRB2 . 20/30 (puncak)
Plat Lantai

PEKERJAAN BETON MENARA KECIL PADA ELEVASI (TOC.7.00 S/D +19,32)


K1. Ø 50)
K2.30/35
Ringbalk rb2 20/30
Ringbalk 20/30 (puncak)
K5.20/20
Plat Lantai Atap

PEKERJAAN PASANGAN DAN PLESTERAN


Pekerjaan Lantai I
Batu Kosong 165 1
Pondasi Batu Kali 165 0.45
Pas. Trassraam 1:3 69.027 1
Pasangan Dinding Batu Tela 1 :4 48.873 1
Plesteran Trasramm 172.5675 1
Plesteran Dinding 1:4 488.73 1
Plesteran Beton 1 : 3 345.135 1
Acian Dinding Dan Beton 1,322.60 1
Pasangan Keramik Lantai (60x60)
Lantai dalam
131.89 Aula 833.76375 1
77.6 Podiunm 156.17511 1
32.95 R. Pendeta 50.5411 1
32.95 R. Majelis 50.5411 1
33.86 Tras Depan 64.867 1
70 Teras Samping 59.945 1
205.538 Sealasr 81.9165 1
584.788
Pasangan Keramik Tangga (60x60)
Tangga dalam (anak) 5.3 1.7
Bordes 1.7 1.7
Tangga Altar 1.43 16.54
Tangga Teras Depan 2.57 5.1
Tanggaa Teras Samping 2.57 8.7
Tangga Selasar 1.23 2.85
2.615 1
Tangga Belakang 12.414 2.45

Pasangan Keramik Lantai Km/WC (20x20) 1.5 2


Pasangan Keramik Dinding Km/WC (20x25) 7 1.75
Pas. Plin Keramik 10x60 584.788 1

Profilan Lisplan
Profilan Kolom

B. Pekerjaan Lantai 2
1 Pek. Pasangan Dinding Batu Tela 1 :4 52.111 1
2 Pek. Plesteran Dinding 1:4 521.11 1
3 Pek. Plesteran Beton 1 : 3 208.444 1
4 Pek. Acian Dinding Dan Beton 1250.664 1
5 Pek. Pasangan Keramik Lantai (60x60) 445.7442 1
Pas. Plin Keramik 10x60 164.35 1
6 Pek. Profilan Lisplan
7 Pek. Profilan Kolom

Pekerjaan Menara Besar


Pekerjaan Menara Besar
Pasangan Dinding Batu Tela 1 :4 24
Plesteran Dinding 1:4 240
Plesteran Beton 1 : 3 40
Acian Dinding Dan Beton 280
Profilan Beton

PEKERJAAN KOSEN, PINTU DAN JENDELA


Pekerjaan Lantai I
Kosen Pintu Dan Jendela Kayu Kelas I 2
Pintu papan Panil Kelas I Bh Pintu Lebar
P1 1 0.82
p2 5 0.82
p3 4 0.82
pj 4 0.82

Daun Pintu Tripleks Lapis Formika P4) 2 0.72


Daun Jendela Kaca Buka Bh
pj 4 0.72
j1 10 0.82
j2 4 0.72
j3 4 0.72
j4 2 0.72

Daun ventilasi kaca buka


p2 5 0.82
p3 4 0.82
j1 10 0.82
j2 4 0.72
j3 4 0.72
j4 2 0.72
v3 2 0.82

Daun Jendela Kaca Mati


pj 4 0.72
v1 14 0.62
v2 42 0.62

V. PEKERJAAN PENGGANTUNG DAN PENGUNCI


Pek. Kunci Tanam Pintu dobel
p1 11
p2 51
pj 41

Pek. Kunci Tanam Biasa--P3 41


Pek. Kunci cilinder 21
Pek. Tarikan Pintu Dobel 10 1
Pek. Engsel Pintu
p1 1 1.5
p2 5 1.5
p3 4 1.5
p4 2 1.5
pj 4 1.5

Pek. Engsel Jendela


p1 0
p2 0
p3 0
p4 0
pj 41
j1 10 1
j2 41
j3 41
j4 21
Engsel Ventilasi
p1 0
p2 52
p3 41
p4 0
j1 10 2
j2 41
j3 41
j4 21
v3 21

Pek. Grendel Jendela


Pek. Hak Angin jendela dan ventilasi

VI. PEKERJAAN PLAFON DAN ATAP


Pek. Rangka kuda-kuda baja Bh Mtr

KKB1 6
7,38 KG/M L. 70.70.7 47.447
5,42 KG/M L.60.60.6
Kk.atas 49.518
Skor-datar/tegak 62.543
skor miring 10.608

32,29 kg/m2 Plat 8mm 3.69231


kkb2

Uraian perhitungan berat baja kuda2 Bh m


kkb1 6 35.12
kkb2 2 15.14
kkb2a 2 10.25
kkb3 4 9.96
kkb4 2 15.29
kkb4a 1 15.38
kkb5 2 15.15
kb5a 1 10.005
ks1 4 5.1
ks2 8 2.56

Meni besi
4,06 KG/M Pek. Gording LIP Cannal 100X50X2X2,3 Kg
37,011
38,922
40,750
42,570
44,406
46,234
48,062
49,890
51,718
53,546
55,374
24,643
24,935
19,548
21,162
22,790
1.07693034684812 24,543
26,431
28,465
30,655
33,013
35,552
68,970
72,729
104% 75,558
78,497
81,550
84,723
88,018
91,442
94,999
98,694
102,533
106,521
110,665
114,969
119,441

Baja Penarik (Terstang) Kg


Papan Lisplan Kayu Besi 175

Balok Bubungan atap kayu besi 5/10 130 0.05


Talang 21 3
Nok atap spandek 130 1.2
Luasan Atap koif =(1.40735332)
=(1.40735332) Luas Koif
1 695 1.42
2 252 1.42
3 53 1.42
4 18 1.42

Pek. Plafon Gysum + Rangka, Lantai 1


Pek. Plafon Triplex + Rangka, Lantai 1
Pek. List Plafon Profil Gysum, Lantai 1
Pek. List Plafon Profil Kayu, Lantai 1

Pek. Railing tangga dan Selasar Latai 1


r1 8.52 2
r2 7.87 2
r3 11.44 2
r4 9.11 2
r5 6.42 2

Pek. Railing Balkon Lantai 2


r6 35.42 1
r7 8.37 2

Lt
R1 50.40 1
R2 44.67 1
r2 43.79 1

Uraian Pek 1m railing


kayu 10/10 tiang 0.209 m 0.1
kayu 5/5
Tiang 0.837 m 0.05
Melintang 2.000 m 0.05
Tegak 22.400 m 0.05
Paku 0.209 kg
Cat Kayu 5.089 m2
Tinggi Jumlah

2.15 36 309.60
2.12 28 192.33
2.15 16 88.06
589.99

0.6 1 99.00
0.5 1 46.88
145.88
735.87 m3

0.1 36 14.40
0.1 28 9.07
0.1 16 4.10
27.57

0.1 1 16.50
0.1 1 9.38
25.88
53.44 m3

0.1 1 194.25 m3
0.8 1 1,554.00 m3

0.05 36 7.20
0.05 28 4.54
0.05 16 2.05
13.78
0.05 1 4.69
m3
0.07 1 135.98 m3

35.28
20.02
6.40
61.70 m3
Solid
1 12.00 3.53 3.06
1 16.00 7.69 7.70
10.76
0.35 2.00 0.315 0.32
0.35 28.00 7.203 7.20
7.52
0.6 0 -
0.6 6.00 1.764 1.76

0.4 16.00 1.920 1.81

22.43 m3

389.13 1.00 38.913 38.91


135.30 1.00 9.471 9.47
48.38
37.53 1.00 1.126 1.13

Solid
1 12.00 11.82 11.95
1 18.00 14.02 14.03
25.98
0.35 2.00 1.054 1.05
0.35 28.00 11.672 11.53
12.58
0.6 0 -
0.6 6.00 2.858 2.86

0.4 16.00 7.104 6.66

0.2 4.00 0.803 0.80


0.2 2.00 0.318 0.31
1.12
48.53 m3

6.73
11.63
18.36

0.45 1.00 32.285 32.29


0.3 1.00 6.582 6.58
0.68
3.63
0.45 1.00 11.297 11.30
0.5 1.00 4.642 4.64
7.82

0.5 1.00 8.034 8.03 8,034


45.47

0.35 26.00 8.408 8.41


0.2 3.00 0.667 0.67
0.6 6 7.57
0.4 6 14.158 14.16
0.3 6 1.410 1.41
2.12
1.64
1.11
9.39

2.447
1.586
2.65
13.246
19.93
.7.00 S/D +27.92)
15.708
1.00
7.694
1.772
1.08
14.745

7.00 S/D +19,32)


9.425
5.056
6.461
1.044
1.12
2.613

0.2 1 33.00 m3
0.8 1 59.40 m3
1 1 69.03 m3
1 1 48.87 m3
1 1 172.57 m2
1 2 977.46 m2
1 1 345.14 m2
1 1 1,322.60 m2

m2
1 1 833.76
1 1 156.18
1 1 50.54
1 1 50.54
1 1 64.87
1 2 119.89
1 2 163.83
1,439.61 m2

1 4 36.04
1 2 5.78
1 1 23.65
1 1 13.11
1 2 44.72
2 2 14.02
2 2 10.46
2 2 121.66
269.44 m2
1 2 6.00 m2
1 2 24.50 m2
1 1 584.79

1 1 52.11
1 1 521.11
1 1 208.44
1 1 1,250.66
1 1 445.74 Area = 2941542.7, Length = 9210.0
1 1 164.35 Area = 1515922.0, Length = 7224.5

Tinggi Lembar luas


2.85 2 4.67 m2
2.1 2 17.22 m2
2.1 1 6.89 m2
2.1 2 13.78 m2 Cat
42.56 m2 87.24 m2
2.1 1 3.02 m2 6.20 m2

0.88 4 10.14 m2
1.52 3 37.39 m2
1.47 2 8.47 m2
1.47 1 4.23 m2
1.47 1 2.12 m2
62.35 m2

0.47 2 3.85 m2
0.47 1 1.54 m2
0.47 2 7.71 m2
0.47 2 2.71 m2
0.47 1 1.35 m2
0.47 1 0.68 m2
0.47 1 0.77 m2
18.61 m2
0.47 8 10.83 m2
0.92 1 7.99
0.62 1 16.14
34.96 m2

1 1 1.00 Ps
1 1 5.00 Ps
1 1 4.00 Ps
10.00 Ps
1 1 4.00 Ps
1 1 2.00 Ps
1 1 10.00 Ps

1 2 3.00 Ps
1 2 15.00 Ps
1 1 6.00 Ps
1 1 3.00 Ps
1 2 12.00 Ps
39.00 Ps

1 4 16.00 Ps
1 2 20.00 Ps
1 3 12.00 Ps
1 1 4.00 Ps
1 1 2.00 Ps

1 1 10.00 Ps
1 1 4.00 Ps
- Ps
1 1 20.00 Ps
1 3 12.00 Ps
1 1 4.00 Ps
1 1 2.00 Ps
1 1 2.00 Ps
108.00 Ps
108.00 Ps
108.00 Ps

Kg/m

7.38 2 700.32 32.58%

5.42 2 536.78
5.42 2 677.97
5.42 2 114.99
1,329.73 0.6 61.87%
32.29 1 119.22 5.55%
2,149.27 kg 100.00% panjang kuda2 kkb1 tampak atas =35,12m

kkb2 15.14 2 30.28


kkb2a 10.25 2 20.5
kkb3 9.96 4 39.84
kkb4 15.29 2 30.58
kkb4a 15.38 1 15.38
kkb5 15.15 2 30.3
kb5a 10.005 1 10.005
ks1 5.1 4 20.4
ks2 2.56 8 20.48

L. 70.70.7 L.60.60.6 Plat 8mm Total


4,201.91 7,978.39 715.35 12,895.65 kg
603.80 1,146.48 102.79 1,853.08 kg
408.78 776.18 69.59 1,254.56 kg
794.44 1,508.44 135.25 2,438.13 kg
609.79 1,157.84 103.81 1,871.44 kg
306.69 582.33 52.21 941.23 kg
604.20 1,147.23 102.86 1,854.30 kg
199.51 378.81 33.96 612.29 kg
406.79 772.40 69.25 1,248.44 kg
408.39 775.42 69.53 1,253.34 kg
8,544.29 16,223.53 1,454.61 - 26,222.43 kg
1,157.764 m 2,993.27 m 45.05 m2
680.8 1,508.6 90.1 2,279.5 m2

37.011 2 74.022
38.922 2 77.844
40.75 2 81.5
42.57 2 85.14
44.406 2 88.812
46.234 2 92.468
48.062 2 96.124
49.89 2 99.78
51.718 2 103.436
53.546 2 107.092
55.374 2 110.748
24.643 2 49.286
24.935 2 49.87
19.548 2 39.096
21.162 2 42.324
22.79 2 45.58
24.5432426 2 49.08648521
26.43136277 2 52.86272554
28.46473668 2 56.92947335
30.65453874 2 61.30907748
33.01280304 2 66.02560608
35.55248943 2 71.10497886
68.97 1 68.97
72.729 1 72.729
75.558 1 75.558
78.49704195 1 78.49704195
81.55040624 1 81.55040624
84.72253977 1 84.72253977
88.0180624 1 88.0180624
91.44177369 1 91.44177369
94.9986599 1 94.9986599
98.69390126 1 98.69390126
102.5328795 1 102.5328795
106.5211856 1 106.5211856
110.6646282 1 110.6646282
114.9692416 1 114.9692416
119.4412952 1 119.4412952
2,989.75 m 12,138.38 kg
cat meni 1,209.65 m2

1.3 1 227.31 m
cat 181.85 m2
0.1 1 0.65 m3
1 1 63.95 m
1 1 155.45 m

fakt lempeng
1 2 1972.49928
1 1 357.56878
1 6 452.65056
1 2 49.9272
2,832.65 m2

17.03
15.75
22.87
18.22
12.83
86.70 m

35.42
16.74
52.16 m
138.86

50.40 m
44.67 m
43.79 m

0.1 1 0.00209205

0.1 1 0.0041841
0.1 1 0.01
0.1 1 0.112
0.1261841 m3
Slof S1

Slof S2

Slof S1

k1
k2

k3

k4
kp
k5
19.94

15.28
19.30
3.27

3.39
61.20 per m Patokan

1,853.08 kg
1,254.56 kg
2,438.13 kg
1,871.44 kg
941.23 kg
1,854.30 kg
612.29 kg
1,248.44 kg
1,253.34 kg
13,326.79 15,476.06
UKURAN
P L
m m

Beton K225 m3 1.4 1.4


D19 39.92 m
D16 33.97 m
Ø 12 5.40 m
P1
Ø 10 - m
Ø8 - m

Bawah 39.918667
atas 33.973333

Beton K225 m3 1.2 1.2


D19 30.80 m
D16 25.81 m
Ø 12 4.50 m
P2
Ø 10 - m
Ø8 - m

Bawah 30.8
atas 25.813333

Beton K225 m3 1 1
D19 21.66 m
D16 19.76 m
Ø 12 3.70 m
P3
Ø 10 - m
Ø8 - m

Bawah 21.66
atas 19.76

S1
Beton K225 0.1 m3 1 0.25
D19 7.00 m
S1
D16 - m
Ø 12 2.00 m
Ø 10 12.00 m
Ø8 - m
Beton K225 m3 1 0.2
D19 m
D16 4 m
Ø 12 2 m
S2
Ø 10 10 m
m

Beton K225 m3 1 0.15


D19 - m
D16 - m
Ø 12 2.00 m
S3
Ø 10 m
Ø8 6 m

Beton K225 m3 1 0.5024


D19 16.00 m
D16 - m
Ø 12 - m
K1 D80
Ø 10 36.325 m
Ø8 m

Beton K225 m3 1 0.5024


D19 12.00 m
D16 - m
Ø 12 - m
K1 D70
Ø 10 27.533 m
Ø8 m

Beton K225 m3 1 0.3


D19 - m
D16 10.00 m
Ø 12 - m
K2
Ø 10 12.000 m
Ø8 - m

Beton K225 m3 1 0.2


D19 - m
D16 8.00 m
Ø 12 - m
K3
Ø 10 15.000 m
Ø8 - m

Beton K225 m3 1 0.2


D19 - m
D16 6.00 m
K4
Ø 12 - m
K4
Ø 10 11.000 m
Ø8 - m

Beton K175 m3 1 0.2


D19 - m
D16 - m
Ø 12 4.00 m
K5
Ø 10 - m
Ø8 7.000 m

Beton K175 m3 1 0.12


D19 - m
D16 - m
Ø 12 4.00 m
KP
Ø 10 - m
Ø8 3.800 m

Beton K175 m3 1 0.12


D19 - m
D16 - m
Ø 12 4.00 m
KP
Ø 10 - m
Ø8 3.800 m

UKURAN
P L
m m

Balok
B1

Beton K225 m3 1 0.3


D19 9.00 m
D16 - m
Ø 12 2.00 m
Ø 10 14.000 m
Ø8 - m

BALOK B2. (20/30) Beton K225 m3 1 0.2


D19 - m
D16 5.00 m
Ø 12 - m
Ø 10 6.667 m
Ø8 - m
Ring Balok RB1. (30/45) Beton K225 m3 1 0.3
D19 - m
D16 8.00 m
Ø 12 2.00 m
Ø 10 14.000 m
Ø8 - m

Ring Balok RB1a. (20/50) Beton K225 m3 1 0.2


D19 - m
D16 6.00 m
Ø 12 4.00 m
Ø 10 14.000 m
Ø8 - m

Ring Balok RB2. (20/30) Beton K225 m3 1 0.2


D19 - m
D16 5.00 m
Ø 12 - m
Ø 10 7.333 m
Ø8 - m

Ring Balok RB3. (15/50) Beton K225 m3 1 0.15


D19 - m
D16 4.00 m
Ø 12 4.00 m
Ø 10 11.000 m
Ø8 - m

Ring Balok RB4. (20/40) Beton K225 m3 1 0.2


D19 - m
D16 4.00 m
Ø 12 2.00 m
Ø 10 7.333 m
Ø8 - m

Konsol KB
0.085 8 Bh
Beton K225 m3 1 0.085
D19 15.76 m
D16 m
Ø 12 2.90 m
Ø 10 8.480 m
Ø8 - m

Tul. atas D19 2.233 5 11.165


Tul. bawah D19 1.53 3 4.59
Tul Samping 12 1.45 2 2.9

Begel 10 1.33 1 1.33


1.29 1 1.29
1.26 1 1.26
1.2 1 1.2
1.16 1 1.16
1.12 2 2.24
8.48

Lisplan Beton Pembatas Plafond


3.628 87.211538 m
Beton K225 m3 1 0.08
D19 - m
D16 m
Ø 12 1.20 m
Ø 10 9.000 m
Ø8 - m

Beton plat lantai


0m
Beton K225 m3 1 1
D19 - m
D16 m
Ø 12 - m
Ø 10 40.000 m
Ø8 - m

Beton plat rbd


0m
Beton K225 m3 1 1
D19 - m
D16 2.00 m
Ø 12 2.00 m
Ø 10 40.000 m
Ø8 - m
K1. Ø 50 (-2,60 s/d. -1,10)
K1. Ø 50 (-2,60 s/d. -0,05)
K2. 30/35 (-2,60 s/d. -1,10)
K2. 30/35 (-2,60 s/d. -0,05)
K3. 20/60 (-2,60 s/d. -1,10)
K3. 20/60 (-2,60 s/d. -0,05)
K4.15/30 (-2,60 s/d. -1,10)
Slof
S1 (-0,05 & -1,10)
S2 (-1,10)
S3
Kolom
K1. Ø 50 (-1,1 s/d. +3,92)
K1. Ø 50 (-0,05 s/d. -3,92)
K2. 30/35 (-1,1 s/d. +3,92)
K2. 30/35 (-0,05 s/d. -3,92)
K3. 20/60 (-1,1 s/d. +3,92)
K3. 20/60 (-0,05 s/d. -3,92)
K4.20/40 (-1,1 s/d. +3,92)
K5.20/20 (-1,1 s/d. +4,45)
K5.20/20 (-0,05 s/d. -3,92)
Tangga beton
Tangga Dalam 2 Unit
Tangga Luar 2 Unit
Balok Lantai B1 .30/45 +3,92
Balok Lantai B2. 20/30 +3,93
Konsol Beton (kb)
Lisplan Beton Pembatas Plafond
Ring Balk Rb1. 30/45 +3,92
Ring Balk Rb1a. 25/50 +3,93
Ring Balk Rbd.
Rbs (20/30)
Ring Balk Rb3. 15/50 +2,92
Plat Lantai 2 (+3.92)

PEKERJAAN PADA ELEVASI (TOC.3,92 S/D +22.25 )


Kolom
K2. 30/35 (3.92 s/d. +7.00)
K5.20/20 (7.00 s/d. +12.03 dan +22,25)
K3. 20/60 (+3,92 s/d 16.93)
Ring Balk Rb4. 20/40 +7.0
Ring Balk Rb2. 20/30 +7.0
Ring Balok Sopy2 Depan RBS
Ring Balok Sopy2 Samping RB1
Konsol Beton KB3,KB4
Lisplan Beton Besar

Kanopy Depan (+6.80)


Balok Lantai B1 .30/45 +6.80 Kanopy
Konsol Kanopy (Kb2)
Plat Kanopy
Lisplan Kanopy

PEKERJAAN BETON MENARA BESAR PADA ELEVASI (TOC.7.00 S/D +27.92)


K1. Ø 50)
K6.25/25
Balok Lantai 25/35
Balok lantai 15/25
RingbalkRB2 . 20/30 (puncak)
Plat Lantai

PEKERJAAN BETON MENARA KECIL PADA ELEVASI (TOC.7.00 S/D +19,32)


K1. Ø 50)
K2.30/35
Ringbalk rb2 20/30
Ringbalk 20/30 (puncak)
K5.20/20
Plat Lantai Atap
UKURAN Volume BESI BETON
Bekisting
T Panjang (m/m3)
(m3/m) (m/m3) (m2/m3)
m
D19 D16 Ø 12 Ø 10 Ø8

0.5 0.980 1.020 3.878 44.807 38.133 6.061 - -

0.5 0.720 1.389 4.722 47.056 39.437 6.875 - -

0.4 0.400 2.500 7.000 59.565 54.340 10.175 - -


0.4 0.100 10.000 8.000 77.000 - 22.000 132.000 -

0.35 0.070 14.286 10.000 - 62.857 31.429 157.143 -

0.2 0.030 33.333 13.333 - - 73.333 - 220.000

1 0.502 1.990 8.000 35.032 - - 79.533 -

1 0.502 1.990 7.031 26.274 - - 60.283 -

0.35 0.105 9.524 12.381 - 104.762 - 125.714 -

0.6 0.120 8.333 13.333 - 73.333 - 137.500 -

0.4 0.080 12.500 15.000 - 82.500 - 151.250 -


0.2 0.040 25.000 20.000 - - 110.000 - 192.500

0.12 0.014 69.444 33.333 - - 305.556 - 290.278

0.12 0.014 69.444 33.333 - - 305.556 - 290.278

UKURAN Volume BESI BETON


Bekisting
T Panjang (m/m3)
(m3/BH) (BH/m3) (m2/m3)
m
D19 D16 Ø 12 Ø 10 Ø8

0.45 0.135 7.407 8.889 73.333 - 16.296 114.074 -

0.3 0.060 16.667 13.333 - 91.667 - 122.222 -


0.45 0.135 7.407 8.889 - 65.185 16.296 114.074 -

0.5 0.100 10.000 12.000 - 66.000 44.000 154.000 -

0.3 0.060 16.667 13.333 - 91.667 - 134.444 -

0.5 0.075 13.333 15.333 - 58.667 58.667 161.333 -

0.4 0.080 12.500 12.500 - 55.000 27.500 100.833 -

bh/m3
1 0.085 11.765 20.235 203.888 - 37.529 109.741 -
m/m3
0.52 0.042 24.038 26.923 - - 31.731 237.981 -

m/m3
0.12 0.120 8.333 8.333 - - - 366.667 -

m/m3
0.2 0.200 5.000 10.000 - 11.000 11.000 220.000 -
BESI BETON
Berat (Kg/m3)
D19 D16 Ø 12 Ø 10 Ø8 Jumlah
2.225565 1.57824 0.88776 0.6165 0.39456 (kg)

99.720 60.184 5.381 - - 165.285

104.725 62.241 6.103 - - 173.070

132.566 85.762 9.033 - - 227.360


171.369 - 19.531 81.378 - 272.277

- 99.204 27.901 96.879 - 223.983

- - 65.102 - 86.803 151.906

77.966 - - 49.032 - 126.998

58.474 - - 37.165 - 95.639

- 165.339 - 77.503 - 242.842

- 115.738 - 84.769 - 200.506

- 130.205 - 93.246 - 223.450


- - 97.654 - 75.953 173.606

- - 271.260 - 114.532 385.792

- - 271.260 - 114.532 385.792

BESI BETON
Berat (Kg/m3)
D19 D16 Ø 12 Ø 10 Ø8 Jumlah
2.225565 1.57824 0.88776 0.6165 0.39456 (kg)

163.208 - 14.467 70.327 - 248.002

- 144.672 - 75.350 - 220.022


- 102.878 14.467 70.327 - 187.672

- 104.164 39.061 94.941 - 238.166

- 144.672 - 82.885 - 227.557

- 92.590 52.082 99.462 - 244.134

- 86.803 24.413 62.164 - 173.380

453.767 - 33.317 67.655 - 554.739


- - 28.169 146.715 - 174.884

- - - 226.050 - 226.050

- 17.361 9.765 135.630 - 162.756


DAFTAR ANALISA PEKERJAAN
PEKERJAAN PERSIAPAN
RSNI T-15-2002.1
1 m' Pagar sementara dari seng gelombang tinggi 2 m
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu Kelas II (Balok) btg 0.030 Rp. 2,000,000.00 Rp. Rp. 60,000.00
Portland Semen kg 2.500 Rp. 1,700.00 Rp. Rp. 4,250.00
Atap Seng Super Deck3'x6' bjls 0,30 lbr 1.200 Rp. 80,000.00 Rp. Rp. 96,000.00
Pasir pasang m3 1.200 Rp. 400,000.00 Rp. Rp. 480,000.00
Bahan
Kerikil beton m3 0.009 Rp. 450,000.00 Rp. Rp. 4,050.00
Kayu Kelas II (Papan) m3 0.072 Rp. 2,200,000.00 Rp. Rp. 158,400.00
Paku biasa kg 0.060 Rp. 20,000.00 Rp. Rp. 1,200.00
Meni besi Lt 0.450 Rp. 28,900.00 Rp. Rp. 13,005.00
Pekerja Oh 0.400 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.200 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.020 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.020 Rp. Rp. 150,000.00 Rp.
816,905.00
Jumlah harga =
Pembulatan =

RSNI.T-15-2002.2
1 m' Pek. Pengukuran & pemasangan Bowplank
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu Kelas II (Balok) btg 0.012 Rp. 2,000,000.00 Rp. Rp. 24,000.00
Bahan Paku biasa kg 0.020 Rp. 20,000.00 Rp. Rp. 400.00
Kayu Kelas II (Papan) m3 0.007 Rp. 2,200,000.00 Rp. Rp. 15,400.00
Pekerja Oh 0.100 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.100 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.010 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.005 Rp. Rp. 150,000.00 Rp.
39,800.00
Jumlah harga =
Pembulatan =

RSNI.T-15-2002.3
1 m2 Pek. Kantor direksi keet dengan lantai plesteran
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu Dolken Ǿ 8-10 m' 5.625 Rp. 25,000.00 Rp. Rp. 140,625.00
Kayu Kelas II (Balok) m3 0.180 Rp. 2,000,000.00 Rp. Rp. 360,000.00
Paku biasa kg 0.850 Rp. 20,000.00 Rp. Rp. 17,000.00
Besi Strip kg 1.100 Rp. 14,800.00 Rp. Rp. 16,280.00
Portland Semen kg 35.000 Rp. 1,700.00 Rp. Rp. 59,500.00
Pasir pasang m3 0.250 Rp. 400,000.00 Rp. Rp. 100,000.00
Bahan Kerikil beton m3 0.150 Rp. 450,000.00 Rp. Rp. 67,500.00
Batu Tela bh 30.000 Rp. 2,300.00 Rp. Rp. 69,000.00
Seng Gelombang BJLS 32 lbr 1.500 Rp. 64,000.00 Rp. Rp. 96,000.00
Kaca Nako Set 0.500 Rp. 175,900.00 Rp. Rp. 87,950.00
Kaca Polos m2 0.080 Rp. 157,800.00 Rp. Rp. 12,624.00
Kunci Tanam Biasa bh 0.150 Rp. 97,900.00 Rp. Rp. 14,685.00
Tripleks 6mm lbr 0.060 Rp. 84,700.00 Rp. Rp. 5,082.00
Pekerja Oh 2.000 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 2.000 Rp. Rp. 110,000.00 Rp.
Tenaga Tukang Batu Oh 1.000 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.300 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.050 Rp. Rp. 150,000.00 Rp.
1,046,246.00
Jumlah harga =
Pembulatan =
RSNI.T-15-2002.4
1 m2 Pembuatan gudang sementara dan alat-alat
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu Dolken Ǿ 8-10 m' 7.650 Rp. 25,000.00 Rp. Rp. 191,250.00
Kayu Kelas II (Balok) m3 0.210 Rp. 2,000,000.00 Rp. Rp. 420,000.00
Paku biasa kg 0.300 Rp. 20,000.00 Rp. Rp. 6,000.00
Bahan Portland Semen kg 10.500 Rp. 1,700.00 Rp. Rp. 17,850.00
Pasir pasang m3 0.030 Rp. 400,000.00 Rp. Rp. 12,000.00
Kerikil beton m3 0.050 Rp. 450,000.00 Rp. Rp. 22,500.00
Seng Gelombang BJLS 32 lbr 1.500 Rp. 64,000.00 Rp. Rp. 96,000.00
Pekerja Oh 1.000 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 2.000 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.200 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.050 Rp. Rp. 150,000.00 Rp.
765,600.00
Jumlah harga =
Pembulatan =

RSNI.T-15-2002.5
1 m2 Pembuatan rumah jaga konstruksi kayu
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu Dolken Ǿ 8-10 m' 13.500 Rp. 25,000.00 Rp. Rp. 337,500.00
Kayu Kelas II (Balok) m3 0.276 Rp. 2,000,000.00 Rp. Rp. 552,000.00
Bahan
Paku biasa kg 0.700 Rp. 20,000.00 Rp. Rp. 14,000.00
Seng Gelombang BJLS 32 lbr 1.500 Rp. 64,000.00 Rp. Rp. 96,000.00
Pekerja Oh 1.000 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 1.500 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.150 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.050 Rp. Rp. 150,000.00 Rp.
999,500.00
Jumlah harga =
Pembulatan =

RSNI.T-15-2002.6
1 m2 Membersihkan lapangan dan perataan
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Pekerja Oh 0.100 Rp. Rp. 100,000.00 Rp.
Tenaga
Mandor Oh 0.050 Rp. Rp. 150,000.00 Rp.
0.00
Jumlah harga =
Pembulatan =

RSNI.T-15-2002.7
1 m2 Pembuatan bedeng buruh
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu Dolken Ǿ 8-10 m' 5.625 Rp. 25,000.00 Rp. Rp. 140,625.00
Kayu Kelas II (Balok) m3 0.186 Rp. 2,000,000.00 Rp. Rp. 372,000.00
Paku biasa kg 0.300 Rp. 20,000.00 Rp. Rp. 6,000.00
Bahan Portland Semen kg 18.000 Rp. 1,700.00 Rp. Rp. 30,600.00
Pasir pasang m3 0.030 Rp. 400,000.00 Rp. Rp. 12,000.00
Kerikil beton m3 0.050 Rp. 450,000.00 Rp. Rp. 22,500.00
Seng Gelombang BJLS 32 lbr 1.500 Rp. 64,000.00 Rp. Rp. 96,000.00
Tripleks 6mm lbr 1.350 Rp. 84,700.00 Rp. Rp. 114,345.00
Pekerja Oh 1.000 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 2.000 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.200 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.050 Rp. Rp. 150,000.00 Rp.
794,070.00
Jumlah harga =
Pembulatan =

PEKERJAAN TANAH
SNI.DT 91-0006-2007.6.1
Menggali 1 m3 tanah biasa sedalam 1 meter
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Pekerja Oh 0.750 Rp. Rp. 100,000.00 Rp.
Tenaga
Mandor Oh 0.025 Rp. Rp. 150,000.00 Rp.
0.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0006-2007.6.2
Menggali 1 m3 tanah biasa sedalam 2 meter
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Pekerja Oh 0.900 Rp. Rp. 100,000.00 Rp.
Tenaga
Mandor Oh 0.045 Rp. Rp. 150,000.00 Rp.
0.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0006-2007.6.3
Menggali 1 m3 tanah biasa sedalam 3 meter
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Pekerja Oh 1.050 Rp. Rp. 100,000.00 Rp.
Tenaga
Mandor Oh 0.067 Rp. Rp. 150,000.00 Rp.
0.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0006-2007.6.5
Menggali 1 m3 tanah cadas sedalam 1 meter
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Pekerja Oh 1.500 Rp. Rp. 100,000.00 Rp.
Tenaga
Mandor Oh 0.060 Rp. Rp. 150,000.00 Rp.
0.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0006-2007.6.6
Menggali 1 m3 tanah lumpur sedalam 1 meter
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Pekerja Oh 1.200 Rp. Rp. 100,000.00 Rp.
Tenaga
Mandor Oh 0.045 Rp. Rp. 150,000.00 Rp.
0.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0006-2007.6.7
Mengerjakan 1 m2 stripping tebing setinggi 1 meter
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Pekerja Oh 0.050 Rp. Rp. 100,000.00 Rp.
Tenaga
Mandor Oh 0.005 Rp. Rp. 150,000.00 Rp.
0.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0006-2007.6.8
Membuang 1 m3 tanah sejauh 30 meter
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Pekerja Oh 0.330 Rp. Rp. 100,000.00 Rp.
Tenaga
Mandor Oh 0.010 Rp. Rp. 150,000.00 Rp.
0.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0006-2007.6.9
Mengurug kembali 1 m3 galian
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Mengurug kembali 1 m3 galian dihitung dari 1/3 kali upah pekerjaan
Menggali 1 m3 tanah biasa sedalam 3 meter Jumlah harga =
Pembulatan =

SNI.DT 91-0006-2007.6.10
Memadatkan 1 m3 tanah (per 20 cm)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Pekerja Oh 0.500 Rp. Rp. 100,000.00 Rp.
Tenaga
Mandor Oh 0.050 Rp. Rp. 150,000.00 Rp.
0.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0006-2007.6.11
Mengurug 1 m3 pasir urug
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Pasir Urug m3 1.200 Rp. 226,000.00 Rp. Rp. 271,200.00
Bahan
Pekerja Oh 0.300 Rp. Rp. 100,000.00 Rp.
Tenaga
Mandor Oh 0.010 Rp. Rp. 150,000.00 Rp.
271,200.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0006-2007.6.12
Mengurug 1 m3 tanah urug
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Tanah Timbun m3 1.200 Rp. 69,000.00 Rp. Rp. 82,800.00
Bahan
Pekerja Oh 0.300 Rp. Rp. 100,000.00 Rp.
Tenaga
Mandor Oh 0.010 Rp. Rp. 150,000.00 Rp.
82,800.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0006-2007.6.14
Memasang 1 m2 lapisan ijuk tebal 10 cm
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Ijuk kg 6.000 Rp. 27,000.00 Rp. Rp. 162,000.00
Bahan
Pekerja Oh 0.150 Rp. Rp. 100,000.00 Rp.
Tenaga
Mandor Oh 0.015 Rp. Rp. 150,000.00 Rp.
162,000.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0006-2007.6.15
Mengurug 1 m3 sirtu padat untuk peninggian lantai bangunan
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Sirtu m3 1.200 Rp. 329,000.00 Rp. Rp. 394,800.00
Bahan
Rp.
Pekerja Oh 0.250 Rp. Rp. 100,000.00 Rp.
Tenaga
Mandor Oh 0.025 Rp. Rp. 150,000.00 Rp.
394,800.00
Jumlah harga =
Pembulatan =

PEKERJAAN PONDASI

SNI.DT 91-0007-2006.6.1
Memasang 1 m3 pondasi batu belah, campuran 1 PC: 3 PP
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Batu belah 10-15cm m3 1.200 Rp. 600,000.00 Rp. Rp. 720,000.00
Bahan Portland Semen kg 202.000 Rp. 1,700.00 Rp. Rp. 343,400.00
Pasir pasang m3 0.485 Rp. Rp. Rp. 0.00
Pekerja Oh 1.500 Rp. Rp. 100,000.00 Rp.
Tukang Batu Oh 0.750 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.075 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.075 Rp. Rp. 150,000.00 Rp.
1,063,400.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0007-2006.6.2
Memasang 1 m3 pondasi batu belah, campuran 1 PC: 4 PP
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Batu belah 10-15cm m3 1.200 Rp. 600,000.00 Rp. Rp. 720,000.00
Bahan Portland Semen kg 163.000 Rp. 1,700.00 Rp. Rp. 277,100.00
Pasir pasang m3 0.520 Rp. 400,000.00 Rp. Rp. 208,000.00
Pekerja Oh 1.500 Rp. Rp. 100,000.00 Rp.
Tukang Batu Oh 0.750 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.075 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.075 Rp. Rp. 150,000.00 Rp.
1,205,100.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0007-2006.6.9
Memasang 1 m3 batu kosong (anstamping)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Batu belah 10-15cm m3 1.200 Rp. 600,000.00 Rp. Rp. 720,000.00
Bahan
Pasir Urug m3 0.432 Rp. 226,060.00 Rp. Rp. 97,657.92
Pekerja Oh 0.780 Rp. Rp. 100,000.00 Rp.
Tukang Batu Oh 0.390 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.039 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.039 Rp. Rp. 150,000.00 Rp.
817,657.92
Jumlah harga =
Pembulatan =

SNI.DT 91-0007-2006.6.10
Memasang 1 m3 pondasi siklop campuran 1 PC:2PB:3KR
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Batu belah 10-15cm m3 0.480 Rp. 600,000.00 Rp. Rp. 288,000.00
Portland Semen kg 194.000 Rp. 1,700.00 Rp. Rp. 329,800.00
Pasir pasang m3 0.312 Rp. 400,000.00 Rp. Rp. 124,800.00
Bahan
Batu pecah 5-7 m3 0.468 Rp. 750,000.00 Rp. Rp. 351,000.00
Besi beton kg 126.000 Rp. 20,000.00 Rp. Rp. 2,520,000.00
Kawat beton kg 1.800 Rp. 18,300.00 Rp. Rp. 32,940.00
Pekerja Oh 3.400 Rp. Rp. 100,000.00 Rp.
Tukang Batu Oh 0.850 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.085 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.170 Rp. Rp. 150,000.00 Rp.
3,646,540.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0007-2006.6.11
Memasang 1 m3 pondasi sumuran, diameter 100 cm
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Batu belah 10-15cm m3 0.450 Rp. 600,000.00 Rp. Rp. 270,000.00
Portland Semen kg 194.000 Rp. 1,700.00 Rp. Rp. 329,800.00
Bahan
Pasir pasang m3 0.312 Rp. 400,000.00 Rp. Rp. 124,800.00
Batu pecah 5-7 m3 0.468 Rp. 750,000.00 Rp. Rp. 351,000.00
Pekerja Oh 2.400 Rp. Rp. 100,000.00 Rp.
Tukang Batu Oh 0.800 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.080 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.119 Rp. Rp. 150,000.00 Rp.
1,075,600.00
Jumlah harga =
Pembulatan =
DAFTAR ANALISA PEKERJAAN
SNI.DT 91-0008-2007
PEKERJAAN BETON

SNI.DT 91-0008-2007.6.1
Membuat 1 m3 beton mutu K 100
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Portland Semen kg 247.000 Rp. 1,700.00 Rp. Rp. 419,900.00
Bahan Pasir pasang m3 0.869 Rp. 400,000.00 Rp. Rp. 347,600.00
Batu Pecah 5-7 m3 0.999 Rp. 750,000.00 Rp. Rp. 749,250.00
Air Liter 215.000 Rp. 75.00 Rp. Rp. 16,125.00
Pekerja Oh 1.650 Rp. Rp. 100,000.00 Rp.
Tukang Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.028 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.083 Rp. Rp. 150,000.00 Rp.
1,532,875.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.2
Membuat 1 m3 beton mutu K 125
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Portland Semen kg 276.000 Rp. 1,700.00 Rp. Rp. 469,200.00
Bahan Pasir pasang m3 0.828 Rp. 400,000.00 Rp. Rp. 331,200.00
Kerikil Beton m3 1.012 Rp. 450,000.00 Rp. Rp. 455,400.00
Air Liter 215.000 Rp. 75.00 Rp. Rp. 16,125.00
Pekerja Oh 1.650 Rp. Rp. 100,000.00 Rp.
Tukang Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.028 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.083 Rp. Rp. 150,000.00 Rp.
1,271,925.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.4
Membuat 1 m3 beton mutu K 150
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Portland Semen kg 299.000 Rp. 1,700.00 Rp. Rp. 508,300.00
Bahan Pasir pasang m3 0.799 Rp. 400,000.00 Rp. 319,600.00
Kerikil Beton m3 1.017 Rp. 450,000.00 Rp. Rp. 457,650.00
Air Liter 215.000 Rp. 75.00 Rp. Rp. 16,125.00
Pekerja Oh 1.650 Rp. Rp. 100,000.00 Rp.
Tukang Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.028 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.083 Rp. Rp. 150,000.00 Rp.
1,301,675.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.5
Membuat 1 m3 beton mutu K 175
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Portland Semen kg 326.000 Rp. 1,700.00 Rp. Rp. 554,200.00
Bahan Pasir pasang m3 0.760 Rp. 400,000.00 Rp. Rp. 304,000.00
Kerikil Beton m3 1.029 Rp. 450,000.00 Rp. Rp. 463,050.00
Air Liter 215.000 Rp. 75.00 Rp. Rp. 16,125.00
Pekerja Oh 1.650 Rp. Rp. 100,000.00 Rp.
Tukang Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.028 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.083 Rp. Rp. 150,000.00 Rp.
1,337,375.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.6
Membuat 1 m3 beton mutu f'c = 16.9 Mpa k200
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Portland Semen kg 352.000 Rp. 1,700.00 Rp. Rp. 598,400.00
Bahan Pasir pasang m3 0.731 Rp. 400,000.00 Rp. Rp. 292,400.00
Kerikil Beton m3 1.031 Rp. 450,000.00 Rp. Rp. 463,950.00
Air Liter 215.000 Rp. 75.00 Rp. Rp. 16,125.00
Pekerja Oh 1.650 Rp. Rp. 100,000.00 Rp.
Tukang Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.028 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.083 Rp. Rp. 150,000.00 Rp.
1,370,875.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.7
Membuat 1 m3 beton mutu K 225
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Portland Semen kg 371.000 Rp. 1,700.00 Rp. Rp. 630,700.00
Bahan Pasir pasang m3 0.698 Rp. 400,000.00 Rp. Rp. 279,200.00
Kerikil Beton m3 1.047 Rp. 450,000.00 Rp. Rp. 471,150.00
Air Liter 215.000 Rp. 75.00 Rp. Rp. 16,125.00
Pekerja Oh 1.650 Rp. Rp. 100,000.00 Rp.
Tukang Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.028 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.083 Rp. Rp. 150,000.00 Rp.
1,397,175.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.8
Membuat 1 m3 beton mutu K 250
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Portland Semen kg 384.000 Rp. 1,700.00 Rp. Rp. 652,800.00
Bahan Pasir pasang m3 0.692 Rp. 400,000.00 Rp. Rp. 276,800.00
Kerikil Beton m3 1.039 Rp. 450,000.00 Rp. Rp. 467,550.00
Air Liter 215.000 Rp. 75.00 Rp. Rp. 16,125.00
Pekerja Oh 1.650 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.028 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.083 Rp. Rp. 150,000.00 Rp.
1,413,275.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.9
Membuat 1 m3 beton mutu K 275
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Portland Semen kg 406.000 Rp. 1,700.00 Rp. Rp. 690,200.00
Bahan Pasir pasang m3 0.684 Rp. 400,000.00 Rp. Rp. 273,600.00
Kerikil Beton m3 1.026 Rp. 450,000.00 Rp. Rp. 461,700.00
Air Liter 215.000 Rp. 75.00 Rp. Rp. 16,125.00
Pekerja Oh 1.650 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.028 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.083 Rp. Rp. 150,000.00 Rp.
1,441,625.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.10
Membuat 1 m3 beton mutu K 300
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Portland Semen kg 413.000 Rp. 1,700.00 Rp. Rp. 702,100.00
Bahan Pasir pasang m3 0.681 Rp. 400,000.00 Rp. Rp. 272,400.00
Kerikil Beton m3 1.021 Rp. 450,000.00 Rp. Rp. 459,450.00
Air Liter 215.000 Rp. 75.00 Rp. Rp. 16,125.00
Pekerja Oh 1.650 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.028 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.083 Rp. Rp. 150,000.00 Rp.
1,450,075.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.11
Membuat 1 m3 beton mutu K 325
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Portland Semen kg 439.000 Rp. 1,700.00 Rp. Rp. 746,300.00
Bahan Pasir pasang m3 0.670 Rp. 400,000.00 Rp. Rp. 268,000.00
Kerikil Beton m3 1.006 Rp. 450,000.00 Rp. Rp. 452,700.00
Air Liter 215.000 Rp. 75.00 Rp. Rp. 16,125.00
Pekerja Oh 2.100 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.350 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.035 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.105 Rp. Rp. 150,000.00 Rp.
1,483,125.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.12
Membuat 1 m3 beton mutu K 350
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Portland Semen kg 448.000 Rp. 1,700.00 Rp. Rp. 761,600.00
Bahan Pasir pasang m3 0.667 Rp. 400,000.00 Rp. Rp. 266,800.00
Kerikil Beton m3 1.000 Rp. 450,000.00 Rp. Rp. 450,000.00
Air Liter 215.000 Rp. 75.00 Rp. Rp. 16,125.00
Pekerja Oh 2.100 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.350 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.035 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.105 Rp. Rp. 150,000.00 Rp.
1,494,525.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.17
Pembesian 10 kg dengan besi polos atau besi ulir
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Besi beton (polos/ulir) kg 10.500 Rp. 20,000.00 Rp. Rp. 210,000.00
Bahan
Kawat beton kg 0.150 Rp. 18,300.00 Rp. Rp. 2,745.00
Pekerja Oh 0.070 Rp. Rp. 100000 Rp.
Tukang batu Oh 0.070 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.007 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.004 Rp. Rp. 150,000.00 Rp.
Rp. 212,745.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.18
Memasang 10 kg kabel pres stressed polos /strands
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Besi beton (polos/ulir) kg 10.500 Rp. 20,000.00 Rp. Rp. 210,000.00
Bahan
Kawat beton kg 0.100 Rp. 18,300.00 Rp. Rp. 1,830.00
Pekerja Oh 0.050 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.050 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.005 Rp. Rp. 125,000.00 Rp.
Tenaga
Mandor Oh 0.003 Rp. Rp. 150,000.00 Rp.
211,830.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.19
Memasang 10 kg jaring kawat baja/wire mest
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Jaring kawat baja kg 10.200 Rp. 30,000.00 Rp. Rp. 306,000.00
Bahan
Kawat beton kg 0.050 Rp. 18,300.00 Rp. Rp. 915.00
Pekerja Oh 0.025 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.025 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.025 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.001 Rp. Rp. 150,000.00 Rp.
306,915.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.20
Memasang 1 m2 bekisting untuk pondasi
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.040 Rp. 1,850,000.00 Rp. Rp. 74,000.00
Bahan Paku 5cm-10cm kg 0.300 Rp. 20,000.00 Rp. Rp. 6,000.00
minyak bekisting Ltr 0.100 Rp. 6,900.00 Rp. Rp. 690.00
Pekerja Oh 0.520 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.260 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.026 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.026 Rp. Rp. 150,000.00 Rp.
80,690.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.21
Memasang 1 m2 bekisting untuk sloof
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.045 Rp. 1,850,000.00 Rp. Rp. 83,250.00
Bahan Paku 5cm-10cm kg 0.300 Rp. 20,000.00 Rp. Rp. 6,000.00
minyak bekisting Ltr 0.100 Rp. 6,900.00 Rp. Rp. 690.00
Pekerja Oh 0.520 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.260 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.026 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.026 Rp. Rp. 150,000.00 Rp.
89,940.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.22
Memasang 1 m2 bekisting untuk kolom
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.040 Rp. 1,850,000.00 Rp. Rp. 74,000.00
Bahan Paku 5cm-10cm kg 0.400 Rp. 20,000.00 Rp. Rp. 8,000.00
minyak bekisting Ltr 0.200 Rp. 6,900.00 Rp. Rp. 1,380.00
kayu klas II m3 0.015 Rp. 2,200,000.00 Rp. Rp. 33,000.00
Tripleks tebal 9 mm Lbr 0.350 Rp. 127,000.00 Rp. Rp. 44,450.00
Kayu Bulat O4" K Btg 2.000 Rp. 25,000.00 Rp. Rp. 50,000.00
Pekerja Oh 0.660 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.330 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.033 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.033 Rp. Rp. 150,000.00 Rp.
210,830.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.23
Memasang 1 m2 bekisting untuk balok
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.040 Rp. 1,850,000.00 Rp. Rp. 74,000.00
Bahan Paku 5cm-10cm kg 0.400 Rp. 20,000.00 Rp. Rp. 8,000.00
minyak bekisting Ltr 0.200 Rp. 6,900.00 Rp. Rp. 1,380.00
kayu klas II m3 0.018 Rp. 2,200,000.00 Rp. Rp. 39,600.00
Tripleks tebal 9 mm Lbr 0.350 Rp. 127,000.00 Rp. Rp. 44,450.00
Kayu Bulat O4" K Btg 2.000 Rp. 25,000.00 Rp. Rp. 50,000.00
Pekerja Oh 0.660 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.330 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.033 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.033 Rp. Rp. 150,000.00 Rp.
217,430.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.24
Memasang 1 m2 bekisting untuk lantai
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.040 Rp. 1,850,000.00 Rp. Rp. 74,000.00
Bahan Paku 5cm-10cm kg 0.400 Rp. 20,000.00 Rp. Rp. 8,000.00
minyak bekisting Ltr 0.200 Rp. 6,900.00 Rp. Rp. 1,380.00
kayu klas II m3 0.015 Rp. 2,200,000.00 Rp. Rp. 33,000.00
Tripleks tebal 9 mm Lbr 0.350 Rp. 127,000.00 Rp. Rp. 44,450.00
Kayu Bulat O4" K Btg 6.000 Rp. 25,000.00 Rp. Rp. 150,000.00
Pekerja Oh 0.660 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.330 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.033 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.033 Rp. Rp. 150,000.00 Rp.
310,830.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.25
Memasang 1 m2 bekisting untuk dinding
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.030 Rp. 1,850,000.00 Rp. Rp. 55,500.00
Bahan Paku 5cm-10cm kg 0.400 Rp. 20,000.00 Rp. Rp. 8,000.00
minyak bekisting Ltr 0.200 Rp. 6,900.00 Rp. Rp. 1,380.00
kayu klas II m3 0.020 Rp. 2,200,000.00 Rp. Rp. 44,000.00
Tripleks tebal 9 mm Lbr 0.350 Rp. 127,000.00 Rp. Rp. 44,450.00
Kayu Bulat O4" K Btg 3.000 Rp. 25,000.00 Rp. Rp. 75,000.00
Pekerja Oh 0.660 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.330 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.033 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.033 Rp. Rp. 150,000.00 Rp.
228,330.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.26
Memasang 1 m2 bekisting untuk tangga
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.030 Rp. 1,850,000.00 Rp. Rp. 55,500.00
Bahan Paku 5cm-10cm kg 0.400 Rp. 20,000.00 Rp. Rp. 8,000.00
minyak bekisting Ltr 0.150 Rp. 6,900.00 Rp. Rp. 1,035.00
kayu klas II m3 0.015 Rp. 2,200,000.00 Rp. Rp. 33,000.00
Tripleks tebal 9 mm Lbr 0.350 Rp. 127,000.00 Rp. Rp. 44,450.00
Kayu Bulat O4" K Btg 2.000 Rp. 25,000.00 Rp. Rp. 50,000.00
Pekerja Oh 0.660 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.330 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.033 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.033 Rp. Rp. 150,000.00 Rp.
191,985.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.27
Memasang 1 m2 jembatan untuk pengecoran beton
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.026 Rp. 1,850,000.00 Rp. Rp. 48,100.00
Bahan Paku 5cm-10cm kg 0.600 Rp. 20,000.00 Rp. Rp. 12,000.00
Kayu Bulat O4" K Btg 0.500 Rp. 25,000.00 Rp. Rp. 12,500.00
Pekerja Oh 0.150 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.050 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.005 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.008 Rp. Rp. 150,000.00 Rp.
72,600.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.28
Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.200 Rp. 1,850,000.00 Rp. Rp. 370,000.00
Paku 5cm-10cm kg 1.500 Rp. 20,000.00 Rp. Rp. 30,000.00
minyak bekisting Ltr 0.400 Rp. 6,900.00 Rp. Rp. 2,760.00
Besi beton polos kg 157.500 Rp. 17,500.00 Rp. Rp. 2,756,250.00
Bahan
Kawat beton kg 2.250 Rp. 18,300.00 Rp. Rp. 41,175.00
Portland Semen kg 336.000 Rp. 1,700.00 Rp. Rp. 571,200.00
Pasir beton m3 0.540 Rp. 400,000.00 Rp. Rp. 216,000.00
Kerikil Beton m3 0.810 Rp. 450,000.00 Rp. Rp. 364,500.00
Pekerja Oh 5.300 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tukang kayu Oh 1.300 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 1.050 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.262 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.265 Rp. Rp. 150,000.00 Rp.
4,351,885.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.28A
Membuat 1 m3 pondasi beton bertulang (125 kg besi + bekisting)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.200 Rp. 1,850,000.00 Rp. Rp. 370,000.00
Paku 5cm-10cm kg 1.500 Rp. 20,000.00 Rp. Rp. 30,000.00
minyak bekisting Ltr 0.400 Rp. 6,900.00 Rp. Rp. 2,760.00
Besi beton polos kg 131.250 Rp. 17,500.00 Rp. Rp. 2,296,875.00
Bahan
Kawat beton kg 2.250 Rp. 18,300.00 Rp. Rp. 41,175.00
Portland Semen kg 336.000 Rp. 1,700.00 Rp. Rp. 571,200.00
Pasir beton m3 0.540 Rp. 400,000.00 Rp. Rp. 216,000.00
Kerikil Beton m3 0.810 Rp. 450,000.00 Rp. Rp. 364,500.00
Pekerja Oh 5.300 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tukang kayu Oh 1.300 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 1.050 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.262 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.265 Rp. Rp. 150,000.00 Rp.
3,892,510.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.28B
Membuat 1 m3 pondasi beton bertulang (100 kg besi + bekisting)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.200 Rp. 1,850,000.00 Rp. Rp. 370,000.00
Paku 5cm-10cm kg 1.500 Rp. 20,000.00 Rp. Rp. 30,000.00

Bahan
minyak bekisting Ltr 0.400 Rp. 6,900.00 Rp. Rp. 2,760.00
Besi beton polos kg 105.000 Rp. 17,500.00 Rp. Rp. 1,837,500.00
Bahan
Kawat beton kg 2.250 Rp. 18,300.00 Rp. Rp. 41,175.00
Portland Semen kg 336.000 Rp. 1,700.00 Rp. Rp. 571,200.00
Pasir beton m3 0.540 Rp. 400,000.00 Rp. Rp. 216,000.00
Kerikil Beton m3 0.810 Rp. 450,000.00 Rp. Rp. 364,500.00
Pekerja Oh 5.300 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tukang kayu Oh 1.300 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 1.050 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.262 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.265 Rp. Rp. 150,000.00 Rp.
3,433,135.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.29
Membuat 1 m3 sloof beton bertulang (200 kg besi + bekisting)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.270 Rp. 1,850,000.00 Rp. Rp. 499,500.00
Paku 5cm-10cm kg 2.000 Rp. 20,000.00 Rp. Rp. 40,000.00
minyak bekisting Ltr 0.600 Rp. 6,900.00 Rp. Rp. 4,140.00
Besi beton polos kg 210.000 Rp. 17,500.00 Rp. Rp. 3,675,000.00
Bahan Kawat beton kg 3.000 Rp. 18,300.00 Rp. Rp. 54,900.00
Portland Semen kg 336.000 Rp. 1,700.00 Rp. Rp. 571,200.00
Tripleks tebal 9 mm Lbr 3.500 Rp. 127,000.00 Rp. Rp. 444,500.00
Pasir beton m3 0.540 Rp. 400,000.00 Rp. Rp. 216,000.00
Kerikil Beton m3 0.810 Rp. 450,000.00 Rp. Rp. 364,500.00
Pekerja Oh 5.650 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tukang kayu Oh 1.560 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 1.400 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.323 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.283 Rp. Rp. 150,000.00 Rp.
5,869,740.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.29A
Membuat 1 m3 sloof beton bertulang (200 kg besi + bekisting)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.270 Rp. 1,850,000.00 Rp. Rp. 499,500.00
Paku 5cm-10cm kg 2.000 Rp. 20,000.00 Rp. Rp. 40,000.00
minyak bekisting Ltr 0.600 Rp. 6,900.00 Rp. Rp. 4,140.00
Besi beton polos kg 157.500 Rp. 17,500.00 Rp. Rp. 2,756,250.00
Bahan Kawat beton kg 3.000 Rp. 18,300.00 Rp. Rp. 54,900.00
Portland Semen kg 336.000 Rp. 1,700.00 Rp. Rp. 571,200.00
Tripleks tebal 9 mm Lbr 3.500 Rp. 127,000.00 Rp. Rp. 444,500.00
Pasir beton m3 0.540 Rp. 400,000.00 Rp. Rp. 216,000.00
Kerikil Beton m3 0.810 Rp. 450,000.00 Rp. Rp. 364,500.00
Pekerja Oh 5.650 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tukang kayu Oh 1.560 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 1.400 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.323 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.283 Rp. Rp. 150,000.00 Rp.
4,950,990.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.29B
Membuat 1 m3 sloof beton bertulang (125 kg besi + bekisting)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.270 Rp. 1,850,000.00 Rp. Rp. 499,500.00

Bahan
Paku 5cm-10cm kg 2.000 Rp. 20,000.00 Rp. Rp. 40,000.00
minyak bekisting Ltr 0.600 Rp. 6,900.00 Rp. Rp. 4,140.00
Besi beton polos kg 131.250 Rp. 17,500.00 Rp. Rp. 2,296,875.00
Bahan Kawat beton kg 3.000 Rp. 18,300.00 Rp. Rp. 54,900.00
Portland Semen kg 336.000 Rp. 1,700.00 Rp. Rp. 571,200.00
Tripleks tebal 9 mm Lbr 3.500 Rp. 127,000.00 Rp. Rp. 444,500.00
Pasir beton m3 0.540 Rp. 400,000.00 Rp. Rp. 216,000.00
Kerikil Beton m3 0.810 Rp. 450,000.00 Rp. Rp. 364,500.00
Pekerja Oh 5.650 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tukang kayu Oh 1.560 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 1.400 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.323 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.283 Rp. Rp. 150,000.00 Rp.
4,491,615.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.29C
Membuat 1 m3 sloof beton bertulang (100 kg besi + bekisting)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.270 Rp. 1,850,000.00 Rp. Rp. 499,500.00
Paku 5cm-10cm kg 2.000 Rp. 20,000.00 Rp. Rp. 40,000.00
minyak bekisting Ltr 0.600 Rp. 6,900.00 Rp. Rp. 4,140.00
Besi beton polos kg 105.000 Rp. 17,500.00 Rp. Rp. 1,837,500.00
Bahan Kawat beton kg 3.000 Rp. 18,300.00 Rp. Rp. 54,900.00
Portland Semen kg 336.000 Rp. 1,700.00 Rp. Rp. 571,200.00
Tripleks tebal 9 mm Lbr 3.500 Rp. 127,000.00 Rp. Rp. 444,500.00
Pasir beton m3 0.540 Rp. 400,000.00 Rp. Rp. 216,000.00
Kerikil Beton m3 0.810 Rp. 450,000.00 Rp. Rp. 364,500.00
Pekerja Oh 5.650 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tukang kayu Oh 1.560 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 1.400 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.323 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.283 Rp. Rp. 150,000.00 Rp.
4,032,240.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.30
Membuat 1 m3 kolom beton bertulang (300 kg besi + bekisting)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.400 Rp. 1,850,000.00 Rp. Rp. 740,000.00
Paku 5cm-10cm kg 4.000 Rp. 20,000.00 Rp. Rp. 80,000.00
minyak bekisting Ltr 2.000 Rp. 6,900.00 Rp. Rp. 13,800.00
Besi beton polos kg 315.000 Rp. 17,500.00 Rp. Rp. 5,512,500.00
Kawat beton kg 4.500 Rp. 18,300.00 Rp. Rp. 82,350.00
Bahan Portland Semen kg 336.000 Rp. 1,700.00 Rp. Rp. 571,200.00
Tripleks tebal 9 mm Lbr 3.500 Rp. 127,000.00 Rp. Rp. 444,500.00
Pasir beton m3 0.540 Rp. 400,000.00 Rp. Rp. 216,000.00
Kerikil Beton m3 0.810 Rp. 450,000.00 Rp. Rp. 364,500.00
kayu klas II m3 0.150 Rp. 2,200,000.00 Rp. Rp. 330,000.00
Kayu Bulat O4" K Btg 20.000 Rp. 25,000.00 Rp. Rp. 500,000.00
Pekerja Oh 7.050 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tukang kayu Oh 1.650 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 2.100 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.403 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.353 Rp. Rp. 150,000.00 Rp.
8,854,850.00
Jumlah harga =
Pembulatan =
SNI.DT 91-0008-2007.6.30
Membuat 1 m3 kolom beton bertulang (200 kg besi + bekisting)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.400 Rp. 1,850,000.00 Rp. Rp. 740,000.00
Paku 5cm-10cm kg 4.000 Rp. 20,000.00 Rp. Rp. 80,000.00
minyak bekisting Ltr 2.000 Rp. 6,900.00 Rp. Rp. 13,800.00
Besi beton polos kg 210.000 Rp. 17,500.00 Rp. Rp. 3,675,000.00
Kawat beton kg 4.500 Rp. 18,300.00 Rp. Rp. 82,350.00
Bahan Portland Semen kg 336.000 Rp. 1,700.00 Rp. Rp. 571,200.00
Tripleks tebal 9 mm Lbr 3.500 Rp. 127,000.00 Rp. Rp. 444,500.00
Pasir beton m3 0.540 Rp. 400,000.00 Rp. Rp. 216,000.00
Kerikil Beton m3 0.810 Rp. 450,000.00 Rp. Rp. 364,500.00
kayu klas II m3 0.150 Rp. 2,200,000.00 Rp. Rp. 330,000.00
Kayu Bulat O4" K Btg 20.000 Rp. 25,000.00 Rp. Rp. 500,000.00
Pekerja Oh 7.050 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tukang kayu Oh 1.650 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 2.100 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.403 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.353 Rp. Rp. 150,000.00 Rp.
7,017,350.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.31
Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.320 Rp. 1,850,000.00 Rp. Rp. 592,000.00
Paku 5cm-10cm kg 3.200 Rp. 20,000.00 Rp. Rp. 64,000.00
minyak bekisting Ltr 1.600 Rp. 6,900.00 Rp. Rp. 11,040.00
Besi beton polos kg 210.000 Rp. 17,500.00 Rp. Rp. 3,675,000.00
Kawat beton kg 3.000 Rp. 18,300.00 Rp. Rp. 54,900.00
Bahan Portland Semen kg 336.000 Rp. 1,700.00 Rp. Rp. 571,200.00
Tripleks tebal 9 mm Lbr 2.800 Rp. 127,000.00 Rp. Rp. 355,600.00
Pasir beton m3 0.540 Rp. 400,000.00 Rp. Rp. 216,000.00
Kerikil Beton m3 0.810 Rp. 450,000.00 Rp. Rp. 364,500.00
kayu klas II m3 0.140 Rp. 2,200,000.00 Rp. Rp. 308,000.00
Kayu Bulat O4" K Btg 16.000 Rp. 25,000.00 Rp. Rp. 400,000.00
Pekerja Oh 6.350 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tukang kayu Oh 1.650 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 1.400 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.333 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.318 Rp. Rp. 150,000.00 Rp.
6,612,240.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.31A
Membuat 1 m3 balok beton bertulang (150 kg besi + bekisting)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.320 Rp. 1,850,000.00 Rp. Rp. 592,000.00
Paku 5cm-10cm kg 3.200 Rp. 20,000.00 Rp. Rp. 64,000.00
minyak bekisting Ltr 1.600 Rp. 6,900.00 Rp. Rp. 11,040.00
Besi beton polos kg 157.500 Rp. 17,500.00 Rp. Rp. 2,756,250.00
Kawat beton kg 3.000 Rp. 18,300.00 Rp. Rp. 54,900.00
Bahan Portland Semen kg 336.000 Rp. 1,700.00 Rp. Rp. 571,200.00
Tripleks tebal 9 mm Lbr 2.800 Rp. 127,000.00 Rp. Rp. 355,600.00
Pasir beton m3 0.540 Rp. 400,000.00 Rp. Rp. 216,000.00
Kerikil Beton m3 0.810 Rp. 450,000.00 Rp. Rp. 364,500.00
kayu klas II m3 0.140 Rp. 2,200,000.00 Rp. Rp. 308,000.00
Kayu Bulat O4" K Btg 16.000 Rp. 25,000.00 Rp. Rp. 400,000.00
Pekerja Oh 6.350 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang kayu Oh 1.650 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 1.400 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.333 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.318 Rp. Rp. 150,000.00 Rp.
5,693,490.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.31B
Membuat 1 m3 kolom beton bertulang (100 kg besi + bekisting)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.320 Rp. 1,850,000.00 Rp. Rp. 592,000.00
Paku 5cm-10cm kg 3.200 Rp. 20,000.00 Rp. Rp. 64,000.00
minyak bekisting Ltr 1.600 Rp. 6,900.00 Rp. Rp. 11,040.00
Besi beton polos kg 131.250 Rp. 17,500.00 Rp. Rp. 2,296,875.00
Kawat beton kg 3.000 Rp. 18,300.00 Rp. Rp. 54,900.00
Bahan Portland Semen kg 336.000 Rp. 1,700.00 Rp. Rp. 571,200.00
Tripleks tebal 9 mm Lbr 2.800 Rp. 127,000.00 Rp. Rp. 355,600.00
Pasir beton m3 0.540 Rp. 400,000.00 Rp. Rp. 216,000.00
Kerikil Beton m3 0.810 Rp. 450,000.00 Rp. Rp. 364,500.00
kayu klas II m3 0.140 Rp. 2,200,000.00 Rp. Rp. 308,000.00
Kayu Bulat O4" K Btg 16.000 Rp. 25,000.00 Rp. Rp. 400,000.00
Pekerja Oh 6.350 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tukang kayu Oh 1.650 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 1.400 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.333 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.318 Rp. Rp. 150,000.00 Rp.
5,234,115.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.31C
Membuat 1 m3 balok beton bertulang (100 kg besi + bekisting)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.320 Rp. 1,850,000.00 Rp. Rp. 592,000.00
Paku 5cm-10cm kg 3.200 Rp. 20,000.00 Rp. Rp. 64,000.00
minyak bekisting Ltr 1.600 Rp. 6,900.00 Rp. Rp. 11,040.00
Besi beton polos kg 105.000 Rp. 17,500.00 Rp. Rp. 1,837,500.00
Kawat beton kg 3.000 Rp. 18,300.00 Rp. Rp. 54,900.00
Bahan Portland Semen kg 336.000 Rp. 1,700.00 Rp. Rp. 571,200.00
Tripleks tebal 9 mm Lbr 2.800 Rp. 127,000.00 Rp. Rp. 355,600.00
Pasir beton m3 0.540 Rp. 400,000.00 Rp. Rp. 216,000.00
Kerikil Beton m3 0.810 Rp. 450,000.00 Rp. Rp. 364,500.00
kayu klas II m3 0.140 Rp. 2,200,000.00 Rp. Rp. 308,000.00
Kayu Bulat O4" K Btg 16.000 Rp. 25,000.00 Rp. Rp. 400,000.00
Pekerja Oh 6.350 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tukang kayu Oh 1.650 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 1.400 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.333 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.318 Rp. Rp. 150,000.00 Rp.
4,774,740.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.32
Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.320 Rp. 1,850,000.00 Rp. Rp. 592,000.00
Paku 5cm-10cm kg 3.200 Rp. 20,000.00 Rp. Rp. 64,000.00
minyak bekisting Ltr 1.600 Rp. 6,900.00 Rp. Rp. 11,040.00
Besi beton polos kg 157.500 Rp. 17,500.00 Rp. Rp. 2,756,250.00
Kawat beton kg 2.250 Rp. 18,300.00 Rp. Rp. 41,175.00
Bahan
Bahan Portland Semen kg 336.000 Rp. 1,700.00 Rp. Rp. 571,200.00
Tripleks tebal 9 mm Lbr 2.800 Rp. 127,000.00 Rp. Rp. 355,600.00
Pasir beton m3 0.540 Rp. 400,000.00 Rp. Rp. 216,000.00
Kerikil Beton m3 0.810 Rp. 450,000.00 Rp. Rp. 364,500.00
kayu klas II m3 0.120 Rp. 2,200,000.00 Rp. Rp. 264,000.00
Kayu Bulat O4" K Btg 32.000 Rp. 25,000.00 Rp. Rp. 800,000.00
Pekerja Oh 5.300 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tukang kayu Oh 1.300 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 1.050 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.265 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.265 Rp. Rp. 150,000.00 Rp.
6,035,765.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.32A
Membuat 1 m3 kolom beton bertulang (125 kg besi + bekisting)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.320 Rp. 1,850,000.00 Rp. Rp. 592,000.00
Paku 5cm-10cm kg 3.200 Rp. 20,000.00 Rp. Rp. 64,000.00
minyak bekisting Ltr 1.600 Rp. 6,900.00 Rp. Rp. 11,040.00
Besi beton polos kg 131.250 Rp. 17,500.00 Rp. Rp. 2,296,875.00
Kawat beton kg 2.250 Rp. 18,300.00 Rp. Rp. 41,175.00
Bahan Portland Semen kg 336.000 Rp. 1,700.00 Rp. Rp. 571,200.00
Tripleks tebal 9 mm Lbr 2.800 Rp. 127,000.00 Rp. Rp. 355,600.00
Pasir beton m3 0.540 Rp. 400,000.00 Rp. Rp. 216,000.00
Kerikil Beton m3 0.810 Rp. 450,000.00 Rp. Rp. 364,500.00
kayu klas II m3 0.120 Rp. 2,200,000.00 Rp. Rp. 264,000.00
Kayu Bulat O4" K Btg 32.000 Rp. 25,000.00 Rp. Rp. 800,000.00
Pekerja Oh 5.300 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tukang kayu Oh 1.300 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 1.050 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.265 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.265 Rp. Rp. 150,000.00 Rp.
5,576,390.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.32B
Membuat 1 m3 kolom beton bertulang (100 kg besi + bekisting)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.320 Rp. 1,850,000.00 Rp. Rp. 592,000.00
Paku 5cm-10cm kg 3.200 Rp. 20,000.00 Rp. Rp. 64,000.00
minyak bekisting Ltr 1.600 Rp. 6,900.00 Rp. Rp. 11,040.00
Besi beton polos kg 105.000 Rp. 17,500.00 Rp. Rp. 1,837,500.00
Kawat beton kg 2.250 Rp. 18,300.00 Rp. Rp. 41,175.00
Bahan Portland Semen kg 336.000 Rp. 1,700.00 Rp. Rp. 571,200.00
Tripleks tebal 9 mm Lbr 2.800 Rp. 127,000.00 Rp. Rp. 355,600.00
Pasir beton m3 0.540 Rp. 400,000.00 Rp. Rp. 216,000.00
Kerikil Beton m3 0.810 Rp. 450,000.00 Rp. Rp. 364,500.00
kayu klas II m3 0.120 Rp. 2,200,000.00 Rp. Rp. 264,000.00
Kayu Bulat O4" K Btg 32.000 Rp. 25,000.00 Rp. Rp. 800,000.00
Pekerja Oh 5.300 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tukang kayu Oh 1.300 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 1.050 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.265 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.265 Rp. Rp. 150,000.00 Rp.
5,117,015.00
Jumlah harga =
Pembulatan =
SNI.DT 91-0008-2007.6.33
Membuat 1 m3 dinding beton bertulang (150 kg besi + bekisting)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.240 Rp. 1,850,000.00 Rp. Rp. 444,000.00
Paku 5cm-10cm kg 3.200 Rp. 20,000.00 Rp. Rp. 64,000.00
minyak bekisting Ltr 1.600 Rp. 6,900.00 Rp. Rp. 11,040.00
Besi beton polos kg 157.500 Rp. 17,500.00 Rp. Rp. 2,756,250.00
Kawat beton kg 2.250 Rp. 18,300.00 Rp. Rp. 41,175.00
Bahan Portland Semen kg 336.000 Rp. 1,700.00 Rp. Rp. 571,200.00
Tripleks tebal 9 mm Lbr 2.800 Rp. 127,000.00 Rp. Rp. 355,600.00
Pasir beton m3 0.540 Rp. 400,000.00 Rp. Rp. 216,000.00
Kerikil beton m3 0.810 Rp. 450,000.00 Rp. Rp. 364,500.00
kayu klas II m3 0.160 Rp. 2,200,000.00 Rp. Rp. 352,000.00
Kayu Bulat O4" K Btg 24.000 Rp. 25,000.00 Rp. Rp. 600,000.00
Pekerja Oh 5.300 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tukang kayu Oh 1.300 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 1.050 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.265 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.265 Rp. Rp. 150,000.00 Rp.
5,775,765.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.33A
Membuat 1 m3 dinding beton bertulang (125 kg besi + bekisting)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.240 Rp. 1,850,000.00 Rp. Rp. 444,000.00
Paku 5cm-10cm kg 3.200 Rp. 20,000.00 Rp. Rp. 64,000.00
minyak bekisting Ltr 1.600 Rp. 6,900.00 Rp. Rp. 11,040.00
Besi beton polos kg 131.250 Rp. 17,500.00 Rp. Rp. 2,296,875.00
Kawat beton kg 2.250 Rp. 18,300.00 Rp. Rp. 41,175.00
Bahan Portland Semen kg 336.000 Rp. 1,700.00 Rp. Rp. 571,200.00
Tripleks tebal 9 mm Lbr 2.800 Rp. 127,000.00 Rp. Rp. 355,600.00
Pasir beton m3 0.540 Rp. 400,000.00 Rp. Rp. 216,000.00
Kerikil Beton m3 0.810 Rp. 450,000.00 Rp. Rp. 364,500.00
kayu klas II m3 0.160 Rp. 2,200,000.00 Rp. Rp. 352,000.00
Kayu Bulat O4" K Btg 24.000 Rp. 25,000.00 Rp. Rp. 600,000.00
Pekerja Oh 5.300 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tukang kayu Oh 1.300 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 1.050 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.265 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.265 Rp. Rp. 150,000.00 Rp.
5,316,390.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.33B
Membuat 1 m3 dinding beton bertulang (100 kg besi + bekisting)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.240 Rp. 1,850,000.00 Rp. Rp. 444,000.00
Paku 5cm-10cm kg 3.200 Rp. 20,000.00 Rp. Rp. 64,000.00
minyak bekisting Ltr 1.600 Rp. 6,900.00 Rp. Rp. 11,040.00
Besi beton polos kg 105.000 Rp. 17,500.00 Rp. Rp. 1,837,500.00
Kawat beton kg 2.250 Rp. 18,300.00 Rp. Rp. 41,175.00
Bahan Portland Semen kg 336.000 Rp. 1,700.00 Rp. Rp. 571,200.00
Tripleks tebal 9 mm Lbr 2.800 Rp. 127,000.00 Rp. Rp. 355,600.00
Pasir beton m3 0.540 Rp. 400,000.00 Rp. Rp. 216,000.00
Kerikil Beton m3 0.810 Rp. 450,000.00 Rp. Rp. 364,500.00
kayu klas II m3 0.160 Rp. 2,200,000.00 Rp. Rp. 352,000.00
Kayu Bulat O4" K Btg 24.000 Rp. 25,000.00 Rp. Rp. 600,000.00
Pekerja Oh 5.300 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang kayu Oh 1.300 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 1.050 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.262 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.265 Rp. Rp. 150,000.00 Rp.
4,857,015.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.34
Membuat 1 m3 dinding beton bertulang (200 kg besi + bekisting)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.250 Rp. 1,850,000.00 Rp. Rp. 462,500.00
Paku 5cm-10cm kg 3.000 Rp. 20,000.00 Rp. Rp. 60,000.00
minyak bekisting Ltr 1.200 Rp. 6,900.00 Rp. Rp. 8,280.00
Besi beton polos kg 210.000 Rp. 17,500.00 Rp. Rp. 3,675,000.00
Kawat beton kg 3.000 Rp. 18,300.00 Rp. Rp. 54,900.00
Bahan Portland Semen kg 336.000 Rp. 1,700.00 Rp. Rp. 571,200.00
Tripleks tebal 9 mm Lbr 2.500 Rp. 127,000.00 Rp. Rp. 317,500.00
Pasir beton m3 0.540 Rp. 400,000.00 Rp. Rp. 216,000.00
Kerikil Beton m3 0.810 Rp. 450,000.00 Rp. Rp. 364,500.00
kayu klas II m3 0.105 Rp. 2,200,000.00 Rp. Rp. 231,000.00
Kayu Bulat O4" K Btg 14.000 Rp. 25,000.00 Rp. Rp. 350,000.00
Pekerja Oh 5.650 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.275 Rp. Rp. 110,000.00 Rp.
Tukang kayu Oh 1.560 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 1.400 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.323 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.283 Rp. Rp. 150,000.00 Rp.
6,310,880.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.35
Membuat 1 m' kolom praktis beton bertulang (11x11) cm
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.002 Rp. 1,850,000.00 Rp. Rp. 3,700.00
Paku 5cm-10cm kg 0.010 Rp. 20,000.00 Rp. Rp. 200.00
minyak bekisting Ltr 1.200 Rp. 6,900.00 Rp. Rp. 8,280.00
Besi beton polos kg 3.000 Rp. 17,500.00 Rp. Rp. 52,500.00
Bahan
Kawat beton kg 0.450 Rp. 18,300.00 Rp. Rp. 8,235.00
Portland Semen kg 4.000 Rp. 1,700.00 Rp. Rp. 6,800.00
Pasir beton m3 0.006 Rp. 400,000.00 Rp. Rp. 2,400.00
Kerikil Beton m3 0.009 Rp. 450,000.00 Rp. Rp. 4,050.00
Pekerja Oh 0.180 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.020 Rp. Rp. 110,000.00 Rp.
Tukang kayu Oh 0.020 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 0.020 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.006 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.009 Rp. Rp. 150,000.00 Rp.
86,165.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0008-2007.6.36
Membuat 1 m' ring balok beton bertulang (10x15) cm
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.003 Rp. 1,850,000.00 Rp. Rp. 5,550.00
Paku 5cm-10cm kg 0.020 Rp. 20,000.00 Rp. Rp. 400.00
minyak bekisting Ltr 1.200 Rp. 6,900.00 Rp. Rp. 8,280.00
Besi beton polos kg 3.600 Rp. 17,500.00 Rp. Rp. 63,000.00
Bahan
Kawat beton kg 0.050 Rp. 18,300.00 Rp. Rp. 915.00
Portland Semen kg 5.500 Rp. 1,700.00 Rp. Rp. 9,350.00
Pasir beton m3 0.009 Rp. 400,000.00 Rp. Rp. 3,600.00
Kerikil Beton m3 0.015 Rp. 450,000.00 Rp. Rp. 6,750.00
Pekerja Oh 0.297 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.033 Rp. Rp. 110,000.00 Rp.
Tukang kayu Oh 0.033 Rp. Rp. 110,000.00 Rp.
Tenaga
Tukang Besi Oh 0.033 Rp. Rp. 110,000.00 Rp.
Kepala Tukang Oh 0.010 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.015 Rp. Rp. 150,000.00 Rp.
97,845.00
Jumlah harga =
Pembulatan =
DAFTAR ANALISA PEKERJAAN
SNI.DT 91-0009-2007
PEKERJAAN DINDING

SNI.DT 91-0009-2007.6.1
Memasang 1 m2 dinding bata merah tebal 1 bata, campuran spesi 1 PC: 2PP
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bata merah bh 140.000 Rp. - Rp. Rp. 0.00
Bahan Portland Semen kg 43.500 Rp. 1,700.00 Rp. Rp. 73,950.00
Pasir pasang m3 0.080 Rp. 400,000.00 Rp. Rp. 32,000.00
Pekerja Oh 0.600 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.200 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.020 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.030 Rp. Rp. 150,000.00 Rp.
105,950.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0009-2007.6.2
Memasang 1 m2 dinding bata merah tebal 1 bata, campuran spesi 1 PC: 3PP
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bata merah bh 140.000 Rp. - Rp. Rp. 0.00
Bahan Portland Semen kg 32.950 Rp. 1,700.00 Rp. Rp. 56,015.00
Pasir pasang m3 0.091 Rp. 400,000.00 Rp. Rp. 36,400.00
Pekerja Oh 0.600 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.200 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.020 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.030 Rp. Rp. 150,000.00 Rp.
92,415.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0009-2007.6.3
Memasang 1 m2 dinding bata merah tebal 1 bata, campuran spesi 1 PC: 4PP
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bata merah bh 140.000 Rp. - Rp. Rp. 0.00
Bahan Portland Semen kg 26.550 Rp. 1,700.00 Rp. Rp. 45,135.00
Pasir pasang m3 0.093 Rp. 400,000.00 Rp. Rp. 37,200.00
Pekerja Oh 0.600 Rp. Rp. 100,000.00 Rp.
Tukang Batu Oh 0.200 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.020 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.030 Rp. Rp. 150,000.00 Rp.
82,335.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0009-2007.6.7
Memasang 1 m2 dinding bata merah tebal 1/2 bata, campuran spesi 1 PC: 2PP
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bata merah bh 70.000 Rp. - Rp. Rp. 0.00
Bahan Portland Semen kg 18.950 Rp. 1,700.00 Rp. Rp. 32,215.00
Pasir pasang m3 0.038 Rp. 400,000.00 Rp. Rp. 15,200.00
Pekerja Oh 0.300 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.100 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.010 Rp. Rp. 125,000.00 Rp.
Tenaga
Mandor Oh 0.015 Rp. Rp. 150,000.00 Rp.
47,415.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0009-2007.6.8
Memasang 1 m2 dinding bata merah tebal 1/2 bata, campuran spesi 1 PC: 3PP
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bata merah bh 70.000 Rp. - Rp. Rp. 0.00
Bahan Portland Semen kg 14.370 Rp. 1,700.00 Rp. Rp. 24,429.00
Pasir pasang m3 0.040 Rp. 400,000.00 Rp. Rp. 16,000.00
Pekerja Oh 0.300 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.100 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.010 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.015 Rp. Rp. 150,000.00 Rp.
40,429.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0009-2007.6.9
Memasang 1 m2 dinding bata merah tebal 1/2 bata, campuran spesi 1 PC: 4PP
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bata merah bh 70.000 Rp. - Rp. Rp. 0.00
Bahan Portland Semen kg 11.500 Rp. 1,700.00 Rp. Rp. 19,550.00
Pasir pasang m3 0.043 Rp. 400,000.00 Rp. Rp. 17,200.00
Pekerja Oh 0.300 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.100 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.010 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.015 Rp. Rp. 150,000.00 Rp.
36,750.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0009-2007.6.23
Memasang 1 m2 dinding terawang campuran spesi 1 PC: 4PP
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Batu kerawang bh 30.000 Rp. 6,000.00 Rp. Rp. 180,000.00
Bahan Portland Semen kg 11.000 Rp. 1,700.00 Rp. Rp. 18,700.00
Pasir pasang m3 0.035 Rp. 400,000.00 Rp. Rp. 14,000.00
Pekerja Oh 0.300 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.100 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.010 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.015 Rp. Rp. 150,000.00 Rp.
212,700.00
Jumlah harga =
Pembulatan =
DAFTAR ANALISA PEKERJAAN
SNI.DT 91-0010-2007
PEKERJAAN PLESTERAN

SNI.DT 91-0010-2007.6.1
Memasang 1 m2 plesteran 1 PC: 1PP, tebal 15 mm
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Portland Semen kg 15.504 Rp. 1,700.00 Rp. Rp. 26,356.80
Bahan
Pasir pasang m3 0.016 Rp. 400,000.00 Rp. Rp. 6,400.00
Pekerja Oh 0.300 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.150 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.015 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.015 Rp. Rp. 150,000.00 Rp.
32,756.80
Jumlah harga =
Pembulatan =

SNI.DT 91-0010-2007.6.2
Memasang 1 m2 plesteran 1 PC: 2PP, tebal 15 mm
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Portland Semen kg 10.224 Rp. 1,700.00 Rp. Rp. 17,380.80
Bahan
Pasir pasang m3 0.020 Rp. 400,000.00 Rp. Rp. 8,000.00
Pekerja Oh 0.300 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.150 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.015 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.015 Rp. Rp. 150,000.00 Rp.
25,380.80
Jumlah harga =
Pembulatan =

SNI.DT 91-0010-2007.6.3
Memasang 1 m2 plesteran 1 PC: 3PP, tebal 15 mm
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Semen portland kg 7.776 Rp. #N/A Rp. Rp. #N/A
Bahan
Pasir pasang m3 0.023 Rp. 400,000.00 Rp. Rp. 9,200.00
Pekerja Oh 0.300 Rp. Rp. 100,000.00 Rp.
Tukang Batu Oh 0.150 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.015 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.015 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI.DT 91-0010-2007.6.4
Memasang 1 m2 plesteran 1 PC: 4PP, tebal 15 mm
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Portland Semen kg 6.240 Rp. 1,700.00 Rp. Rp. 10,608.00
Bahan
Pasir pasang m3 0.024 Rp. 400,000.00 Rp. Rp. 9,600.00
Pekerja Oh 0.300 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.150 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.015 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.015 Rp. Rp. 150,000.00 Rp.
20,208.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0010-2007.6.23
Memasang 1 m2 plesteran ciprat 1 PC: 2PP
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Portland Semen kg 4.320 Rp. 1,700.00 Rp. Rp. 7,344.00
Bahan
Pasir pasang m3 0.006 Rp. 400,000.00 Rp. Rp. 2,400.00
Pekerja Oh 0.300 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.100 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.010 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.015 Rp. Rp. 150,000.00 Rp.
9,744.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0010-2007.6.27
Memasang 1 m2 acian
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Portland Semen kg 3.250 Rp. 1,700.00 Rp. Rp. 5,525.00
Pekerja Oh 0.200 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.100 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.010 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.010 Rp. Rp. 150,000.00 Rp.
5,525.00
Jumlah harga =
Pembulatan =
DAFTAR ANALISA PEKERJAAN
SNI.DT 91-0012-2007
PEKERJAAN PENUTUP LANTAI DAN DINDING

SNI.DT 91-0012-2007.6.13
Memasang 1 m2 lantai keramik ukuran (60x60) cm
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Lantai keramik 60x60 Bh 3.100 Rp. 75,800.00 Rp. Rp. 234,980.00
Portland Semen kg 9.600 Rp. 1,700.00 Rp. Rp. 16,320.00
Bahan
Pasir pasang m3 0.045 Rp. 400,000.00 Rp. Rp. 18,000.00
Semen warna kg 1.500 Rp. 5,000.00 Rp. Rp. 7,500.00
Pekerja Oh 0.240 Rp. Rp. 100,000.00 Rp.
Tukang Batu Oh 0.120 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.012 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.012 Rp. Rp. 150,000.00 Rp.
276,800.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0012-2007.6.34
Memasang 1 m2 lantai keramik ukuran (40x40) cm
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Lantai keramik 40x40 Bh 6.500 Rp. 16,900.00 Rp. Rp. 109,850.00
Portland Semen kg 8.190 Rp. 1,700.00 Rp. Rp. 13,923.00
Bahan
Pasir pasang m3 0.045 Rp. 400,000.00 Rp. Rp. 18,000.00
Semen warna kg 1.620 Rp. 5,000.00 Rp. Rp. 8,100.00
Pekerja Oh 0.700 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.350 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.035 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.035 Rp. Rp. 150,000.00 Rp.
149,873.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0012-2007.6.35
Memasang 1 m2 lantai keramik ukuran (30x30) cm
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Lantai keramik 30x30 Bh 11.500 Rp. 9,500.00 Rp. Rp. 109,250.00
Portland Semen kg 10.000 Rp. 1,700.00 Rp. Rp. 17,000.00
Bahan
Pasir pasang m3 0.045 Rp. 400,000.00 Rp. Rp. 18,000.00
Semen warna kg 1.500 Rp. 5,000.00 Rp. Rp. 7,500.00
Pekerja Oh 0.700 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.350 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.035 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.035 Rp. Rp. 150,000.00 Rp.
151,750.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0012-2007.6.36
Memasang 1 m2 lantai keramik ukuran (20x20) cm
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Lantai keramik 20x20 Bh 25.000 Rp. 3,800.00 Rp. Rp. 95,000.00
Portland Semen kg 10.400 Rp. 1,700.00 Rp. Rp. 17,680.00
Bahan
Pasir pasang m3 0.045 Rp. 400,000.00 Rp. Rp. 18,000.00
Semen warna kg 1.620 Rp. 5,000.00 Rp. Rp. 8,100.00
Pekerja Oh 0.700 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.350 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.035 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.035 Rp. Rp. 150,000.00 Rp.
138,780.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0012-2007.6.36.1
Memasang 1 m2 dinding keramik ukuran (20x25) cm
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Keramik 20x25 Bh 20.000 Rp. 4,100.00 Rp. Rp. 82,000.00
Portland Semen kg 10.400 Rp. 1,700.00 Rp. Rp. 17,680.00
Bahan
Pasir pasang m3 0.045 Rp. 400,000.00 Rp. Rp. 18,000.00
Semen warna kg 1.620 Rp. 5,000.00 Rp. Rp. 8,100.00
Pekerja Oh 0.700 Rp. Rp. 100,000.00 Rp.
Tukang Batu Oh 0.350 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.035 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.035 Rp. Rp. 150,000.00 Rp.
125,780.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0012-2007.6.44
Memasang 1 m2 lantai karpet
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Karpet m2 1.050 Rp. 98,700.00 Rp. Rp. 103,635.00
Bahan
Lem karpet kg 0.350 Rp. 50,000.00 Rp. Rp. 17,500.00
Pekerja Oh 0.170 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.170 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.017 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.009 Rp. Rp. 150,000.00 Rp.
121,135.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0012-2007.6.46
Memasang 1 m2 lantai parquet
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Parquet m2 1.050 Rp. 175,000.00 Rp. Rp. 183,750.00
Bahan
Lem Kayu kg 0.600 Rp. 40,700.00 Rp. Rp. 24,420.00
Pekerja Oh 0.700 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.350 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.035 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.035 Rp. Rp. 150,000.00 Rp.
208,170.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0012-2007.6.47
Memasang 1 m2 lantai kayu (gym floor)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Gymfloor m2 1.050 Rp. 250,000.00 Rp. Rp. 262,500.00
Bahan
Lem kg 0.600 Rp. 35,000.00 Rp. Rp. 21,000.00
Pekerja Oh 0.700 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.350 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.035 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.035 Rp. Rp. 150,000.00 Rp.
283,500.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0012-2007.6.57
Memasang 1 m2 dinding batu paras
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Batu paras m2 1.100 Rp. 300,000.00 Rp. Rp. 330,000.00
Bahan Portland Semen kg 11.750 Rp. 1,700.00 Rp. Rp. 19,975.00
Pasir pasang m3 0.035 Rp. 400,000.00 Rp. Rp. 14,000.00
Pekerja Oh 0.700 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.350 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.035 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.035 Rp. Rp. 150,000.00 Rp.
363,975.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0012-2007.6.58
Memasang 1 m2 dinding batu tempel hitam
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Batu tempel hitam m2 1.100 Rp. 113,600.00 Rp. Rp. 124,960.00
Bahan Portland Semen kg 11.750 Rp. 1,700.00 Rp. Rp. 19,975.00
Pasir pasang m3 0.035 Rp. 400,000.00 Rp. Rp. 14,000.00
Pekerja Oh 0.700 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.350 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.035 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.035 Rp. Rp. 150,000.00 Rp.
158,935.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0012-2007.6.60
Memasang 1 m2 wall paper
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Wallpaper m2 2.200 Rp. 33,300.00 Rp. Rp. 73,260.00
Bahan
Lem kg 0.250 Rp. 35,000.00 Rp. Rp. 8,750.00
Pekerja Oh 0.350 Rp. Rp. 100,000.00 Rp.
Tukang Oh 0.175 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.017 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.002 Rp. Rp. 150,000.00 Rp.
82,010.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0012-2007.6.61
Memasang 1 m2 floor hardener
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Floor Hardener kg 5.000 Rp. 150,000.00 Rp. Rp. 750,000.00
Pekerja Oh 0.120 Rp. Rp. 100,000.00 Rp.
Tukang Oh 0.120 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.012 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.006 Rp. Rp. 150,000.00 Rp.
750,000.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0012-2007.6.7
Memasang 1 m2 conblok #6 cm
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Conblok #6cm bh 44.000 Rp. 25,000.00 Rp. Rp. 1,100,000.00
Bahan
Pasir urug m3 0.055 Rp. 226,060.00 Rp. Rp. 12,433.30
Pekerja Oh 0.300 Rp. Rp. 100,000.00 Rp.
Tukang Oh 0.200 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.010 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.010 Rp. Rp. 150,000.00 Rp.
1,112,433.30
Jumlah harga =
Pembulatan =
DAFTAR ANALISA PEKERJAAN
SNI.DT 91-0011-2007
PEKERJAAN KAYU

SNI.DT 91-0011-2007.6.1
Membuat dan memasang 1 m3 kusen pintu dan kusen jendela kayu klas I
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Balok kayu kls I m3 1.100 Rp. 3,400,000.00 Rp. Rp. 3,740,000.00
Bahan Paku biasa kg 1.250 Rp. 20,000.00 Rp. Rp. 25,000.00
Lem kayu kg 1.000 Rp. 40,700.00 Rp. Rp. 40,700.00
Pekerja Oh 7.000 Rp. Rp. 100,000.00 Rp.
Tenaga
Tukang Kayu Oh 21.000 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 2.100 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.350 Rp. Rp. 150,000.00 Rp.
3,805,700.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0011-2007.6.2
Membuat dan memasang 1 m3 kusen pintu dan kusen jendela kayu klas II
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Balok kayu kls II m3 1.200 Rp. #N/A Rp. Rp. #N/A
Bahan Paku biasa kg 1.250 Rp. 20,000.00 Rp. Rp. 25,000.00
Lem kayu kg 1.000 Rp. 40,700.00 Rp. Rp. 40,700.00
Pekerja Oh 6.000 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 18.000 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 1.800 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.300 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI.DT 91-0011-2007.6.3
Membuat dan memasang 1 m2 daun pintu panel , kayu klas II
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Papan kayu kls II m3 0.040 Rp. #N/A Rp. Rp. #N/A
Bahan
Lem kayu kg 0.500 Rp. 40,700.00 Rp. Rp. 20,350.00
Pekerja Oh 1.000 Rp. Rp. 100,000.00Rp.
Tukang Kayu Oh 3.000 Rp. Rp. 110,000.00Rp.
Tenaga
Kepala Tukang Oh 0.300 Rp. Rp. 125,000.00Rp.
Mandor Oh 0.050 Rp. Rp. 150,000.00Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI.DT 91-0011-2007.6.6
Membuat dan memasang 1 m2 pintu dan jendela kaca , kayu klas II
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Papan kayu kls II m3 0.024 Rp. #N/A Rp. Rp. #N/A
Bahan
Lem kayu kg 0.300 Rp. 40,700.00 Rp. Rp. 12,210.00
Pekerja Oh 0.800 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 2.400 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.240 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.040 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI.DT 91-0011-2007.6.7
Membuat dan memasang 1 m2 pintu dan jendela jalusi , kayu klas II
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Papan kayu kls II m3 0.064 Rp. #N/A Rp. Rp. #N/A
Bahan
Lem kayu kg 0.500 Rp. 40,700.00 Rp. Rp. 20,350.00
Pekerja Oh 1.000 Rp. Rp. 100,000.00Rp.
Tukang Kayu Oh 3.000 Rp. Rp. 110,000.00Rp.
Tenaga
Kepala Tukang Oh 0.300 Rp. Rp. 125,000.00Rp.
Mandor Oh 0.050 Rp. Rp. 150,000.00Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI.DT 91-0011-2007.6.9
Membuat 1 m2 pintu plywood rangkap rangka expose , kayu klas II
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Papan kayu kls II m3 0.026 Rp. #N/A Rp. Rp. #REF!
Bahan
Bahan Paku Biasa kg 0.030 Rp. 20,000.00 Rp. Rp. 600.00
Lem kayu kg 0.500 Rp. 40,700.00 Rp. Rp. 20,350.00
Tripleks tebal 9 mm lbr 1.000 Rp. 127,000.00 Rp. Rp. 127,000.00
Pekerja Oh 0.800 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 2.400 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.240 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.040 Rp. Rp. 150,000.00 Rp.
#REF!
Jumlah harga =
Pembulatan =

SNI.DT 91-0011-2007.6.10
Memasang 1 m2 jalusi kusen, kayu klas II
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Papan kayu kls II m3 0.060 Rp. #N/A Rp. Rp. #N/A
Bahan
Paku Biasa kg 0.150 Rp. 20,000.00 Rp. Rp. 3,000.00
Pekerja Oh 0.670 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 2.000 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.200 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.335 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI.DT 91-0011-2007.6.13
Memasang 1 m3 konstruksi kuda-kuda konvensional, kayu klas II
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas II m3 1.100 Rp. 2,200,000.00 Rp. Rp. 2,420,000.00
Bahan Besi strip kg 15.000 Rp. 14,800.00 Rp. Rp. 222,000.00
Paku Biasa kg 5.600 Rp. 20,000.00 Rp. Rp. 112,000.00
Pekerja Oh 4.000 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 12.000 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 1.200 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.200 Rp. Rp. 150,000.00 Rp.
2,754,000.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0011-2007.6.15
Memasang 1 m3 konstruksi gordeng, kayu klas II
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas II m3 1.100 Rp. 2,200,000.00 Rp. Rp. 2,420,000.00
Bahan Besi strip kg 15.000 Rp. 14,800.00 Rp. Rp. 222,000.00
Paku Biasa kg 3.000 Rp. 20,000.00 Rp. Rp. 60,000.00
Pekerja Oh 2.400 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 7.200 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.720 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.120 Rp. Rp. 150,000.00 Rp.
2,702,000.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0011-2007.6.16
Memasang 1 m2 rangka atap genteng keramik, kayu klas II
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kaso-kaso (5x5)cm m3 0.014 Rp. 2,300,000.00 Rp. Rp. 32,200.00
Bahan Reng (2x3)cm m3 0.036 Rp. 2,350,000.00 Rp. Rp. 84,600.00
Paku Biasa kg 0.250 Rp. 20,000.00 Rp. Rp. 5,000.00
Pekerja Oh 0.100 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.100 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.010 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.005 Rp. Rp. 150,000.00 Rp.
121,800.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0011-2007.6.17
Memasang 1 m2 rangka atap genteng beton, kayu klas II
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kaso-kaso (5x5)cm m3 0.014 Rp. 2,300,000.00 Rp. Rp. 32,200.00
Bahan Reng (2x3)cm m3 0.057 Rp. 2,350,000.00 Rp. Rp. 133,950.00
Paku Biasa kg 0.250 Rp. 20,000.00 Rp. Rp. 5,000.00
Pekerja Oh 0.100 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.100 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.010 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.005 Rp. Rp. 150,000.00 Rp.
171,150.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0011-2007.6.18
Memasang 1 m2 rangka atap seng BJLS, kayu klas II
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas II m3 0.165 Rp. 2,200,000.00 Rp. Rp. 363,000.00
Bahan
Paku Biasa kg 0.200 Rp. 20,000.00 Rp. Rp. 4,000.00
Pekerja Oh 0.120 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.120 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.012 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.006 Rp. Rp. 150,000.00 Rp.
367,000.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0011-2007.6.19
Memasang 1 m2 rangka plafond, kayu klas III
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.015 Rp. 1,850,000.00 Rp. Rp. 28,490.00
Bahan
Paku Biasa kg 0.200 Rp. 20,000.00 Rp. Rp. 4,000.00
Pekerja Oh 0.150 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.300 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.030 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.075 Rp. Rp. 150,000.00 Rp.
32,490.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0011-2007.6.21
Memasang 1 m' lisplank ukuran ( 1.5"x8") cm, kayu klas II
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas II m3 0.011 Rp. 2,200,000.00 Rp. Rp. 23,760.00
Bahan
Paku Biasa kg 0.100 Rp. 20,000.00 Rp. Rp. 2,000.00
Pekerja Oh 0.100 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.200 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.020 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.005 Rp. Rp. 150,000.00 Rp.
25,760.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0011-2007.6.23
Memasang 1 m2 dinding pemisah (60x120)cm kayu klasIII
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.028 Rp. 1,850,000.00 Rp. Rp. 51,800.00
Bahan
Paku Biasa kg 0.150 Rp. 20,000.00 Rp. Rp. 3,000.00
Pekerja Oh 0.150 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.450 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.045 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.008 Rp. Rp. 150,000.00 Rp.
54,800.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0011-2007.6.25
Memasang 1 m2 dinding partisi plywood rangkap, rangka kayu klas III
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kayu klas III m3 0.028 Rp. 1,850,000.00 Rp. Rp. 51,800.00
Bahan Paku Biasa kg 0.150 Rp. 20,000.00 Rp. Rp. 3,000.00
Lem kayu kg 0.560 Rp. 40,700.00 Rp. Rp. 22,792.00
Tripleks 6mm lbr 0.860 Rp. 84,700.00 Rp. Rp. 72,842.00
Pekerja Oh 0.200 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.600 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.060 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.010 Rp. Rp. 150,000.00 Rp.
150,434.00
Jumlah harga =
Pembulatan =
DAFTAR ANALISA PEKERJAAN
SNI.DT 91-0013-2007
PEKERJAAN LANGIT-LANGIT

SNI.DT 91-0013-2007.6.1
Memasang 1 m2 langit-langit asbes semen
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Asbes m2 1.100 Rp. 10,200.00 Rp. Rp. 11,220.00
Bahan
Paku tripleks kg 0.010 Rp. 25,000.00 Rp. Rp. 250.00
Pekerja Oh 0.030 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.070 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.007 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.004 Rp. Rp. 150,000.00 Rp.
11,470.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0013-2007.6.5
Memasang 1 m2 langit-langit tripleks ukuran (120x240) cm
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Tripleks 4 mm Lbr 0.375 Rp. 56,400.00 Rp. Rp. 21,150.00
Bahan
Paku tripleks kg 0.030 Rp. 25,000.00 Rp. Rp. 750.00
Pekerja Oh 0.100 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.100 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.010 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.005 Rp. Rp. 150,000.00 Rp.
21,900.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0013-2007.6.6
Memasang 1 m2 langit-langit lambriziring kayu, tebal 9 mm
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Lambersering Lbr 4.000 Rp. 15,000.00 Rp. Rp. 60,000.00
Bahan
Paku tripleks kg 0.010 Rp. 25,000.00 Rp. Rp. 250.00
Pekerja Oh 0.800 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.800 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.080 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.040 Rp. Rp. 150,000.00 Rp.
60,250.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0013-2007.6.7
Memasang 1 m2 langit-langit gypsum board ukuran (120x240x 90)mm
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Gypsum board lbr 0.364 Rp. 77,900.00 Rp. Rp. 28,355.60
Bahan
Bahan
Paku skrup kg 0.110 Rp. 50,000.00 Rp. Rp. 5,500.00
Pekerja Oh 0.100 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.050 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.005 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.005 Rp. Rp. 150,000.00 Rp.
33,855.60
Jumlah harga =
Pembulatan =

SNI.DT 91-0013-2007.6.9
Memasang 1 m' list langit-langit kayu profil
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
List kayu profil m' 1.050 Rp. 6,800.00 Rp. Rp. 7,140.00
Bahan
Paku Biasa kg 0.010 Rp. 20,000.00 Rp. Rp. 200.00
Pekerja Oh 0.050 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.050 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.005 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.003 Rp. Rp. 150,000.00 Rp.
7,340.00
Jumlah harga =
Pembulatan =
DAFTAR ANALISA PEKERJAAN
PT. T-38-2000-C
PEKERJAAN PENGECATAN

PT. T-38-2000-C.1
1 m2 pelaburan bidang kayu dengan vernis
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Vernis kg 0.150 Rp. 52,500.00 Rp. Rp. 7,875.00
Dempul kg 0.050 Rp. 12,900.00 Rp. Rp. 645.00
Bahan
Ampelas lbr 0.100 Rp. 2,000.00 Rp. Rp. 200.00
Kuas bh 0.010 Rp. 8,600.00 Rp. Rp. 86.00
Pekerja Oh 0.160 Rp. Rp. 100,000.00 Rp.
Tukang cat Oh 0.160 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.016 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.003 Rp. Rp. 150,000.00 Rp.
8,806.00
Jumlah harga =
Pembulatan =

PT. T-38-2000-C.2
1 m2 pengecatan bidang kayu lama
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Plamur Kayu kg 0.150 Rp. 17,100.00 Rp. Rp. 2,565.00
Bahan Cat dasar kg 0.170 Rp. 17,100.00 Rp. Rp. 2,907.00
Cat Minyak untuk kayu kg 0.170 Rp. 38,800.00 Rp. Rp. 6,596.00
Pekerja Oh 0.070 Rp. Rp. 100,000.00 Rp.
Tukang cat Oh 0.075 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.008 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.003 Rp. Rp. 150,000.00 Rp.
12,068.00
Jumlah harga =
Pembulatan =

PT. T-38-2000-C.3
1 m2 pengecatan bidang kayu baru
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Meni Kayu kg 0.200 Rp. 27,800.00 Rp. Rp. 5,560.00
Plamur Kayu Kg 0.150 Rp. 17,100.00 Rp. Rp. 2,565.00
Bahan
Cat dasar Kg 0.170 Rp. 17,100.00 Rp. Rp. 2,907.00
Cat Minyak untuk kayu Kg 0.260 Rp. 38,800.00 Rp. Rp. 10,088.00
Pekerja Oh 0.070 Rp. Rp. 100,000.00 Rp.
Tukang Batu Oh 0.009 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.006 Rp. Rp. 125,000.00 Rp.
Tenaga
Mandor Oh 0.003 Rp. Rp. 150,000.00 Rp.
21,120.00
Jumlah harga =
Pembulatan =

PT. T-38-2000-C.4
1 m2 pengecatan tembok/plafond baru str vinilex (1 lps plamur, 1 lps cat dasar,2 lps cat penutup)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Plamur Tembok kg 0.100 Rp. 15,000.00 Rp. Rp. 1,500.00
Bahan Cat dasar kg 0.110 Rp. 17,100.00 Rp. Rp. 1,881.00
Cat tembok kg 0.260 Rp. 41,500.00 Rp. Rp. 10,790.00
Pekerja Oh 0.020 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.063 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.006 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.003 Rp. Rp. 150,000.00 Rp.
14,171.00
Jumlah harga =
Pembulatan =

PT. T-38-2000-C.4.1
1 m2 pengecatan tembok/plafond lama str vinilex ( 1 lps cat dasar,2 lps cat penutup)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Cat dasar kg 0.100 Rp. 17,100.00 Rp. Rp. 1,710.00
Bahan
Cat tembok kg 0.260 Rp. 41,500.00 Rp. Rp. 10,790.00
Pekerja Oh 0.020 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.063 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.006 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.003 Rp. Rp. 150,000.00 Rp.
12,500.00
Jumlah harga =
Pembulatan =

PT. T-38-2000-C.4.2
1 m2 pengecatan tembok/plafond lama str vinilex ( 2 lps cat penutup)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Cat dasar kg 0.260 Rp. 17,100.00 Rp. Rp. 4,446.00
Pekerja Oh 0.020 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.063 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.006 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.003 Rp. Rp. 150,000.00 Rp.
4,446.00
Jumlah harga =
Pembulatan =

PT. T-38-2000-C.5
1 m2 pengecatan tembok/plafond baru str paragon (1 lps plamur, 1 lps cat dasar,2 lps cat penutup)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Plamur Tembok kg 0.100 Rp. 15,000.00 Rp. Rp. 1,500.00
Bahan Cat dasar kg 0.100 Rp. 17,100.00 Rp. Rp. 1,710.00
Cat tembok kg 0.260 Rp. 41,500.00 Rp. Rp. 10,790.00
Pekerja Oh 0.020 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.063 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.006 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.003 Rp. Rp. 150,000.00 Rp.
14,000.00
Jumlah harga =
Pembulatan =

PT. T-38-2000-C.5.1
1 m2 pengecatan tembok/plafond lama str paragon ( 1 lps cat dasar,2 lps cat penutup)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Cat dasar kg 0.100 Rp. 17,100.00 Rp. Rp. 1,710.00
Bahan
Cat tembok kg 0.260 Rp. 41,500.00 Rp. Rp. 10,790.00
Pekerja Oh 0.020 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.063 Rp. Rp. 110,000.00 Rp.
Tenaga
Tenaga
Kepala Tukang Oh 0.006 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.003 Rp. Rp. 150,000.00 Rp.
12,500.00
Jumlah harga =
Pembulatan =

PT. T-38-2000-C.5.2
1 m2 pengecatan tembok/plafond lama str paragon (2 lps cat penutup)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Cat tembok kg 0.260 Rp. 41,500.00 Rp. Rp. 10,790.00
Pekerja Oh 0.020 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.063 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.006 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.003 Rp. Rp. 150,000.00 Rp.
10,790.00
Jumlah harga =
Pembulatan =

PT. T-38-2000-C.6
1 m2 pengecatan permukaan baja dengan meni besi dan perancah
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Meni besi kg 0.100 Rp. 28,900.00 Rp. Rp. 2,890.00
Bahan Kuas bh 0.010 Rp. 8,600.00 Rp. Rp. 86.00
Kayu Kelas II (Balok) m3 0.002 Rp. 2,000,000.00 Rp. Rp. 4,000.00
Pekerja Oh 0.250 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.225 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.023 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.008 Rp. Rp. 150,000.00 Rp.
6,976.00
Jumlah harga =
Pembulatan =
DAFTAR ANALISA PEKERJAAN
PT. T-30-2000-C
PEKERJAAN KUNCI DAN KACA

PT. T-30-2000-C.1
1 Buah pasang kunci tanam antik
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Kunci Lock KCL biasa 6" (antik) bh 1.000 Rp. 233,100.00 Rp. Rp. 233,100.00
Pekerja Oh 0.060 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.600 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.060 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.003 Rp. Rp. 150,000.00 Rp.
233,100.00
Jumlah harga =
Pembulatan =

PT. T-30-2000-C.2
1 Buah pasang kunci tanam biasa
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Kunci tanam biasa bh 1.000 Rp. 97,900.00 Rp. Rp. 97,900.00
Pekerja Oh 0.010 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.500 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.010 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.005 Rp. Rp. 150,000.00 Rp.
97,900.00
Jumlah harga =
Pembulatan =

PT. T-30-2000-C.3
1 Buah pasang kunci tanam kamar mandi
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Kunci tanam kamar mandi bh 1.000 Rp. 59,500.00 Rp. Rp. 59,500.00
Pekerja Oh 0.005 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.500 Rp. Rp. 110,000.00 Rp.
Tenaga
Tenaga
Kepala Tukang Oh 0.005 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.003 Rp. Rp. 150,000.00 Rp.
59,500.00
Jumlah harga =
Pembulatan =

PT. T-30-2000-C.4
1 Buah pasang kunci silinder
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Kunci silinder bh 1.000 Rp. 37,500.00 Rp. Rp. 37,500.00
Pekerja Oh 0.005 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.500 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.005 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.000 Rp. Rp. 150,000.00 Rp.
37,500.00
Jumlah harga =
Pembulatan =

PT. T-30-2000-C.5
1 Buah pasang engsel pintu
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Engsel pintu Nyilon 4" bh 1.000 Rp. 16,500.00 Rp. Rp. 16,500.00
Pekerja Oh 0.015 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.150 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.015 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.001 Rp. Rp. 150,000.00 Rp.
16,500.00
Jumlah harga =
Pembulatan =

PT. T-30-2000-C.6
1 Buah pasang ensel jendela
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Engsel jendela Nyilon 3" bh 1.000 Rp. 12,200.00 Rp. Rp. 12,200.00
Pekerja Oh 0.010 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.100 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.010 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.001 Rp. Rp. 150,000.00 Rp.
12,200.00
Jumlah harga =
Pembulatan =

PT. T-30-2000-C.7
1 Buah pasang hak angin
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Hak angin biasa pasang 1.000 Rp. 27,200.00 Rp. Rp. 27,200.00
Pekerja Oh 0.020 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.200 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.020 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.010 Rp. Rp. 150,000.00 Rp.
27,200.00
Jumlah harga =
Pembulatan =

PT. T-30-2000-C.8
1 Buah pasang pegangan jendela
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Handle (pegangan) bh 1.000 Rp. 174,200.00 Rp. Rp. 174,200.00
Pekerja Oh 0.015 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.150 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.015 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.001 Rp. Rp. 150,000.00 Rp.
174,200.00
Jumlah harga =
Pembulatan =
PT. T-30-2000-C.9
1 Buah pasang door closer
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Door closer bh 1.000 Rp. 119,300.00 Rp. Rp. 119,300.00
Pekerja Oh 0.050 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.500 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.050 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.003 Rp. Rp. 150,000.00 Rp.
119,300.00
Jumlah harga =
Pembulatan =

PT. T-30-2000-C.11
1 Buah pasang pegangan pintu/door holder
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Door Holder bh 1.000 Rp. 41,500.00 Rp. Rp. 41,500.00
Pekerja Oh 0.050 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.500 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.050 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.003 Rp. Rp. 150,000.00 Rp.
41,500.00
Jumlah harga =
Pembulatan =

PT. T-30-2000-C.12
1 m2 pasang kaca tebal 3 mm
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Kaca 3 mm m2 1.100 Rp. 94,700.00 Rp. Rp. 104,170.00
Pekerja Oh 0.015 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.150 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.015 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.001 Rp. Rp. 150,000.00 Rp.
104,170.00
Jumlah harga =
Pembulatan =

PT. T-30-2000-C.13
1 m2 pasang kaca tebal 5 mm
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Kaca 5 mm m2 1.100 Rp. 157,800.00 Rp. Rp. 173,580.00
Pekerja Oh 0.015 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.150 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.015 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.001 Rp. Rp. 150,000.00 Rp.
173,580.00
Jumlah harga =
Pembulatan =

PT. T-30-2000-C.14
1 m2 pasang kaca tebal 8 mm
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Kaca 8 mm m2 1.100 Rp. 252,500.00 Rp. Rp. 277,750.00
Pekerja Oh 0.017 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.165 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.017 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.001 Rp. Rp. 150,000.00 Rp.
277,750.00
Jumlah harga =
Pembulatan =

PT. T-30-2000-C.15
1 m2 pasang kaca buram tebal 12 mm
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Kaca 12 mm m2 1.100 Rp. 378,800.00 Rp. Rp. 416,680.00
Pekerja Oh 0.025 Rp. Rp. 100,000.00 Rp.
Tukang kayu Oh 0.250 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.025 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.001 Rp. Rp. 150,000.00 Rp.
416,680.00
Jumlah harga =
Pembulatan =
DAFTAR ANALISA PEKERJAAN
RSNI. T-15-2002
PEKERJAAN SANITASI

RSNI. T-15-2002.1
Memasang 1 buah kloset duduk/monobox
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kloset duduk bh 1.000 Rp. 2,099,200.00 Rp. Rp. 2,099,200.00
Bahan
Perlengkapan 30% Dari bahaRp. 629,760.00 Rp. Rp. 629,760.00
Pekerja Oh 3.300 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 1.100 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.001 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.160 Rp. Rp. 150,000.00 Rp.
2,728,960.00
Jumlah harga =
Pembulatan =

RSNI. T-15-2002.2
Memasang I buah kloset jongkok porselen
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Kloset jongkok porselin bh 1.000 Rp. 244,900.00 Rp. Rp. 244,900.00
Bahan Portland Semen kg 6.000 Rp. 1,700.00 Rp. Rp. 10,200.00
Pasir pasang m3 0.010 Rp. 400,000.00 Rp. Rp. 4,000.00
Pekerja Oh 1.000 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 1.500 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 1.500 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.160 Rp. Rp. 150,000.00 Rp.
259,100.00
Jumlah harga =
Pembulatan =

RSNI. T-15-2002.3
Memasang i1 buah urinoir
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Urinoir bh 1.000 Rp. 605,900.00 Rp. Rp. 605,900.00
Perlengkapan 30% ari bahan Rp. 181,770.00 Rp. Rp. 181,770.00
Bahan
Portland Semen kg 6.000 Rp. 1,700.00 Rp. Rp. 10,200.00
Pasir pasang m3 0.010 Rp. 400,000.00 Rp. Rp. 4,000.00
Pekerja Oh 1.000 Rp. Rp. 100,000.00 Rp.
Tukang Batu Oh 1.000 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.100 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.100 Rp. Rp. 150,000.00 Rp.
801,870.00
Jumlah harga =
Pembulatan =

RSNI. T-15-2002.4
Memasang 1 buah wastafel
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Westafel biasa bh 1.000 Rp. 572,000.00 Rp. Rp. 572,000.00
Perlengkapan 30% dari bahanRp. 171,600.00 Rp. Rp. 171,600.00
Bahan
Semen Warna kg 6.000 Rp. 5,000.00 Rp. Rp. 30,000.00
Pasir pasang m3 0.010 Rp. 400,000.00 Rp. Rp. 4,000.00
Pekerja Oh 1.000 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 1.450 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.150 Rp. Rp. 125,000.00 Rp.
Tenaga
Mandor Oh 0.100 Rp. Rp. 150,000.00 Rp.
777,600.00
Jumlah harga =
Pembulatan =

RSNI. T-15-2002.6
Memasang 1 buah bak mandi fiberglass volume 0.3 m3
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bak fibreglass bh 1.000 Rp. #N/A Rp. Rp. #N/A
Bahan
Perlengkapan
Pekerja Oh 1.800 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 2.700 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.540 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.110 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

RSNI. T-15-2002.7
Memasang 1 buah bak mandi batu bata volume 0.3 m3
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bata merah bh 0.400 Rp. - Rp. Rp. 0.00
Semen portland kg 120.000 Rp. #N/A Rp. Rp. #N/A
Bahan Pair pasang m3 0.300 Rp. #N/A Rp. Rp. #N/A
Keramik polos 20x20cm m2 7.200 Rp. #N/A Rp. Rp. #N/A
Semen putih 40 kg kg 6.000 Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 6.000 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 3.000 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.300 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.300 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

RSNI. T-15-2002.8
Memasang 1 buah bak cuci piring stainless steel
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Bak cuci stainless steel 2 lobang komplit unit 1.000 Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.030 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.300 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.030 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.002 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

RSNI. T-15-2002.10
Memasang 1 buah kran Ø 3/4" atau 1/2"
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Kran air lokal bh 1.000 Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.010 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.100 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.010 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.005 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

RSNI. T-15-2002.11
Memasanh 1 buah floor drain
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Floor drain bh 1.000 Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.010 Rp. Rp. 100,000.00 Rp.
Tukang batu Oh 0.100 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.010 Rp. Rp. 125,000.00 Rp.
Tenaga
Mandor Oh 0.005 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

RSNI. T-15-2002.12
Memasang 1 m' pipa PVC tipe AW Ø1/2"
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Pipa PVC D 1/2" m' 1.200 Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.036 Rp. Rp. 100,000.00Rp.
Tukang batu Oh 0.060 Rp. Rp. 110,000.00Rp.
Tenaga
Kepala Tukang Oh 0.006 Rp. Rp. 125,000.00Rp.
Mandor Oh 0.002 Rp. Rp. 150,000.00Rp.
#N/A
Jumlah harga =
Pembulatan =

RSNI. T-15-2002.13
Memasang 1 m' pipa PVC tipe AW Ø3/4"
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Pipa PVC tipe AW Ø 3/4' m' 1.200 Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.036 Rp. Rp. 100,000.00Rp.
Tukang batu Oh 0.060 Rp. Rp. 110,000.00Rp.
Tenaga
Kepala Tukang Oh 0.006 Rp. Rp. 125,000.00Rp.
Mandor Oh 0.002 Rp. Rp. 150,000.00Rp.
#N/A
Jumlah harga =
Pembulatan =

RSNI. T-15-2002.14
Memasang 1 m' pipa PVC tipe AW Ø1 "
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Pipa PVC tipe AW Ø 1' m' 1.200 Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.036 Rp. Rp. 100,000.00Rp.
Tukang batu Oh 0.060 Rp. Rp. 110,000.00Rp.
Tenaga
Kepala Tukang Oh 0.006 Rp. Rp. 125,000.00Rp.
Mandor Oh 0.002 Rp. Rp. 150,000.00Rp.
#N/A
Jumlah harga =
Pembulatan =

RSNI. T-15-2002.15
Memasang 1 m' pipa PVC tipe AW Ø 1 1/2"
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Pipa PVC tipe AW Ø 1 1/2" m' 1.200 Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.036 Rp. Rp. 100,000.00Rp.
Tukang batu Oh 0.060 Rp. Rp. 110,000.00Rp.
Tenaga
Kepala Tukang Oh 0.006 Rp. Rp. 125,000.00Rp.
Mandor Oh 0.002 Rp. Rp. 150,000.00Rp.
#N/A
Jumlah harga =
Pembulatan =

RSNI. T-15-2002.16
Memasang 1 m' pipa PVC tipe AW Ø 2"
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Pipa PVC tipe AW Ø 2" m' 1.200 Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.054 Rp. Rp. 100,000.00Rp.
Tukang batu Oh 0.090 Rp. Rp. 110,000.00Rp.
Tenaga
Kepala Tukang Oh 0.009 Rp. Rp. 125,000.00Rp.
Mandor Oh 0.003 Rp. Rp. 150,000.00Rp.
#N/A
Jumlah harga =
Pembulatan =
RSNI. T-15-2002.17
Memasang 1 m' pipa PVC tipe AW Ø 2 1/2"
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Pipa PVC tipe AW Ø 2 1/2" m' 1.200 Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.036 Rp. Rp. 100,000.00
Rp.
Tukang batu Oh 0.060 Rp. Rp. 110,000.00
Rp.
Tenaga
Kepala Tukang Oh 0.006 Rp. Rp. 125,000.00
Rp.
Mandor Oh 0.002 Rp. Rp. 150,000.00
Rp.
#N/A
Jumlah harga =
Pembulatan =

RSNI. T-15-2002.18
Memasang 1 m' pipa PVC tipe AW Ø 3"
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Pipa PVC tipe AW Ø 3" m' 1.200 Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.081 Rp. Rp. 100,000.00
Rp.
Tukang kayu Oh 0.135 Rp. Rp. 110,000.00
Rp.
Tenaga
Kepala Tukang Oh 0.014 Rp. Rp. 125,000.00
Rp.
Mandor Oh 0.004 Rp. Rp. 150,000.00
Rp.
#N/A
Jumlah harga =
Pembulatan =

RSNI. T-15-2002.19
Memasang 1 m' pipa PVC tipe AW Ø 4"
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Pipa PVC tipe AW Ø 4" m' 1.200 Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.081 Rp. Rp. 100,000.00
Rp.
Tukang kayu Oh 0.135 Rp. Rp. 110,000.00
Rp.
Tenaga
Kepala Tukang Oh 0.014 Rp. Rp. 125,000.00
Rp.
Mandor Oh 0.004 Rp. Rp. 150,000.00
Rp.
#N/A
Jumlah harga =
Pembulatan =
DAFTAR ANALISA PEKERJAAN
SNI. 03-3436-1994
PEKERJAAN PENUTUP ATAP

SNI. 03-3436-1994.1
1 m2 pasang atap genteng keramik
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Genteng keramik Lbr 11.000 Rp. #N/A Rp. Rp. #N/A
Bahan
Paku biasa 2"-5" kg 0.030 Rp. 16,300.00 Rp. Rp. 489.00
Pekerja Oh 0.200 Rp. Rp. 100,000.00
Rp.
Tukang Kayu Oh 0.100 Rp. Rp. 110,000.00
Rp.
Tenaga
Kepala Tukang Oh 0.010 Rp. Rp. 125,000.00
Rp.
Mandor Oh 0.010 Rp. Rp. 150,000.00
Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI. 03-3436-1994.2
1 m' pasang nok genteng keramik
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Rabung genteng keramik lbr 3.500 Rp. #N/A Rp. Rp. #N/A
Paku biasa 2"-5" kg 0.050 Rp. 16,300.00 Rp. Rp. 815.00
Bahan Semen abu-abu kg 10.800 Rp. #N/A Rp. Rp. #N/A
Pasir pasang m3 0.032 Rp. 400,000.00 Rp. Rp. 12,800.00
Semen warna kg 1.000 Rp. 5,000.00 Rp. Rp. 5,000.00
Pekerja Oh 0.400 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.200 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.020 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.020 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI. 03-3436-1994.3
1 m2 pasang atap genteng beton
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Genteng beton Lbr 11.000 Rp. #N/A Rp. Rp. #N/A
Bahan
Paku biasa 2"-5" kg 0.030 Rp. 16,300.00 Rp. Rp. 489.00
Pekerja Oh 0.200 Rp. Rp. 100,000.00
Rp.
Tukang Kayu Oh 0.100 Rp. Rp. 110,000.00
Rp.
Tenaga
Kepala Tukang Oh 0.010 Rp. Rp. 125,000.00
Rp.
Mandor Oh 0.010 Rp. Rp. 150,000.00
Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI. 03-3436-1994.4
1 m' pasang nok genteng beton
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Rabung genteng beton lbr 3.500 Rp. #N/A Rp. Rp. #N/A
Paku biasa 2"-5" kg 0.050 Rp. 16,300.00 Rp. Rp. 815.00
Bahan Semen abu-abu kg 10.800 Rp. #N/A Rp. Rp. #N/A
Pasir pasang m3 0.032 Rp. 400,000.00 Rp. Rp. 12,800.00
Semen warna kg 1.000 Rp. 5,000.00 Rp. Rp. 5,000.00
Pekerja Oh 0.400 Rp. Rp. 100,000.00
Rp.
Tukang Kayu Oh 0.200 Rp. Rp. 110,000.00
Rp.
Tenaga
Kepala Tukang Oh 0.020 Rp. Rp. 125,000.00
Rp.
Mandor Oh 0.020 Rp. Rp. 150,000.00
Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI. 03-3436-1994.5
1 m2 pasang atap genteng metal
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Genteng metal Lbr 1.020 Rp. #N/A Rp. Rp. #N/A
Bahan
Paku biasa 2"-5" kg 0.200 Rp. 16,300.00 Rp. Rp. 3,260.00
Pekerja Oh 0.200 Rp. Rp. 100,000.00
Rp.
Tukang Kayu Oh 0.100 Rp. Rp. 110,000.00
Rp.
Tenaga
Kepala Tukang Oh 0.010 Rp. Rp. 125,000.00
Rp.
Mandor Oh 0.001 Rp. Rp. 150,000.00
Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI. 03-3436-1994.6
1 m' pasang nok genteng metal
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Rabung genteng metal Lbr 1.100 Rp. #N/A Rp. Rp. #N/A
Bahan
Paku biasa 1/2"-1" kg 0.050 Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.250 Rp. Rp. 100,000.00
Rp.
Tukang Kayu Oh 0.150 Rp. Rp. 110,000.00
Rp.
Tenaga
Kepala Tukang Oh 0.015 Rp. Rp. 125,000.00
Rp.
Mandor Oh 0.013 Rp. Rp. 150,000.00
Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI. 03-3436-1994.7
1 m2 pasang atap seng gelombang
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Seng gelombang 3"x6" BJLS 32 Lbr 0.700 Rp. #N/A Rp. Rp. #N/A
Bahan
Paku biasa 1/2"-1" kg 0.020 Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.120 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.060 Rp. Rp. 110,000.00 Rp.
Tenaga
Tenaga
Kepala Tukang Oh 0.006 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.006 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI. 03-3436-1994.8
1 m2 pasang atap nok seng
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Rabung seng Lbr 0.300 Rp. #N/A Rp. Rp. #N/A
Bahan
Paku biasa 1/2"-1" kg 0.040 Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.015 Rp. Rp. 100,000.00 Rp.
Tukang Kayu Oh 0.070 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.008 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.006 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =
DAFTAR ANALISA PEKERJAAN
SNI.DT 91-0014-2007
PEKERJAAN BESI DAN ALUMINIUM

SNI.DT 91-0014-2007.6.1
Memasang 1 kg besi profil
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Besi Profil kg 1.150 Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.060 Rp. Rp. 100,000.00 Rp.
Tukang las Oh 0.060 Rp. Rp. #N/A Rp.
Tenaga
Kepala Tukang Oh 0.006 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.003 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI.DT 91-0014-2007.6.2
Memasang 1 kg rangka kuda-kuda baj IWF
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Besi baja IWF kg 1.150 Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.060 Rp. Rp. 100,000.00 Rp.
Tukang Oh 0.060 Rp. Rp. #N/A Rp.
Tenaga
Kepala Tukang Oh 0.006 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.003 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI.DT 91-0014-2007.6.7
Memasang 1 m2 pintu rollling door besi
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Pintu gulung besi m2 1.000 Rp. 899,900.00 Rp. Rp. 899,900.00
Pekerja Oh 1.200 Rp. Rp. 100,000.00 Rp.
Tukang Oh 1.200 Rp. Rp. #N/A Rp.
Tenaga
Kepala Tukang Oh 0.120 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.006 Rp. Rp. 150,000.00 Rp.
899,900.00
Jumlah harga =
Pembulatan =

SNI.DT 91-0014-2007.6.8
Memasang 1 m2 pintu lipat (folding door)
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Bahan Pintu lipat m2 1.000 Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.440 Rp. Rp. 100,000.00 Rp.
Tukang Oh 0.440 Rp. Rp. #N/A Rp.
Tenaga
Kepala Tukang Oh 0.044 Rp. Rp. 125,000.00 Rp.
Tenaga
Mandor Oh 0.022 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI.DT 91-0014-2007.6.20
Memasang 1 m' pipa galvanis diameter 1/2"
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Pipa galvanis m' 1.200 Rp. #N/A Rp. Rp. #N/A
Bahan
Perlengkapan 35% Harga pipRp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.054 Rp. Rp. 100,000.00 Rp.
Tukang Oh 0.090 Rp. Rp. #N/A Rp.
Tenaga
Kepala Tukang Oh 0.009 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.027 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI.DT 91-0014-2007.6.20A
Memasang 1 m' pipa galvanis diameter 3/4"
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Pipa galvanis m' 1.200 Rp. #N/A Rp. Rp. #N/A
Bahan
Perlengkapan 35% Harga pip Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.054 Rp. Rp. 100,000.00 Rp.
Tukang Oh 0.090 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.009 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.027 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI.DT 91-0014-2007.6.20B
Memasang 1 m' pipa galvanis diameter 1"
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Pipa galvanis m' 1.200 Rp. #N/A Rp. Rp. #N/A
Bahan
Perlengkapan 35% Harga pip Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.054 Rp. Rp. 100,000.00 Rp.
Tukang Oh 0.090 Rp. Rp. #N/A Rp.
Tenaga
Kepala Tukang Oh 0.009 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.027 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI.DT 91-0014-2007.6.20C
Memasang 1 m' pipa galvanis diameter 1 1/2"
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Pipa galvanis m' 1.200 Rp. #N/A Rp. Rp. #N/A
Bahan
Perlengkapan 35% Harga pipRp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.108 Rp. Rp. 100,000.00 Rp.
Tukang Oh 0.180 Rp. Rp. #N/A Rp.
Tenaga
Kepala Tukang Oh 0.018 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.005 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI.DT 91-0014-2007.6.20D
Memasang 1 m' pipa galvanis diameter 2"
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Pipa galvanis m' 1.200 Rp. #N/A Rp. Rp. #N/A
Bahan
Perlengkapan 35% Harga pipRp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.108 Rp. Rp. 100,000.00 Rp.
Tukang Oh 0.180 Rp. Rp. #N/A Rp.
Tenaga
Kepala Tukang Oh 0.018 Rp. Rp. 125,000.00 Rp.
Tenaga
Mandor Oh 0.005 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI.DT 91-0014-2007.6.20E
Memasang 1 m' pipa galvanis diameter 2 1/2"
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Pipa galvanis m' 1.200 Rp. #N/A Rp. Rp. #N/A
Bahan
Perlengkapan 35% Harga pipRp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.108 Rp. Rp. 100,000.00 Rp.
Tukang Oh 0.180 Rp. Rp. #N/A Rp.
Tenaga
Kepala Tukang Oh 0.018 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.005 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI.DT 91-0014-2007.6.20F
Memasang 1 m' pipa galvanis diameter 3"
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Pipa galvanis m' 1.200 Rp. #N/A Rp. Rp. #N/A
Bahan
Perlengkapan 35% Harga pipRp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.108 Rp. Rp. 100,000.00 Rp.
Tukang Oh 0.180 Rp. Rp. #N/A Rp.
Tenaga
Kepala Tukang Oh 0.018 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.005 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI.DT 91-0014-2007.6.20G
Memasang 1 m' pipa galvanis diameter 4"
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Pipa galvanis m' 1.200 Rp. #N/A Rp. Rp. #N/A
Bahan
Perlengkapan 35% Harga pip Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.108 Rp. Rp. 100,000.00 Rp.
Tukang Oh 0.180 Rp. Rp. #N/A Rp.
Tenaga
Kepala Tukang Oh 0.018 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.005 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI.DT 91-0014-2007.6.20H
Memasang 1 m' pipa galvanis diameter 5"
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Pipa galvanis m' 1.200 Rp. #N/A Rp. Rp. #N/A
Bahan
Perlengkapan 35% Harga pip Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.108 Rp. Rp. 100,000.00 Rp.
Tukang Oh 0.180 Rp. Rp. 110,000.00 Rp.
Tenaga
Kepala Tukang Oh 0.018 Rp. Rp. 125,000.00 Rp.
Mandor Oh 0.005 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =

SNI.DT 91-0014-2007.6.20I
Memasang 1 m' pipa galvanis diameter 6"
Kebutuhan Satuan Indeks Harga satuan Harga satuan Jumlah harga bahan
Pipa galvanis m' 1.200 Rp. #N/A Rp. Rp. #N/A
Bahan
Perlengkapan 35% Harga pip Rp. #N/A Rp. Rp. #N/A
Pekerja Oh 0.108 Rp. Rp. 100,000.00 Rp.
Tukang Oh 0.180 Rp. Rp. #N/A Rp.
Tenaga
Kepala Tukang Oh 0.018 Rp. Rp. 125,000.00 Rp.
Tenaga
Mandor Oh 0.005 Rp. Rp. 150,000.00 Rp.
#N/A
Jumlah harga =
Pembulatan =
Jumlah harga upah
Rp. #N/A
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 40,000.00
Rp. 22,000.00
Rp. 2,500.00
Rp. 3,000.00
67,500.00
Rp. 884,405.00
Rp. 884,410.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 10,000.00
Rp. 11,000.00
Rp. 1,250.00
Rp. 750.00
23,000.00
Rp. 62,800.00
Rp. 62,800.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 200,000.00
Rp. 220,000.00
Rp. 110,000.00
Rp. 37,500.00
Rp. 7,500.00
575,000.00
Rp. 1,621,246.00
Rp. 1,621,250.00
Jumlah harga upah
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 100,000.00
Rp. 220,000.00
Rp. 25,000.00
Rp. 7,500.00
352,500.00
Rp. 1,118,100.00
Rp. 1,118,100.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp. 100,000.00
Rp. 165,000.00
Rp. 18,750.00
Rp. 7,500.00
291,250.00
Rp. 1,290,750.00
Rp. 1,290,750.00

Jumlah harga upah


Rp. 10,000.00
Rp. 7,500.00
17,500.00
Rp. 17,500.00
Rp. 17,500.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

Rp. 100,000.00
Rp. 220,000.00
Rp. 25,000.00
Rp. 7,500.00
352,500.00
Rp. 1,146,570.00
Rp. 1,146,570.00
Jumlah harga upah
Rp. 75,000.00
Rp. 3,750.00
78,750.00
Rp. 78,750.00
Rp. 78,750.00

Jumlah harga upah


Rp. 90,000.00
Rp. 6,750.00
96,750.00
Rp. 96,750.00
Rp. 96,800.00

Jumlah harga upah


Rp. 105,000.00
Rp. 10,050.00
115,050.00
Rp. 115,050.00
Rp. 115,100.00

Jumlah harga upah


Rp. 150,000.00
Rp. 9,000.00
159,000.00
Rp. 159,000.00
Rp. 159,000.00

Jumlah harga upah


Rp. 120,000.00
Rp. 6,750.00
126,750.00
Rp. 126,750.00
Rp. 126,800.00

Jumlah harga upah


Rp. 5,000.00
Rp. 750.00
5,750.00
Rp. 5,750.00
Rp. 5,750.00

Jumlah harga upah


Rp. 33,000.00
Rp. 1,500.00
34,500.00
Rp. 34,500.00
Rp. 34,500.00

Jumlah harga upah


Rp. 38,366.67
Rp. 38,370.00

Jumlah harga upah


Rp. 50,000.00
Rp. 7,500.00
57,500.00
Rp. 57,500.00
Rp. 57,500.00

Jumlah harga upah


Rp.

Rp. 30,000.00
Rp. 1,500.00
31,500.00
Rp. 302,700.00
Rp. 302,700.00

Jumlah harga upah


Rp.

Rp. 30,000.00
Rp. 1,500.00
31,500.00
Rp. 114,300.00
Rp. 114,300.00

Jumlah harga upah


Rp.

Rp. 15,000.00
Rp. 2,250.00
17,250.00
Rp. 179,250.00
Rp. 179,250.00

Jumlah harga upah


Rp.

Rp. 25,000.00
Rp. 3,750.00
28,750.00
Rp. 423,550.00
Rp. 423,550.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 150,000.00
Rp. 82,500.00
Rp. 9,375.00
Rp. 11,250.00
253,125.00
Rp. 1,316,525.00
Rp. 1,316,530.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 150,000.00
Rp. 82,500.00
Rp. 9,375.00
Rp. 11,250.00
253,125.00
Rp. 1,458,225.00
Rp. 1,458,230.00

Jumlah harga upah


Rp.
Rp.
Rp. 78,000.00
Rp. 42,900.00
Rp. 4,875.00
Rp. 5,850.00
131,625.00
Rp. 949,282.92
Rp. 949,280.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 340,000.00
Rp. 93,500.00
Rp. 10,625.00
Rp. 25,500.00
469,625.00
Rp. 4,116,165.00
Rp. 4,116,170.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp. 240,000.00
Rp. 88,000.00
Rp. 10,000.00
Rp. 17,850.00
355,850.00
Rp. 1,431,450.00
Rp. 1,431,450.00

Jumlah harga upah


Rp. 3150
Rp. 1400
Rp. 1350
Rp. 1000
Rp. 165,000.00
Rp. 30,250.00
Rp. 3,500.00
Rp. 12,450.00
211,200.00
Rp. 1,744,075.00
Rp. 1,744,080.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 0
Rp. 165,000.00
Rp. 30,250.00
Rp. 3,500.00
Rp. 12,450.00
211,200.00
Rp. 1,483,125.00
Rp. 1,483,130.00

Jumlah harga upah


Rp.

Rp.
Rp. 0
Rp. 165,000.00
Rp. 30,250.00
Rp. 3,500.00
Rp. 12,450.00
211,200.00
Rp. 1,512,875.00
Rp. 1,512,880.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 0
Rp. 165,000.00
Rp. 30,250.00
Rp. 3,500.00
Rp. 12,450.00
211,200.00
Rp. 1,548,575.00
Rp. 1,548,580.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 0
Rp. 165,000.00
Rp. 30,250.00
Rp. 3,500.00
Rp. 12,450.00 SNI.DT 91-0008-2007.6.7
211,200.00
Rp. 1,582,075.00
Rp. 1,582,080.00

Jumlah harga upah SNI.DT 91-0008-2007.6.28A


Rp.
Rp.
Rp.
Rp. 0
Rp. 165,000.00
Rp. 30,250.00
Rp. 3,500.00
Rp. 12,450.00
211,200.00
Rp. 1,608,375.00
Rp. 1,608,380.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 0
Rp. 165,000.00
Rp. 30,250.00
Rp. 3,500.00
Rp. 12,450.00
211,200.00
Rp. 1,624,475.00
Rp. 1,624,480.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 0
Rp. 165,000.00
Rp. 30,250.00
Rp. 3,500.00
Rp. 12,450.00
211,200.00
Rp. 1,652,825.00
Rp. 1,652,830.00
Jumlah harga upah
Rp.
Rp.
Rp.
Rp. 0
Rp. 165,000.00
Rp. 30,250.00
Rp. 3,500.00
Rp. 12,450.00
211,200.00
Rp. 1,661,275.00
Rp. 1,661,280.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 0
Rp. 210,000.00
Rp. 38,500.00
Rp. 4,375.00
Rp. 15,750.00
268,625.00
Rp. 1,751,750.00
Rp. 1,751,750.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 0
Rp. 210,000.00
Rp. 38,500.00
Rp. 4,375.00
Rp. 15,750.00
268,625.00
Rp. 1,763,150.00
Rp. 1,763,150.00

Jumlah harga upah


Rp.
Rp.
Rp. 7,000.00
Rp. 7,700.00
Rp. 875.00
Rp. 600.00
16,175.00
Rp. 228,920.00
Rp. 228,900.00

Jumlah harga upah


Rp.
Rp.
Rp. 5,000.00
Rp. 5,500.00
Rp. 625.00
Rp. 450.00
11,575.00
Rp. 223,405.00
Rp. 223,400.00

Jumlah harga upah


Rp.
Rp.
Rp. 2,500.00
Rp. 2,750.00
Rp. 3,162.50
Rp. 150.00
8,562.50
Rp. 315,477.50
Rp. 315,500.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 52,000.00
Rp. 28,600.00
Rp. 3,250.00
Rp. 3,900.00
87,750.00
Rp. 168,440.00
Rp. 168,440.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 52,000.00
Rp. 28,600.00
Rp. 3,250.00
Rp. 3,900.00
87,750.00
Rp. 177,690.00
Rp. 177,690.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 66,000.00
Rp. 36,300.00
Rp. 4,125.00
Rp. 4,950.00
111,375.00
Rp. 322,205.00
Rp. 322,210.00
Jumlah harga upah
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 66,000.00
Rp. 36,300.00
Rp. 4,125.00
Rp. 4,950.00
111,375.00
Rp. 328,805.00
Rp. 328,810.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 66,000.00
Rp. 36,300.00
Rp. 4,125.00
Rp. 4,950.00
111,375.00
Rp. 422,205.00
Rp. 422,210.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 66,000.00
Rp. 36,300.00
Rp. 4,125.00
Rp. 4,950.00
111,375.00
Rp. 339,705.00
Rp. 339,710.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 66,000.00
Rp. 36,300.00
Rp. 4,125.00
Rp. 4,950.00
111,375.00
Rp. 303,360.00
Rp. 303,360.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 15,000.00
Rp. 5,500.00
Rp. 625.00
Rp. 1,200.00
22,325.00
Rp. 94,925.00
Rp. 94,930.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 530,000.00
Rp. 30,250.00
Rp. 143,000.00
Rp. 115,500.00
Rp. 32,750.00
Rp. 39,750.00
891,250.00
Rp. 5,243,135.00
Rp. 5,243,140.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 530,000.00
Rp. 30,250.00
Rp. 143,000.00
Rp. 115,500.00
Rp. 32,750.00
Rp. 39,750.00
891,250.00
Rp. 4,783,760.00
Rp. 4,783,760.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 530,000.00
Rp. 30,250.00
Rp. 143,000.00
Rp. 115,500.00
Rp. 32,750.00
Rp. 39,750.00
891,250.00
Rp. 4,324,385.00
Rp. 4,324,390.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 565,000.00
Rp. 30,250.00
Rp. 171,600.00
Rp. 154,000.00
Rp. 40,375.00
Rp. 42,450.00
1,003,675.00
Rp. 6,873,415.00
Rp. 6,873,420.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 565,000.00
Rp. 30,250.00
Rp. 171,600.00
Rp. 154,000.00
Rp. 40,375.00
Rp. 42,450.00
1,003,675.00
Rp. 5,954,665.00
Rp. 5,954,670.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 565,000.00
Rp. 30,250.00
Rp. 171,600.00
Rp. 154,000.00
Rp. 40,375.00
Rp. 42,450.00
1,003,675.00
Rp. 5,495,290.00
Rp. 5,495,290.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 565,000.00
Rp. 30,250.00
Rp. 171,600.00
Rp. 154,000.00
Rp. 40,375.00
Rp. 42,450.00
1,003,675.00
Rp. 5,035,915.00
Rp. 5,035,920.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 705,000.00
Rp. 30,250.00
Rp. 181,500.00
Rp. 231,000.00
Rp. 50,375.00
Rp. 52,950.00
1,251,075.00
Rp. 10,105,925.00
Rp. 10,105,930.00
Jumlah harga upah
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 705,000.00
Rp. 30,250.00
Rp. 181,500.00
Rp. 231,000.00
Rp. 50,375.00
Rp. 52,950.00
1,251,075.00
Rp. 8,268,425.00
Rp. 8,268,430.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 635,000.00
Rp. 30,250.00
Rp. 181,500.00
Rp. 154,000.00
Rp. 41,625.00
Rp. 47,700.00
1,090,075.00
Rp. 7,702,315.00
Rp. 7,702,320.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 635,000.00
Rp. 30,250.00
Rp. 181,500.00
Rp. 154,000.00
Rp. 41,625.00
Rp. 47,700.00
1,090,075.00
Rp. 6,783,565.00
Rp. 6,783,570.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 635,000.00
Rp. 30,250.00
Rp. 181,500.00
Rp. 154,000.00
Rp. 41,625.00
Rp. 47,700.00
1,090,075.00
Rp. 6,324,190.00
Rp. 6,324,190.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 635,000.00
Rp. 30,250.00
Rp. 181,500.00
Rp. 154,000.00
Rp. 41,625.00
Rp. 47,700.00
1,090,075.00
Rp. 5,864,815.00
Rp. 5,864,820.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 530,000.00
Rp. 30,250.00
Rp. 143,000.00
Rp. 115,500.00
Rp. 33,125.00
Rp. 39,750.00
891,625.00
Rp. 6,927,390.00
Rp. 6,927,400.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 530,000.00
Rp. 30,250.00
Rp. 143,000.00
Rp. 115,500.00
Rp. 33,125.00
Rp. 39,750.00
891,625.00
Rp. 6,468,015.00
Rp. 6,468,000.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 530,000.00
Rp. 30,250.00
Rp. 143,000.00
Rp. 115,500.00
Rp. 33,125.00
Rp. 39,750.00
891,625.00
Rp. 6,008,640.00
Rp. 6,008,600.00
Jumlah harga upah
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 530,000.00
Rp. 30,250.00
Rp. 143,000.00
Rp. 115,500.00
Rp. 33,125.00
Rp. 39,750.00
891,625.00
Rp. 6,667,390.00
Rp. 6,667,400.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 530,000.00
Rp. 30,250.00
Rp. 143,000.00
Rp. 115,500.00
Rp. 33,125.00
Rp. 39,750.00
891,625.00
Rp. 6,208,015.00
Rp. 6,208,000.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 530,000.00
Rp. 30,250.00
Rp. 143,000.00
Rp. 115,500.00
Rp. 32,750.00
Rp. 39,750.00
891,250.00
Rp. 5,748,265.00
Rp. 5,748,270.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 565,000.00
Rp. 30,250.00
Rp. 171,600.00
Rp. 154,000.00
Rp. 40,375.00
Rp. 42,450.00
1,003,675.00
Rp. 7,314,555.00
Rp. 7,314,560.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 18,000.00
Rp. 2,200.00
Rp. 2,200.00
Rp. 2,200.00
Rp. 750.00
Rp. 1,350.00
26,700.00
Rp. 112,865.00
Rp. 112,870.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 29,700.00
Rp. 3,630.00
Rp. 3,630.00
Rp. 3,630.00
Rp. 1,250.00
Rp. 2,250.00
44,090.00
Rp. 141,935.00
Rp. 141,940.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 60,000.00
Rp. 22,000.00
Rp. 2,500.00
Rp. 4,500.00
89,000.00
Rp. 194,950.00
Rp. 194,950.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 60,000.00
Rp. 22,000.00
Rp. 2,500.00
Rp. 4,500.00
89,000.00
Rp. 181,415.00
Rp. 181,420.00

Jumlah harga upah


Rp.

Rp.
Rp. 60,000.00
Rp. 22,000.00
Rp. 2,500.00
Rp. 4,500.00
89,000.00
Rp. 171,335.00
Rp. 171,340.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 30,000.00
Rp. 11,000.00
Rp. 1,250.00
Rp. 2,250.00
44,500.00
Rp. 91,915.00
Rp. 91,920.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 30,000.00
Rp. 11,000.00
Rp. 1,250.00
Rp. 2,250.00
44,500.00
Rp. 84,929.00
Rp. 84,930.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 30,000.00
Rp. 11,000.00
Rp. 1,250.00
Rp. 2,250.00
44,500.00
Rp. 81,250.00
Rp. 81,250.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 30,000.00
Rp. 11,000.00
Rp. 1,250.00
Rp. 2,250.00
44,500.00
Rp. 257,200.00
Rp. 257,200.00

Jumlah harga upah


Rp.
Rp.
Rp. 30,000.00
Rp. 16,500.00
Rp. 1,875.00
Rp. 2,250.00
50,625.00
Rp. 83,381.80
Rp. 83,380.00
Jumlah harga upah
Rp.
Rp.
Rp. 30,000.00
Rp. 16,500.00
Rp. 1,875.00
Rp. 2,250.00
50,625.00
Rp. 76,005.80
Rp. 76,010.00

Jumlah harga upah

Rp.
Rp. 30,000.00
Rp. 16,500.00
Rp. 1,875.00
Rp. 2,250.00
50,625.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp. 30,000.00
Rp. 16,500.00
Rp. 1,875.00
Rp. 2,250.00
50,625.00
Rp. 70,833.00
Rp. 70,830.00

Jumlah harga upah


Rp.
Rp.
Rp. 30,000.00
Rp. 11,000.00
Rp. 1,250.00
Rp. 2,250.00
44,500.00
Rp. 54,244.00
Rp. 54,240.00

Jumlah harga upah


Rp.
Rp. 20,000.00
Rp. 11,000.00
Rp. 1,250.00
Rp. 1,500.00
33,750.00
Rp. 39,275.00
Rp. 39,280.00
Jumlah harga upah
Rp.
Rp.
Rp.
Rp.
Rp. 24,000.00
Rp. 13,200.00
Rp. 1,500.00
Rp. 1,800.00
40,500.00
Rp. 317,300.00
Rp. 317,300.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp. 70,000.00
Rp. 38,500.00
Rp. 4,375.00
Rp. 5,250.00
118,125.00
Rp. 267,998.00
Rp. 268,000.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp. 70,000.00
Rp. 38,500.00
Rp. 4,375.00
Rp. 5,250.00
118,125.00
Rp. 269,875.00
Rp. 269,880.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp. 70,000.00
Rp. 38,500.00
Rp. 4,375.00
Rp. 5,250.00
118,125.00
Rp. 256,905.00
Rp. 256,910.00
Jumlah harga upah
Rp.
Rp.
Rp.
Rp.
Rp. 70,000.00
Rp. 38,500.00
Rp. 4,375.00
Rp. 5,250.00
118,125.00
Rp. 243,905.00
Rp. 243,910.00

Jumlah harga upah


Rp.
Rp.
Rp. 17,000.00
Rp. 18,700.00
Rp. 2,125.00
Rp. 1,350.00
39,175.00
Rp. 160,310.00
Rp. 160,310.00

Jumlah harga upah


Rp.
Rp.
Rp. 70,000.00
Rp. 38,500.00
Rp. 4,375.00
Rp. 5,250.00
118,125.00
Rp. 326,295.00
Rp. 326,300.00

Jumlah harga upah


Rp.
Rp.
Rp. 70,000.00
Rp. 38,500.00
Rp. 4,375.00
Rp. 5,250.00
118,125.00
Rp. 401,625.00
Rp. 401,630.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 70,000.00
Rp. 38,500.00
Rp. 4,375.00
Rp. 5,250.00
118,125.00
Rp. 482,100.00
Rp. 482,100.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 70,000.00
Rp. 38,500.00
Rp. 4,375.00
Rp. 5,250.00
118,125.00
Rp. 277,060.00
Rp. 277,060.00

Jumlah harga upah


Rp.
Rp.
Rp. 35,000.00
Rp. 19,250.00
Rp. 2,125.00
Rp. 300.00
56,675.00
Rp. 138,685.00
Rp. 138,690.00

Jumlah harga upah


Rp.
Rp. 12,000.00
Rp. 13,200.00
Rp. 1,500.00
Rp. 900.00
27,600.00
Rp. 777,600.00
Rp. 777,600.00

Jumlah harga upah


Rp.
Rp.
Rp. 30,000.00
Rp. 22,000.00
Rp. 1,250.00
Rp. 1,500.00
54,750.00
Rp. 1,167,183.30
Rp. 1,167,180.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 700,000.00
Rp. 2,310,000.00
Rp. 262,500.00
Rp. 52,500.00
3,325,000.00
Rp. 7,130,700.00
Rp. 7,130,700.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 600,000.00
Rp. 1,980,000.00
Rp. 225,000.00
Rp. 45,000.00
2,850,000.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp. 100,000.00
Rp. 330,000.00
Rp. 37,500.00
Rp. 7,500.00
475,000.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp. 80,000.00
Rp. 264,000.00
Rp. 30,000.00
Rp. 6,000.00
380,000.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp. 100,000.00
Rp. 330,000.00
Rp. 37,500.00
Rp. 7,500.00
475,000.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp.

Rp. 80,000.00
Rp. 264,000.00
Rp. 30,000.00
Rp. 6,000.00
380,000.00
Rp. #REF!
Rp. #REF!

Jumlah harga upah


Rp.
Rp.
Rp. 67,000.00
Rp. 220,000.00
Rp. 25,000.00
Rp. 50,250.00
362,250.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 400,000.00
Rp. 1,320,000.00
Rp. 150,000.00
Rp. 30,000.00
1,900,000.00
Rp. 4,654,000.00
Rp. 4,654,000.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 240,000.00
Rp. 792,000.00
Rp. 90,000.00
Rp. 18,000.00
1,140,000.00
Rp. 3,842,000.00
Rp. 3,842,000.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 10,000.00
Rp. 11,000.00
Rp. 1,250.00
Rp. 750.00
23,000.00
Rp. 144,800.00
Rp. 144,800.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 10,000.00
Rp. 11,000.00
Rp. 1,250.00
Rp. 750.00
23,000.00
Rp. 194,150.00
Rp. 194,150.00

Jumlah harga upah


Rp.
Rp.
Rp. 12,000.00
Rp. 13,200.00
Rp. 1,500.00
Rp. 900.00
27,600.00
Rp. 394,600.00
Rp. 394,600.00

Jumlah harga upah


Rp.
Rp.
Rp. 15,000.00
Rp. 33,000.00
Rp. 3,750.00
Rp. 11,250.00
63,000.00
Rp. 95,490.00
Rp. 95,490.00

Jumlah harga upah


Rp.
Rp.
Rp. 10,000.00
Rp. 22,000.00
Rp. 2,500.00
Rp. 750.00
35,250.00
Rp. 61,010.00
Rp. 61,010.00

Jumlah harga upah


Rp.
Rp.
Rp. 15,000.00
Rp. 49,500.00
Rp. 5,625.00
Rp. 1,200.00
71,325.00
Rp. 126,125.00
Rp. 126,130.00

Jumlah harga upah


Rp.
Rp.
Rp.

Rp. 20,000.00
Rp. 66,000.00
Rp. 7,500.00
Rp. 1,500.00
95,000.00
Rp. 245,434.00
Rp. 245,430.00

Jumlah harga upah


Rp.
Rp.
Rp. 3,000.00
Rp. 7,700.00
Rp. 875.00
Rp. 600.00
12,175.00
Rp. 23,645.00
Rp. 23,650.00

Jumlah harga upah


Rp.
Rp.
Rp. 10,000.00
Rp. 11,000.00
Rp. 1,250.00
Rp. 750.00
23,000.00
Rp. 44,900.00
Rp. 44,900.00

Jumlah harga upah


Rp.
Rp.
Rp. 80,000.00
Rp. 88,000.00
Rp. 10,000.00
Rp. 6,000.00
184,000.00
Rp. 244,250.00
Rp. 244,250.00

Jumlah harga upah


Rp.
Rp.
Rp. 10,000.00
Rp. 5,500.00
Rp. 625.00
Rp. 750.00
16,875.00
Rp. 50,730.60
Rp. 50,730.00

Jumlah harga upah


Rp.
Rp.
Rp. 5,000.00
Rp. 5,500.00
Rp. 625.00
Rp. 450.00
11,575.00
Rp. 18,915.00
Rp. 18,920.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp. 16,000.00
Rp. 17,600.00
Rp. 2,000.00
Rp. 375.00
35,975.00
Rp. 44,781.00
Rp. 44,780.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 7,000.00
Rp. 8,250.00
Rp. 937.50
Rp. 375.00
16,562.50
Rp. 28,630.50
Rp. 28,630.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp. 7,000.00
Rp. 990.00
Rp. 750.00
Rp. 375.00
9,115.00
Rp. 30,235.00
Rp. 30,240.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 2,000.00
Rp. 6,930.00
Rp. 787.50
Rp. 375.00
10,092.50
Rp. 24,263.50
Rp. 24,260.00

Jumlah harga upah


Rp.
Rp.
Rp. 2,000.00
Rp. 6,930.00
Rp. 787.50
Rp. 375.00
10,092.50
Rp. 22,592.50
Rp. 22,590.00

Jumlah harga upah


Rp.
Rp. 2,000.00
Rp. 6,930.00
Rp. 787.50
Rp. 375.00
10,092.50
Rp. 14,538.50
Rp. 14,540.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 2,000.00
Rp. 6,930.00
Rp. 787.50
Rp. 375.00
10,092.50
Rp. 24,092.50
Rp. 24,090.00

Jumlah harga upah


Rp.
Rp.
Rp. 2,000.00
Rp. 6,930.00
Rp. 787.50
Rp. 375.00
10,092.50
Rp. 22,592.50
Rp. 22,590.00

Jumlah harga upah


Rp.
Rp. 2,000.00
Rp. 6,930.00
Rp. 787.50
Rp. 375.00
10,092.50
Rp. 20,882.50
Rp. 20,880.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 25,000.00
Rp. 24,750.00
Rp. 2,812.50
Rp. 1,125.00
53,687.50
Rp. 60,663.50
Rp. 60,660.00

Jumlah harga upah


Rp.
Rp. 6,000.00
Rp. 66,000.00
Rp. 7,500.00
Rp. 450.00
79,950.00
Rp. 313,050.00
Rp. 313,050.00

Jumlah harga upah


Rp.
Rp. 1,000.00
Rp. 55,000.00
Rp. 1,250.00
Rp. 750.00
58,000.00
Rp. 155,900.00
Rp. 155,900.00

Jumlah harga upah


Rp.
Rp. 500.00
Rp. 55,000.00
Rp. 625.00
Rp. 375.00
56,500.00
Rp. 116,000.00
Rp. 116,000.00

Jumlah harga upah


Rp.
Rp. 500.00
Rp. 55,000.00
Rp. 625.00
Rp. 37.50
56,162.50
Rp. 93,662.50
Rp. 93,660.00

Jumlah harga upah


Rp.
Rp. 1,500.00
Rp. 16,500.00
Rp. 1,875.00
Rp. 112.50
19,987.50
Rp. 36,487.50
Rp. 36,490.00

Jumlah harga upah


Rp.
Rp. 1,000.00
Rp. 11,000.00
Rp. 1,250.00
Rp. 75.00
13,325.00
Rp. 25,525.00
Rp. 25,530.00

Jumlah harga upah


Rp.
Rp. 2,000.00
Rp. 22,000.00
Rp. 2,500.00
Rp. 1,500.00
28,000.00
Rp. 55,200.00
Rp. 55,200.00

Jumlah harga upah


Rp.
Rp. 1,500.00
Rp. 16,500.00
Rp. 1,875.00
Rp. 112.50
19,987.50
Rp. 194,187.50
Rp. 194,190.00
Jumlah harga upah
Rp.
Rp. 5,000.00
Rp. 55,000.00
Rp. 6,250.00
Rp. 375.00
66,625.00
Rp. 185,925.00
Rp. 185,930.00

Jumlah harga upah


Rp.
Rp. 5,000.00
Rp. 55,000.00
Rp. 6,250.00
Rp. 375.00
66,625.00
Rp. 108,125.00
Rp. 108,130.00

Jumlah harga upah


Rp.
Rp. 1,500.00
Rp. 16,500.00
Rp. 1,875.00
Rp. 112.50
19,987.50
Rp. 124,157.50
Rp. 124,160.00

Jumlah harga upah


Rp.
Rp. 1,500.00
Rp. 16,500.00
Rp. 1,875.00
Rp. 112.50
19,987.50
Rp. 193,567.50
Rp. 193,600.00

Jumlah harga upah


Rp.
Rp. 1,650.00
Rp. 18,150.00
Rp. 2,062.50
Rp. 120.00
21,982.50
Rp. 299,732.50
Rp. 299,700.00

Jumlah harga upah


Rp.
Rp. 2,500.00
Rp. 27,500.00
Rp. 3,125.00
Rp. 187.50
33,312.50
Rp. 449,992.50
Rp. 450,000.00

Jumlah harga upah


Rp.
Rp.
Rp. 330,000.00
Rp. 121,000.00
Rp. 125.00
Rp. 24,000.00
475,125.00
Rp. 3,204,085.00
Rp. 3,204,090.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp. 100,000.00
Rp. 165,000.00
Rp. 187,500.00
Rp. 24,000.00
476,500.00
Rp. 735,600.00
Rp. 735,600.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp. 100,000.00
Rp. 110,000.00
Rp. 12,500.00
Rp. 15,000.00
237,500.00
Rp. 1,039,370.00
Rp. 1,039,370.00

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp. 100,000.00
Rp. 159,500.00
Rp. 18,750.00
Rp. 15,000.00
293,250.00
Rp. 1,070,850.00
Rp. 1,070,850.00

Jumlah harga upah


Rp.
Rp.
Rp. 180,000.00
Rp. 297,000.00
Rp. 67,500.00
Rp. 16,500.00
561,000.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 600,000.00
Rp. 330,000.00
Rp. 37,500.00
Rp. 45,000.00
1,012,500.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp. 3,000.00
Rp. 33,000.00
Rp. 3,750.00
Rp. 300.00
40,050.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp. 1,000.00
Rp. 11,000.00
Rp. 1,250.00
Rp. 750.00
14,000.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp. 1,000.00
Rp. 11,000.00
Rp. 1,250.00
Rp. 750.00
14,000.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp. 3,600.00
Rp. 6,600.00
Rp. 750.00
Rp. 270.00
11,220.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp. 3,600.00
Rp. 6,600.00
Rp. 750.00
Rp. 270.00
11,220.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp. 3,600.00
Rp. 6,600.00
Rp. 750.00
Rp. 270.00
11,220.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp. 3,600.00
Rp. 6,600.00
Rp. 750.00
Rp. 270.00
11,220.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp. 5,400.00
Rp. 9,900.00
Rp. 1,125.00
Rp. 405.00
16,830.00
Rp. #N/A
Rp. #N/A
Jumlah harga upah
Rp.
Rp. 3,600.00
Rp. 6,600.00
Rp. 750.00
Rp. 270.00
11,220.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp. 8,100.00
Rp. 14,850.00
Rp. 1,687.50
Rp. 615.00
25,252.50
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp. 8,100.00
Rp. 14,850.00
Rp. 1,687.50
Rp. 615.00
25,252.50
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp. 20,000.00
Rp. 11,000.00
Rp. 1,250.00
Rp. 1,500.00
33,750.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 40,000.00
Rp. 22,000.00
Rp. 2,500.00
Rp. 3,000.00
67,500.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp. 20,000.00
Rp. 11,000.00
Rp. 1,250.00
Rp. 1,500.00
33,750.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp.
Rp.
Rp.
Rp. 40,000.00
Rp. 22,000.00
Rp. 2,500.00
Rp. 3,000.00
67,500.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp. 20,000.00
Rp. 11,000.00
Rp. 1,250.00
Rp. 150.00
32,400.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp. 25,000.00
Rp. 16,500.00
Rp. 1,875.00
Rp. 1,950.00
45,325.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp. 12,000.00
Rp. 6,600.00
Rp. 750.00
Rp. 900.00
20,250.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp. 1,500.00
Rp. 7,700.00
Rp. 1,000.00
Rp. 900.00
11,100.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp. 6,000.00
Rp. #N/A
Rp. 750.00
Rp. 450.00
#N/A
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp. 6,000.00
Rp. #N/A
Rp. 750.00
Rp. 450.00
#N/A
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp. 120,000.00
Rp. #N/A
Rp. 15,000.00
Rp. 900.00
#N/A
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp. 44,000.00
Rp. #N/A
Rp. 5,500.00
Rp. 3,300.00
#N/A
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp. 5,400.00
Rp. #N/A
Rp. 1,125.00
Rp. 4,050.00
#N/A
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp. 5,400.00
Rp. 9,900.00
Rp. 1,125.00
Rp. 4,050.00
20,475.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp. 5,400.00
Rp. #N/A
Rp. 1,125.00
Rp. 4,050.00
#N/A
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp. 10,800.00
Rp. #N/A
Rp. 2,250.00
Rp. 810.00
#N/A
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp. 10,800.00
Rp. #N/A
Rp. 2,250.00
Rp. 810.00
#N/A
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp. 10,800.00
Rp. #N/A
Rp. 2,250.00
Rp. 810.00
#N/A
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp. 10,800.00
Rp. #N/A
Rp. 2,250.00
Rp. 810.00
#N/A
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp. 10,800.00
Rp. #N/A
Rp. 2,250.00
Rp. 810.00
#N/A
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp. 10,800.00
Rp. 19,800.00
Rp. 2,250.00
Rp. 810.00
33,660.00
Rp. #N/A
Rp. #N/A

Jumlah harga upah


Rp.
Rp.
Rp. 10,800.00
Rp. #N/A
Rp. 2,250.00
Rp. 810.00
#N/A
Rp. #N/A
Rp. #N/A
sero ) Pelabuhan Indonesia I
231
REKAPITULASI ANALYSA PEKERJAAN TEKNIK SIPIL

No. No.SNI JENIS PEKERJAAN H. SATUAN (Rp.)

1 2 3 4
A. RSNI.T-15-2002
PEKERJAAN PERSIAPAN
1 RSNI.T-15-2002.1 1 m' Pagar sementara dari seng gelombang tinggi 2 m Rp. 884,410.00
2 RSNI.T-15-2002.2 1 m' Pek. Pengukuran & pemasangan Bowplank Rp. 62,800.00
3 RSNI.T-15-2002.3 1 m2 Pek. Kantor direksi keet dengan lantai plesteran Rp. 1,621,250.00
4 RSNI.T-15-2002.4 1 m2 Pembuatan gudang sementara dan alat-alat Rp. 1,118,100.00
5 RSNI.T-15-2002.5 1 m2 Pembuatan rumah jaga konstruksi kayu Rp. 1,290,750.00
6 RSNI.T-15-2002.6 1 m2 Membersihkan lapangan dan perataan Rp. 17,500.00
7 RSNI.T-15-2002.7 1 m2 Pembuatan bedeng buruh Rp. 1,146,570.00

B. SNI.DT 91-0006-2007
PEKERJAAN TANAH
1 SNI.DT 91-0006-2007.6.1 Menggali 1 m3 tanah biasa sedalam 1 meter Rp. 78,750.00
2 SNI.DT 91-0006-2007.6.2 Menggali 1 m3 tanah biasa sedalam 2 meter Rp. 96,800.00
3 SNI.DT 91-0006-2007.6.3 Menggali 1 m3 tanah biasa sedalam 3 meter Rp. 115,100.00
4 SNI.DT 91-0006-2007.6.5 Menggali 1 m3 tanah cadas sedalam 1 meter Rp. 159,000.00
5 SNI.DT 91-0006-2007.6.6 Menggali 1 m3 tanah lumpur sedalam 1 meter Rp. 126,800.00
6 SNI.DT 91-0006-2007.6.7 Mengerjakan 1 m2 stripping tebing setinggi 1 meter Rp. 5,750.00
7 SNI.DT 91-0006-2007.6.8 Membuang 1 m3 tanah sejauh 30 meter Rp. 34,500.00
8 SNI.DT 91-0006-2007.6.8 A Membuang 1 m3 tanah /bahan galian/adukan beton/mortar/dll
Rp.
sejauh 60 meter
9 SNI.DT 91-0006-2007.6.8 B Membuang 1 m3 tanah /bahan galian/adukan beton/mortar/dll
Rp.
sejauh 90 meter
10 SNI.DT 91-0006-2007.6.8 C Membuang 1 m3 tanah /bahan galian/adukan beton/mortar/dll
Rp.
sejauh 120 meter
11 SNI.DT 91-0006-2007.6.8 D Membuang 1 m3 tanah /bahan galian/adukan beton/mortar/dll
Rp.
sejauh 150 meter
12 SNI.DT 91-0006-2007.6.8 E Membuang 1 m3 tanah /bahan galian/adukan beton/mortar/dll
Rp.
sejauh 180 meter
13 SNI.DT 91-0006-2007.6.8 F Membuang 1 m3 tanah /bahan galian/adukan beton/mortar/dll
Rp.
sejauh 180 meter
14 SNI.DT 91-0006-2007.6.8 G Membuang 1 m3 tanah /bahan galian/adukan beton/mortar/dll
Rp.
sejauh 240 meter
15 SNI.DT 91-0006-2007.6.8 H Membuang 1 m3 tanah /bahan galian/adukan beton/mortar/dll
Rp.
sejauh 270 meter
16 SNI.DT 91-0006-2007.6.8 I Membuang 1 m3 tanah /bahan galian/adukan beton/mortar/dll
Rp.
sejauh 300 meter
17 SNI.DT 91-0006-2007.6.9 Mengurug kembali 1 m3 galian Rp. 38,370.00
18 SNI.DT 91-0006-2007.6.10 Memadatkan 1 m3 tanah (per 20 cm) Rp. 57,500.00
19 SNI.DT 91-0006-2007.6.11 Mengurug 1 m3 pasir urug Rp. 302,700.00
20 SNI.DT 91-0006-2007.6.12 Mengurug 1 m3 tanah urug Rp. 114,300.00
22 SNI.DT 91-0006-2007.6.14 Memasang 1 m2 lapisan ijuk tebal 10 cm Rp. 179,250.00
23 SNI.DT 91-0006-2007.6.15 Mengurug 1 m3 sirtu padat untuk peninggian lantai bangunan Rp. 423,550.00

C. SNI.DT 91-0007-2006
PEKERJAAN PONDASI
1 SNI.DT 91-0007-2006.6.1 Memasang 1 m3 pondasi batu belah, campuran 1 PC: 3 PP Rp. 1,316,530.00
2 SNI.DT 91-0007-2006.6.2 Memasang 1 m3 pondasi batu belah, campuran 1 PC: 4 PP Rp. 1,458,230.00
3 SNI.DT 91-0007-2006.6.9 Memasang 1 m3 batu kosong (anstamping) Rp. 949,280.00
4 SNI.DT 91-0007-2006.6.10 Memasang 1 m3 pondasi siklop campuran 1 PC:2PB:3KR Rp. 4,116,170.00
5 SNI.DT 91-0007-2006.6.11 Memasang 1 m3 pondasi sumuran, diameter 100 cm Rp. 1,431,450.00

D. SNI.DT 91-0008-2007
PEKERJAAN BETON
1 SNI.DT 91-0008-2007.6.1 Membuat 1 m3 beton mutu K 100 Rp. 1,744,080.00
2 SNI.DT 91-0008-2007.6.2 Membuat 1 m3 beton mutu K 125 Rp. 1,483,130.00
3 SNI.DT 91-0008-2007.6.4 Membuat 1 m3 beton mutu K 150 Rp. 1,512,880.00
4 SNI.DT 91-0008-2007.6.5 Membuat 1 m3 beton mutu K 175 Rp. 1,548,580.00
5 SNI.DT 91-0008-2007.6.6 Membuat 1 m3 beton mutu f'c = 16.9 Mpa k200 Rp. 1,582,080.00
sero ) Pelabuhan Indonesia I
232
REKAPITULASI ANALYSA PEKERJAAN TEKNIK SIPIL

No. No.SNI JENIS PEKERJAAN H. SATUAN (Rp.)

1 2 3 4
6 SNI.DT 91-0008-2007.6.7 Membuat 1 m3 beton mutu K 225 Rp. 1,608,380.00
7 SNI.DT 91-0008-2007.6.8 Membuat 1 m3 beton mutu K 250 Rp. 1,624,480.00
8 SNI.DT 91-0008-2007.6.9 Membuat 1 m3 beton mutu K 275 Rp. 1,652,830.00
9 SNI.DT 91-0008-2007.6.10 Membuat 1 m3 beton mutu K 300 Rp. 1,661,280.00
10 SNI.DT 91-0008-2007.6.11 Membuat 1 m3 beton mutu K 325 Rp. 1,751,750.00
11 SNI.DT 91-0008-2007.6.12 Membuat 1 m3 beton mutu K 350 Rp. 1,763,150.00
12 SNI.DT 91-0008-2007.6.17 Pembesian 10 kg dengan besi polos atau besi ulir Rp. 228,900.00
13 SNI.DT 91-0008-2007.6.18 Memasang 10 kg kabel pres stressed polos /strands Rp. 223,400.00
14 SNI.DT 91-0008-2007.6.19 Memasang 10 kg jaring kawat baja/wire mest Rp. 315,500.00
15 SNI.DT 91-0008-2007.6.20 Memasang 1 m2 bekisting untuk pondasi Rp. 168,440.00
16 SNI.DT 91-0008-2007.6.21 Memasang 1 m2 bekisting untuk sloof Rp. 177,690.00
17 SNI.DT 91-0008-2007.6.22 Memasang 1 m2 bekisting untuk kolom Rp. 322,210.00
18 SNI.DT 91-0008-2007.6.23 Memasang 1 m2 bekisting untuk balok Rp. 328,810.00
19 SNI.DT 91-0008-2007.6.24 Memasang 1 m2 bekisting untuk lantai Rp. 422,210.00
20 SNI.DT 91-0008-2007.6.25 Memasang 1 m2 bekisting untuk dinding Rp. 339,710.00
21 SNI.DT 91-0008-2007.6.26 Memasang 1 m2 bekisting untuk tangga Rp. 303,360.00
22 SNI.DT 91-0008-2007.6.27 Memasang 1 m2 jembatan untuk pengecoran beton Rp. 94,930.00
23 SNI.DT 91-0008-2007.6.28 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting) Rp. 5,243,140.00
24 SNI.DT 91-0008-2007.6.28A Membuat 1 m3 pondasi beton bertulang (125 kg besi + bekisting) Rp. 4,783,760.00
25 SNI.DT 91-0008-2007.6.28B Membuat 1 m3 pondasi beton bertulang (100 kg besi + bekisting) Rp. 4,324,390.00
26 SNI.DT 91-0008-2007.6.29 Membuat 1 m3 sloof beton bertulang (200 kg besi + bekisting) Rp. 6,873,420.00
27 SNI.DT 91-0008-2007.6.29A Membuat 1 m3 sloof beton bertulang (150 kg besi + bekisting) Rp. 5,954,670.00
28 SNI.DT 91-0008-2007.6.29B Membuat 1 m3 sloof beton bertulang (125 kg besi + bekisting) Rp. 5,495,290.00
29 SNI.DT 91-0008-2007.6.29C Membuat 1 m3 sloof beton bertulang (100 kg besi + bekisting) Rp. 5,035,920.00
30 SNI.DT 91-0008-2007.6.30 Membuat 1 m3 kolom beton bertulang (300 kg besi + bekisting) Rp. 10,105,930.00
31 SNI.DT 91-0008-2007.6.30A Membuat 1 m3 kolom beton bertulang (200 kg besi + bekisting) Rp. 8,268,430.00
32 SNI.DT 91-0008-2007.6.31 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) Rp. 7,702,320.00
33 SNI.DT 91-0008-2007.6.31A Membuat 1 m3 balok beton bertulang (150 kg besi + bekisting) Rp. 6,783,570.00
34 SNI.DT 91-0008-2007.6.31B Membuat 1 m3 balok beton bertulang (125 kg besi + bekisting) Rp. 6,324,190.00
35 SNI.DT 91-0008-2007.6.31C Membuat 1 m3 balok beton bertulang (100 kg besi + bekisting) Rp. 5,864,820.00
36 SNI.DT 91-0008-2007.6.32 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) Rp. 6,927,400.00
37 SNI.DT 91-0008-2007.6.32A Membuat 1 m3 kolom beton bertulang (125 kg besi + bekisting) Rp. 6,468,000.00
38 SNI.DT 91-0008-2007.6.32B Membuat 1 m3 kolom beton bertulang (100 kg besi + bekisting) Rp. 6,008,600.00
39 SNI.DT 91-0008-2007.6.33 Membuat 1 m3 dinding beton bertulang (150 kg besi + bekisting) Rp. 6,667,400.00
40 SNI.DT 91-0008-2007.6.33A Membuat 1 m3 dinding beton bertulang (125 kg besi + bekisting) Rp. 6,208,000.00
41 SNI.DT 91-0008-2007.6.33B Membuat 1 m3 dinding beton bertulang (100 kg besi + bekisting) Rp. 5,748,270.00
42 SNI.DT 91-0008-2007.6.34 Membuat 1 m3 dinding beton bertulang (200 kg besi + bekisting) Rp. 7,314,560.00
43 SNI.DT 91-0008-2007.6.35 Membuat 1 m' kolom praktis beton bertulang (11x11) cm Rp. 112,870.00
44 SNI.DT 91-0008-2007.6.36 Membuat 1 m' ring balok beton bertulang (10x15) cm Rp. 141,940.00

E. SNI.DT 91-0009-2007
PEKERJAAN DINDING
1 SNI.DT 91-0009-2007.6.1 Memasang 1 m2 dinding bata merah tebal 1 bata, campuran spesi
Rp.
1 PC: 2PP 194,950.00
2 SNI.DT 91-0009-2007.6.2 Memasang 1 m2 dinding bata merah tebal 1 bata, campuran spesi
Rp.
1 PC: 3PP 181,420.00
3 SNI.DT 91-0009-2007.6.3 Memasang 1 m2 dinding bata merah tebal 1 bata, campuran spesi
Rp.
1 PC: 4PP 171,340.00
4 SNI.DT 91-0009-2007.6.7 Memasang 1 m2 dinding bata merah tebal 1/2 bata, campuran
Rp.
spesi 1 PC: 2PP 91,920.00
5 SNI.DT 91-0009-2007.6.8 Memasang 1 m2 dinding bata merah tebal 1/2 bata, campuran
Rp.
spesi 1 PC: 3PP 84,930.00
6 SNI.DT 91-0009-2007.6.9 Memasang 1 m2 dinding bata merah tebal 1/2 bata, campuran
Rp.
spesi 1 PC: 4PP 81,250.00
7 SNI.DT 91-0009-2007.6.23 Memasang 1 m2 dinding terawang campuran spesi 1 PC: 4PP Rp. 257,200.00

F. SNI.DT 91-0010-2007
PEKERJAAN PLESTERAN
1 SNI.DT 91-0010-2007.6.1 Memasang 1 m2 plesteran 1 PC: 1PP, tebal 15 mm Rp. 83,380.00
2 SNI.DT 91-0010-2007.6.2 Memasang 1 m2 plesteran 1 PC: 2PP, tebal 15 mm Rp. 76,010.00
3 SNI.DT 91-0010-2007.6.3 Memasang 1 m2 plesteran 1 PC: 3PP, tebal 15 mm Rp. #N/A
4 SNI.DT 91-0010-2007.6.4 Memasang 1 m2 plesteran 1 PC: 4PP, tebal 15 mm Rp. 70,830.00
sero ) Pelabuhan Indonesia I
233
REKAPITULASI ANALYSA PEKERJAAN TEKNIK SIPIL

No. No.SNI JENIS PEKERJAAN H. SATUAN (Rp.)

1 2 3 4
5 SNI.DT 91-0010-2007.6.23 Memasang 1 m2 plesteran ciprat 1 PC: 2PP Rp. 54,240.00
6 SNI.DT 91-0010-2007.6.27 Memasang 1 m2 acian Rp. 39,280.00
sero ) Pelabuhan Indonesia I
234
REKAPITULASI ANALYSA PEKERJAAN TEKNIK SIPIL

No. No.SNI JENIS PEKERJAAN H. SATUAN (Rp.)

1 2 3 4

G. SNI.DT 91-0011-2007
PEKERJAAN KAYU
1 SNI.DT 91-0011-2007.6.1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela kayu
Rp.
klas I 7,130,700.00
2 SNI.DT 91-0011-2007.6.2 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela kayu
Rp.
klas II #N/A
3 SNI.DT 91-0011-2007.6.3 Membuat dan memasang 1 m2 daun pintu panel , kayu klas II Rp. #N/A
4 SNI.DT 91-0011-2007.6.6 Membuat dan memasang 1 m2 pintu dan jendela kaca , kayu klas II
Rp.
#N/A
5 SNI.DT 91-0011-2007.6.7 Membuat dan memasang 1 m2 pintu dan jendela jalusi , kayu klas
Rp.
II #N/A
6 SNI.DT 91-0011-2007.6.9 Membuat 1 m2 pintu plywood rangkap rangka expose , kayu klas II
Rp.
#REF!
7 SNI.DT 91-0011-2007.6.10 Memasang 1 m2 jalusi kusen, kayu klas II Rp. #N/A
8 SNI.DT 91-0011-2007.6.13 Memasang 1 m3 konstruksi kuda-kuda konvensional, kayu klas II
Rp.
4,654,000.00
9 SNI.DT 91-0011-2007.6.15 Memasang 1 m3 konstruksi gordeng, kayu klas II Rp. 3,842,000.00
10 SNI.DT 91-0011-2007.6.16 Memasang 1 m2 rangka atap genteng keramik, kayu klas II Rp. 144,800.00
11 SNI.DT 91-0011-2007.6.17 Memasang 1 m2 rangka atap genteng beton, kayu klas II Rp. 194,150.00
12 SNI.DT 91-0011-2007.6.18 Memasang 1 m2 rangka atap seng BJLS, kayu klas II Rp. 394,600.00
13 SNI.DT 91-0011-2007.6.19 Memasang 1 m2 rangka plafond, kayu klas III Rp. 95,490.00
14 SNI.DT 91-0011-2007.6.21 Memasang 1 m' lisplank ukuran ( 1.5"x8") cm, kayu klas II Rp. 61,010.00
15 SNI.DT 91-0011-2007.6.23 Memasang 1 m2 dinding pemisah (60x120)cm kayu klasIII Rp. 126,130.00
16 SNI.DT 91-0011-2007.6.25 Memasang 1 m2 dinding partisi plywood rangkap, rangka kayu klas
Rp.
III 245,430.00

H. SNI.DT 91-0012-2007
PEKERJAAN PENUTUP LANTAI DAN DINDING
1 SNI.DT 91-0012-2007.6.13 Memasang 1 m2 lantai keramik ukuran (60x60) cm Rp. 317,300.00
2 SNI.DT 91-0012-2007.6.34 Memasang 1 m2 lantai keramik ukuran (40x40) cm Rp. 268,000.00
3 SNI.DT 91-0012-2007.6.35 Memasang 1 m2 lantai keramik ukuran (30x30) cm Rp. 269,880.00
4 SNI.DT 91-0012-2007.6.36 Memasang 1 m2 lantai keramik ukuran (20x20) cm Rp. 256,910.00
5 SNI.DT 91-0012-2007.6.36.1 Memasang 1 m2 dinding keramik ukuran (20x25) cm Rp. 243,910.00
6 SNI.DT 91-0012-2007.6.44 Memasang 1 m2 lantai karpet Rp. 160,310.00
7 SNI.DT 91-0012-2007.6.46 Memasang 1 m2 lantai parquet Rp. 326,300.00
8 SNI.DT 91-0012-2007.6.47 Memasang 1 m2 lantai kayu (gym floor) Rp. 401,630.00
9 SNI.DT 91-0012-2007.6.57 Memasang 1 m2 dinding batu paras Rp. 482,100.00
10 SNI.DT 91-0012-2007.6.58 Memasang 1 m2 dinding batu tempel hitam Rp. 277,060.00
11 SNI.DT 91-0012-2007.6.60 Memasang 1 m2 wall paper Rp. 138,690.00
12 SNI.DT 91-0012-2007.6.61 Memasang 1 m2 floor hardener Rp. 777,600.00
13 SNI.DT 91-0012-2007.6.7 Memasang 1 m2 conblok #6 cm Rp. 1,167,180.00

I. SNI.DT 91-0013-2007
PEKERJAAN LANGIT-LANGIT
1 SNI.DT 91-0013-2007.6.1 Memasang 1 m2 langit-langit asbes semen Rp. 23,650.00
2 SNI.DT 91-0013-2007.6.5 Memasang 1 m2 langit-langit tripleks ukuran (120x240) cm Rp. 44,900.00
3 SNI.DT 91-0013-2007.6.6 Memasang 1 m2 langit-langit lambriziring kayu, tebal 9 mm Rp. 244,250.00
4 SNI.DT 91-0013-2007.6.7 Memasang 1 m2 langit-langit gypsum board ukuran (120x240x
Rp.
90)mm 50,730.00
5 SNI.DT 91-0013-2007.6.9 Memasang 1 m' list langit-langit kayu profil Rp. 18,920.00

J. SNI.DT 91-0014-2007
PEKERJAAN BESI DAN ALUMINIUM
1 SNI.DT 91-0014-2007.6.1 Memasang 1 kg besi profil Rp. #N/A
2 SNI.DT 91-0014-2007.6.2 Memasang 1 kg rangka kuda-kuda baj IWF Rp. #N/A
3 SNI.DT 91-0014-2007.6.7 Memasang 1 m2 pintu rollling door besi Rp. #N/A
4 SNI.DT 91-0014-2007.6.8 Memasang 1 m2 pintu lipat (folding door) Rp. #N/A
sero ) Pelabuhan Indonesia I
235
REKAPITULASI ANALYSA PEKERJAAN TEKNIK SIPIL

No. No.SNI JENIS PEKERJAAN H. SATUAN (Rp.)

1 2 3 4
5 SNI.DT 91-0014-2007.6.20 Memasang 1 m' pipa galvanis diameter 1/2" Rp. #N/A
6 SNI.DT 91-0014-2007.6.20A Memasang 1 m' pipa galvanis diameter 3/4" Rp. #N/A
7 SNI.DT 91-0014-2007.6.20B Memasang 1 m' pipa galvanis diameter 1" Rp. #N/A
8 SNI.DT 91-0014-2007.6.20C Memasang 1 m' pipa galvanis diameter 1 1/2" Rp. #N/A
9 SNI.DT 91-0014-2007.6.20D Memasang 1 m' pipa galvanis diameter 2" Rp. #N/A
10 SNI.DT 91-0014-2007.6.20E Memasang 1 m' pipa galvanis diameter 2 1/2" Rp. #N/A
11 SNI.DT 91-0014-2007.6.20F Memasang 1 m' pipa galvanis diameter 3" Rp. #N/A
12 SNI.DT 91-0014-2007.6.20G Memasang 1 m' pipa galvanis diameter 4" Rp. #N/A
13 SNI.DT 91-0014-2007.6.20H Memasang 1 m' pipa galvanis diameter 5" Rp. #N/A
14 SNI.DT 91-0014-2007.6.20I Memasang 1 m' pipa galvanis diameter 6" Rp. #N/A

K. SNI. 03-3436-1994
PEKERJAAN PENUTUP ATAP
1 SNI. 03-3436-1994.1 1 m2 pasang atap genteng keramik Rp. #N/A
2 SNI. 03-3436-1994.2 1 m' pasang nok genteng keramik Rp. #N/A
3 SNI. 03-3436-1994.3 1 m2 pasang atap genteng beton Rp. #N/A
4 SNI. 03-3436-1994.4 1 m' pasang nok genteng beton Rp. #N/A
5 SNI. 03-3436-1994.5 1 m2 pasang atap genteng metal Rp. #N/A
6 SNI. 03-3436-1994.6 1 m' pasang nok genteng metal Rp. #N/A
7 SNI. 03-3436-1994.7 1 m2 pasang atap seng gelombang Rp. #N/A
8 SNI. 03-3436-1994.8 1 m2 pasang atap nok seng Rp. #N/A

L. RSNI. T-15-2002
PEKERJAAN SANITASI
1 RSNI. T-15-2002.1 Memasang 1 buah kloset duduk/monobox Rp. 3,204,090.00
2 RSNI. T-15-2002.2 Memasang I buah kloset jongkok porselen Rp. 735,600.00
3 RSNI. T-15-2002.3 Memasang i1 buah urinoir Rp. 1,039,370.00
4 RSNI. T-15-2002.4 Memasang 1 buah wastafel Rp. 1,070,850.00
5 RSNI. T-15-2002.6 Memasang 1 buah bak mandi fiberglass volume 0.3 m3 Rp. #N/A
6 RSNI. T-15-2002.7 Memasang 1 buah bak mandi batu bata volume 0.3 m3 Rp. #N/A
7 RSNI. T-15-2002.8 Memasang 1 buah bak cuci piring stainless steel Rp. #N/A
8 RSNI. T-15-2002.10 Memasang 1 buah kran Ø 3/4" atau 1/2" Rp. #N/A
9 RSNI. T-15-2002.11 Memasanh 1 buah floor drain Rp. #N/A
10 RSNI. T-15-2002.12 Memasang 1 m' pipa PVC tipe AW Ø1/2" Rp. #N/A
11 RSNI. T-15-2002.13 Memasang 1 m' pipa PVC tipe AW Ø3/4" Rp. #N/A
12 RSNI. T-15-2002.14 Memasang 1 m' pipa PVC tipe AW Ø1 " Rp. #N/A
13 RSNI. T-15-2002.15 Memasang 1 m' pipa PVC tipe AW Ø 1 1/2" Rp. #N/A
14 RSNI. T-15-2002.16 Memasang 1 m' pipa PVC tipe AW Ø 2" Rp. #N/A
15 RSNI. T-15-2002.17 Memasang 1 m' pipa PVC tipe AW Ø 2 1/2" Rp. #N/A
16 RSNI. T-15-2002.18 Memasang 1 m' pipa PVC tipe AW Ø 3" Rp. #N/A
17 RSNI. T-15-2002.19 Memasang 1 m' pipa PVC tipe AW Ø 4" Rp. #N/A

M. PT. T-30-2000-C
PEKERJAAN KUNCI DAN KACA
1 PT. T-30-2000-C.1 1 Buah pasang kunci tanam antik Rp. 313,050.00
2 PT. T-30-2000-C.2 1 Buah pasang kunci tanam biasa Rp. 155,900.00
3 PT. T-30-2000-C.3 1 Buah pasang kunci tanam kamar mandi Rp. 116,000.00
4 PT. T-30-2000-C.4 1 Buah pasang kunci silinder Rp. 93,660.00
5 PT. T-30-2000-C.5 1 Buah pasang engsel pintu Rp. 36,490.00
6 PT. T-30-2000-C.6 1 Buah pasang ensel jendela Rp. 25,530.00
7 PT. T-30-2000-C.7 1 Buah pasang hak angin Rp. 55,200.00
8 PT. T-30-2000-C.8 1 Buah pasang pegangan jendela Rp. 194,190.00
9 PT. T-30-2000-C.9 1 Buah pasang door closer Rp. 185,930.00
10 PT. T-30-2000-C.11 1 Buah pasang pegangan pintu/door holder Rp. 108,130.00
11 PT. T-30-2000-C.12 1 m2 pasang kaca tebal 3 mm Rp. 124,160.00
12 PT. T-30-2000-C.13 1 m2 pasang kaca tebal 5 mm Rp. 193,600.00
13 PT. T-30-2000-C.14 1 m2 pasang kaca tebal 8 mm Rp. 299,700.00
14 PT. T-30-2000-C.15 1 m2 pasang kaca buram tebal 12 mm Rp. 450,000.00
sero ) Pelabuhan Indonesia I
236
REKAPITULASI ANALYSA PEKERJAAN TEKNIK SIPIL

No. No.SNI JENIS PEKERJAAN H. SATUAN (Rp.)

1 2 3 4

N. PT. T-38-2000-C
PEKERJAAN PENGECATAN
1 PT. T-38-2000-C.1 1 m2 pelaburan bidang kayu dengan vernis Rp. 44,780.00
2 PT. T-38-2000-C.2 1 m2 pengecatan bidang kayu lama Rp. 28,630.00
3 PT. T-38-2000-C.3 1 m2 pengecatan bidang kayu baru Rp. 30,240.00
4 PT. T-38-2000-C.4 1 m2 pengecatan tembok/plafond baru str vinilex (1 lps plamur, 1 24,260.00
Rp.
lps cat dasar,2 lps cat penutup)
5 PT. T-38-2000-C.4.1 1 m2 pengecatan tembok/plafond lama str vinilex ( 1 lps cat
Rp.
dasar,2 lps cat penutup) 22,590.00
6 PT. T-38-2000-C.4.2 1 m2 pengecatan tembok/plafond lama str vinilex ( 2 lps cat
Rp.
penutup) 14,540.00
7 PT. T-38-2000-C.5 1 m2 pengecatan tembok/plafond baru str paragon (1 lps plamur, 1
Rp.
lps cat dasar,2 lps cat penutup) 24,090.00
8 PT. T-38-2000-C.5.1 1 m2 pengecatan tembok/plafond lama str paragon ( 1 lps cat
Rp.
dasar,2 lps cat penutup) 22,590.00
9 PT. T-38-2000-C.5.2 1 m2 pengecatan tembok/plafond lama str paragon (2 lps cat
Rp.
penutup) 20,880.00
10 PT. T-38-2000-C.6 1 m2 pengecatan permukaan baja dengan meni besi dan perancah
Rp.
60,660.00

PEKERJAAN PEMASANGAN KOZEN


O.
PINTU/JENDELA METAL
1 1 Unit Kozen Metal Type PJ1 Rp.
2 1 Unit Kozen Metal Type P1 Rp.
3 1 Unit Kozen Metal Type P2 Rp.
4 1 Unit Kozen Metal Type P3 Rp.
5 1 Unit Kozen Metal Type P4 Rp.
6 1 Unit Kozen Metal Type J1 Rp.
7 1 Unit Kozen Metal Type J2 Rp.
8 1 Unit Kozen Metal Type J3 Rp.
9 1 Unit Kozen Metal Type J4 Rp.
10 1 Unit Kozen Metal Type V1 Rp.
11 1 Unit Kozen Metal Type V2 Rp.
12 1 Unit Kozen Metal Type V3 Rp.
13 1 Unit Kozen Metal Type V4 Rp.
14 1 Unit Kozen Metal Type PJ 1K Rp.
15 1 Unit Kozen Metal Type P1 K Rp.
16 1 Unit Kozen Metal Type P2 K Rp.
17 1 Unit Kozen Metal Type P3 K Rp.
18 1 Unit Kozen Metal Type J 1 K Rp.
19 1 Unit Kozen Metal Type J 2 K Rp.
20 1 Unit Kozen Metal Type J 3 K Rp.
21 1 Unit Kozen Metal Type J 4 K Rp.
22 1 Unit Kozen Metal Type V 1 K Rp.
23 1 Unit Kozen Metal Type V 2 K Rp.
24 1 Unit Kozen Metal Type V 3 K Rp.
25 1 Unit Kozen Metal Type V 4 K Rp.
ANALISA HARGA SATUAN PEKERJAAN

KEGIATAN : PEMBANGUNAN GEDUNG KANTOR


PEKERJAAN : PEMBANGUNAN GEDUNG DPRD - KABUPATEN MIMIKA (TAHAP III)
LOKASI : KOTA TIMIKA
T. ANGGARAN : 2011

HARGA JUMLAH
NO JENIS PEKERJAAN SATUAN ( Rp) HARGA (Rp)
1 2 3 4

1 1 M' PAGAR SEMENTARA dari SENG GELOMBANG


TINGGI 2 METER
0.0300 M3 Kayu Matoa 5/10 (pengganti dolken) 2,180,000.00 65,400.00
2.5000 Kg Semen Portland 1,600.00 4,000.00
1.2000 Lbr Seng Gelombang 3" - 5" 75,000.00 90,000.00
0.0050 M3 Pasir Beton 245,000.00 1,225.00
0.0090 M3 Koral Beton 250,000.00 2,250.00
0.0720 M3 Kayu 5/7 2,180,000.00 156,960.00
0.0600 Kg Paku Biasa 2" - 5" 21,000.00 1,260.00
0.4000 Oh Pekerja 80,000.00 32,000.00
0.2000 Oh Tukang Kayu 110,000.00 22,000.00
0.0200 Oh Kepala Tukang 120,000.00 2,400.00
0.0200 Oh Mandor 125,000.00 2,500.00
Jumlah 379,995.00

2 1 M2 PEMBUATAN DIREKSI KEET / KONSTRUKSI KAYU


0.0600 m3 Balok Kayu Matoa 5/10 2,180,000.00 130,800.00
0.2760 m3 Kayu Matoa 2,180,000.00 601,680.00
0.7000 kg Paku campur 21,000.00 14,700.00
1.5000 lbr Seng Gelombang Bjls 30 75,000.00 112,500.00
1.0000 o/h Pekerja 80,000.00 80,000.00
1.5000 o/h Tukang 110,000.00 165,000.00
0.1500 o/h Kepala Tukang 120,000.00 18,000.00
0.0500 o/h Mandor 125,000.00 6,250.00
Jumlah 1,128,930.00

3 1 M' PEMASANGAN PAPAN BOUWPLANK


0.0120 m3 Balok Kayu Matoa 2,180,000.00 26,160.00
0.0200 kg Paku campur 21,000.00 420.00
0.0070 m3 Papan Kayu Matoa 2,180,000.00 15,260.00
0.1000 o/h Pekerja 80,000.00 8,000.00
0.1000 o/h Tukang 110,000.00 11,000.00
0.0100 o/h Kepala Tukang 120,000.00 1,200.00
0.0050 o/h Mandor 125,000.00 625.00
Jumlah 62,665.00

4 1 M3 GALIAN TANAH sedalam 1 meter


0.7500 o/h Pekerja 80,000.00 60,000.00
0.0250 o/h Mandor 125,000.00 3,125.00
Jumlah 63,125.00

5 1 M3 GALIAN TANAH (u/ Pondasi Poer)


1.5000 o/h Pekerja 80,000.00 120,000.00
0.0600 o/h Mandor 125,000.00 7,500.00
Jumlah 127,500.00

6 1 M3 URUGAN TANAH KEMBALI


0.2500 o/h Pekerja 80,000.00 20,000.00
0.0083 o/h Mandor 125,000.00 1,041.67
Jumlah 21,041.67

237/314 517211341.xlsx/ANALISA (2)


1 2 3 4

7 1 M3 MEMADATKAN TANAH DIBAWAH LANTAI


0.2500 o/h Pekerja 80,000.00 20,000.00
0.0250 o/h Mandor 125,000.00 3,125.00
Jumlah 23,125.00
8 1 M3 MEMBUANG TANAH KE LUAR LOKASI
0.5160 o/h Pekerja 80,000.00 41,280.00
0.0500 o/h Mandor 125,000.00 6,250.00
1.0000 M3 Angkutan 40,000.00 40,000.00
Jumlah 87,530.00

9 1 M3 URUGAN SIRTU TIMBUNAN pada LOKASI


1.2000 M3 Sirtu Timbunan 175,000.00 210,000.00
0.3000 o/h Pekerja 80,000.00 24,000.00
0.0100 o/h Mandor 125,000.00 1,250.00
Jumlah 235,250.00

10 1 M3 URUGAN PASIR
1.2000 M3 Pasir urugan 180,000.00 216,000.00
0.3000 o/h Pekerja 80,000.00 24,000.00
0.0100 o/h Mandor 125,000.00 1,250.00
Jumlah 241,250.00

238/314 517211341.xlsx/ANALISA (2)


1 2 3 4
11 1 M3 URUGAN KERIKIL
1.2000 M3 Kerikil 250,000.00 300,000.00
0.3000 o/h Pekerja 80,000.00 24,000.00
0.0100 o/h Mandor 125,000.00 1,250.00
Jumlah 325,250.00

12 1 M3 MEMASANG LAPISAN BATU KOSONG (AAMSTAMPING)


1.2000 m3 Batu gunung 500,000.00 600,000.00
0.4320 M3 Pasir Urug 180,000.00 77,760.00
0.7800 Oh Pekerja 80,000.00 62,400.00
0.3900 o/h Tukang batu 110,000.00 42,900.00
0.0390 o/h Kepala tukang 120,000.00 4,680.00
0.0390 Oh Mandor 125,000.00 4,875.00
Jumlah 792,615.00

13 1 M3 MEMASANG PONDASI BATU GUNUNG


(campuran 1 pc : 4 psr)
1.2000 M3 Batu gunung 500,000.00 600,000.00
163.0000 Kg Semen 1,600.00 260,800.00
0.5200 M3 Pasir 235,000.00 122,200.00
1.5000 o/h Pekerja 80,000.00 120,000.00
0.7500 o/h Tukang batu 110,000.00 82,500.00
0.0750 o/h Kepala tukang 120,000.00 9,000.00
0.0750 o/h Mandor 125,000.00 9,375.00
Jumlah 1,203,875.00

14 1 M2 PASANGAN BATAKO 1 PC : 2 PSR


23.0000 Bh Batako 10 x 18 x 24 cm 2,400.00 55,200.00
18.9500 Kg Semen 1,600.00 30,320.00
0.0380 M3 Pasir pasang 235,000.00 8,930.00
0.3000 o/h Pekerja 80,000.00 24,000.00
0.1000 o/h Tukang batu 110,000.00 11,000.00
0.0100 o/h Kepala Tukang 120,000.00 1,200.00
0.0150 o/h Mandor 125,000.00 1,875.00
Jumlah 132,525.00
Untuk 1 M3 1,325,250.00

15 1 M2 PASANGAN BATAKO 1 PC : 4 PSR


23.0000 Bh Batako 10 x 18 x 24 cm 2,400.00 55,200.00
11.5000 Kg Semen Pc 1,600.00 18,400.00
0.0430 M3 Pasir Pasang 235,000.00 10,105.00
0.3000 o/h Pekerja 80,000.00 24,000.00
0.1000 o/h Tukang 110,000.00 11,000.00
0.0100 o/h Kepala Tukang 120,000.00 1,200.00
0.0150 o/h Mandor 125,000.00 1,875.00
Jumlah 121,780.00
Untuk 1 M3 1,217,800.00

16 1 M3 LANTAI BETON TUMBUK K.100


230.00 Kg Semen PC 1,600.00 368,000.00

239/314 517211341.xlsx/ANALISA (2)


1 2 3 4
893.00 Kg Pasir Cor 175.00 156,275.00
1,027.00 Kg Kerikil 185.19 190,185.19
200.00 Ltr Air 100.00 20,000.00
1.20 o/h Pekerja 80,000.00 96,000.00
0.20 o/h Tukang 110,000.00 22,000.00
0.02 o/h Kepala Tukang 120,000.00 2,400.00
0.06 o/h Mandor 125,000.00 7,500.00
Jumlah 862,360.19

17 1 M3 LANTAI BETON TUMBUK K.100 (BERTULANG) RG


1.0000 M3 Beton Tumbuk K. 125 862,360.19 862,360.19
49.3300 Kg Besi Beton 22,764.00 1,122,948.12
Jumlah 1,985,308.31

18 1 M3 CAMPURAN BETON K. 225


371.000 Kg Semen Pc 1,600.00 593,600.00
698.000 Kg Pasir cor 175.00 122,150.00
1,047.000 Kg Batu Pecah 2/3 648.15 678,611.11
215.000 Ltr Air 100.00 21,500.00
1.650 o/h Pekerja 80,000.00 132,000.00
0.275 o/h Tukang 110,000.00 30,250.00
0.028 o/h Kepala Tukang 120,000.00 3,360.00
0.083 o/h Mandor 125,000.00 10,375.00
Jumlah 1,591,846.11

240/314 517211341.xlsx/ANALISA (2)


1 2 3 4

19 1 M3 CAMPURAN BETON K. 175


326.0000 Kg Semen Pc 1,600.00 521,600.00
760.0000 Kg Pasir cor 175.00 133,000.00
1,029.000 Kg Batu Pecah 2/3 648.15 666,944.44
215.0000 Ltr Air 100.00 21,500.00
1.6500 o/h Pekerja 80,000.00 132,000.00
0.2750 o/h Tukang 110,000.00 30,250.00
0.0280 o/h Kepala Tukang 120,000.00 3,360.00
0.0830 o/h Mandor 125,000.00 10,375.00
Jumlah 1,519,029.44

1 2 3 4
20 1 M3 CAMPURAN BETON K. 125 (Beton Kolom, Sloof Praktis)
276.0000 Kg Semen Pc 1,600.00 441,600.00
829.0000 Kg Pasir cor 175.00 145,075.00
1,012.000 Kg Kerikil 185.19 187,407.41
215.0000 Ltr Air 100.00 21,500.00
1.6500 o/h Pekerja 80,000.00 132,000.00
0.2750 o/h Tukang 110,000.00 30,250.00
0.0280 o/h Kepala Tukang 120,000.00 3,360.00
0.0830 o/h Mandor 125,000.00 10,375.00
Jumlah 971,567.41

21 10 KG PEMBESIAN (BESI POLOS / ULIR)


10.5000 Kg Besi beton 20,000.00 210,000.00
0.1500 Kg Kawat pengikat 20,000.00 3,000.00
0.0700 o/h Pekerja 80,000.00 5,600.00
0.0700 o/h Tukang besi 110,000.00 7,700.00
0.0070 o/h Kepala Tukang 120,000.00 840.00
0.0040 o/h Mandor 125,000.00 500.00
Jumlah 227,640.00
Untuk 1 Kg 22,764.00

22 1 M2 BEKISTING untuk PONDASI


0.0400 M3 Balok / Papan Kayu Matoa 2,180,000.00 87,200.00
0.3000 Kg Paku campur 21,000.00 6,300.00
0.1000 Ltr Minyak Bekisting 12,000.00 1,200.00
0.5200 o/h Pekerja 80,000.00 41,600.00
0.2600 o/h Tukang 110,000.00 28,600.00
0.0260 o/h Kepala tukang 120,000.00 3,120.00
0.0260 o/h Mandor 125,000.00 3,250.00
Jumlah 171,270.00

23 1 M2 BEKISTING untuk SLOOF


0.0450 M3 Balok / Papan Kayu Matoa 2,180,000.00 98,100.00
0.3000 Kg Paku campur 21,000.00 6,300.00
0.1000 Ltr Minyak Bekisting 12,000.00 1,200.00
0.5200 o/h Pekerja 80,000.00 41,600.00
0.2600 o/h Tukang 110,000.00 28,600.00
0.0260 o/h Kepala tukang 120,000.00 3,120.00
0.0260 o/h Mandor 125,000.00 3,250.00

241/314 517211341.xlsx/ANALISA (2)


1 2 3 4
Jumlah 182,170.00

2 3 4

24 1 M2 BEKISTING untuk KOLOM


0.0400 M3 Balok Kayu kelas III 2,180,000.00 87,200.00
0.4000 Kg Paku campur 21,000.00 8,400.00
0.2000 Ltr Minyak Bekisting 12,000.00 2,400.00
2.0000 Btg Dolken Kayu - 4 mtr 40,000.00 80,000.00
0.3500 Lbr Tripleks 9 mm 165,000.00 57,750.00
0.0150 M3 Balok Kayu kelas II 2,180,000.00 32,700.00
0.6600 o/h Pekerja 80,000.00 52,800.00
0.3300 o/h Tukang 110,000.00 36,300.00
0.0330 o/h Kepala tukang 120,000.00 3,960.00
0.0330 o/h Mandor 125,000.00 4,125.00
Jumlah 365,635.00

25 1 M2 BEKISTING untuk BALOK


0.0400 M3 Balok Kayu kelas III 2,180,000.00 87,200.00
0.4000 Kg Paku campur 21,000.00 8,400.00
0.2000 Ltr Minyak Bekisting 12,000.00 2,400.00
2.0000 Btg Dolken Kayu - 4 mtr 40,000.00 80,000.00
0.3500 Lbr Tripleks 9 mm 165,000.00 57,750.00
0.0180 M3 Balok Kayu kelas II 2,180,000.00 39,240.00
0.6600 o/h Pekerja 80,000.00 52,800.00
0.3300 o/h Tukang 110,000.00 36,300.00
0.0330 o/h Kepala tukang 120,000.00 3,960.00
0.0330 o/h Mandor 125,000.00 4,125.00
Jumlah 372,175.00

1 2 3 4

242/314 517211341.xlsx/ANALISA (2)


1 2 3 4

26 1 M2 BEKISTING untuk PLAT LANTAI


0.0400 M3 Balok Kayu kelas III 2,180,000.00 87,200.00
0.4000 Kg Paku campur 21,000.00 8,400.00
0.2000 Ltr Minyak Bekisting 12,000.00 2,400.00
0.0150 M3 Balok Kayu kelas II 2,180,000.00 32,700.00
0.3500 Lbr Tripleks 9 mm 165,000.00 57,750.00
6.0000 Btg Dolken Kayu - 4 mtr 40,000.00 240,000.00
0.6600 o/h Pekerja 80,000.00 52,800.00
0.3300 o/h Tukang 110,000.00 36,300.00
0.0330 o/h Kepala tukang 120,000.00 3,960.00
0.0330 o/h Mandor 125,000.00 4,125.00
Jumlah 525,635.00

27 1 M2 BEKISTING untuk TANGGA


0.0300 M3 Balok Kayu kelas III 2,180,000.00 65,400.00
0.4000 Kg Paku campur 21,000.00 8,400.00
0.1500 Ltr Minyak Bekisting 12,000.00 1,800.00
0.0150 M3 Balok Kayu kelas II 2,180,000.00 32,700.00
0.3500 Lbr Tripleks 9 mm 165,000.00 57,750.00
2.0000 Btg Dolken Kayu - 4 mtr 40,000.00 80,000.00
0.6600 o/h Pekerja 80,000.00 52,800.00
0.3300 o/h Tukang 110,000.00 36,300.00
0.0330 o/h Kepala tukang 120,000.00 3,960.00
0.0330 o/h Mandor 125,000.00 4,125.00
Jumlah 343,235.00

27 1 M2 BEKISTING untuk DINDING


0.0300 M3 Balok Kayu kelas III 2,180,000.00 65,400.00
0.4000 Kg Paku campur 21,000.00 8,400.00
0.2000 Ltr Minyak Bekisting 12,000.00 2,400.00
0.0200 M3 Balok Kayu kelas II 2,180,000.00 43,600.00
0.3500 Lbr Tripleks 9 mm 165,000.00 57,750.00
3.0000 Btg Dolken Kayu - 4 mtr 40,000.00 120,000.00
0.6600 o/h Pekerja 80,000.00 52,800.00
0.3300 o/h Tukang 110,000.00 36,300.00
0.0330 o/h Kepala tukang 120,000.00 3,960.00
0.0330 o/h Mandor 125,000.00 4,125.00
Jumlah 394,735.00

28 1 M' KOLOM PRAKTIS BETON BERTULANG (11 x 11) cm


0.0020 M3 Balok Kayu kelas III 2,180,000.00 4,360.00
0.0100 Kg Paku campur 21,000.00 210.00
3.0000 Kg Besi Beton Polos 20,000.00 60,000.00
0.0450 Kg Kawat Beton 20,000.00 900.00
4.0000 Kg Semen 1,600.00 6,400.00
0.0060 M3 Pasir Cor 245,000.00 1,470.00
0.0090 M3 Kerikil 250,000.00 2,250.00
0.1800 o/h Pekerja 80,000.00 14,400.00
0.0200 o/h Tukang Batu 110,000.00 2,200.00
0.0200 o/h Tukang Kayu 110,000.00 2,200.00
0.0200 o/h Tukang Besi 110,000.00 2,200.00
0.0060 o/h Kepala tukang 120,000.00 720.00
0.0090 o/h Mandor 125,000.00 1,125.00
Jumlah 98,435.00

29 1 M' RINGBALK BETON BERTULANG (10 x 15) cm


0.0030 M3 Balok Kayu kelas III 2,180,000.00 6,540.00
0.0200 Kg Paku campur 21,000.00 420.00
3.6000 Kg Besi Beton Polos 20,000.00 72,000.00
0.0500 Kg Kawat Beton 20,000.00 1,000.00
5.5000 Kg Semen 1,600.00 8,800.00

243/314 517211341.xlsx/ANALISA (2)


1 2 3 4
0.0090 M3 Pasir Cor 245,000.00 2,205.00
0.0150 M3 Kerikil 250,000.00 3,750.00
0.2970 o/h Pekerja 80,000.00 23,760.00
0.0330 o/h Tukang Batu 110,000.00 3,630.00
0.0330 o/h Tukang Kayu 110,000.00 3,630.00
0.0330 o/h Tukang Besi 110,000.00 3,630.00
0.0100 o/h Kepala tukang 120,000.00 1,200.00
0.0150 o/h Mandor 125,000.00 1,875.00
Jumlah 132,440.00

244/314 517211341.xlsx/ANALISA (2)


1 2 3 4
30 1 M3 DINDING BETON BERTULANG
(150 Kg Besi + Bekisting)
0.2400 M3 Balok Kayu kelas III 2,180,000.00 523,200.00
3.2000 Kg Paku campur 21,000.00 67,200.00
1.6000 Ltr Minyak Bekisting 12,000.00 19,200.00
157.5000 Kg Besi Beton Polos 20,000.00 3,150,000.00
2.2500 Kg Kawat Beton 20,000.00 45,000.00
336.0000 Kg Semen 1,600.00 537,600.00
0.5400 M3 Pasir Cor 245,000.00 132,300.00
0.8100 M3 Kerikil 250,000.00 202,500.00
0.1600 M3 Balok Kayu kelas II 2,180,000.00 348,800.00
2.8000 Lbr Tripleks 9 mm 165,000.00 462,000.00
24.0000 Btg Dolken Kayu - 4 mtr 40,000.00 960,000.00
5.3000 o/h Pekerja 80,000.00 424,000.00
0.2750 o/h Tukang Batu 110,000.00 30,250.00
1.3000 o/h Tukang Kayu 110,000.00 143,000.00
1.0500 o/h Tukang Besi 110,000.00 115,500.00
0.2620 o/h Kepala tukang 120,000.00 31,440.00
0.2650 o/h Mandor 125,000.00 33,125.00
Jumlah 7,225,115.00

31 1 M3 SLOOF PRAKTIS
0.9800 M3 Beton K.175 1,519,029.44 1,488,648.86
110.0000 Kg Besi beton 22,764.00 2,504,040.00
13.3330 M2 Bekisting 182,170.00 2,428,872.61
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 6,461,561.47

32 1 M3 BETON PENUTUP SEPTICTANK


1.0000 M3 Beton K.225 1,591,846.11 1,591,846.11
150.0000 Kg Besi beton 22,764.00 3,414,600.00
8.3330 M2 Bekisting 525,635.00 4,380,116.46
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 9,426,562.57

33 1 M3 KOLOM LISTPLANK pada ENTRANCE


1.0000 M3 Beton K.125 971,567.41 971,567.41
110.0000 Kg Besi beton 22,764.00 2,504,040.00
9.6000 M2 Bekisting 365,635.00 3,510,096.00
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,025,703.41
34 1 M3 BETON SLOOF S.1
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
202.7540 Kg Besi beton 22,764.00 4,615,492.06
6.6000 M2 Bekisting 182,170.00 1,202,322.00
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,449,660.17

1 2 3 4

35 1 M3 BETON SLOOF S.2


1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
203.8400 Kg Besi beton 22,764.00 4,640,213.76
8.0000 M2 Bekisting 182,170.00 1,457,360.00
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,729,419.87
36 1 M3 PONDASI SUMURAN P.1, P.2 & P.3
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
162.1630 Kg Besi beton 22,764.00 3,691,478.53
4.4445 M2 Bekisting 171,270.00 761,209.52

245/314 517211341.xlsx/ANALISA (2)


1 2 3 4
Jumlah 6,044,534.16
37 1 M3 PONDASI SUMURAN P.4, P.6, & P.7
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
103.3732 Kg Besi beton 22,764.00 2,353,187.52
3.6364 M2 Bekisting 171,270.00 622,806.23
Jumlah 4,567,839.86
38 1 M3 PONDASI SUMURAN P.5
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
95.1160 Kg Besi beton 22,764.00 2,165,220.62
3.2000 M2 Bekisting 171,270.00 548,064.00
Jumlah 4,305,130.74
39 1 M3 BETON KOLOM BULAT K.1 ' Ø 45 (LT. 01 & LT. 02)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
123.9340 Kg Besi beton 22,764.00 2,821,233.58
8.8900 M2 Bekisting 365,635.00 3,250,495.15
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,703,574.84
40 1 M3 BETON KOLOM BULAT K.1 ' Ø 45 (LT. 03)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
123.9340 Kg Besi beton 22,764.00 2,821,233.58
8.8900 M2 Bekisting 365,635.00 3,250,495.15
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,703,574.84
41 1 M3 BETON KOLOM K.1 (LT. 01 & LT. 02)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
123.9340 Kg Besi beton 22,764.00 2,821,233.58
8.8900 M2 Bekisting 365,635.00 3,250,495.15
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,703,574.84
42 1 M3 BETON KOLOM K.1 (LT. 03)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
123.9340 Kg Besi beton 22,764.00 2,821,233.58
8.8900 M2 Bekisting 365,635.00 3,250,495.15
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,703,574.84
43 1 M3 BETON KOLOM K.2 (LT. 01 & LT. 02)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
212.0240 Kg Besi beton 22,764.00 4,826,514.34
8.8900 M2 Bekisting 365,635.00 3,250,495.15
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 9,708,855.60
44 1 M3 BETON KOLOM K.2 (LT. 03)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
212.0240 Kg Besi beton 22,764.00 4,826,514.34
8.8900 M2 Bekisting 365,635.00 3,250,495.15
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 9,708,855.60
45 1 M3 BETON KOLOM K.3 (LT. 01 & LT. 02)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
167.9770 Kg Besi beton 22,764.00 3,823,828.43
8.8900 M2 Bekisting 365,635.00 3,250,495.15
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 8,706,169.69

1 2 3 4

46 1 M3 BETON KOLOM K.3 (LT. 03)


1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
167.9770 Kg Besi beton 22,764.00 3,823,828.43

246/314 517211341.xlsx/ANALISA (2)


1 2 3 4
8.8900 M2 Bekisting 365,635.00 3,250,495.15
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 8,706,169.69
47 1 M3 BETON KOLOM K.4 (LT. 01 & LT. 02)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
157.6680 Kg Besi beton 22,764.00 3,589,154.35
10.1600 M2 Bekisting 365,635.00 3,714,851.60
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 8,935,852.06
48 1 M3 BETON KOLOM K.4 (LT. 03)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
157.6680 Kg Besi beton 22,764.00 3,589,154.35
10.1600 M2 Bekisting 365,635.00 3,714,851.60
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 8,935,852.06
49 1 M3 BETON KOLOM K.5 (LT. 01 & LT. 02)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
150.2610 Kg Besi beton 22,764.00 3,420,541.40
13.3330 M2 Bekisting 365,635.00 4,875,011.46
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 9,927,398.97
50 1 M3 BETON KOLOM K.5 (LT. 03)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
150.2610 Kg Besi beton 22,764.00 3,420,541.40
13.3330 M2 Bekisting 365,635.00 4,875,011.46
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 9,927,398.97
51 1 M3 BETON KOLOM K.6
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
123.5430 Kg Besi beton 22,764.00 2,812,332.85
7.9920 M2 Bekisting 365,635.00 2,922,154.92
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,366,333.88

33 1 M3 BETON POER PLAT (GSG)


1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
124.6835 Kg Besi beton 22,764.00 2,838,295.19
2.0000 M2 Bekisting 171,270.00 342,540.00
Jumlah 4,772,681.31

34 1 M3 BETON KOLOM 40/60 (GSG)


1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
147.6828 Kg Besi beton 22,764.00 3,361,851.26
8.3332 M2 Bekisting 365,635.00 3,046,909.58
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 8,040,606.95

1 2 3 4
35 1 M3 BETON KOLOM BULAT Ø 50 (GSG)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
97.4316 Kg Besi beton 22,764.00 2,217,932.94
7.9999 M2 Bekisting 365,635.00 2,925,043.44
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 6,774,822.49
36 1 M3 BETON SLOOF 30/50 (GSG)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
119.0728 Kg Besi beton 22,764.00 2,710,573.22

247/314 517211341.xlsx/ANALISA (2)


1 2 3 4
6.6666 M2 Bekisting 182,170.00 1,214,454.52
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 5,556,873.85

1 2 3 4

37 1 M3 BETON SLOOF 15/20 (GSG)


1.0000 M3 Beton K. 175 1,519,029.44 1,519,029.44
162.7757 Kg Besi beton 22,764.00 3,705,426.03
13.3332 M2 Bekisting 182,170.00 2,428,909.04
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,693,364.52

38 1 M3 PLAT LANTAI (GSG)


1.0000 M3 Beton K. 175 1,519,029.44 1,519,029.44
152.4300 Kg Besi beton 22,764.00 3,469,916.52
8.3300 M2 Bekisting 525,635.00 4,378,539.55
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 9,407,485.51

39 1 M3 BETON RINGBALK 30/50 (GSG)


1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
119.0733 Kg Besi beton 22,764.00 2,710,584.60
8.6665 M2 Bekisting 372,175.00 3,225,454.64
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,567,885.35

40 1 M3 BETON RINGBALK 20/30 (GSG)


1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
179.0949 Kg Besi beton 22,764.00 4,076,916.30
13.3280 M2 Bekisting 372,175.00 4,960,348.40
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 10,669,110.81

41 1 M3 BETON RINGBALK KONSOL 30/50 (GSG)


1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
119.0733 Kg Besi beton 22,764.00 2,710,584.60
8.6665 M2 Bekisting 372,175.00 3,225,454.64
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,567,885.35
42 1 M3 BETON BALOK UTAMA 30/50 (GSG)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
119.0733 Kg Besi beton 22,764.00 2,710,584.60
8.6665 M2 Bekisting 372,175.00 3,225,454.64
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,567,885.35
43 1 M3 BETON BALOK ANAK 20/30 (GSG)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
157.6782 Kg Besi beton 22,764.00 3,589,386.54
13.3328 M2 Bekisting 372,175.00 4,962,134.84
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 10,183,367.50

44 1 M3 BETON KONSOL (GSG)


1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
119.0733 Kg Besi beton 22,764.00 2,710,584.60
8.6665 M2 Bekisting 372,175.00 3,225,454.64
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00

248/314 517211341.xlsx/ANALISA (2)


1 2 3 4
Jumlah 7,567,885.35

1 2 3 4

45 1 M3 PLAT ATAP BETON (GSG)


1.0000 M3 Beton K. 175 1,519,029.44 1,519,029.44
142.6700 Kg Besi beton 22,764.00 3,247,739.88
10.0000 M2 Bekisting 525,635.00 5,256,350.00
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 10,063,119.32

46 1 M3 PLAT LANTAI (SERVICE)


1.0000 M3 Beton K. 175 1,519,029.44 1,519,029.44
152.4300 Kg Besi beton 22,764.00 3,469,916.52
8.3300 M2 Bekisting 525,635.00 4,378,539.55
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 9,407,485.51

47 1 M3 BETON KOLOM 25/25 (SERVICE)


1.0000 M3 Beton K. 175 1,519,029.44 1,519,029.44
211.1999 Kg Besi beton 22,764.00 4,807,754.52
16.0000 M2 Bekisting 365,635.00 5,850,160.00
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 12,216,943.97

48 1 M3 BETON SLOOF 20/30 (SERVICE)


1.0000 M3 Beton K. 175 1,519,029.44 1,519,029.44
179.0949 Kg Besi beton 22,764.00 4,076,916.30
13.3280 M2 Bekisting 182,170.00 2,427,961.76
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 8,063,907.51

49 1 M3 BETON POER PLAT type 1 (SERVICE)


1.0000 M3 Beton K. 175 1,519,029.44 1,519,029.44
130.4378 Kg Besi beton 22,764.00 2,969,286.08
3.3333 M2 Bekisting 171,270.00 570,894.29
Jumlah 5,059,209.81

50 1 M3 BETON POER PLAT type 2 (SERVICE)


1.0000 M3 Beton K. 175 1,519,029.44 1,519,029.44
126.6660 Kg Besi beton 22,764.00 2,883,424.82
2.6666 M2 Bekisting 171,270.00 456,708.58
Jumlah 4,859,162.85

51 1 M3 BETON RINGBALK 20/30 (SERVICE)


1.0000 M3 Beton K. 175 1,519,029.44 1,519,029.44
179.0949 Kg Besi beton 22,764.00 4,076,916.30
13.3280 M2 Bekisting 372,175.00 4,960,348.40
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 10,596,294.15
52 1 M3 BETON KOLOM 12/25 (POS)
1.0000 M3 Beton K. 175 1,519,029.44 1,519,029.44
239.7539 Kg Besi beton 22,764.00 5,457,757.78
24.6642 M2 Bekisting 365,635.00 9,018,094.77
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 16,034,881.99

249/314 517211341.xlsx/ANALISA (2)


1 2 3 4
53 1 M3 BETON SLOOF 15/20 (POS)
1.0000 M3 Beton K. 175 1,519,029.44 1,519,029.44
162.7757 Kg Besi beton 22,764.00 3,705,426.03
13.3332 M2 Bekisting 182,170.00 2,428,909.04
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,693,364.52
54 1 M3 BETON RINGBALK 15/20 (POS)
1.0000 M3 Beton K. 175 1,519,029.44 1,519,029.44
162.7757 Kg Besi beton 22,764.00 3,705,426.03
13.3332 M2 Bekisting 372,175.00 4,962,283.71
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 10,226,739.19
55 1 M3 BETON POER PLAT (P)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
167.8573 Kg Besi beton 22,764.00 3,821,103.58
2.2222 M2 Bekisting 171,270.00 380,596.19
Jumlah 5,793,545.88

1 2 3 4
56 1 M3 BETON POER PLAT P.1
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
201.1738 Kg Besi beton 22,764.00 4,579,520.38
3.0000 M2 Bekisting 171,270.00 513,810.00
Jumlah 6,685,176.49

57 1 M3 BETON POER PLAT P.2


1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
159.3944 Kg Besi beton 22,764.00 3,628,454.12
2.9682 M2 Bekisting 171,270.00 508,363.61
Jumlah 5,728,663.85

58 1 M3 BETON POER PLAT P.3


1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
139.7745 Kg Besi beton 22,764.00 3,181,826.72
2.3323 M2 Bekisting 171,270.00 399,453.02
Jumlah 5,173,125.85
59 1 M3 BETON POER PLAT P.4
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
113.3843 Kg Besi beton 22,764.00 2,581,080.21
1.3162 M2 Bekisting 171,270.00 225,425.57
Jumlah 4,398,351.89
60 1 M3 BETON POER PLAT P.5
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
76.5739 Kg Besi beton 22,764.00 1,743,128.26
1.0577 M2 Bekisting 171,270.00 181,152.28
Jumlah 3,516,126.65
61 1 M3 BETON POER PLAT P.6
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
107.6388 Kg Besi beton 22,764.00 2,450,289.64
1.4852 M2 Bekisting 171,270.00 254,370.20
Jumlah 4,296,505.96
62 1 M3 BETON POER PLAT P.7
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
105.8564 Kg Besi beton 22,764.00 2,409,715.09
1.6660 M2 Bekisting 171,270.00 285,335.82
Jumlah 4,286,897.02
63 1 M3 BETON BALOK B.1 (30/60)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11

250/314 517211341.xlsx/ANALISA (2)


1 2 3 4
114.4600 Kg Besi beton 22,764.00 2,605,567.44
8.3330 M2 Bekisting 372,175.00 3,101,334.28
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,338,747.83
64 1 M3 BETON BALOK B.2 (30/60)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
136.5939 Kg Besi beton 22,764.00 3,109,423.54
8.3330 M2 Bekisting 372,175.00 3,101,334.28
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,842,603.93
65 1 M3 BETON BALOK B.3 (30/60)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
136.5939 Kg Besi beton 22,764.00 3,109,423.54
8.3330 M2 Bekisting 372,175.00 3,101,334.28
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,842,603.93
66 1 M3 BETON BALOK B.4 (30/60)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
114.4600 Kg Besi beton 22,764.00 2,605,567.44
8.3330 M2 Bekisting 372,175.00 3,101,334.28
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,338,747.83
67 1 M3 BETON BALOK B.5 (30/60)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
136.5939 Kg Besi beton 22,764.00 3,109,423.54
8.3330 M2 Bekisting 372,175.00 3,101,334.28
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,842,603.93
68 1 M3 BETON BALOK B.6 (30/60)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
130.3912 Kg Besi beton 22,764.00 2,968,225.28
8.3330 M2 Bekisting 372,175.00 3,101,334.28
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,701,405.66

1 2 3 4

69 1 M3 BETON BALOK B.7 (30/60)


1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
114.4600 Kg Besi beton 22,764.00 2,605,567.44
8.3330 M2 Bekisting 372,175.00 3,101,334.28
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,338,747.83
70 1 M3 BETON BALOK B.8 (30/60)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
192.4276 Kg Besi beton 22,764.00 4,380,421.89
8.3330 M2 Bekisting 372,175.00 3,101,334.28
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 9,113,602.27
71 1 M3 BETON BALOK B.9 (30/60)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
130.3912 Kg Besi beton 22,764.00 2,968,225.28
8.3330 M2 Bekisting 372,175.00 3,101,334.28
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,701,405.66

72 1 M3 BETON BALOK B.10 (25/45)

251/314 517211341.xlsx/ANALISA (2)


1 2 3 4
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
163.1995 Kg Besi beton 22,764.00 3,715,073.42
10.2212 M2 Bekisting 372,175.00 3,804,075.11
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 9,150,994.64
73 1 M3 BETON BALOK B.11 (30/60)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
198.6313 Kg Besi beton 22,764.00 4,521,642.91
8.3330 M2 Bekisting 372,175.00 3,101,334.28
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 9,254,823.30
74 1 M3 BETON BALOK B.12 (35/70)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
194.9401 Kg Besi beton 22,764.00 4,437,616.44
7.1428 M2 Bekisting 372,175.00 2,658,371.59
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 8,727,834.14
75 1 M3 BETON BALOK B.13 (25/45)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
163.1995 Kg Besi beton 22,764.00 3,715,073.42
10.2212 M2 Bekisting 372,175.00 3,804,075.11
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 9,150,994.64
76 1 M3 BETON BALOK B.14 (35/70)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
172.1511 Kg Besi beton 22,764.00 3,918,847.64
7.1428 M2 Bekisting 372,175.00 2,658,371.59
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 8,209,065.34
77 1 M3 BETON BALOK B.15 (30/60)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
192.4276 Kg Besi beton 22,764.00 4,380,421.89
8.3330 M2 Bekisting 372,175.00 3,101,334.28
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 9,113,602.27
78 1 M3 BETON BALOK B.16 (25/45)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
120.2408 Kg Besi beton 22,764.00 2,737,161.57
10.2212 M2 Bekisting 372,175.00 3,804,075.11
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 8,173,082.79

1 2 3 4

79 1 M3 BETON BALOK B.17 (20/30)


1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
197.4333 Kg Besi beton 22,764.00 4,494,371.64
13.3328 M2 Bekisting 372,175.00 4,962,134.84
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 11,088,352.59
80 1 M3 BETON BALOK B.18 (20/40)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
168.7982 Kg Besi beton 22,764.00 3,842,522.22
12.5000 M2 Bekisting 372,175.00 4,652,187.50
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 10,126,555.84
81 1 M3 BETON BALOK B.19 (30/60)

252/314 517211341.xlsx/ANALISA (2)


1 2 3 4
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
91.0823 Kg Besi beton 22,764.00 2,073,397.48
8.3330 M2 Bekisting 372,175.00 3,101,334.28
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 6,806,577.86
82 1 M3 BETON BALOK B.20 (30/60)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
115.7154 Kg Besi beton 22,764.00 2,634,145.37
8.3330 M2 Bekisting 372,175.00 3,101,334.28
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,367,325.75
83 1 M3 BETON BALOK B.21 (35/70)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
176.7090 Kg Besi beton 22,764.00 4,022,603.68
7.1428 M2 Bekisting 372,175.00 2,658,371.59
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 8,312,821.38
84 1 M3 BETON BALOK B.22 (35/70)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
153.9200 Kg Besi beton 22,764.00 3,503,834.88
7.1428 M2 Bekisting 372,175.00 2,658,371.59
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,794,052.58
85 1 M3 BETON BALOK B.23 (30/60)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
99.3730 Kg Besi beton 22,764.00 2,262,126.97
8.3330 M2 Bekisting 372,175.00 3,101,334.28
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 6,995,307.36
86 1 M3 BETON BALOK B.24 (30/60)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
108.0528 Kg Besi beton 22,764.00 2,459,713.94
8.3330 M2 Bekisting 372,175.00 3,101,334.28
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,192,894.33
87 1 M3 BETON BALOK B.25 (30/60)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
120.4654 Kg Besi beton 22,764.00 2,742,274.37
8.3330 M2 Bekisting 372,175.00 3,101,334.28
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,475,454.75
88 1 M3 BETON BALOK B.26 (24/45)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
157.2445 Kg Besi beton 22,764.00 3,579,513.80
10.2212 M2 Bekisting 372,175.00 3,804,075.11
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 9,015,435.02

1 2 3 4

89 1 M3 BETON BALOK B.27 (24/45)


1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
168.1620 Kg Besi beton 22,764.00 3,828,039.77
10.2212 M2 Bekisting 372,175.00 3,804,075.11
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 9,263,960.99

253/314 517211341.xlsx/ANALISA (2)


1 2 3 4
90 1 M3 BETON BALOK B.28 (30/50)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
146.5589 Kg Besi beton 22,764.00 3,336,266.80
8.6658 M2 Bekisting 372,175.00 3,225,194.12
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 8,193,307.03
91 1 M3 BETON BALOK B.29 (30/50)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
146.5589 Kg Besi beton 22,764.00 3,336,266.80
8.6658 M2 Bekisting 372,175.00 3,225,194.12
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 8,193,307.03
92 1 M3 BETON BALOK B.30 (30/50)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
113.0623 Kg Besi beton 22,764.00 2,573,750.20
8.6658 M2 Bekisting 372,175.00 3,225,194.12
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,430,790.42
93 1 M3 BETON BALOK B.31 (30/50)
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
138.3708 Kg Besi beton 22,764.00 3,149,872.89
8.6658 M2 Bekisting 372,175.00 3,225,194.12
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 8,006,913.12
94 1 M3 BETON RING BALK (RB. 1) 30/50
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
123.4834 Kg Besi beton 22,764.00 2,810,976.12
8.6658 M2 Bekisting 372,175.00 3,225,194.12
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,668,016.34
95 1 M3 BETON RING BALK (RB. 2) 30/50
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
123.4834 Kg Besi beton 22,764.00 2,810,976.12
8.6658 M2 Bekisting 372,175.00 3,225,194.12
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,668,016.34
96 1 M3 BETON RING BALK (RB. 3) 30/60
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
139.3912 Kg Besi beton 22,764.00 3,173,101.28
8.6658 M2 Bekisting 372,175.00 3,225,194.12
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 8,030,141.50

97 1 M3 BETON RING BALK (RB. 4) 30/50


1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
109.2935 Kg Besi beton 22,764.00 2,487,957.23
8.6658 M2 Bekisting 372,175.00 3,225,194.12
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,344,997.46
98 1 M3 BETON RING BALK (RB. 5) 30/50
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
109.2935 Kg Besi beton 22,764.00 2,487,957.23
8.6658 M2 Bekisting 372,175.00 3,225,194.12
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,344,997.46

1 2 3 4

254/314 517211341.xlsx/ANALISA (2)


1 2 3 4

99 1 M3 BETON RING BALK (RB. 6) 25/45


1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
143.2782 Kg Besi beton 22,764.00 3,261,584.94
10.2212 M2 Bekisting 372,175.00 3,804,075.11
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 8,697,506.17
100 1 M3 BETON RING BALK (RB. 7) 25/45
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
143.2782 Kg Besi beton 22,764.00 3,261,584.94
10.2212 M2 Bekisting 372,175.00 3,804,075.11
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 8,697,506.17
101 1 M3 BETON RING BALK (RB. 8) 30/50
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
109.2900 Kg Besi beton 22,764.00 2,487,877.56
10.2212 M2 Bekisting 372,175.00 3,804,075.11
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,923,798.78
102 1 M3 BETON RING BALK (RB. 9) 20/30
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
250.2080 Kg Besi beton 22,764.00 5,695,734.91
13.3328 M2 Bekisting 372,175.00 4,962,134.84
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 12,289,715.86
103 1 M3 BETON RING BALK (RB. 10) 20/30
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
250.2080 Kg Besi beton 22,764.00 5,695,734.91
13.3328 M2 Bekisting 372,175.00 4,962,134.84
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 12,289,715.86
104 1 M3 BETON RING BALK (RB. 11) 30/60
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
155.2058 Kg Besi beton 22,764.00 3,533,104.83
8.3330 M2 Bekisting 372,175.00 3,101,334.28
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
8,266,285.22
105 1 M3 BETON RING BALK (RB. 12) 30/60
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
99.3730 Kg Besi beton 22,764.00 2,262,126.97
8.3330 M2 Bekisting 372,175.00 3,101,334.28
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 6,995,307.36
106 1 M3 BETON RING BALK (RB. 13) 20/30
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
250.2080 Kg Besi beton 22,764.00 5,695,734.91
13.3328 M2 Bekisting 372,175.00 4,962,134.84
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 12,289,715.86

107 1 M3 BETON RING BALK (RB. 14) 30/60


1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
180.0203 Kg Besi beton 22,764.00 4,097,982.11
8.3330 M2 Bekisting 372,175.00 3,101,334.28
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 8,831,162.50
108 1 M3 BETON RING BALK (RB. 15) 30/60
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
102.4748 Kg Besi beton 22,764.00 2,332,736.35

255/314 517211341.xlsx/ANALISA (2)


1 2 3 4
8.3330 M2 Bekisting 372,175.00 3,101,334.28
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,065,916.73

1 2 3 4

109 1 M3 BETON RING BALK (RB. 16) 30/50


1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
109.2935 Kg Besi beton 22,764.00 2,487,957.23
8.6658 M2 Bekisting 372,175.00 3,225,194.12
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,344,997.46

110 1 M3 BETON RING BALK (RB. 17) 30/50


1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
167.2157 Kg Besi beton 22,764.00 3,806,498.19
7.1428 M2 Bekisting 372,175.00 2,658,371.59
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 8,096,715.90

111 1 M3 BETON RING BALK (RB. 18) 20/30


1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
250.2080 Kg Besi beton 22,764.00 5,695,734.91
13.3328 M2 Bekisting 372,175.00 4,962,134.84
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 12,289,715.86

112 1 M3 BETON RING BALK (RB. 19) 25/45


1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
157.2445 Kg Besi beton 22,764.00 3,579,513.80
10.2212 M2 Bekisting 372,175.00 3,804,075.11
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 9,015,435.02

58 1 M3 COR SPESIE 1 : 5
190.0000 Kg Semen Pc 1,600.00 304,000.00
0.8500 M3 Pasir cor 245,000.00 208,250.00
6.0000 o/h Pekerja 80,000.00 480,000.00
0.5000 o/h Tukang 110,000.00 55,000.00
0.0500 o/h Kepala tukang 120,000.00 6,000.00
0.3000 o/h Mandor 125,000.00 37,500.00
Jumlah 1,090,750.00

256/314 517211341.xlsx/ANALISA (2)


1 2 3 4

59 1 M3 LISTPLANK BETON
1.0000 M3 Beton K.175 1,519,029.44 1,519,029.44
102.3660 Kg Besi beton 22,764.00 2,330,259.62
10.0000 M2 Bekisting 365,635.00 3,656,350.00
0.7500 o/h Tukang bongkar 80,000.00 60,000.00
Jumlah 7,565,639.07
60 1 M3 SIRIP BETON
1.0000 M3 Beton K.175 1519029.4444445 1,519,029.44
125.1854 Kg Besi beton 22764 2,849,720.45
8.3000 M2 Bekisting 365635 3,034,770.50
0.7500 o/h Tukang bongkar 80000 60,000.00
Jumlah 7,463,520.39

61 1 M3 PLAT BETON untuk TANGGA


1.0000 M3 Beton K. 225 1591846.1111111 1,591,846.11
142.6700 Kg Besi beton 22764 3,247,739.88
8.5000 M2 Bekisting 343235 2,917,497.50
0.5000 o/h Tukang bongkar/siram 80000 40,000.00
Jumlah 7,797,083.49

60 1 M3 PLAT LANTAI
1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
152.4300 Kg Besi beton 22,764.00 3,469,916.52
8.3300 M2 Bekisting 525,635.00 4,378,539.55
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 9,480,302.18

61 1 M3 PLAT ATAP BETON


1.0000 M3 Beton K. 225 1,591,846.11 1,591,846.11
142.6700 Kg Besi beton 22,764.00 3,247,739.88
10.0000 M2 Bekisting 525,635.00 5,256,350.00
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 10,135,935.99

62 1 M' PEKERJAAN CANSTIN


0.1000 m3 Beton tumbuk K.100 862,360.19 86,236.02
0.8000 m2 Plesteran 62,021.60 49,617.28
0.8000 m2 Acian 34,650.00 27,720.00
0.8000 m2 Cat Minyak 99,725.00 79,780.00
Jumlah 243,353.30

63 1 M3 MEJA BETON (WASHTAFEL)


1.0000 M3 Beton K. 125 971,567.41 971,567.41
35.5500 Kg Besi beton 22,764.00 809,260.20
10.0000 M2 Bekisting 525,635.00 5,256,350.00
0.5000 o/h Tukang bongkar/siram 80,000.00 40,000.00
Jumlah 7,077,177.61

64 1 M2 PLESTERAN 1 PC : 2 PSR (Tebal 1,5 cm)


10.2240 Kg Semen 1,600.00 16,358.40
0.0200 m3 Pasir 235,000.00 4,700.00
0.3000 o/h Pekerja 80,000.00 24,000.00
0.1500 o/h Tukang batu 110,000.00 16,500.00

257/314 517211341.xlsx/ANALISA (2)


1 2 3 4
0.0150 o/h Kepala tukang 120,000.00 1,800.00
0.0150 o/h Mandor 125,000.00 1,875.00
Jumlah 65,233.40

1 2 3 4

65 1 M2 PLESTERAN 1 PC : 3 PSR (Tebal 1,5 cm)


7.7760 Kg Semen 1,600.00 12,441.60
0.0230 m3 Pasir 235,000.00 5,405.00
0.3000 o/h Pekerja 80,000.00 24,000.00
0.1500 o/h Tukang batu 110,000.00 16,500.00
0.0150 o/h Kepala tukang 120,000.00 1,800.00
0.0150 o/h Mandor 125,000.00 1,875.00
Jumlah 62,021.60

1 2 3 4

66 1 M2 ACIAN
3.2500 Kg Semen Pc 1,600.00 5,200.00
0.2000 o/h Pekerja 80,000.00 16,000.00
0.1000 o/h Tukang 110,000.00 11,000.00
0.0100 o/h Kepala tukang 120,000.00 1,200.00
0.0100 o/h Mandor 125,000.00 1,250.00
Jumlah 34,650.00

67 1 M2 PLESTERAN 1 PC : 4 PSR (Tebal 1,5 cm)


6.2400 Kg Semen 1,600.00 9,984.00
0.0240 m3 Pasir 235,000.00 5,640.00
0.3000 o/h Pekerja 80,000.00 24,000.00
0.1500 o/h Tukang batu 110,000.00 16,500.00
0.0150 o/h Kepala tukang 120,000.00 1,800.00
0.0150 o/h Mandor 125,000.00 1,875.00
Jumlah 59,799.00

68 1 M2 WATER PROOFING
2.9000 kg Water proofing 30,000.00 87,000.00
0.3000 o/h Pekerja 80,000.00 24,000.00
0.2000 o/h Tukang batu 110,000.00 22,000.00
0.0200 o/h Kepala tukang 120,000.00 2,400.00
0.0150 o/h Mandor 125,000.00 1,875.00
Jumlah 137,275.00

258/314 517211341.xlsx/ANALISA (2)


1 2 3 4

1 2 3 4.00

1 2 3 4.00
69 1 M' PASANGAN PLINT KERAMIK 10/60
0.6820 Bh Plint Keramik 10/60 cm 128,005.76 87,299.93
1.9200 Kg Semen 1,600.00 3,072.00
0.0090 M3 Pasir 235,000.00 2,115.00
0.3240 Kg Semen Warna 7,500.00 2,430.00
0.1400 o/h Pekerja 80,000.00 11,200.00
0.0700 o/h Tukang batu 110,000.00 7,700.00
0.0070 o/h Kepala tukang 120,000.00 840.00
0.0070 o/h Mandor 125,000.00 875.00
Jumlah Lt 1 x 1.00 115,531.93
70 1 M' PASANGAN BORDER KERAMIK 6/20
5.3000 Bh List Keramik 6/20 cm 15,000.00 79,500.00
1.1400 Kg Semen 1,600.00 1,824.00
0.0030 M3 Pasir 235,000.00 705.00
0.1000 Kg Semen Warna 7,500.00 750.00
0.0900 o/h Pekerja 80,000.00 7,200.00
0.0900 o/h Tukang batu 110,000.00 9,900.00
0.0090 o/h Kepala tukang 120,000.00 1,080.00
0.0050 o/h Mandor 125,000.00 625.00
Jumlah Lt 1 x 1.00 101,584.00
71 1 M2 PASANGAN DINDING KERAMIK 20/25
21.6000 Bh Tegel keramik 20/25 cm 4,700.00 101,520.00
9.3000 Kg Semen 1,600.00 14,880.00
0.0180 M3 Pasir 235,000.00 4,230.00
1.9400 Kg Semen Warna 7,500.00 14,550.00
0.9000 o/h Pekerja 80,000.00 72,000.00
0.4500 o/h Tukang batu 110,000.00 49,500.00
0.0450 o/h Kepala tukang 120,000.00 5,400.00
0.0450 o/h Mandor 125,000.00 5,625.00
Jumlah Lt 1 1.00 267,705.00

1 2 3 4
72 1 M2 PASANGAN LANTAI KERAMIK (Granito) 60/60 (SNI 7395:2008)
3.1000 Bh Keramik 60/60 cm 128,005.76 396,817.85
0.0450 M3 Pasir 235,000.00 10,575.00
9.6000 Kg Semen 1,600.00 15,360.00
1.6200 Kg Semen Warna 7,500.00 12,150.00
0.7000 o/h Pekerja 80,000.00 56,000.00
0.3500 o/h Tukang batu 110,000.00 38,500.00
0.0350 o/h Kepala tukang 120,000.00 4,200.00
0.0350 o/h Mandor 125,000.00 4,375.00
Jumlah Lt 1 1.00 537,977.85
Jumlah Lt 2 X 1.05 564,876.75
1 M 2 PASANG LANTAI GRANITO 60 x 60
1.0500 M2 Granito 60 x 60 cm 128,005.76 134,406.05
2.0000 Bh Pacu Pancing 60 x 230 6,000.00 12,000.00
12.4400 Kg Semen Portland 1,500.00 18,660.00
0.0250 M3 Pasir Pasang 250,000.00 6,250.00
1.5000 Kg Semen Warna 3,000.00 4,500.00
0.5200 h.o Pekerja 75,000.00 39,000.00

259/314 517211341.xlsx/ANALISA (2)


1 2 3 4
0.6500 h.o Tukang Batu 100,000.00 65,000.00
0.0650 h.o Kepala Tukang 105,000.00 6,825.00
0.0350 h.o Mandor 110,000.00 3,850.00
290,491.05
Jumlah Lt 3 X 1.09 586,395.86

1 2 3 4
73 1 M2 PASANG DINDING GRANIT 30/60
1.0600 M2 Granit 2,050,000.00 2,173,000.00
3.0030 Bh Paku 12 1,200.00 3,603.60
0.0250 M3 Pasir 235,000.00 5,875.00
12.4400 Kg Semen 1,600.00 19,904.00
0.6500 Kg Semen Warna 7,500.00 4,875.00
1.3000 o/h Pekerja 80,000.00 104,000.00
0.6500 o/h Tukang batu 110,000.00 71,500.00
0.0650 o/h Kepala tukang 120,000.00 7,800.00
0.0650 o/h Mandor 125,000.00 8,125.00
Jumlah Lt 1 1 2,398,682.60

74 1 M2 PASANGAN LANTAI KERAMIK 40/40


6.6300 Bh Keramik 40/40 cm 17,000.00 112,710.00
0.0450 M3 Pasir 235,000.00 10,575.00
8.1900 Kg Semen 1,600.00 13,104.00
1.6200 Kg Semen Warna 7,500.00 12,150.00
0.7000 o/h Pekerja 80,000.00 56,000.00
0.3500 o/h Tukang batu 110,000.00 38,500.00
0.0350 o/h Kepala tukang 120,000.00 4,200.00
0.0350 o/h Mandor 125,000.00 4,375.00
Jumlah Lt 1 x 1.00 251,614.00

75 1 M2 PASANGAN LANTAI KERAMIK 30/30


11.8700 Bh Keramik 30/30 cm 8,000.00 94,960.00
0.0450 M3 Pasir 235,000.00 10,575.00
10.0000 Kg Semen 1,600.00 16,000.00
1.5000 Kg Semen Warna 7,500.00 11,250.00
0.7000 o/h Pekerja 80,000.00 56,000.00
0.3500 o/h Tukang batu 110,000.00 38,500.00
0.0350 o/h Kepala tukang 120,000.00 4,200.00
0.0350 o/h Mandor 125,000.00 4,375.00
Jumlah Lt 1 x 1.00 235,860.00

260/314 517211341.xlsx/ANALISA (2)


1 2 3 4

76 1 M2 PASANGAN LANTAI KERAMIK 20/20


26.5000 Bh Keramik 20/20 cm 3,500.00 92,750.00
0.0450 M3 Pasir 235,000.00 10,575.00
10.4000 Kg Semen 1,600.00 16,640.00
1.6200 Kg Semen Warna 7,500.00 12,150.00
0.7000 o/h Pekerja 80,000.00 56,000.00
0.3500 o/h Tukang batu 110,000.00 38,500.00
0.0350 o/h Kepala tukang 120,000.00 4,200.00
0.0350 o/h Mandor 125,000.00 4,375.00
Jumlah Lt 1 x 1.00 235,190.00

77 1 M2 PASANG DINDING LOSTER KERAMIK 30/30


25.0000 Bh Loster Keramik 30/30 50,000.00 1,250,000.00
9.3000 Kg Semen Pc 1,600.00 14,880.00
0.0180 M3 Pasir Pasang 235,000.00 4,230.00
0.6000 o/h Pekerja 80,000.00 48,000.00
0.1000 o/h Tukang 110,000.00 11,000.00
0.0450 o/h Kepala Tukang 120,000.00 5,400.00
0.0300 o/h Mandor 125,000.00 3,750.00
Jumlah Lt 1 x 1.00 1,337,260.00

Jumlah Lt 2 X 1.05 1,404,123.00


Jumlah Lt 3 X 1.09 1,530,494.07
Jumlah 1,337,260.00
78 1 M2 PASANG STIKER SAND BLASTING
1.2000 M2 Stiker Sand Blasting 230,000.00 276,000.00
1.0000 Scht Perekat (sampo 250 mg) 1,200.00 1,200.00
0.0200 o/h Pekerja 80,000.00 1,600.00
0.2000 o/h Tukang 110,000.00 22,000.00
0.0200 o/h Kepala Tukang 120,000.00 2,400.00
0.0025 o/h Mandor 125,000.00 312.50
Jumlah 303,512.50

79 1 M2 PASANG WALLPAPER lebar 50 cm


2.2000 M' Wallpaper 90,000.00 198,000.00
0.2500 Kg Lem Wallpaper (perekat) 40,000.00 10,000.00
0.3500 o/h Pekerja 80,000.00 28,000.00
0.1750 o/h Tukang 110,000.00 19,250.00
0.0170 o/h Kepala Tukang 120,000.00 2,040.00
0.0020 o/h Mandor 125,000.00 250.00
Jumlah 257,540.00
80 1 M' PASANG BORDER WALLPAPER
1.2000 M' Border Wallpaper 45,000.00 54,000.00
0.1000 Kg Lem Wallpaper 40,000.00 4,000.00
0.2500 o/h Pekerja 80,000.00 20,000.00
0.2500 o/h Tukang 110,000.00 27,500.00
0.0250 o/h Kepala tukang 120,000.00 3,000.00
Jumlah 108,500.00
81 1 M2 PELABURAN BIDANG KAYU DENGAN VERNIS
81 1 M2 0.15 Ltr Vernis 32,000.00 4,800.00
0.0500 Kg Dempul 45,000.00 2,250.00
0.1000 Lbr Amplas 5,000.00 500.00
0.0100 Bh Kuas 12,000.00 120.00
0.1600 H.o Pekerja 75,000.00 12,000.00
0.1600 H.o Tukang Cat 100,000.00 16,000.00
0.0160 H.o Kepala Tukang 105,000.00 1,680.00
0.0025 H.o Mandor 110,000.00 275.00
37,625.00

261/314 517211341.xlsx/ANALISA (2)


1 2 3 4
1 2 3 4

0.1500 Ltr Vernis 35,000.00 5,250.0000


0.0500 Kg Dempul 50,000.00 2,500.0000
0.1000 Lbr Amplas 4,000.00 400.0000
0.0100 Bh Kuas 12,000.00 120.0000
0.1600 H.o Pekerja 80,000.00 12,800.0000
0.1600 H.o Tukang Cat 110,000.00 17,600.0000
0.0160 H.o Kepala Tukang 120,000.00 1,920.0000
0.0025 H.o Mandor 125,000.00 312.5000
Jumlah 40,902.5000
82 1 M' PEKERJAAN COMPOUND
1.2000 M' Plester "Cotton Tape" 700.00 840.00
0.4500 Kg Compound (2 x Lari ) 9,500.00 4,275.00
0.0200 o/h Pekerja 80,000.00 1,600.00
0.0630 o/h Tukang 110,000.00 6,930.00
0.0063 o/h Kepala Tukang 120,000.00 756.00
0.0025 o/h Mandor 125,000.00 312.50
Jumlah 14,713.50

83 1 M2 CAT MINYAK (1 x Lapis Plamur Kayu, 1 x Cat Dasar, 3 x Cat Penutup)

0.2000 Kg Cat Meny 25,000.00 5,000.00


0.1500 Kg Plamur 34,000.00 5,100.00
0.1700 Kg Cat Dasar (Minyak) 75,000.00 12,750.00
0.3500 kg Cat minyak / Cat Penutup 75,000.00 26,250.00
0.2500 o/h Pekerja 80,000.00 20,000.00
0.2500 o/h Tukang cat 110,000.00 27,500.00
0.0250 o/h Kepala tukang 120,000.00 3,000.00
0.0010 o/h Mandor 125,000.00 125.00
Jumlah 99,725.00

262/314 517211341.xlsx/ANALISA (2)


1 2 3 4

84 1 M2 CAT PLAFON
0.1100 Kg Cat Plafon 40,000.00 4,400.00
0.0800 o/h Pekerja 80,000.00 6,400.00
0.1100 o/h Tukang cat 110,000.00 12,100.00
0.0110 o/h Kepala tukang 120,000.00 1,320.00
0.0050 o/h Mandor 125,000.00 625.00
Jumlah 24,845.00

1 2 3 4

85 1 M2 CAT DINDING TEMBOK BARU / DINDING DALAM


(1 Lapis Plamir, 1 Lapis Cat Dasar, dan 2 lapis cat penutup)

0.1000 Kg Plamur 34,000.00 3,400.00


0.1000 Kg Cat Tembok Dasar 40,000.00 4,000.00
0.2600 Kg Cat Penutup 2 x 45,000.00 11,700.00
0.0200 o/h Pekerja 80,000.00 1,600.00
0.0630 o/h Tukang cat 110,000.00 6,930.00
0.0063 o/h Kepala tukang 120,000.00 756.00
0.0025 o/h Mandor 125,000.00 312.50
1.0000 Ls Alat Bantu (kuas, amplas, lem, 3,000.00 3,000.00
scafolding)
Jumlah Lt 1 31,698.50
-
86 1 M2 CAT DINDING TEMBOK BARU / LUAR (DULUX)
(1 Lapis Plamir, 1 Lapis Cat Dasar, dan 2 lapis cat penutup)
0.1000 Kg Plamur 34,000.00 3,400.00
0.1000 Kg Cat Tembok Luar (Dulux) 52,500.00 5,250.00
0.2600 Kg Cat Penutup 2 x 85,000.00 22,100.00
0.0200 o/h Pekerja 80,000.00 1,600.00
0.0630 o/h Tukang cat 110,000.00 6,930.00
0.0063 o/h Kepala tukang 120,000.00 756.00
0.0025 o/h Mandor 125,000.00 312.50
1.0000 Ls Alat Bantu (kuas, amplas, lem, 4,000.00 4,000.00
scafolding)
Jumlah Lt 1 44,348.50

87 1 M2 CAT DASAR
0.3300 Ltr Cat Dasar / Meni 25,000.00 8,250.00
0.0100 Bh Kuas 7,500.00 75.00
0.0200 o/h Pekerja 80,000.00 1,600.00
0.2000 o/h Tukang cat 110,000.00 22,000.00
0.0200 o/h Kepala tukang 120,000.00 2,400.00
0.0100 o/h Mandor 125,000.00 1,250.00
Jumlah 35,575.00
88 1 M2 MENCAT DUCO
0.3500 Kg Cat Duco (Nippe) 52,000.00 18,200.00
0.2000 Kg Dempul Isamu Plastik 50,000.00 10,000.00
0.1700 Kg Cat Dasar Abu-abu 42,900.00 7,293.00
1.0000 Lbr Kertas Gosok 4,000.00 4,000.00
1.2500 Kg Thinner 49,700.00 62,125.00
0.3000 Kg Clear 49,700.00 14,910.00
1.0000 Ls Alat Bantu (Kompresor) 7,500.00 7,500.00
0.2500 o/h Pekerja 80,000.00 20,000.00
0.3500 o/h Tukang cat 110,000.00 38,500.00
0.0250 o/h Kepala tukang 120,000.00 3,000.00
0.0010 o/h Mandor 125,000.00 125.00
Jumlah 185,653.00

263/314 517211341.xlsx/ANALISA (2)


1 2 3 4

1 2 3 4

89 1 M2 CAT MELAMIN
0.4000 Kg Wood Filler 46,000.00 18,400.00
1.0000 Kg Thinner 49,700.00 49,700.00
0.3000 Kg Sending 49,700.00 14,910.00
0.3000 Kg Clear 49,700.00 14,910.00
0.3000 Kg Pewarna 55,000.00 16,500.00
0.2000 Lbr Kertas gosok 4,000.00 800.00
0.2500 o/h Pekerja 80,000.00 20,000.00
0.2500 o/h Tukang 110,000.00 27,500.00
0.0250 o/h Kepala tukang 120,000.00 3,000.00
0.0010 o/h Mandor 125,000.00 125.00
Jumlah 165,845.00

90 1 M2 PEKERJAAN RANGKA DINDING PEMISAH / PARTISI


(60 x 120) cm KAYU BESI
0.0280 M3 Balok kayu besi 5/10 3,250,000.00 91,000.00
0.1500 Kg Paku campur 21,000.00 3,150.00
0.1500 o/h Pekerja 80,000.00 12,000.00
0.4500 o/h Tukang 110,000.00 49,500.00
0.0450 o/h Kepala tukang 120,000.00 5,400.00
0.0080 o/h Mandor 125,000.00 1,000.00
Jumlah 162,050.00

264/314 517211341.xlsx/ANALISA (2)


1 2 3 4
91 1 M2 PEKERJAAN RANGKA DINDING Triplex/Dinding Hias
60 x 120) cm
0.0160 M3 Balok kayu matoa 2,180,000.00 34,880.00
0.0804 Kg Paku campur 21,000.00 1,687.50
0.0804 o/h Pekerja 80,000.00 6,428.57
0.2411 o/h Tukang 110,000.00 26,517.86
0.0129 o/h Kepala tukang 120,000.00 1,549.74
0.0043 o/h Mandor 125,000.00 535.71
Jumlah 71,599.39

92 1 M2 PEKERJAAN RANGKA PLAFON 60/60


0.0163 M3 Balok kayu matoa 2,180,000.00 35,534.00
0.2500 Kg Paku campur 21,000.00 5,250.00
0.2000 o/h Pekerja 80,000.00 16,000.00
0.3000 o/h Tukang 110,000.00 33,000.00
0.0300 o/h Kepala tukang 120,000.00 3,600.00
0.0100 o/h Mandor 125,000.00 1,250.00
Jumlah 94,634.00
18 1 M2 PEKERJAAN RANGKA PLAFOND 1,00X1,00 M2, HOLLOW 40X40X1,2 MM
2.9360 Kg Hollow 40x40x3,2 mm 23,000.00 67,528.00
1.0000 set assessories 13,362.00 13,362.00
0.0900 o/h Pekerja 80,000.00 7,200.00
0.0150 o/h Tukang 110,000.00 1,650.00
0.0090 o/h Kepala Tukang 120,000.00 1,080.00
0.0005 o/h Mandor 125,000.00 56.25
Jumlah 90,876.25
18 1 M2 PEKERJAAN RANGKA PLAFOND 1,00X1,00 M2, HOLLOW 40X40X1,2 MM
0.8500 Bttg Hollow steel 40x40x3,2 mm 23,000.00 19,550.00
1.0000 set assessories 13,362.00 13,362.00
0.0900 o/h Pekerja 80,000.00 7,200.00
0.0150 o/h Tukang 110,000.00 1,650.00
0.0090 o/h Kepala Tukang 120,000.00 1,080.00
0.0005 o/h Mandor 125,000.00 56.25
Jumlah 42,898.25
Lantai 2 x 1.09 103,151.06
Lantai 3 x 1.15 108,829.10

92 1 Kg PEKERJAAN BESI HOLLOW PADA RANGKA PLAFOND


1.1500 Kg Hollow 40x40x3.2 Mm 20,000.00 23,000.00
1.0000 Ls Bending dan Las 3,450.00 3,450.00
0.0800 Kg Meni Besi 25,000.00 2,000.00
0.0600 o/h Pekerja 80,000.00 4,800.00
0.0600 o/h Tukang 110,000.00 6,600.00
0.0060 o/h Kepala Tukang 120,000.00 720.00
0.0030 o/h Mandor 125,000.00 375.00
1.0000 Ls Alat Bantu 1,000.00 1,000.00
Jumlah 41,945.00

93 1 M2 PEKERJAAN RANGKA PLAFON KAYU 60/60 PADA DOME


0.0283 M3 Balok kayu matoa 2,180,000.00 61,694.00
0.4000 Kg Paku campur 21,000.00 8,400.00
1.0000 Ls Perlengkapan/pengikat 1,000.00 1,000.00
0.2700 o/h Pekerja 80,000.00 21,600.00
0.4050 o/h Tukang 110,000.00 44,550.00
0.0405 o/h Kepala tukang 120,000.00 4,860.00
0.0135 o/h Mandor 125,000.00 1,687.50
Jumlah 143,791.50

265/314 517211341.xlsx/ANALISA (2)


1 2 3 4

1 2 3 4

94 1 M2 PEKERJAAN PLAFON GYPSUM


0.8500 Btg Hollow steel 50,000.00 42,500.00
1.0000 Ls Penggantung 17,000.00 17,000.00
0.3640 Lbr Gypsum Board 118,000.00 42,952.00
0.0700 Doz Sekrup Gypsum 280,000.00 19,600.00
0.3300 o/h Pekerja 80,000.00 26,400.00
0.4186 o/h Tukang 110,000.00 46,046.00
0.0470 o/h Kepala Tukang 120,000.00 5,640.00
0.0155 o/h Mandor 125,000.00 1,937.50
Jumlah 202,075.50

1 2 3 4

Lantai 2 x 1.09 220,262.30


Lantai 3 x 1.5 303,113.25

95 1 M2 PEKERJAAN PLAFON GYPSUM (DOME)


0.8500 Btg Hollow steel 50,000.00 42,500.00
1.0000 Ls Perlengkapan/pengikat 1,000.00 1,000.00
0.3640 Lbr Gypsum Board 118,000.00 42,952.00
0.0700 Doz Sekrup Gypsum 280,000.00 19,600.00
0.4950 o/h Pekerja 80,000.00 39,600.00
0.6279 o/h Tukang 110,000.00 69,069.00
0.0705 o/h Kepala Tukang 120,000.00 8,460.00
0.0233 o/h Mandor 125,000.00 2,906.25
1.0000 Ls Alat Bantu 1,000.00 1,000.00
Jumlah 226,087.25

96 1 M2 PEKERJAAN PLAFON TRIPLEKS 6 MM


0.3360 Lbr Tripleks 6 mm 112,000.00 37,632.00
0.0200 Kg Paku Tripleks 22,000.00 440.00
0.1000 o/h Pekerja 80,000.00 8,000.00
0.0500 o/h Tukang 110,000.00 5,500.00
0.0050 o/h Kepala Tukang 120,000.00 600.00
0.0050 o/h Mandor 125,000.00 625.00
Jumlah 52,797.00
97 1 M2 PEKERJAAN DINDING TRIPLEKS 6 MM
0.3670 Lbr Tripleks 6 mm 112,000.00 41,104.00
0.2500 Kg Paku Tripleks 22,000.00 5,500.00
0.1000 o/h Pekerja 80,000.00 8,000.00
0.0500 o/h Tukang 110,000.00 5,500.00
0.0050 o/h Kepala Tukang 120,000.00 600.00
0.0050 o/h Mandor 125,000.00 625.00
Jumlah 61,329.00
Lantai 2 x 1.09 66,848.61
Lantai 3 x 1.15 70,528.35

98 1 M2 PEKERJAAN PLAFON LAMBERSERING


13.7500 M' List profil Lambersering 7,000.00 96,250.00
0.2500 Kg Paku campur 21,000.00 5,250.00

266/314 517211341.xlsx/ANALISA (2)


1 2 3 4
0.0210 o/h Pekerja 80,000.00 1,680.00
0.0210 o/h Tukang kayu 110,000.00 2,310.00
0.0020 o/h Kepala tukang 120,000.00 240.00
0.0010 o/h Mandor 125,000.00 125.00
Jumlah 105,855.00
Lantai 2 x 1.09 115,381.95
Lantai 3 x 1.15 121,733.25
99 1 M2 PLAFON HIAS LAPIS SUNGKAI
0.3670 Lbr Sungkai 175,000.00 64,225.00
0.3600 Lbr Tripleks 6 mm 112,000.00 40,320.00
0.0200 Kg Paku Tripleks 22,000.00 440.00
0.2500 Kg Lem Fox kuning 42,000.00 10,500.00
0.0120 M3 Kayu Penggantung -
0.1500 Kg Paku Campur -
0.2800 o/h Pekerja 80,000.00 22,400.00
0.8000 o/h Tukang 110,000.00 88,000.00
0.0800 o/h Kepala Tukang 120,000.00 9,600.00
0.0140 o/h Mandor 125,000.00 1,750.00
Jumlah 237,235.00

267/314 517211341.xlsx/ANALISA (2)


1 2 3 4

100 1 M2 PLAFON HIAS LAPIS SUNGKAI (DOMB)


0.3670 Lbr Sungkai 175,000.00 64,225.00
0.3600 Lbr Tripleks 6 mm 112,000.00 40,320.00
0.0200 Kg Paku Tripleks 22,000.00 440.00
0.2500 Kg Lem Fox kuning 42,000.00 10,500.00
0.0120 M3 Kayu Penggantung -
0.1500 Kg Paku Campur -
0.3780 o/h Pekerja 80,000.00 30,240.00
1.0800 o/h Tukang 110,000.00 118,800.00
0.1080 o/h Kepala Tukang 120,000.00 12,960.00
0.0189 o/h Mandor 125,000.00 2,362.50
1.0000 Ls Alat Bantu 1,000.00 1,000.00
Jumlah 280,847.50

101 1 M2 PEKERJAAN DINDING GYPSUM BOARD 9 MM


/SATU SISI
0.3640 Lbr Gypsum Board 118,000.00 42,952.00
0.1100 Kg Sekrup Gypsum 280,000.00 30,800.00
0.1000 o/h Pekerja 80,000.00 8,000.00
0.0500 o/h Tukang 110,000.00 5,500.00
0.0050 o/h Kepala Tukang 120,000.00 600.00
0.0050 o/h Mandor 125,000.00 625.00
Jumlah 88,477.00
Lantai 2 x 1.09 96,439.93
Lantai 3 x 1.15 101,748.55
102 1 M' PEKERJAAN LIST PLAFON PROFIL
1.2000 m' List Plafon 20,000.00 24,000.00
0.0100 kg Paku 21,000.00 210.00
0.0500 o/h Pekerja 80,000.00 4,000.00
0.0500 o/h Tukang kayu 110,000.00 5,500.00
0.0050 o/h Kepala tukang 120,000.00 600.00
0.0030 o/h Mandor 125,000.00 375.00
Jumlah 34,685.00
103 1 M' PEKERJAAN LIST PLAFON KAYU PROFIL LURUS
1.2000 m' List Plafon 5 cm 15,000.00 18,000.00
0.0100 kg Paku 21,000.00 210.00
0.0500 o/h Pekerja 80,000.00 4,000.00
0.0500 o/h Tukang kayu 110,000.00 5,500.00
0.0050 o/h Kepala tukang 120,000.00 600.00
0.0030 o/h Mandor 125,000.00 375.00
Jumlah 28,685.00
104 1 M' PEKERJAAN LIST PLAFON KAYU PROFIL LURUS
1.2000 m' List Plafon 4 cm 10,000.00 12,000.00
0.0100 kg Paku 21,000.00 210.00
0.0500 o/h Pekerja 80,000.00 4,000.00
0.0500 o/h Tukang kayu 110,000.00 5,500.00
0.0050 o/h Kepala tukang 120,000.00 600.00
0.0030 o/h Mandor 125,000.00 375.00
Jumlah 22,685.00

1 2 3.00 4

105 1 M' PEKERJAAN LIST PROFIL DINDING


1.2000 m' List Profil Dinding 16,000.00 19,200.00
0.1000 Kg Paku Campur 21,000.00 2,100.00
0.0500 o/h Pekerja 80,000.00 4,000.00
0.0500 o/h Tukang Kayu 110,000.00 5,500.00

268/314 517211341.xlsx/ANALISA (2)


1 2 3 4
0.0050 o/h Kepala Tukang 120,000.00 600.00
0.0030 o/h Mandor 125,000.00 375.00
Jumlah 31,775.00

106 1 M' PEKERJAAN LIST PLINT KAYU


1.0500 m' List Plint Kayu 20,000.00 21,000.00
0.0100 kg Paku 21,000.00 210.00
0.0500 o/h Pekerja 80,000.00 4,000.00
0.0500 o/h Tukang kayu 110,000.00 5,500.00
0.0050 o/h Kepala tukang 120,000.00 600.00
0.0030 o/h Mandor 125,000.00 375.00
Jumlah 31,685.00

1 2 3 4

107 1 M' PEKERJAAN LIST KODOK


1.0500 m' List Kodok 17,500.00 18,375.00
0.0100 kg Paku 21,000.00 210.00
0.0500 o/h Pekerja 80,000.00 4,000.00
0.0500 o/h Tukang kayu 110,000.00 5,500.00
0.0050 o/h Kepala tukang 120,000.00 600.00
0.0030 o/h Mandor 125,000.00 375.00
Jumlah 29,060.00

108 1 M' PEKERJAAN LIST LD 3 Cm


1.0500 m' List LD 3 cm 10,000.00 10,500.00
0.0100 kg Paku 21,000.00 210.00
0.0500 o/h Pekerja 80,000.00 4,000.00
0.0500 o/h Tukang kayu 110,000.00 5,500.00
0.0050 o/h Kepala tukang 120,000.00 600.00
0.0030 o/h Mandor 125,000.00 375.00
Jumlah 21,185.00

269/314 517211341.xlsx/ANALISA (2)


1 2 3 4

1 2 3 4

109 1 M3 KUSEN, PINTU DAN JENDELA (Kayu Besi)


1.1000 M3 Balok kayu besi 5/10 3,250,000.00 3,575,000.00
1.2500 Kg Paku campur 21,000.00 26,250.00
1.0000 Kg Lem Kayu (Lem Fox Putih) 40,000.00 40,000.00
7.0000 o/h Pekerja 80,000.00 560,000.00
21.0000 o/h Tukang 110,000.00 2,310,000.00
2.1000 o/h Kepala tukang 120,000.00 252,000.00
0.3500 o/h Mandor 125,000.00 43,750.00
Jumlah 6,807,000.00

110 1 M2 RANGKA KAYU PINTU / JENDELA KACA


0.0240 M3 Papan Kayu Besi 3,500,000.00 84,000.00
0.3000 Kg Lem Kayu (Lem Fox Putih) 40,000.00 12,000.00
0.8000 o/h Pekerja 80,000.00 64,000.00
2.4000 o/h Tukang 110,000.00 264,000.00
0.2400 o/h Kepala tukang 120,000.00 28,800.00
0.0400 o/h Mandor 125,000.00 5,000.00
Jumlah 457,800.00

111 1 M2 RANGKA DAUN JENDELA + KACA POLOS


1.0000 M3 Rangka kayu 457,800.00 457,800.00
1.0000 M2 Kaca polos 5 mm 234,093.75 234,093.75
Jumlah 691,893.75

1 2 3 4

112 1 M2 JENDELA KACA MATI


1.1000 M2 Kaca polos 5 mm 195,000.00 214,500.00
0.0150 o/h Pekerja 80,000.00 1,200.00
0.1500 o/h Tukang 110,000.00 16,500.00
0.0150 o/h Kepala tukang 120,000.00 1,800.00
0.00075 o/h Mandor 125,000.00 93.75
Jumlah 234,093.75

113 1 M2 PASANG PINTU PANIL KACA (BENING)


0.0240 M3 Papan Kayu Besi 3,500,000.00 84,000.00
1.1000 M2 Kaca bening 5 mm 195,000.00 214,500.00
0.3000 Kg Lem Kayu (Lem Fox Putih) 40,000.00 12,000.00
0.3000 o/h Pekerja 80,000.00 24,000.00
2.4000 o/h Tukang 110,000.00 264,000.00
0.2400 o/h Kepala tukang 120,000.00 28,800.00
0.0400 o/h Mandor 125,000.00 5,000.00
Jumlah 632,300.00

114 1 M2 DAUN PINTU PANIL KAYU


0.0400 M3 Papan Kayu Besi 3,500,000.00 140,000.00
0.5000 Kg Lem Kayu (Lem Fox Putih) 40,000.00 20,000.00
1.0000 o/h Pekerja 80,000.00 80,000.00
3.0000 o/h Tukang 110,000.00 330,000.00
0.3000 o/h Kepala tukang 120,000.00 36,000.00
0.0500 o/h Mandor 125,000.00 6,250.00

270/314 517211341.xlsx/ANALISA (2)


1 2 3 4
Jumlah 612,250.00

115 1 M2 PINTU dan JENDELA JALUSI


0.0640 M3 Papan Kayu Besi 3,500,000.00 224,000.00
0.5000 Kg Lem Kayu (Lem Fox Putih) 40,000.00 20,000.00
1.0000 o/h Pekerja 80,000.00 80,000.00
3.0000 o/h Tukang 110,000.00 330,000.00
0.3000 o/h Kepala tukang 120,000.00 36,000.00
0.0500 o/h Mandor 125,000.00 6,250.00
Jumlah 696,250.00

116 1 M2 PEKERJAAN VERGOLA KAYU


0.0150 M3 Papan Kayu Besi 3,500,000.00 52,500.00
0.5000 Kg Lem Kayu (Lem Fox Putih) 40,000.00 20,000.00
1.2800 M2 Finising Kayu 165,845.00 212,281.60
1.0500 m2 Polycarbonat 375,000.00 393,750.00
0.2500 Kg Paku campur 20,000.00 5,000.00
1.0000 o/h Pekerja 80,000.00 80,000.00
3.0000 o/h Tukang 110,000.00 330,000.00
0.3000 o/h Kepala tukang 120,000.00 36,000.00
0.0500 o/h Mandor 125,000.00 6,250.00
Jumlah 1,135,781.60
117 1 Daun PINTU KACA tebal 12 mm
1.7850 m2 Kaca Polos 341,250.00 609,131.25
1.0000 o/h Pekerja 80,000.00 80,000.00
3.0000 o/h Tukang 110,000.00 330,000.00
0.3000 o/h Kepala Tukang 120,000.00 36,000.00
0.0500 o/h Mandor 125,000.00 6,250.00
Jumlah 1,061,381.25

271/314 517211341.xlsx/ANALISA (2)


1 2 3 4

118 1 M' PASANG KUSEN ALUMUNIUM


1.1000 m' Profil Alumunium 223,000.00 245,300.00
2.0000 bh Sekrup Fixer 2,400.00 4,800.00
0.0600 Tbg Sealant 45,000.00 2,700.00
0.0430 o/h Pekerja 80,000.00 3,440.00
0.0430 o/h Tukang Khusus Alumunium 110,000.00 4,730.00
0.0043 o/h Kepala tukang 120,000.00 516.00
0.0021 o/h Mandor 125,000.00 262.50
Jumlah 261,748.50

119 1 M2 PASANG KACA tebal 6 mm


1.1000 m2 Kaca Polos 540,000.00 594,000.00
0.0430 o/h Pekerja 80,000.00 3,440.00
0.0430 o/h Tukang 110,000.00 4,730.00
0.0043 o/h Kepala Tukang 120,000.00 516.00
0.0021 o/h Mandor 125,000.00 262.50
Jumlah 602,948.50

1 2 3 4

120 1 Unit PINTU PANIL YANG DIUKIR KHAS PAPUA


2.0400 m2 Pintu Panil Kayu 612,250.00 1,248,990.00
4.0800 m2 Ukiran Khas Papua 1,500,000.00 6,120,000.00
4.0800 m2 Cat Melamin 165,845.00 676,647.60
Jumlah 8,045,637.60

121 I Unit PINTU UTAMA dan JENDELA KACA ALUMUNIUM


LAPIS GRANIT
10.5900 m2 Pasang Dinding Granit 2,398,682.60 25,402,048.73
29.6000 m' Kusen Alumunium 261,748.50 7,747,755.60
29.6000 m' Karet Skoning 25,000.00 740,000.00
7.2300 m2 Kaca Polos 6 mm 540,000.00 3,904,200.00
2.0000 daun Pintu Kaca Tebal 12 mm 1,061,381.25 2,122,762.50
2.0000 Psg Flooring + Asesoris 2,750,000.00 5,500,000.00
2.0000 Psg Handle Stainless 1,250,000.00 2,500,000.00
2.0000 Bh Kunci 250,000.00 500,000.00
Jumlah 48,416,766.83

122 I Set PASANG PINTU PANIL UKIRAN dan GERBANG


LAPIS GRANIT (PU. 2)
14.4000 m2 Pasang Dinding Granit 2,398,682.60 34,541,029.44
7.2000 m2 Pintu Panil yang diukir 8,045,637.60 57,928,590.72
12.0000 Bh Engsel Pintu Stainless Steel 79,593.75 955,125.00
2.0000 set Kunci Tanam 323,375.00 646,750.00
4.0000 Psg Handle Pintu 294,593.75 1,178,375.00
2.0000 Psg Grendel Tanam 188,425.00 376,850.00
4.0000 set Door Closer 605,312.50 2,421,250.00
Jumlah 98,047,970.16

123 1 M2 PINTU KM/W DOUBLE TEAKWOOD LAPIS


ALUMUNIUM (210 x 72)
0.0250 M3 Papan Kayu Besi 3,500,000.00 87,500.00
0.5000 Kg Lem Kayu (Lem Fox Putih) 40,000.00 20,000.00
0.0300 Kg Paku Campur 21,000.00 630.00
1.0000 Lbr Teakwood ukuran 90 x 220 cm 97,000.00 97,000.00
0.5000 Lbr Plat Alumunium 90 x 220 cm 100,000.00 50,000.00
0.8000 o/h Pekerja 80,000.00 64,000.00
2.4000 o/h Tukang 110,000.00 264,000.00

272/314 517211341.xlsx/ANALISA (2)


1 2 3 4
0.2400 o/h Kepala tukang 120,000.00 28,800.00
0.0400 o/h Mandor 125,000.00 5,000.00
Jumlah 616,930.00
124 1 M2 PINTU DOUBLE TEAKWOOD (pintu shaft)
(150 x 82)
0.0250 M3 Papan Kayu Besi 3,500,000.00 87,500.00
0.5000 Kg Lem Kayu (Lem Fox Putih) 40,000.00 20,000.00
0.0300 Kg Paku Campur 80,000.00 2,400.00
1.0000 Lbr Teakwood ukuran 90 x 220 cm 97,000.00 97,000.00
0.8000 o/h Pekerja 80,000.00 64,000.00
2.4000 o/h Tukang 110,000.00 264,000.00
0.2400 o/h Kepala tukang 120,000.00 28,800.00
0.0400 o/h Mandor 125,000.00 5,000.00
Jumlah 568,700.00

125 1 Unit PINTU RAK LEMARI DIBAWAH MEJA


0.2400 M2 Pintu Panil 612,250.00 146,940.00
4.0000 Bh Engsel 34,593.75 138,375.00
2.0000 Bh Grendel 29,393.75 58,787.50
1.0000 Bh Kunci Gembok 61,393.75 61,393.75
2.0000 Bh Tarikan 15,000.00 30,000.00
0.5400 M2 Cat Minyak 99,725.00 53,851.50
Jumlah 489,347.75

273/314 517211341.xlsx/ANALISA (2)


1 2 3 4

1 2 3 4.00

126 1 Set PASANG PINTU HARMONIKA


1.0000 Set Pintu Harmonika 8,500,000.00 8,500,000.00
0.5000 Dos Kawat Las 75,000.00 37,500.00
8.0000 Jam Mesin Las 25,000.00 200,000.00
2.0000 Psg Handle 250,000.00 500,000.00
1.0000 Bh Kunci 125,000.00 125,000.00
2.0000 Bh Gembok 75,000.00 150,000.00
0.0360 M3 Cor 1 : 3 : 5 sekitar Kusen 862,360.19 31,044.97
0.6000 M2 Acian sekitar Kusen 34,650.00 20,790.00
0.6000 M2 Plesteran sekitar Kusen 65,233.40 39,140.04
6.0000 o/h Pekerja 80,000.00 480,000.00
8.0000 o/h Tukang 110,000.00 880,000.00
0.8000 o/h Kepala tukang 120,000.00 96,000.00
0.2000 o/h Mandor 125,000.00 25,000.00
Jumlah 1,721,975.01
127 1 M2 PASANG TERALIS BESI STRIP 2 x 3 mm
6.1770 Kg Besi Strip 20,000.00 123,540.00
27.0280 Cm Pengelasan 4,071.50 110,044.50
1.6700 o/h Pekerja 80,000.00 133,600.00
1.6700 o/h Tukang 110,000.00 183,700.00
0.0167 o/h Kepala tukang 120,000.00 2,004.00
0.0830 o/h Mandor 125,000.00 10,375.00
Jumlah 563,263.50

128 1 Unit PINTU BESI pada RUANG PANEL


1.5000 Btg Besi Kotak 4 cm 135,000.00 202,500.00
1.2000 Btg Besi Kotak 2 cm 110,000.00 132,000.00
0.2750 Lbr Besi Plat 3 mm 800,000.00 220,000.00
1.1000 Btg Besi Beton Ø 12 mm 128,000.00 140,800.00
1.0000 Set Kunci + Gembok 100,000.00 100,000.00
368.0000 Cm Pengelasan 4,071.50 1,498,312.00
1.6700 o/h Pekerja 80,000.00 133,600.00
1.6700 o/h Tukang 110,000.00 183,700.00
0.0167 o/h Kepala tukang 120,000.00 2,004.00
0.0830 o/h Mandor 125,000.00 10,375.00
Jumlah 2,623,291.00

129 1 M3 MEMASANG KONSTRUKSI KUDA-KUDA KONVENSIONAL


(Bentangan lebih 6 m')
1.1000 m3 Balok kayu besi 5/10 3,250,000.00 3,575,000.00
15.0000 Kg Besi Strip tebal 5 mm 20,000.00 300,000.00
5.6000 Kg Paku campur 21,000.00 117,600.00
4.0000 o/h Pekerja 80,000.00 320,000.00
12.0000 o/h Tukang 110,000.00 1,320,000.00
1.2000 o/h Kepala Tukang 120,000.00 144,000.00
0.2000 o/h Mandor 125,000.00 25,000.00
Jumlah 5,801,600.00

130 1 M3 MEMASANG KONSTRUKSI KUDA-KUDA EXPOSE


1.2000 m3 Balok kayu besi 5/10 3,250,000.00 3,900,000.00
15.0000 Kg Besi Strip tebal 5 mm 20,000.00 300,000.00
5.6000 Kg Paku campur 21,000.00 117,600.00
6.7000 o/h Pekerja 80,000.00 536,000.00
20.1000 o/h Tukang 110,000.00 2,211,000.00

274/314 517211341.xlsx/ANALISA (2)


1 2 3 4
2.0100 o/h Kepala Tukang 120,000.00 241,200.00
0.3350 o/h Mandor 125,000.00 41,875.00
Jumlah 7,347,675.00

1 2 3 4

131 1 M3 MEMASANG KONSTRUKSI GORDING


1.1000 m3 Balok kayu besi 3,250,000.00 3,575,000.00
15.0000 Kg Besi Strip tebal 5 mm 20,000.00 300,000.00
3.0000 Kg Paku campur 21,000.00 63,000.00
2.4000 o/h Pekerja 80,000.00 192,000.00
7.2000 o/h Tukang 110,000.00 792,000.00
0.7200 o/h Kepala Tukang 120,000.00 86,400.00
0.1200 o/h Mandor 125,000.00 15,000.00
Jumlah 5,023,400.00
132 1 M3 MEMASANG KONSTRUKSI GORDING
1.1000 m3 Balok Kayu Matoa 2,180,000.00 2,398,000.00
15.0000 Kg Besi Strip tebal 5 mm 20,000.00 300,000.00
3.0000 Kg Paku campur 21,000.00 63,000.00
2.4000 o/h Pekerja 80,000.00 192,000.00
7.2000 o/h Tukang 110,000.00 792,000.00
0.7200 o/h Kepala Tukang 120,000.00 86,400.00
0.1200 o/h Mandor 125,000.00 15,000.00
Jumlah 3,846,400.00

135 1 M2 PASANG PELAPIS ALUMUNIUM FOIL


1.0500 M2 Alumunium Foil 15,000.00 15,750.00
0.1500 o/h Pekerja 80,000.00 12,000.00
0.0500 o/h Tukang 110,000.00 5,500.00
0.0050 o/h Kepala Tukang 120,000.00 600.00
0.0080 o/h Mandor 125,000.00 1,000.00
Jumlah 34,850.00

136 1 M2 PEKERJAAN GLASS WALL + KAWAT RAM


1.0500 M2 Glass Wall 25,000.00 26,250.00
1.0500 M2 Kawat Ram 17,000.00 17,850.00
0.1500 o/h Pekerja 80,000.00 12,000.00
0.0500 o/h Tukang 110,000.00 5,500.00
0.0050 o/h Kepala Tukang 120,000.00 600.00
0.0080 o/h Mandor 125,000.00 1,000.00
Jumlah 63,200.00

275/314 517211341.xlsx/ANALISA (2)


1 2 3 4
133 1 M2 PASANG ATAP ALUMUNIUM (SPANDEK/SUPER DEK)
1.3125 Lbr Atap Super Deck (type lebar 80 cm) 135,000.00 177,187.50
0.0200 Kg Paku Atap 27,500.00 550.00
0.1500 o/h Pekerja 80,000.00 12,000.00
0.7500 o/h Tukang 110,000.00 82,500.00
0.0080 o/h Kepala tukang 120,000.00 960.00
0.0060 o/h Mandor 125,000.00 750.00
Jumlah 273,947.50
371,997.50

1 1 M2 PEKERJAAN MULTIPLEKS 12 MM Pelapis Atap


0.3360 Lbr Tripleks 12 mm 240,000.00 80,640.00
0.0200 Kg Paku Tripleks 20,000.00 400.00
0.2000 Kg Paku Biasa 1/2" - 1" 18,000.00 3,600.00
10.0000 Bj Sekrup Baja 275.00 2,750.00
0.1250 Btg Vinil J Channel 115,000.00 14,375.00
0.1000 o/h Pekerja 80,000.00 8,000.00
0.0500 o/h Tukang 110,000.00 5,500.00
0.0050 o/h Kepala Tukang 120,000.00 600.00
0.0050 o/h Mandor 125,000.00 625.00
1.0000 Ls Alat Bantu 3,000.00 3,000.00
Jumlah 119,490.00

136 I M2 PASANG ATAP GENTENG shingles (Owens)


3.0500 Bdl Genteng Shingles Per Sguare 175,000.00 533,750.00
0.1500 H.o Pekerja 80,000.00 12,000.00
0.2000 H.o Tukuang Kayu 110,000.00 22,000.00
0.0200 H.o Kepala Tukang 120,000.00 2,400.00
0.0015 H.o Mandor 125,000.00 187.50
1.0000 Ls Alat Bantu 2,500.00 2,500.00
Jumlah 572,837.50

137 1 M2 PEMASANGAN WATERPROOFING MEMBRANE


2.9000 kg Membrane 51,625.00 149,712.50
0.3000 o/h Pekerja 80,000.00 24,000.00
0.2000 o/h Tukang Kayu 110,000.00 22,000.00
0.0200 o/h Kepala tukang 120,000.00 2,400.00
0.0150 o/h Mandor 125,000.00 1,875.00
1.0000 Ls Alat Bantu 1,000.00 1,000.00
Jumlah 200,987.50
893,315.00

138 1 M2 PASANG PAVING BLOCK


57.0000 Bh Paving Block - -
0.1000 M3 Pasir Pasang - -
0.3000 Oh Pekerja 110,000.00 33,000.00
0.2000 Oh Tukang Batu 120,000.00 24,000.00
0.0200 Oh Kepala Tukang 125,000.00 2,500.00
0.0020 Oh Mandor Jumlah #VALUE!
Jumlah #VALUE!

134 1 M' PASANG NOK ATAP ALUMUNIUM (SPANDEK/SUPER DEK


1.2000 M' Nok Atap 65,000.00 78,000.00
0.0400 Kg Paku Atap 27,500.00 1,100.00
0.1000 o/h Pekerja 80,000.00 8,000.00
1.0000 o/h Tukang 110,000.00 110,000.00
0.0100 o/h Kepala Tukang 120,000.00 1,200.00

276/314 517211341.xlsx/ANALISA (2)


1 2 3 4
0.0100 o/h Mandor 125,000.00 1,250.00
Jumlah 199,550.00

137 1 Kg RANGKA KUDA-KUDA BAJA IWF


1.1500 Kg Besi Baja IWF 20,500.00 23,575.00
0.0600 o/h Pekerja 80,000.00 4,800.00
0.0600 o/h Tukang besi 110,000.00 6,600.00
0.0060 o/h Kepala Tukang 120,000.00 720.00
0.0030 o/h Mandor 125,000.00 375.00
Jumlah 36,070.00

1 2 3 4

138 1 Kg PEKERJAAN GORDING CANAL


1.1500 Kg Gording Canal 20,000.00 23,000.00
0.0600 o/h Pekerja 80,000.00 4,800.00
0.0600 o/h Tukang 110,000.00 6,600.00
0.0060 o/h Kepala Tukang 120,000.00 720.00
0.0030 o/h Mandor 125,000.00 375.00
Jumlah 35,495.00
139 100 Kg PEKERJAAN PERAKITAN KUDA-KUDA BAJA
1.0000 Ltr Solar 7,000.00 7,000.00
0.1000 Ltr Minyak Pelumas 35,000.00 3,500.00
0.1000 o/h Pekerja 80,000.00 8,000.00
0.1000 o/h Tukang 110,000.00 11,000.00
0.0010 o/h Kepala Tukang 120,000.00 120.00
0.0050 o/h Mandor 125,000.00 625.00
0.8000 Jam Sewa Alat 6,250.00 5,000.00
Jumlah 35,245.00
Untuk 1 Kg 352.45

140 1 Kg PEKERJAAN KUDA-KUDA BAJA


1.0000 Kg Besi Baja (IWF/Siku) 36,070.00 36,070.00
1.0000 Kg Perakitan 352.45 352.45
Jumlah 36,422.45

141 I Unit UPAH SETTING KUDA-KUDA BAJA


3.9650 m3 Balok Kayu Matoa 2,180,000.00 8,643,700.00
9.9125 kg Paku Campur 21,000.00 208,162.50
24.0000 o/h Pekerja 80,000.00 1,920,000.00
4.0000 o/h Tukang Las 110,000.00 440,000.00
6.0000 o/h Tukang Kayu 110,000.00 660,000.00
2.0000 o/h Kepala Tukang 120,000.00 240,000.00
0.6000 Ls Mandor 125,000.00 75,000.00
Jumlah 12,186,862.50

142 1 M' PAPAN LISTPLANK KAYU BESI 3/30


0.0110 M3 Papan kayu besi 3,500,000.00 38,500.00
0.0500 Kg Paku Campur 21,000.00 1,050.00
0.1000 o/h Pekerja 80,000.00 8,000.00
0.2000 o/h Tukang 110,000.00 22,000.00
0.0200 o/h Kepala tukang 120,000.00 2,400.00
0.0050 o/h Mandor 125,000.00 625.00
Jumlah 72,575.00

277/314 517211341.xlsx/ANALISA (2)


1 2 3 4
143 1 M2 PASANG PAVING BLOCK
57.0000 Bh Paving Block 2,900.00 165,300.00
0.1000 M3 Pasir Pasang 235,000.00 23,500.00
0.3000 Oh Pekerja 80,000.00 24,000.00
0.2000 Oh Tukang Batu 110,000.00 22,000.00
0.0200 Oh Kepala Tukang 120,000.00 2,400.00
0.0020 Oh Mandor 125,000.00 250.00
Jumlah 237,450.00

144 10 CM PENGELASAN DENGAN LAS LISTRIK


0.4000 Dos Kawat Las Listrik 75,000.00 30,000.00
0.3000 Ltr Solar 6,000.00 1,800.00
0.0400 Ltr Minyak Pelumas 22,500.00 900.00
0.0400 o/h Pekerja 80,000.00 3,200.00
0.0200 o/h Tukang 110,000.00 2,200.00
0.0020 o/h Kepala tukang 120,000.00 240.00
0.0020 o/h Mandor 125,000.00 250.00
0.1700 Jam Sewa Alat 12,500.00 2,125.00
Jumlah 40,715.00
Untuk 1 cm 4,071.50

145 1 M' PEKERJAAN TRUNKING CABLE


4.0000 Kg Besi Siku 40.40.3 20,000.00 80,000.00
1.9000 Kg Besi Beton dia. 10 20,000.00 38,000.00
8.0000 Cm Pengelasan 4,071.50 32,572.00
0.5600 o/h Pekerja 80,000.00 44,800.00
0.5600 o/h Tukang 110,000.00 61,600.00
0.0560 o/h Kepala tukang 120,000.00 6,720.00
0.0083 o/h Mandor 125,000.00 1,037.50
Jumlah 264,729.50

146 1 M' PASANG RAILING TANGGA STAINLESS


0.3990 m' Pipa Stainless Ø 3 " 434,000.00 173,166.00
1.0000 m' Pipa Stainless Ø 2 ½ " 292,000.00 292,000.00
11.7500 m' Pipa Stainless Ø 1 " 100,000.00 1,175,000.00
0.1570 bh Ring Kaki Ø 3 " 20,000.00 3,140.00
10.0000 bh Ring Kaki Ø 1 " 12,000.00 120,000.00
0.1578 bh Bola Ø 4 " 360,000.00 56,808.00
0.3157 bh Cincin Ø 3 " 40,000.00 12,628.00
15.0000 bh Cincin Ø 1 " 12,000.00 180,000.00
10.0000 bh Dina Bolt 7,500.00 75,000.00
279.7500 cm Pengelasan 4,071.50 1,139,002.13
1.2000 o/h Pekerja 80,000.00 96,000.00
1.2000 o/h Tukang 110,000.00 132,000.00
0.1200 o/h Kepala tukang 120,000.00 14,400.00
0.0060 o/h Mandor 125,000.00 750.00
Jumlah 3,469,894.13

147 1 M' PASANG RAILING BALKON STAINLESS


1.1000 m' Pipa Stainless Ø 2 ½ " 292,000.00 321,200.00
0.5000 m' Pipa Stainless Ø 2 " 200,000.00 100,000.00
0.1570 bh Ring Kaki Ø 2 " 20,000.00 3,140.00
2.0000 bh Dina Bolt 7,500.00 15,000.00
39.5000 cm Pengelasan 4,071.50 160,824.25
1.2000 o/h Pekerja 80,000.00 96,000.00
1.2000 o/h Tukang 110,000.00 132,000.00

278/314 517211341.xlsx/ANALISA (2)


1 2 3 4
0.1200 o/h Kepala tukang 120,000.00 14,400.00
0.0060 o/h Mandor 125,000.00 750.00
Jumlah 843,314.25

148 1 M' PAGAR STAINLESS STEEL


2.4000 m' Pipa Stainless Ø 2 " 200,000.00 480,000.00
6.3000 m' Pipa Stainless Ø 1 ½ " 166,000.00 1,045,800.00
1.2000 m' Pipa Stainless Ø ½ " 133,000.00 159,600.00
171.3000 cm Pengelasan 4,071.50 697,447.95
1.6700 o/h Pekerja 80,000.00 133,600.00
1.6700 o/h Tukang 110,000.00 183,700.00
0.1670 o/h Kepala tukang 120,000.00 20,040.00
0.0830 o/h Mandor 125,000.00 10,375.00
Jumlah 2,730,562.95

279/314 517211341.xlsx/ANALISA (2)


1 2 3 4

149 1 Unit PINTU GERBANG STAINLESS STEEL (Panjang 4,25 m)


8.9250 m' Pipa Stainless Ø 2 " 200,000.00 1,785,000.00
26.7750 m' Pipa Stainless Ø 1 ½ " 166,000.00 4,444,650.00
5.1000 m' Pipa Stainless Ø ½ " 133,000.00 678,300.00
1.0000 lbr Plat Stainless (Double) 2,650,000.00 2,650,000.00
3.0000 bh Roda 100,000.00 300,000.00
928.0000 cm Pengelasan 4,071.50 3,778,352.00
7.0975 o/h Pekerja 80,000.00 567,800.00
7.0975 o/h Tukang 110,000.00 780,725.00
0.7097 o/h Kepala tukang 120,000.00 85,164.00
0.3527 o/h Mandor 125,000.00 44,087.50
Jumlah 15,114,078.50

150 1 M' SALURAN Type 1 (Tepi Pagar)


0.4095 m3 Galian Tanah 63,125.00 25,849.69
0.1023 m3 Urugan Tanah kembali 21,041.67 2,152.56
0.0300 m3 Pasir Urug 241,250.00 7,237.50
0.0900 m3 Pondasi Batu Kali 1,203,875.00 108,348.75
0.0400 m3 Cor Lantai Rabat 862,360.19 34,494.41
1.6000 m2 Plesteran 1 : 3 62,021.60 99,234.56
1.0000 m2 Acian 34,650.00 34,650.00
Jumlah 311,967.47

151 1 M' SALURAN Type 2 (dari Halaman ke Saluran type 1)


0.2500 m3 Galian Tanah 63,125.00 15,781.25
0.0625 m3 Urugan Tanah kembali 21,041.67 1,315.10
0.0250 m3 Pasir Urug 241,250.00 6,031.25
0.2250 m3 Cor Rabat Bertulang 1,985,308.31 446,694.37
0.8000 m2 Bekisting Dinding Cor 394,735.00 315,788.00
1.2000 m2 Plesteran 1 : 3 62,021.60 74,425.92
1.2000 m2 Plesteran Beton 65,233.40 78,280.08
48.9780 kg Besi Grill (Penutup saluran) 36,070.00 1,766,636.46
Jumlah 2,704,952.43
152 1 M' SALURAN DITEPI JALAN Type 3
0.9600 m3 Galian Tanah 63,125.00 60,600.00
0.2400 m3 Urugan Tanah kembali 21,041.67 5,050.00
0.1200 m3 Pasir Urug 241,250.00 28,950.00
0.2400 m3 Lapisan Batu Kosong 792,615.00 190,227.60
0.4800 m3 Pondasi Batu Gunung 1,203,875.00 577,860.00
0.1200 m3 Cor Lantai Rabat 862,360.19 103,483.22
3.0000 m2 Plesteran 1 : 3 62,021.60 186,064.80
3.0000 m2 Acian 34,650.00 103,950.00
Jumlah 1,256,185.62

153 1 M' PASANG KAWAT DURI pada PAGAR KELILING


1.2000 m' Besi Siku 50.50.5 50,000.00 60,000.00
7.7000 m' Kawat Duri 10,000.00 77,000.00
0.4000 m2 Cat Minyak pada Besi Siku 99,725.00 39,890.00
Jumlah 176,890.00

154 1 M' PROFIL BETON LIST PLANK


12.50000 Kg Semen PC 1,600.00 20,000.00
25.0000 Bh Paku beton 1,000.00 25,000.00
0.0010 M3 Pasir pasang 235,000.00 235.00
0.7500 o/h Pekerja 80,000.00 60,000.00
1.0000 o/h Tukang 110,000.00 110,000.00
0.5000 o/h Kepala tukang 120,000.00 60,000.00
0.1000 o/h Mandor 125,000.00 12,500.00

280/314 517211341.xlsx/ANALISA (2)


1 2 3 4
Jumlah 287,735.00

155 1 M' PEKERJAAN SALURAN KELILING BANGUNAN


0.1000 m3 Cor Rabat 1 Pc : 3 Psr : 5 Krl 862,360.19 86,236.02
2.2000 m2 Plesteran 1 Pc : 3 Psr 62,021.60 136,447.52
2.2000 m2 Acian 34,650.00 76,230.00
Jumlah 298,913.54

156 1 M' PEK. SALURAN PEMBUANGAN KE RIOL KOTA


0.2500 m3 Beton bertulang 7,565,639.07 1,891,409.77
1.7000 m2 Plesteran 1 Pc : 3 Psr 62,021.60 105,436.72
Jumlah 1,996,846.49

281/314 517211341.xlsx/ANALISA (2)


1 2 3 4
157 1 Unit PEKERJAAN SEPTICTANK & REMBESAN
21.3650 M3 Galian tanah 63,125.00 1,348,665.63
6.4095 M3 Urugan tanah kembali 21,041.67 134,866.56
0.3800 M3 Urugan Pasir 241,250.00 91,675.00
1.2190 M3 Pasangan Pondasi Batu Kali 1 : 4 1,203,875.00 1,467,523.63
2.2240 M3 Pasangan Tembok 1 pc : 4 psr 1,217,800.00 2,708,387.20
0.2180 M3 Cor rabat 1 pc : 3 psr : 5 krl 862,360.19 187,994.52
0.5500 M3 Sloof, Kolom, Ringbalk 6,461,561.47 3,553,858.81
0.4200 M3 Beton Plat Penutup 9,426,562.57 3,959,156.28
25.0000 M2 Plesteran 1 pc : 2 psr 62,021.60 1,550,540.00
0.4480 M3 Urugan Kerikil 325,250.00 145,712.00
0.5220 M3 Pekerjaan Ijuk 1,250,000.00 652,500.00
4.0000 M' Pipa PVC Ø 4 " 73,062.50 292,250.00
1.0000 Bh Pipa Udara Gip. Ø 2 " 209,525.00 209,525.00
Jumlah 16,302,654.62

158 1 M2 PEKERJAAN LAPISAN BATU PECAH 5/7


0.0600 M3 Batu Pecah 5/7 875,000.00 52,500.00
0.2000 o/h Pekerja 80,000.00 16,000.00
0.0190 o/h Mandor 125,000.00 2,375.00
0.0045 hari Mesin Gilas (Wales) 4,700,000.00 21,150.00
Jumlah 92,025.00

159 1 M3 PEKERJAAN LAPISAN SIRTU


1.2000 M3 Sirtu 175,000.00 210,000.00
0.3000 o/h Pekerja 80,000.00 24,000.00
0.0100 o/h Mandor 125,000.00 1,250.00
0.0045 hari Mesin Gilas (Wales) 4,700,000.00 21,150.00
Jumlah 256,400.00

1 2 3 4

1m2 51,280.00

160 100 M2 PEKERJAAN LAPISAN PENETRASI (LAPEN) tebal 6 cm


3.6000 M3 Batu Pecah 3/5 850,000.00 3,060,000.00
2.4000 M3 Batu Pecah 2/3 875,000.00 2,100,000.00
1.2000 M3 Batu Pecah 1/2 900,000.00 1,080,000.00
2.0000 M3 Pasir Pasang 235,000.00 470,000.00
120.0000 Kg Aspal 11,354.84 1,362,580.65
1.0000 M3 Kayu Bakar 450,000.00 450,000.00
7.5000 o/h Pekerja 80,000.00 600,000.00
0.3750 o/h Mandor 125,000.00 46,875.00
0.6600 hari Mesin Gilas (Wales) 4,700,000.00 3,102,000.00
Jumlah 12,271,455.65
Untuk 1 M2 122,714.56

161 1 UNIT GROUND RESERVOAR BAWAH WING KANAN BANGUNAN


14.0000 M3 Galian Tanah Pondasi / Bak 127,500.00 1,785,000.00
1.2000 M3 Urugan Tanah kembali 21,041.67 25,250.00
2.1200 M3 Pondasi Poer Plat 4,772,681.31 10,118,084.37
0.3600 M3 Sloof Beton Bertulang 15/20 6,461,561.47 2,326,162.13
0.2160 M3 Kolom Beton Bertulang 25/25 12,216,943.97 2,638,859.90
3.6800 M3 Plat Dinding & Lantai tebal 10 cm 7,225,115.00 26,588,423.20
0.8000 M3 Plat Penutup tebal 12 cm 9,480,302.18 7,584,241.74
0.2880 M3 Balok Beton 20/30 10,183,367.50 2,932,809.84
0.8000 M3 Lantai Cor 1 : 3 : 5 tebal 10 cm 862,360.19 689,888.15
8.0000 M2 Plester pada Plat Lantai 65,233.40 521,867.20

282/314 517211341.xlsx/ANALISA (2)


1 2 3 4
36.8000 M2 Plesteran Bak Air 62,021.60 2,282,394.88
32.0000 M2 Pasang Keramik 20/20 235,190.00 7,526,080.00
1.0000 Unit Tangga Besi turun ke Reservoar 500,000.00 500,000.00
1.0000 Unit Pintu Besi Bak Kontrol 50/50 + Acc 500,000.00 500,000.00
Jumlah 66,019,061.40
162 100 M2 LAPISAN ASPAL GORENG tebal 3 cm (LATASIR)
0.8000 M3 Abu Batu / Filter 1,000,000.00 800,000.00
2.4000 M3 Batu Pecah 2/3 875,000.00 2,100,000.00
1.2000 M3 Batu Pecah 1/2 900,000.00 1,080,000.00
2.0000 M3 Pasir Kasar 245,000.00 490,000.00
120.0000 Kg Aspal 11,354.84 1,362,580.65
1.0000 M3 Kayu Bakar 450,000.00 450,000.00
7.5000 o/h Pekerja 80,000.00 600,000.00
0.3750 o/h Mandor 125,000.00 46,875.00
0.6600 hari Mesin Gilas (Wales) 4,700,000.00 3,102,000.00
Jumlah 10,031,455.65
Untuk 1 M2 100,314.56
163 1 Unit KUDA-KUDA PIPA dia. 3 " (K. 5)
18.0000 M' Pipa Gip dia. 3 " 165,000.00 2,970,000.00
2.0000 Bh Besi Plat Dudukan Kuda-kuda 230,000.00 460,000.00
0.4000 Bh Besi Plat Penghubung Dudukan 330,000.00 132,000.00
8.0000 Bh Baut Anker Dudukan Kuda-kuda 18,000.00 144,000.00
1.0000 Dos Kawat Las 75,000.00 75,000.00
8.0000 Jam Sewa Mesin Las 15,000.00 120,000.00
3.0000 o/h Pekerja 80,000.00 240,000.00
4.0000 o/h Tukang 110,000.00 440,000.00
0.4000 o/h Kepala Tukang 120,000.00 48,000.00
0.1000 o/h Mandor 125,000.00 12,500.00
Jumlah 4,641,500.00

164 1 Unit KUDA-KUDA PIPA dia. 2 " (K. 4)


15.0000 M' Pipa Gip dia. 2 " 115,000.00 1,725,000.00
2.0000 Bh Besi Plat Dudukan Kuda-kuda 150,000.00 300,000.00
4.0000 Bh Baut Anker Dudukan Kuda-kuda 18,000.00 72,000.00
0.7500 Dos Kawat Las 75,000.00 56,250.00
6.0000 Jam Sewa Mesin Las 15,000.00 90,000.00
2.5000 o/h Pekerja 80,000.00 200,000.00
3.0000 o/h Tukang 110,000.00 330,000.00
0.3000 o/h Kepala Tukang 120,000.00 36,000.00
0.1000 o/h Mandor 125,000.00 12,500.00
Jumlah 2,821,750.00

165 1 M' GORDING PIPA MEDIUM dia. 1 ½ "


1.0500 M' Pipa Gip dia. 1 ½ " 83,000.00 87,150.00
0.2000 o/h Pekerja 80,000.00 16,000.00
0.2000 o/h Tukang 110,000.00 22,000.00
0.0200 o/h Kepala Tukang 120,000.00 2,400.00
0.0010 o/h Mandor 125,000.00 125.00
Jumlah 127,675.00
166 1 M2 PASANG ATAP POLYCARBONAT
1.1000 M' Atap Polycarbonat 375,000.00 412,500.00
0.2500 Tbg Silent 45,000.00 11,250.00
12.0000 Bh Sekrup 300.00 3,600.00
0.1500 o/h Pekerja 80,000.00 12,000.00
0.2000 o/h Tukang 110,000.00 22,000.00
0.0250 o/h Kepala tukang 120,000.00 3,000.00
0.0050 o/h Mandor 125,000.00 625.00
Jumlah 464,975.00

283/314 517211341.xlsx/ANALISA (2)


1 2 3 4

1 2 3 4

167 1 M' PEKERJAAN PIPA GIP Ø ½ "


1.2000 M' Pipa Gip Ø ½ " 33,000.00 39,600.00
% Perlengkapan (35 % Harga Pipa) 11,550.00 11,550.00
0.0540 o/h Pekerja 80,000.00 4,320.00
0.0900 o/h Tukang 110,000.00 9,900.00
0.0090 o/h Kepala Tukang 120,000.00 1,080.00
0.0270 o/h Mandor 125,000.00 3,375.00
Jumlah 69,825.00
168 1 M' PEKERJAAN PIPA GIP Ø ¾ "
1.2000 M' Pipa Gip Ø ¾ " 46,000.00 55,200.00
% Perlengkapan (35 % Harga Pipa) 16,100.00 16,100.00
0.0540 o/h Pekerja 80,000.00 4,320.00
0.0900 o/h Tukang 110,000.00 9,900.00
0.0090 o/h Kepala Tukang 120,000.00 1,080.00
0.0270 o/h Mandor 125,000.00 3,375.00
Jumlah 89,975.00

169 1 M' PEKERJAAN PIPA GIP Ø 1 "


1.2000 M' Pipa Gip Ø 1 " 48,000.00 57,600.00
% Perlengkapan (35 % Harga Pipa) 16,800.00 16,800.00
0.0540 o/h Pekerja 80,000.00 4,320.00
0.0900 o/h Tukang 110,000.00 9,900.00
0.0090 o/h Kepala Tukang 120,000.00 1,080.00
0.0270 o/h Mandor 125,000.00 3,375.00
Jumlah 93,075.00
170 1 M' PEKERJAAN PIPA GIP Ø 1 ¼ "
1.2000 M' Pipa Gip Ø 1 ¼ " 63,000.00 75,600.00
% Perlengkapan (35 % Harga Pipa) 22,050.00 22,050.00
0.1080 o/h Pekerja 80,000.00 8,640.00
0.1800 o/h Tukang 110,000.00 19,800.00
0.0180 o/h Kepala Tukang 120,000.00 2,160.00
0.0054 o/h Mandor 125,000.00 675.00
Jumlah 128,925.00
171 1 M' PEKERJAAN PIPA GIP Ø 1 ½ "
1.2000 M' Pipa Gip Ø 1 ½ " 83,000.00 99,600.00
% Perlengkapan (35 % Harga Pipa) 29,050.00 29,050.00
0.1080 o/h Pekerja 80,000.00 8,640.00
0.1800 o/h Tukang 110,000.00 19,800.00
0.0180 o/h Kepala Tukang 120,000.00 2,160.00
0.0054 o/h Mandor 125,000.00 675.00
Jumlah 159,925.00

284/314 517211341.xlsx/ANALISA (2)


1 2 3 4
172 1 M' PEKERJAAN PIPA GIP Ø 2 "
1.2000 M' Pipa Gip Ø 2 " 115,000.00 138,000.00
% Perlengkapan (35 % Harga Pipa) 40,250.00 40,250.00
0.1080 o/h Pekerja 80,000.00 8,640.00
0.1800 o/h Tukang 110,000.00 19,800.00
0.0180 o/h Kepala Tukang 120,000.00 2,160.00
0.0054 o/h Mandor 125,000.00 675.00
Jumlah 209,525.00
173 1 M' PEKERJAAN PIPA GIP Ø 3 "
1.2000 M' Pipa Gip Ø 3 " 165,000.00 198,000.00
% Perlengkapan (35 % Harga Pipa) 57,750.00 57,750.00
0.1080 o/h Pekerja 80,000.00 8,640.00
0.1800 o/h Tukang 110,000.00 19,800.00
0.0180 o/h Kepala Tukang 120,000.00 2,160.00
0.0054 o/h Mandor 125,000.00 675.00
Jumlah 287,025.00

174 1 M' PEKERJAAN PIPA GIP Ø 4 "


1.2000 M' Pipa Gip Ø 4 " 190,000.00 228,000.00
% Perlengkapan (35 % Harga Pipa) 66,500.00 66,500.00
0.1350 o/h Pekerja 80,000.00 10,800.00
0.2250 o/h Tukang 110,000.00 24,750.00
0.0225 o/h Kepala Tukang 120,000.00 2,700.00
0.0068 o/h Mandor 125,000.00 850.00
Jumlah 333,600.00
175 1 M' PEKERJAAN PIPA PVC Ø 6 "
1.2000 M' Pipa PVC Ø 6 " 135,000.00 162,000.00
% Perlengkapan (35 % Harga Pipa) 47,250.00 47,250.00
0.0810 o/h Pekerja 80,000.00 6,480.00
0.1350 o/h Tukang 110,000.00 14,850.00
0.0135 o/h Kepala Tukang 120,000.00 1,620.00
0.0041 o/h Mandor 125,000.00 512.50
Jumlah 232,712.50
176 1 M' PEKERJAAN PIPA PVC Ø 4 "
1.2000 M' Pipa PVC Ø 4 " 32,000.00 38,400.00
% Perlengkapan (35 % Harga Pipa) 11,200.00 11,200.00
0.0810 o/h Pekerja 80,000.00 6,480.00
0.1350 o/h Tukang 110,000.00 14,850.00
0.0135 o/h Kepala Tukang 120,000.00 1,620.00
0.0041 o/h Mandor 125,000.00 512.50
Jumlah 73,062.50

177 1 M' PEKERJAAN PIPA PVC Ø 3 "


1.2000 M' Pipa PVC Ø 3 " 18,500.00 22,200.00
% Perlengkapan (35 % Harga Pipa) 6,475.00 6,475.00
0.0810 o/h Pekerja 80,000.00 6,480.00
0.1350 o/h Tukang 110,000.00 14,850.00
0.0135 o/h Kepala Tukang 120,000.00 1,620.00
0.0041 o/h Mandor 125,000.00 512.50
Jumlah 52,137.50

178 1 M' PEKERJAAN PIPA PVC Ø 2 "


1.2000 M' Pipa PVC Ø 2 " 19,500.00 23,400.00
% Perlengkapan (35 % Harga Pipa) 6,825.00 6,825.00
0.0540 o/h Pekerja 80,000.00 4,320.00
0.0900 o/h Tukang 110,000.00 9,900.00
0.0090 o/h Kepala Tukang 120,000.00 1,080.00
0.0027 o/h Mandor 125,000.00 337.50
Jumlah 45,862.50

179 1 M' PEKERJAAN PIPA PVC Ø 1 ½ "


1.2000 M' Pipa PVC Ø 1 ½ " 18,500.00 22,200.00
% Perlengkapan (35 % Harga Pipa) 6,475.00 6,475.00
0.0360 o/h Pekerja 80,000.00 2,880.00

285/314 517211341.xlsx/ANALISA (2)


1 2 3 4
0.0660 o/h Tukang 110,000.00 7,260.00
0.0060 o/h Kepala Tukang 120,000.00 720.00
0.0018 o/h Mandor 125,000.00 225.00
Jumlah 39,760.00
180 1 M' PEKERJAAN PIPA PVC Ø 1 "
1.2000 M' Pipa PVC Ø 1 " 11,000.00 13,200.00
% Perlengkapan (35 % Harga Pipa) 3,850.00 3,850.00
0.0360 o/h Pekerja 80,000.00 2,880.00
0.0600 o/h Tukang 110,000.00 6,600.00
0.0060 o/h Kepala Tukang 120,000.00 720.00
0.0018 o/h Mandor 125,000.00 225.00
Jumlah 27,475.00
181 1 Set POMPA AIR MANCUR + INSTALASI
84.2000 m' Pipa PVC (AW) dia. 2 " 45,862.50 3,861,622.50
15.0000 m' Pipa Gip dia. ¾ " 89,975.00 1,349,625.00
3.0000 bh Nozzle Air Mancur (keatas) 1,500,000.00 4,500,000.00
6.0000 bh Nozzle Air Mancur (ke kolam) 1,250,000.00 7,500,000.00
2.0000 unit Pompa (Pressure Pump) 41,550,000.00 83,100,000.00
110.2000 Jumlah 100,311,247.50
253.a 1 UNIT PEMBUATAN KOLAM AIR MANCUR
1 98.1944 M3 Galian Tanah 63,125.00 6,198,522.37
2 14.2523 M3 Urugan Pasir 241,250.00 3,438,370.82
3 1.2724 M3 Sloof Beton Bertulang 15/20 6,461,561.47 8,221,853.45
4 58.0521 M3 Pas Batu Kali 1,203,875.00 69,887,531.14
5 52.7564 M3 Lantai Cor 1 : 3 : 5 tebal 7 cm 2,737,161.57 144,402,724.01
6 33.9313 M2 Plester 1;2 65,233.40 2,213,456.54
7 111.9906 m2 Keramik Lantai 20/20 235,190.00 26,339,057.96
8 45.0447 M2 Pasang dinding 20/25 267,705.00 12,058,693.53
9 48.8406 m Kanstin beton 243,353.30 11,885,511.90
Jumlah 284,645,721.71
total 384,956,969.21

181 All IN PEK. INSTALASI PIPA AIR BERSIH Lantai 1 (Total 210 m)
18.00 m Pipa GIP medium Ø1¼" 128,925.00 2,320,650.00
12.00 m Pipa GIP medium Ø2" 209,525.00 2,514,300.00
25.00 m Pipa GIP medium Ø1" 93,075.00 2,326,875.00
35.00 m Pipa GIP medium ؾ" 89,975.00 3,149,125.00
120.00 m Pipa GIP medium ؽ" 69,825.00 8,379,000.00
12.00 bh Knie GIP Ø1½" 11,000.00 132,000.00
15.00 bh Knie GIP Ø1" 8,500.00 127,500.00
90.00 bh Knie GIP ؽ" 5,000.00 450,000.00
2.00 bh Testik GIP Ø2" 15,000.00 30,000.00
5.00 bh Testik GIP Ø1½" 13,000.00 65,000.00
7.00 bh Testik GIP Ø1½" x ¾" 13,000.00 91,000.00
10.00 bh Testik GIP Ø1" x ½" 8,000.00 80,000.00
35.00 bh Testik GIP ؽ" 5,000.00 175,000.00
7.00 bh Sock GIP Ø1½" 12,000.00 84,000.00
10.00 bh Sock GIP Ø1" 7,000.00 70,000.00
20.00 bh Sock GIP ؽ" 5,000.00 100,000.00
5.00 bh Double Nepple Ø1½" 12,000.00 60,000.00
7.00 bh Double Nepple Ø1" 7,500.00 52,500.00
50.00 bh Double Nepple ؽ" 4,000.00 200,000.00
3.00 bh Over sock GIP Ø1½" x 1" 12,000.00 36,000.00
5.00 bh Over sock GIP Ø1" x ½" 10,000.00 50,000.00
2.00 bh Over sock GIP Ø2" x 1½" 17,500.00 35,000.00
4.00 bh Water Mor Ø2" 45,000.00 180,000.00
4.00 bh Water Mor Ø1½" 32,000.00 128,000.00
5.00 bh Water Mor Ø1" 20,000.00 100,000.00
25.00 bh Water Mor ؽ" 12,000.00 300,000.00
2.00 bh Boult Valve Ø1½" 350,000.00 700,000.00
1.00 bh Boult Valve Ø2" 450,000.00 450,000.00
Jumlah 22,385,950.00
182 All IN PEK. INSTALASI PIPA AIR BERSIH Lantai 2

286/314 517211341.xlsx/ANALISA (2)


1 2 3 4
45.00 m Pipa GIP mediumØ 1 ¼ " 128,925.00 5,801,625.00
75.00 m Pipa GIP mediumØ 1 " 93,075.00 6,980,625.00
315.00 m Pipa GIP mediumØ ½ " 69,825.00 21,994,875.00
10.00 bh Knie GIP Ø1¼" 11,000.00 110,000.00
17.00 bh Knie GIP Ø1" 8,500.00 144,500.00
200.00 bh Knie GIP ؽ" 5,000.00 1,000,000.00
7.00 bh Testik GIP Ø1¼" x 1" 13,000.00 91,000.00
12.00 bh Testik GIP Ø1" x ½" 8,000.00 96,000.00
30.00 bh Testik GIP ؽ" 5,000.00 150,000.00
10.00 bh Sock GIP Ø1¼" 12,000.00 120,000.00
20.00 bh Sock GIP Ø1" 7,000.00 140,000.00
40.00 bh Sock GIP ؽ" 5,000.00 200,000.00
10.00 bh Double Nepple Ø 1 ¼ " 12,000.00 120,000.00
15.00 bh Double Nepple Ø 1 " 7,500.00 112,500.00
30.00 bh Double Nepple Ø ½ " 4,000.00 120,000.00
3.00 bh Over sock GIP Ø 1 ½ " x 1" 12,000.00 36,000.00
2.00 bh Over sock GIP Ø 1 " x ½" 10,000.00 20,000.00
4.00 bh Water Mor Ø1¼" 32,000.00 128,000.00
6.00 bh Water Mor Ø1" 20,000.00 120,000.00
30.00 bh Water Mor ؽ" 12,000.00 360,000.00
2.00 bh Boult Valve Ø1¼" 350,000.00 700,000.00
70.00 dos Seal tape 17,000.00 1,190,000.00
Jumlah 39,735,125.00

183 All IN PEK. INSTALASI PIPA AIR BERSIH Lantai 3


25.00 m Pipa GIP mediumØ 3 " 287,025.00 7,175,625.00
6.00 m Pipa GIP mediumØ 1 ¼ " 128,925.00 773,550.00
12.00 m Pipa GIP mediumØ 1 " 93,075.00 1,116,900.00
70.00 m Pipa GIP mediumØ ½ " 69,825.00 4,887,750.00
6.00 bh Knie GIP Ø1¼" x ½" 11,000.00 66,000.00
10.00 bh Knie GIP Ø1" 8,500.00 85,000.00
35.00 bh Knie GIP ؽ" 5,000.00 175,000.00
2.00 bh Testik GIP Ø2" 13,000.00 26,000.00
10.00 bh Testik GIP Ø1" x ½" 8,000.00 80,000.00
15.00 bh Testik GIP ؽ" 5,000.00 75,000.00
2.00 bh Sock GIP Ø1¼" 12,000.00 24,000.00
3.00 bh Sock GIP Ø1" 7,000.00 21,000.00
15.00 bh Sock GIP ؽ" 5,000.00 75,000.00
5.00 bh Double Nepple Ø 1 ¼ " 12,000.00 60,000.00
7.00 bh Double Nepple Ø 1 " 7,500.00 52,500.00
12.00 bh Double Nepple Ø ½ " 4,000.00 48,000.00
3.00 bh Over sock GIP Ø 1 ¼ " x 1" 12,000.00 36,000.00
4.00 bh Over sock GIP Ø 1 " x ½" 10,000.00 40,000.00
2.00 bh Water Mor Ø2" 32,000.00 64,000.00
4.00 bh Water Mor Ø1" 20,000.00 80,000.00
15.00 bh Water Mor ؽ" 12,000.00 180,000.00
2.00 bh Boult Valve Ø3" 1,750,000.00 3,500,000.00
1.00 bh Boult Valve Ø1¼" 350,000.00 350,000.00
50.00 dos Seal tape 17,000.00 850,000.00
19,841,325.00

184 All IN PEK. INSTALASI PIPA AIR KOTOR Lantai 1


80.00 m Pipa PVC AW Ø4" 73,062.50 5,845,000.00
70.00 m Pipa PVC AW Ø3" 52,137.50 3,649,625.00
30.00 m Pipa PVC AW Ø2" 45,862.50 1,375,875.00
12.00 m Pipa PVC AW Ø1½" 39,760.00 477,120.00
12.00 m Pipa PVC AW Ø1" 27,475.00 329,700.00
35.00 bh Knie PVC Ø4" 30,000.00 1,050,000.00
20.00 bh Knie PVC Ø2" 15,000.00 300,000.00
10.00 bh Knie PVC Ø1½" 10,000.00 100,000.00
40.00 bh Knie PVC Ø1" 7,000.00 280,000.00
10.00 bh Testik PVC Ø4" x 2" 30,000.00 300,000.00
8.00 bh Ty 90 º Ø4" 75,000.00 600,000.00

287/314 517211341.xlsx/ANALISA (2)


1 2 3 4
12.00 bh Ty 90 º Ø2" 30,000.00 360,000.00
8.00 bh Ty 90 º Ø4" x 2" 90,000.00 720,000.00
5.00 bh Over sock PVC Ø 4 " x 2 " 30,000.00 150,000.00
5.00 bh Over sock PVC Ø 2 " x 1 ½ " 20,000.00 100,000.00
6.00 bh Over sock PVC Ø 2 " x 1 " 15,000.00 90,000.00
15.00 bh Knie PVC 45 º Ø 4 " 35,000.00 525,000.00
20.00 bh Knie PVC 45 º Ø 2 " 10,000.00 200,000.00
30.00 bh Knie PVC type D Ø 3 " 30,000.00 900,000.00
10.00 bh Testik PVC type DØ 3 " 12,000.00 120,000.00
3.00 klg Lem Pipa PVC merk Wavin 500 Gram 40,000.00 120,000.00
Jumlah 17,592,320.00

1 2 3 4

185 All IN PEK. INSTALASI PIPA AIR KOTOR Lantai 2


350.00 m Pipa PVC AW Ø4" 73,062.50 25,571,875.00
100.00 m Ø3" 52,137.50 5,213,750.00
120.00 m Ø2" 45,862.50 5,503,500.00
80.00 m Ø1½" 39,760.00 3,180,800.00
25.00 m Ø1" 27,475.00 686,875.00
50.00 bh Knie PVC Ø3" 30,000.00 1,500,000.00
75.00 bh Ø2" 15,000.00 1,125,000.00
25.00 bh Ø1½" 10,000.00 250,000.00
30.00 bh Ø1" 7,000.00 210,000.00
37.00 bh Testik PVC Ø4" x 2" 30,000.00 1,110,000.00
15.00 bh Ø4" 22,000.00 330,000.00
15.00 bh Ø3" x 2" 10,000.00 150,000.00
20.00 bh Ø1½" 6,500.00 130,000.00
12.00 bh Ty 90 º Ø4" 75,000.00 900,000.00
20.00 bh Ø2" 30,000.00 600,000.00
25.00 bh Ø3" x 2" 90,000.00 2,250,000.00
10.00 bh Over sock PVC Ø 3 " x 2 " 30,000.00 300,000.00
15.00 bh Ø2" x 1½" 20,000.00 300,000.00
10.00 bh Ø2" x 1" 15,000.00 150,000.00
15.00 bh Knie PVC 45 º Ø 4 " 35,000.00 525,000.00
25.00 bh Ø2" 10,000.00 250,000.00
30.00 bh Shock Drat DalamØ 2 " 22,000.00 660,000.00
45.00 bh Knie PVC type D Ø 3 " 30,000.00 1,350,000.00
25.00 bh Testik PVC type DØ 3 " 12,000.00 300,000.00
10.00 klg Lem Pipa PVC merk Wavin 500 Gram 40,000.00 400,000.00
Jumlah (b) 52,946,800.00

186 All IN PEK. INSTALASI PIPA AIR KOTOR Lantai 3


30.00 m Pipa PVC AW Ø4" 73,062.50 2,191,875.00
15.00 m Type D Ø3" 52,137.50 782,062.50
25.00 m Type D Ø2" 45,862.50 1,146,562.50
8.00 m Type D Ø1½" 39,760.00 318,080.00
4.00 m Type D Ø1" 27,475.00 109,900.00
20.00 bh Knie PVC Ø3" 30,000.00 600,000.00
20.00 bh Knie PVC Ø2" 15,000.00 300,000.00
10.00 bh Knie PVC Ø1½" 10,000.00 100,000.00
5.00 bh Knie PVC Ø1" 7,000.00 35,000.00
2.00 bh Testik PVC Ø4" x 2" 30,000.00 60,000.00
3.00 bh Ty 90 º Ø4" 75,000.00 225,000.00
4.00 bh Ty 90 º Ø3" x 2" 30,000.00 120,000.00
3.00 bh Ty 90 º Ø1½" 90,000.00 270,000.00
2.00 bh Over sock PVC Ø 4 " 30,000.00 60,000.00
4.00 bh Over sock PVC Ø 2 " 20,000.00 80,000.00
2.00 bh Over sock PVC Ø 3 " x 2 " 15,000.00 30,000.00

288/314 517211341.xlsx/ANALISA (2)


1 2 3 4
4.00 bh Knie PVC 45 º Ø 3 " x 2 " 35,000.00 140,000.00
6.00 bh Knie PVC 45 º Ø 2 " x 1 ½ " 25,000.00 150,000.00
6.00 bh Knie PVC 45 º Ø 2 " x 1 " 10,000.00 60,000.00
5.00 bh Shock Drat DalamØ 4 " 22,000.00 110,000.00
6.00 bh Knie PVC type D Ø 2 " 30,000.00 180,000.00
2.00 bh Testik PVC type DØ 2 " 12,000.00 24,000.00
Jumlah (b) 7,092,480.00

187 1 Set KUNCI TANAM


1.0000 Bh Kunci Tanam 245,000.00 245,000.00
0.0600 o/h Pekerja 80,000.00 4,800.00
0.6000 o/h Tukang 110,000.00 66,000.00
0.0600 o/h Kepala Tukang 120,000.00 7,200.00
0.0030 o/h Mandor 125,000.00 375.00
Jumlah 323,375.00

188 1 Set KUNCI TANAM RUANGAN


1.0000 Bh Kunci Pintu Ruangan 200,000.00 200,000.00
0.0100 o/h Pekerja 80,000.00 800.00
0.5000 o/h Tukang 110,000.00 55,000.00
0.0100 o/h Kepala Tukang 120,000.00 1,200.00
0.0050 o/h Mandor 125,000.00 625.00
Jumlah 257,625.00

189 1 Bh PASANG KUNCI CYLINDER


1.0000 Bh Kunci Cylinder 148,000.00 148,000.00
0.0050 o/h Pekerja 80,000.00 400.00
0.5000 o/h Tukang Kayu 110,000.00 55,000.00
0.0050 o/h Kepala tukang 120,000.00 600.00
0.00025 o/h Mandor 125,000.00 31.25
Jumlah 204,031.25
190 1 Bh HAK ANGIN
1.0000 Bh Hak Angin 28,000.00 28,000.00
0.0150 o/h Pekerja 80,000.00 1,200.00
0.1500 o/h Tukang 110,000.00 16,500.00
0.0150 o/h Kepala Tukang 120,000.00 1,800.00
0.00075 o/h Mandor 125,000.00 93.75
Jumlah 47,593.75

191 1 Bh ENGSEL PINTU


1.0000 Bh Engsel Pintu 60,000.00 60,000.00
0.0150 o/h Pekerja 80,000.00 1,200.00
0.1500 o/h Tukang 110,000.00 16,500.00
0.0150 o/h Kepala Tukang 120,000.00 1,800.00
0.00075 o/h Mandor 125,000.00 93.75
Jumlah 79,593.75

192 1 Bh ENGSEL PINTU


1.0000 Bh Engsel Pintu 15,000.00 15,000.00
0.0150 o/h Pekerja 80,000.00 1,200.00
0.1500 o/h Tukang 110,000.00 16,500.00
0.0150 o/h Kepala Tukang 120,000.00 1,800.00
0.00075 o/h Mandor 125,000.00 93.75
Jumlah 34,593.75

193 1 Psg GRENDEL + GEMBOK PINTU


1.0000 Bh Grendel 9,800.00 9,800.00
1.0000 Bh Gembok 32,000.00 32,000.00
0.0150 Oh Pakerja 80,000.00 1,200.00
0.1500 Oh Tukang Kayu 110,000.00 16,500.00
0.0150 Oh Kepala Tukang Kayu 120,000.00 1,800.00

289/314 517211341.xlsx/ANALISA (2)


1 2 3 4
0.00075 Oh Mandor 125,000.00 93.75
Jumlah 61,393.75

194 1 Bh ENGSEL JENDELA


1.0000 Bh Engsel Jendela 40,000.00 40,000.00
0.0100 o/h Pekerja 80,000.00 800.00
0.1000 o/h Tukang 110,000.00 11,000.00
0.0100 o/h Kepala Tukang 120,000.00 1,200.00
0.0005 o/h Mandor 125,000.00 62.50
Jumlah 53,062.50

195 1 Bh GRENDEL JENDELA


1.0000 Bh Grendel Jendela 9,800.00 9,800.00
0.0150 Oh Pakerja 80,000.00 1,200.00
0.1500 Oh Tukang Kayu 110,000.00 16,500.00
0.0150 Oh Kepala Tukang Kayu 120,000.00 1,800.00
0.00075 Oh Mandor 125,000.00 93.75
Jumlah 29,393.75

196 1 Psg PASANG GRENDEL PINTU DOUBLE


1.0000 Psg Grendel Pintu Double 120,000.00 120,000.00
0.0100 o/h Pekerja 80,000.00 800.00
0.5000 o/h Tukang Kayu 110,000.00 55,000.00
0.1000 o/h Kepala tukang 120,000.00 12,000.00
0.0050 o/h Mandor 125,000.00 625.00
Jumlah 188,425.00

197 1 Psg PASANG HANDLE PINTU DOUBLE


1.0000 Psg Handle Pintu Double 275,000.00 275,000.00
0.0150 o/h Pekerja 80,000.00 1,200.00
0.1500 o/h Tukang Kayu 110,000.00 16,500.00
0.0150 o/h Kepala tukang 120,000.00 1,800.00
0.00075 o/h Mandor 125,000.00 93.75
Jumlah 294,593.75

290/314 517211341.xlsx/ANALISA (2)


1 2 3 4
198 1 Bh PASANG DOOR CLOSER
1.0000 Bh Door Closer 540,000.00 540,000.00
0.0500 o/h Pekerja 80,000.00 4,000.00
0.5000 o/h Tukang Kayu 110,000.00 55,000.00
0.0500 o/h Kepala tukang 120,000.00 6,000.00
0.00250 o/h Mandor 125,000.00 312.50
Jumlah 605,312.50
199 1 Bh PASANG DOOR STOP
1.0000 Bh Door Stop 82,000.00 82,000.00
0.0100 o/h Pekerja 80,000.00 800.00
0.1000 o/h Tukang Kayu 110,000.00 11,000.00
0.0100 o/h Kepala tukang 120,000.00 1,200.00
0.0005 o/h Mandor 125,000.00 62.50
Jumlah 95,062.50

200 1 Bh PASANG CLOSED DUDUK


1.0000 Bh Closed Duduk 2,325,000.00 2,325,000.00
% Perlengkapan (6 % Harga Closed) 139,500.00 139,500.00
3.3000 o/h Pekerja 80,000.00 264,000.00
1.1000 o/h Tukang 110,000.00 121,000.00
0.0010 o/h Kepala Tukang 120,000.00 120.00
0.1600 o/h Mandor 125,000.00 20,000.00
Jumlah 2,869,620.00

201 1 Bh KLOSET JONGKOK


1.0000 Bh Kloset Jongkok 55,000.00 55,000.00
7.0000 Bh Batu Tela 2,400.00 16,800.00
6.0000 Kg Semen 1,600.00 9,600.00
0.0100 M3 Pasir Pasang 235,000.00 2,350.00
1.0000 o/h Pekerja 80,000.00 80,000.00
1.5000 o/h Tukang 110,000.00 165,000.00
0.3000 o/h Kepala Tukang 120,000.00 36,000.00
0.1100 o/h Mandor 125,000.00 13,750.00
Jumlah 378,500.00

1 2 3 4

202 1 Bh PASANG BATH TUB


1.0000 Bh Bath Tub 5,200,000.00 5,200,000.00
% Perlengkapan (20 % Harga Bak Tub) 1,040,000.00 1,040,000.00
- o/h Pekerja 80,000.00 -
0.0750 o/h Tukang 110,000.00 8,250.00
0.7500 o/h Kepala Tukang 120,000.00 90,000.00
0.2500 o/h Mandor 125,000.00 31,250.00
Jumlah 6,369,500.00
203 1 Bh PASANG WASHTAFEL MEJA
1.0000 Bh Washatfel Meja 2,300,000.00 2,300,000.00
% Perlengkapan (12 % Harga Washtafel 276,000.00 276,000.00
6.0000 Kg Semen 1,600.00 9,600.00
0.0100 M3 Pasir Pasang 235,000.00 2,350.00
1.2000 o/h Pekerja 80,000.00 96,000.00
1.4500 o/h Tukang 110,000.00 159,500.00
0.1500 o/h Kepala Tukang 120,000.00 18,000.00
0.1000 o/h Mandor 125,000.00 12,500.00
Jumlah 2,873,950.00

204 1 Bh PASANG WASHTAFEL GANTUNG


1.0000 Bh Washatfel Gantung 2,675,000.00 2,675,000.00
% Perlengkapan (12 % Harga Washtafel 321,000.00 321,000.00

291/314 517211341.xlsx/ANALISA (2)


1 2 3 4
6.0000 Kg Semen 1,600.00 9,600.00
0.0100 M3 Pasir Pasang 235,000.00 2,350.00
1.2000 o/h Pekerja 80,000.00 96,000.00
1.4500 o/h Tukang 110,000.00 159,500.00
0.1500 o/h Kepala Tukang 120,000.00 18,000.00
0.1000 o/h Mandor 125,000.00 12,500.00
Jumlah 3,293,950.00
205 1 Set PASANG WATER HEATER
1.0000 Set Water Heater 3,550,000.00 3,550,000.00
% Perlengkapan (6 % Harga Heater) 213,000.00 213,000.00
- o/h Pekerja 80,000.00 -
0.0750 o/h Tukang 110,000.00 8,250.00
0.7500 o/h Kepala Tukang 120,000.00 90,000.00
0.2500 o/h Mandor 125,000.00 31,250.00
Jumlah 3,892,500.00
206 1 Unit PASANG TANGKI FIBER GLASS cap 1.5 M3
1.0000 Unit Fiber Glass 4,335,450.00 4,335,450.00
% Perlengkapan (12 % Harga Heater) 520,254.00 520,254.00
1.8000 o/h Pekerja 80,000.00 144,000.00
2.7000 o/h Tukang 110,000.00 297,000.00
0.5400 o/h Kepala Tukang 120,000.00 64,800.00
0.1100 o/h Mandor 125,000.00 13,750.00
Jumlah 5,375,254.00

207 1 Bh PASANG FLOOR DRAIN


1.0000 Bh Floor Drain 300,000.00 300,000.00
% Perlengkapan (12 % Harga F.Drain) 36,000.00 36,000.00
1.6500 o/h Pekerja 80,000.00 132,000.00
0.5500 o/h Tukang 110,000.00 60,500.00
0.0055 o/h Kepala Tukang 120,000.00 660.00
0.0800 o/h Mandor 125,000.00 10,000.00
Jumlah 539,160.00
208 1 Bh PASANG URINOIR
1.0000 Bh Urinoir 2,400,000.00 2,400,000.00
% Perlengkapan (30 % Harga Urinoir) 720,000.00 720,000.00
6.0000 Kg Semen 1,600.00 9,600.00
0.0100 M3 Pasir Pasang 235,000.00 2,350.00
1.0000 o/h Pekerja 80,000.00 80,000.00
1.0000 o/h Tukang 110,000.00 110,000.00
0.1000 o/h Kepala Tukang 120,000.00 12,000.00
0.1000 o/h Mandor 125,000.00 12,500.00
Jumlah 3,346,450.00

1 2 3 4

209 1 Unit PASANG POMPA HISAP


1.0000 Set Pompa Hisap 7,750,000.00 7,750,000.00
% Perlengkapan (6 % Harga Pompa) 465,000.00 465,000.00
1.8000 o/h Pekerja 80,000.00 144,000.00
2.7000 o/h Tukang 110,000.00 297,000.00
0.5400 o/h Kepala Tukang 120,000.00 64,800.00
0.1100 o/h Mandor 125,000.00 13,750.00
Jumlah 8,734,550.00
210 1 Unit PASANG POMPA TEKAN
1.0000 Set Pompa Tekan 5,250,000.00 5,250,000.00
% Perlengkapan (6 % Harga Pompa) 315,000.00 315,000.00
1.8000 o/h Pekerja 80,000.00 144,000.00
2.7000 o/h Tukang 110,000.00 297,000.00
0.5400 o/h Kepala Tukang 120,000.00 64,800.00
0.1100 o/h Mandor 125,000.00 13,750.00
Jumlah 6,084,550.00

292/314 517211341.xlsx/ANALISA (2)


1 2 3 4

211 1m PEKERJAAN SUMUR BOR


1.1000 M Pipa PVC Ø 6 '' 232,712.50 255,983.75
1.1000 m Pipa Gip Ø 1 " 93,075.00 102,382.50
1.1000 m Pipa Gip Ø 1 ¼ " 159,925.00 175,917.50
0.6000 m3 Pekerjaan Tanah 63,125.00 37,875.00
1.0000 unt Sewa alat 1,500,000.00 1,500,000.00
1.0000 o/h Pekerja 80,000.00 80,000.00
0.7746 o/h Tukang 110,000.00 85,201.74
0.5000 o/h Kepala tukang 120,000.00 60,000.00
0.0500 o/h Mandor 125,000.00 6,250.00
Jumlah 2,303,610.49

212 1 Unit MEMASANG 1 BUAH TUTUP MEN HOLE SUMUR BOR


0.6240 M³ Galian Tanah 63,125.00 39,390.00
0.0480 M³ Urugan Pasir 241,250.00 11,580.00
0.1000 M³ Urugan Kerikil 325,250.00 32,525.00
1.6800 M2 Pasang Bekisting 182,170.00 306,045.60
1.6800 M³ Beton 1 : 2 : 3 1,519,029.44 2,551,969.47
0.2500 H.o Plesteran 1 : 2 +Acian 99,883.40 24,970.85
1.0000 Ls Penutup Plat Besi + Rangka 850,000.00 850,000.00
Jumlah 3,816,480.92
213 1 TITIK INSTALASI LAMPU / PENERANGAN
4.5000 m Kabel NYM 3 X 2,5 mm2 20,000.00 90,000.00
10.0000 m Kabel NYM 2 X 2,5 mm2 17,000.00 170,000.00
5.0000 m Pipa PVC Clipsal 3/4" 7,500.00 37,500.00
3.5000 m Pipa PVC Maspion 5/8" 5,000.00 17,500.00
2.0000 bh T.Doos PVC 3/4 4,500.00 9,000.00
2.0000 bh Elbo PVC Clipsal 4,500.00 9,000.00
4.0000 bh Klem PVC Clipsal 700.00 2,800.00
1.0000 bh Sock PVC Clipsal 3/4 2,400.00 2,400.00
3.0000 bh Las Dop Legrand 4 mm2 1,700.00 5,100.00
0.2500 Rol Isolasi Unibel 10,000.00 2,500.00
0.7500 o/h Pekerja 80,000.00 60,000.00
0.5000 o/h Tukang Listrik 110,000.00 55,000.00
0.0500 o/h Kepala Tukang 120,000.00 6,000.00
0.0100 o/h Mandor 125,000.00 1,250.00
Jumlah 468,050.00

214 1 TITIK INSTALASI STOP KONTAK / POWER OUTLET


12.0000 m Kabel NYM 3 x 2,5 mm2 20,000.00 240,000.00
12.0000 m Pipa PVC Clipsal 3/4" 7,500.00 90,000.00
3.5000 m Pipa PVC Maspion 5/8 5,000.00 17,500.00
2.0000 bh T.Doos PVC 3/4 4,500.00 9,000.00
2.0000 bh Elbo PVC Clipsal 4,500.00 9,000.00
4.0000 bh Klem PVC Clipsal 700.00 2,800.00
3.0000 bh Sock PVC Clipsal 3/4 2,400.00 7,200.00
3.0000 bh Las Dop Legrand 4 mm2 1,700.00 5,100.00
0.2500 Rol Isolasi Unibel 10,000.00 2,500.00
0.7500 o/h Pekerja 80,000.00 60,000.00
0.5000 o/h Tukang Listrik 110,000.00 55,000.00
0.0500 o/h Kepala Tukang 120,000.00 6,000.00
0.0100 o/h Mandor 125,000.00 1,250.00
Jumlah 505,350.00

215 1 TITIK INSTALASI AC 1 PHASE


30.0000 m Kabel NYM 3 x 4 mm2 29,000.00 870,000.00
30.0000 m Pipa Clipsal PVC 3/4 7,500.00 225,000.00
2.0000 bh Elbo Clipsal PVC 3/4 4,500.00 9,000.00
10.0000 bh Sock PVC Clipsal 3/4 2,400.00 24,000.00
30.0000 bh Klem Clipsal PVC 3/4 700.00 21,000.00
0.7500 o/h Pekerja 80,000.00 60,000.00
0.5000 o/h Tukang Listrik 110,000.00 55,000.00

293/314 517211341.xlsx/ANALISA (2)


1 2 3 4
0.0500 o/h Kepala Tukang 120,000.00 6,000.00
0.0100 o/h Mandor 125,000.00 1,250.00
Jumlah 1,271,250.00

216 1 TITIK INSTALASI AC 3 PHASE


30.0000 m Kabel NYM 4 x 4 mm2 43,000.00 1,290,000.00
30.0000 m Pipa Clipsal PVC 3/4 7,500.00 225,000.00
2.0000 bh Elbo Clipsal PVC 3/4 4,500.00 9,000.00
10.0000 bh Sock PVC Clipsal 3/4 2,400.00 24,000.00
30.0000 bh Klem Clipsal PVC 3/4 700.00 21,000.00
0.7500 o/h Pekerja 80,000.00 60,000.00
0.5000 o/h Tukang Listrik 110,000.00 55,000.00
0.0500 o/h Kepala Tukang 120,000.00 6,000.00
0.0100 o/h Mandor 125,000.00 1,250.00
Jumlah 1,691,250.00

217 1 TITIK INSTALASI SOUND SYSTEM


12.0000 m Kabel NYM HY 3 X 2,5 mm2 20,000.00 240,000.00
12.0000 m Pipa PVC Clipsal 3/4" 7,500.00 90,000.00
5.0000 m Pipa PVC Maspion 5/8" 5,000.00 25,000.00
2.0000 bh T.Doos PVC 3/4 4,500.00 9,000.00
2.0000 bh Elbo PVC Clipsal 3/4 4,500.00 9,000.00
12.0000 bh Klem PVC Clipsal 3/4 700.00 8,400.00
3.0000 bh Sock PVC Clipsal 3/4 2,400.00 7,200.00
3.0000 bh Las Dop Legrand 4 mm2 1,700.00 5,100.00
0.2500 Rol Isolasi Unibel 10,000.00 2,500.00
0.7500 o/h Pekerja 80,000.00 60,000.00
0.5000 o/h Tukang Listrik 110,000.00 55,000.00
0.0500 o/h Kepala Tukang 120,000.00 6,000.00
0.0100 o/h Mandor 125,000.00 1,250.00
Jumlah 518,450.00

218 1 TITIK INSTALASI TELEPHONE


35.0000 m Kabel ITC 2 x 2 x 0.6 mm2 3,000.00 105,000.00
35.0000 m Pipa PVC Clipsal 3/4" 7,500.00 262,500.00
5.0000 m Pipa PVC Maspion 5/8 5,000.00 25,000.00
1.0000 bh T.Doos PVC 3/4 4,500.00 4,500.00
3.0000 bh Elbo PVC Clipsal 4,500.00 13,500.00
12.0000 bh Klem PVC Clipsal 700.00 8,400.00
10.0000 bh Sock PVC Clipsal 3/4 2,400.00 24,000.00
0.7500 o/h Pekerja 80,000.00 60,000.00
0.5000 o/h Tukang Listrik 110,000.00 55,000.00
0.0500 o/h Kepala Tukang 120,000.00 6,000.00
0.0100 o/h Mandor 125,000.00 1,250.00
Jumlah 565,150.00

219 1 TITIK INSTALASI FIRE ALARM


15.0000 m Kabel NYM 2 X 2,5 mm2 17,000.00 255,000.00
15.0000 m Pipa PVC Clipsal 3/4" 7,500.00 112,500.00
1.0000 bh T.Doos PVC 3/4 4,500.00 4,500.00
2.0000 bh Elbo PVC Clipsal 4,500.00 9,000.00
7.0000 bh Klem PVC Clipsal 700.00 4,900.00
5.0000 bh Sock PVC Clipsal 3/4 2,400.00 12,000.00
2.0000 bh Las Dop Legrand 4 mm2 1,700.00 3,400.00
0.2500 Rol Isolasi Unibel 10,000.00 2,500.00
0.7500 o/h Pekerja 80,000.00 60,000.00
0.5000 o/h Tukang Listrik 110,000.00 55,000.00
0.0500 o/h Kepala Tukang 120,000.00 6,000.00
0.0100 o/h Mandor 125,000.00 1,250.00
Jumlah 526,050.00

1 2 3 4

294/314 517211341.xlsx/ANALISA (2)


1 2 3 4
220 1 Set GROUNDING PENTANAHAN
3.0000 m' Pipa Gip Ø 2 " 115,000.00 345,000.00
2.0000 o/h Kawat BC 2,5 mm 20,000.00 40,000.00
3.0000 o/h Kabel BC 50 mm 75,000.00 225,000.00
1.0000 o/h Box Pengaman Pasangan Batu Tela 250,000.00 250,000.00
1.0000 o/h Upah Kerja 350,000.00 350,000.00
Jumlah 1,210,000.00

1 2 3 4

221 1 M3 GALIAN TANAH dan URUGAN PASIR pada KABEL


FEEDER / INSTALASI LAMPU JALAN
1.0000 m3 Galian Tanah 63,125.00 63,125.00
0.3000 m3 Pasir Urug 241,250.00 72,375.00
0.6440 m3 Urugan Tanah kembali 21,041.67 13,550.83
Jumlah 149,050.83

222 1 M3 URUGAN TANAH SUBUR


1.2000 M3 Tanah Subur 360,000.00 432,000.00
0.3000 o/h Pekerja 80,000.00 24,000.00
0.0100 o/h Mandor 125,000.00 1,250.00
Jumlah 457,250.00
222 1 M2 TANAM RUMPUT HALAMAN
1.1000 M2 Rumput Halaman 30,000.00 33,000.00
0.5000 Kg Pupuk (TSP) 14,400.00 7,200.00
0.0200 o/h Pekerja 80,000.00 1,600.00
0.2000 o/h Tukang 110,000.00 22,000.00
0.0200 o/h Kepala Tukang 120,000.00 2,400.00
0.0100 o/h Mandor 125,000.00 1,250.00
1.0000 Ls Pemeliharaan selama 1 bulan 10,000.00 10,000.00
Jumlah 77,450.00
223 1 Phn TANAM PALEM RAJA
1.0000 Phn Palem Raja 600,000.00 600,000.00
1.0000 Kg Pupuk (TSP) 14,400.00 14,400.00
0.5000 o/h Pekerja 80,000.00 40,000.00
0.2500 o/h Tukang 110,000.00 27,500.00
0.0250 o/h Kepala Tukang 120,000.00 3,000.00
0.0100 o/h Mandor 125,000.00 1,250.00
1.0000 Ls Pemeliharaan selama 1 bulan 100,000.00 100,000.00
Jumlah 786,150.00
224 1 Phn TANAM PALEM BOTOL
1.0000 Phn Palem Botol 425,000.00 425,000.00
1.0000 Kg Pupuk (TSP) 14,400.00 14,400.00
0.5000 o/h Pekerja 80,000.00 40,000.00
0.2500 o/h Tukang 110,000.00 27,500.00
0.0250 o/h Kepala Tukang 120,000.00 3,000.00
0.0100 o/h Mandor 125,000.00 1,250.00
1.0000 Ls Pemeliharaan selama 1 bulan 75,000.00 75,000.00
Jumlah 586,150.00

1 2 3 4

225 1 Phn TANAM CEMARA


1.0000 Phn Cemara 600,000.00 600,000.00
1.0000 Kg Pupuk (TSP) 14,400.00 14,400.00
0.5000 o/h Pekerja 80,000.00 40,000.00

295/314 517211341.xlsx/ANALISA (2)


1 2 3 4
0.2500 o/h Tukang 110,000.00 27,500.00
0.0250 o/h Kepala Tukang 120,000.00 3,000.00
0.0100 o/h Mandor 125,000.00 1,250.00
1.0000 Ls Pemeliharaan selama 1 bulan 75,000.00 75,000.00
Jumlah 761,150.00
226 1 M2 PASANG DINDING BATU ALAM
1.0600 M2 Batu alam Palimanan/Batu Candi 791,872.50 839,384.85
3.0030 Bh Paku 12 1,200.00 3,603.60
0.0250 M3 Pasir 235,000.00 5,875.00
12.4400 Kg Semen 1,600.00 19,904.00
0.6500 Kg Semen Warna 7,500.00 4,875.00
1.3000 o/h Pekerja 80,000.00 104,000.00
0.6500 o/h Tukang batu 110,000.00 71,500.00
0.0650 o/h Kepala tukang 120,000.00 7,800.00
0.0650 o/h Mandor 125,000.00 8,125.00
Jumlah 1,065,067.45

240 1M2 PASANG DINDING BATU ALAM ANDHESIT


1.0500 M2 Batu Andhesit 350,000.00 367,500.00
11.7500 Kg Semen Portland 1,500.00 17,625.00
0.0350 M3 Pasir Pasang 250,000.00 8,750.00
0.7200 h.o Pekerja 75,000.00 54,000.00
0.3800 h.o Tukang Batu 100,000.00 38,000.00
0.0350 h.o Kepala Tukang 105,000.00 3,675.00
0.0300 h.o Mandor 110,000.00 3,300.00
Jumlah 492,850.00

241 1M2 PASANG DINDING BATU ALAM CANDI


1.0500 M2 Batu Alam Candi 375,000.00 393,750.00
11.7500 Kg Semen Portland 1,500.00 17,625.00
0.0350 M3 Pasir Pasang 250,000.00 8,750.00
0.7200 h.o Pekerja 75,000.00 54,000.00
0.3800 h.o Tukang Batu 100,000.00 38,000.00
0.0350 h.o Kepala Tukang 105,000.00 3,675.00
0.0300 h.o Mandor 110,000.00 3,300.00
Jumlah 519,100.00

242 1 M2 PASANG ALUCOBOND FLAFOND ENTRANCE


1.1000 M2 Alucobond 700,000.00 770,000.00
0.4500 Tb Sealant 45,000.00 20,250.00
3.5000 Kg Besi Siku 40.40.3 20,000.00 70,000.00
8.0000 Cm Pengelasan 7,800.00 62,400.00
8.0000 Bj Ree fet 750.00 6,000.00
0.5600 o/h Pekerja 80,000.00 44,800.00
0.5600 o/h Tukang batu 110,000.00 61,600.00
0.0560 o/h Kepala tukang 120,000.00 6,720.00
0.0083 o/h Mandor 125,000.00 1,037.50
Jumlah 1,042,807.50

243 1 UNIT PEMBUATAN Pembuatan stage Ruang Sidang


90.6867 M3 Urugan tanah 325,250.00 29,495,849.18
1.8619 M3 Urugan Pasir 241,250.00 449,183.38
8.6209 M3 Pas Dinding bata 1,217,800.00 10,498,483.31
27.0000 m Kolom Praktis 98,435.00 2,657,745.00
51.3900 m Ring Balk Praktis 132,440.00 6,806,091.60
5.1515 M3 Lantai Cor 1 : 3 : 5 tebal 7 cm 862,360.19 4,442,448.49
114.9448 M2 Plester 1;3 62,021.60 7,129,060.41
114.9448 m2 Acian 34,650.00 3,982,837.32
93.7900 M2 Lantai Keramik 60x60 (Granitto) 290,491.05 27,245,155.35
28.5750 m2 Keramik tangga (Granitto) 290,491.05 8,300,781.68
1.0000 Ls Pek. Finising & Assesories 36,189,452.57 36,189,452.57
Jumlah 137,197,088.28

296/314 517211341.xlsx/ANALISA (2)


1 2 3 4

244 1M2 PASANG DINDING BATU ALAM ANDHESIT


1.0500 M2 Batu Andhesit 350,000.00 367,500.00
11.7500 Kg Semen Portland 1,500.00 17,625.00
0.0350 M3 Pasir Pasang 250,000.00 8,750.00
0.7200 h.o Pekerja 80,000.00 57,600.00
0.3800 h.o Tukang Batu 110,000.00 41,800.00
0.0350 h.o Kepala Tukang 120,000.00 4,200.00
0.0300 h.o Mandor 125,000.00 3,750.00
Jumlah 501,225.00

245 1M2 PASANG DINDING BATU ALAM LIMESTONE


1.0500 M2 Batu Alam Limestone 325,000.00 341,250.00
11.7500 Kg Semen Portland 1,500.00 17,625.00
0.0350 M3 Pasir Pasang 250,000.00 8,750.00
0.7200 h.o Pekerja 80,000.00 57,600.00
0.3800 h.o Tukang Batu 110,000.00 41,800.00
0.0350 h.o Kepala Tukang 120,000.00 4,200.00
0.0300 h.o Mandor 125,000.00 3,750.00
Jumlah 474,975.00

297/314 517211341.xlsx/ANALISA (2)


REKAPITULASI
ENGINEERING ESTIMATE (EE)
KEGIATAN : PERENCANAAN RUMAH IBADAH
PEKERJAAN : PERENCANAAN CENTRAL MONUMENT KRISTUS ALLAH NOL PAPUA
LOKASI : AGIMUGA- MIMIKA
TAHUN ANGG : 2014

NO. JENIS PEKERJAAN JUMLAH HARGA (Rp) KETERANGAN

A PEKERJAAN SITE DEVELOBMENT 12,087,500,000


TOTAL. A 12,087,500,000
B. BANGUNAN UTAMA
1 PEKERJAAN PERSIAPAN 2,846,056,200.00
2 PEKERJAAN TANAH 575,372,853.99
3 PEKERJAAN PONDASI 2,866,956,633.41
4 PEKERJAAN BETON 7,433,345,014.57
5 PEKERJAAN PASANGAN DAN PLESTERAN 1,373,124,695.73
6 PEKERJAAN KOSEN, PINTU DAN JENDELA (Lt 1,2,3 &4) 107,460,984.96
7 PEKERJAAN PENGGANTUNG DAN PENGUNCI 6,839,368.75
8 PEKERJAAN PLAFON DAN INTERIOR/EXTERIOR 1,061,230,670.70
9 PEKERJAAN MECANIKAL ELECTRICAL 137,836,862.31
10 PEKERJAAN PENGECATAN 130,264,075.79
11 PEKERJAAN KHUSUS PATUNG KRISTUS 3,069,286,985.68
12 PEKERJAAN AKHIR 12,500,000.00
TOTAL. B 19,620,274,346

C. BANGUNAN PENUNJANG
1 Kantor Permanen 3,400,000,000.00
2 Pengadaan Tenaga Listrik 1,500,000,000.00
3 Pengadaan Air Bersih 950,000,000.00
4 Sarana Olah Raga dan Pendidikan 2,885,000,000.00
5 Jalan dan Pelataran 2,497,269,380.93
6 Lanscape 350,000,000.00
TOTAL. C 11,582,269,381

TOTAL. (A + B + C )....................................(a) 43,290,043,727

Biaya Desaign dan Revew Desaign .............(b) 649,350,656


Biaya Kepanitiaan dan Supervisi ...................(c) 1,731,601,749
TOTAL BIAYA, (a)+(b)+(c) =.........................(d) 45,670,996,132
PPN 10%,(10%x (d)) =...................................(e) 4,329,004,373
GRAND TOTAL,(d)+(e)..................................(f) 50,000,000,504
PEMBULATAN 50,000,000,000

TERBILANG Lima Puluh Milyar Rupiah


Timika, 12 Mei 2014

Pembangunan Monumen
CENTRAL MONUMENT YESUS KRISTUS ALLAH NOL PAPUA
Distrik Agimuga Kabupaten Mimika

PENANGGUNG JAWAB

AGUSTINUS ANGGAIBAK

517211341.xlsx/nas
REKAPITULASI

KEGIATAN : PEMBANGUNAN RUMAH IBADAH


PEKERJAAN : PEMBANGUNAN GEDUNG GEREJA GKIP (KINGMI) KLASIS MIMIKA
LOKASI : KOTA TIMIKA
TAHUN ANGG : 2013

RENCANA PELAKSANAAN
JUMLAH HARGA KETERANG
NO. JENIS PEKERJAAN BOBOT
(Rp) TAHUN PERTAMA TAHUN KEDUA TAHUN KETIGA TAHUN KEEMPAT AN
Bl ke1 Bl ke2 Bl ke3 Bl ke4 Bl ke5 Bl ke6 Bl ke7 Bl ke8 Bl ke9 Bl ke10 Bl ke11 Bl ke12 Bl ke13 Bl ke14 Bl ke15 Bl ke16 Bl ke17 Bl ke18 Bl ke19 Bl ke20 Bl ke21 Bl ke22 Bl ke23 Bl ke24 Bl ke25 Bl ke26 Bl ke27 Bl ke28 Bl ke29 Bl ke30 Bl ke31 Bl ke32 Bl ke33 Bl ke34 Bl ke35 Bl ke36

I. PEKERJAAN PERSIAPAN 12,087,500,000 #REF! #REF!


II PEKERJAAN TANAH 575,372,854 60.57% 12.17% 16.13% 16.13% 16.13%
III PEKERJAAN BETON 1.10
a Pekrjaan Beton Pada Elevasi (BOC -3,15 S/D TOC. -0,05) 1,823,982,833.05 143.94% 28.79% 28.79% 28.79% 28.79% 28.79%
b Pekrjaan Beton Pada Elevasi (BOC -0,05 S/D TOC. +3,92) 2,631,686,546.17 275.19% 22.93% 22.93% 22.93% 22.93% 22.93% 22.93% 22.93% 22.93% 22.93% 22.93% 22.93% 22.93%

c Pekrjaan Beton Pada Elevasi (BOC.+3,92 S/D TOC.+22,25) #NAME? #NAME? ### ### ### ### ### ###
d Pekerjaan Beton Menara Besar Pada Elevasi (TOC.7.00 S/D +27.92) #NAME? #NAME? ### ### ### ###
0.90
e Pekerjaan Beton Menara Kecil Pada Elevasi (TOC.-0.50 S/D +19,32) #NAME? #NAME? ### ### ### ###

#NAME? #NAME?
IV. PEKERJAAN PASANGAN DAN PLESTERAN
a Pekerjaan Lantai I 796,922,207.17 80.00% ### ### ### ### ### ### ### ### ### ### 3.06% 3.06% 3.06% 0.24% 0.24% 0.24% 0.24% 0.24% 1.21%
b Pekerjaan Lantai 2 287,330,396.67 30.25% 0.33% 0.33% 0.33% 0.94% 0.94% 0.94% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 2.16% 0.70
c. Pekerjaan Menara Besar 108,547,942.44 #REF! ### ### ### ### 0.22% 0.22% 0.45%
d Pekerjaan Menara Kecil 180,324,149.45 #REF! ### ### ### 0.08% 0.08% 0.08% 0.08% 0.32%
1,373,124,696 #REF!
V. PEKERJAAN KOSEN, PINTU DAN JENDELA (Lt 1,2 & menara) 107,460,985 11.31% 0.86% 0.86% 0.86% 0.13% 0.13% 0.13% 0.13% 0.13% 0.67%
0.50
VI. PEKERJAAN PENGGANTUNG DAN PENGUNCI 6,839,369 0.72% 0.36% 0.36%
VII PEKERJAAN PLAFON DAN ATAP
a PEKERJAAN PLAFON 193,607,297.63 20.38% 3.40% 3.40% 3.40% 3.40% 3.40% 3.40%
b PEKERJAAN ATAP 1,856,953,400.00 127.61% 0.12 0.12 11.60% 11.60% 11.60% 11.60% 11.60% 11.60% 11.60% 11.60% 11.60%
2,050,560,698 147.99% 0.30
VIII. PEKERJAAN INTERIOR/EXTERIOR 1,061,230,671 61.96% 12.39% 12.39% 12.39% 12.39% 12.39%
IX PEKERJAAN MECANIKAL ELECTRICAL
a PEKERJAAN ELECTRICAL 95,990,012.50 10.10% 3.37% 3.37% 3.37%
b PEKERJAAN MECANIKAL 41,846,849.81 3.98% 0.19% 1.26% 1.26% 1.26%

137,836,862 14.08% 0.10


X PEKERJAAN PENGECATAN
a Cat Tembok : 116,190,846.64 12.23% 4.08% 4.08% 4.08%

b Cat Kayu dan Besi : 14,073,229.14 1.48% 0.49% 0.49% 0.49%

130,264,076 13.71%
(0.10)
XI PEKERJAAN AKHIR 12,500,000 1.32% 1.32%
GRAND TOTAL....... #NAME? #REF!
PPN 10% 4,329,004,373
Biaya Revew Desaign 649,350,656
Biaya Pengelohan dan Pengawasan 1,731,601,749
TOTAL BIAYA 45,670,996,132
PEMBULATAN 50,000,000,000

PERBULAN #REF! 12.17% 28.79% 28.79% ### ### ### 39.07% 22.93% ### ### ### ### ### ### ### ### ### 11.60% 11.60% ### ### ### ### ### ### ### ### ### ### 18.09% 18.09% 21.73% 24.54% 21.29% 6.11%
BOBOT RENCANA
KOMULATIF - #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Batu alam PalimanaM2
Batu Andhesit M2
Batu Alam Candi M2
Batu Andhesit M2
Batu Alam Limeston M2
Batu Alam Candi M2
Batu Andhesit Susun M2
Batu koral sikat M2
367,500.00 -
350,000.00
375,000.00 393,750.00
350,000.00 367,500.00
325,000.00 341,250.00
375,000.00 393,750.00
380,000.00 399,000.00
180,000.00 189,000.00
DAFTAR ANALISA HARGA SATUAN PEKERJAAN

Pekerjaan : Mobilisasi
Satuan : Ls

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

JUMLAH HARGA TENAGA

B. BAHAN

JUMLAH HARGA BAHAN

C. PERALATAN

1 Excavator Unit 2.00 0.00 0


2 Tronton Unit 1.00 0.00 0.00
3 Motor Greder Unit 1.00 0.00 0.00
4 Vibrator Roller Unit 1.00 0.00 0.00
5 Dump Truk Unit 5.00 0.00 0.00
6 Water Tangker Unit 1.00 0.00 0.00
7 Ponton Pancang Set 1.00 0.00 0.00
8 Ponton Transport Unit 1.00 0.00 0.00
9 Ponton Kerja Unit 1.00 0.00 0.00
10 Crane Unit 1.00 0.00 0.00
11 Vibrator Diesel Hammer Unit 1.00 0.00 0.00
12 Alat Bantu -Ls- Set 0.00 0.00
JUMLAH HARGA PERALATAN 0.00
TOTAL HARGA 0.00

D. DEMOBILISASI 0.00

E. JUMLAH HARGA ( A + B + C + D ) 0.00


DAFTAR ANALISA HARGA SATUAN PEKERJAAN

PEKERJAA: Quality Control


SATUAN : Ls

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

1 Pembuatan Job Mix Design Ls 1.00 0.00 0.00


(JMF) Aggregat Klas C

2 Pembuatan Job Mix Design Ls 1.00 0.00 0.00


(JMF) Beton K.300

3 Tes Kuat Tekan Beton Buah 10.00 0.00 0.00

4 Tes Kepadatan (Sand Cone) Titik 10.00 0.00 0.00

JUMLAH 0.00
DAFTAR ANALISA HARGA SATUAN PEKERJAAN

Pekerjaan : Pengupasan Kepala Tiang Spun Piles dan Sheet Piles Analisa SNI. 6.23
Satuan : 1 Buah

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Jam 1.2500 110,000.00 137,500.00


2. Tukang Jam 1.2500 130,000.00 162,500.00
3. Mandor Jam 0.6250 175,000.00 109,375.00

JUMLAH HARGA TENAGA 409,375.00

B. BAHAN

1. Elektroda Kg 6.0000 75,000.00 450,000.00


2. Oksigen Botol 0.3500 300,000.00 105,000.00

JUMLAH HARGA BAHAN 555,000.00

C. PERALATAN

1. Welding Set Jam 2.5400 250,000.00 635,000.00


2. Alat Bantu Ls 1.0000 2,500.00 2,500.00

JUMLAH HARGA PERALATAN 637,500.00

D. JUMLAH HARGA ( A + B + C ) 1,601,875.00


DAFTAR ANALISA HARGA SATUAN PEKERJAAN

Pekerjaan : Pemancangan Tiang Pancang Spun Piles Analisa EI.


Satuan : 1 M1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Jam 2.2509 110,000.00 247,599.00


2. Mandor Jam 0.2259 175,000.00 39,532.50

JUMLAH HARGA TENAGA 287,131.50

B. BAHAN

JUMLAH HARGA BAHAN -

C. PERALATAN

1. Ponton Transport Jam 0.1500 0.00 0.00


2. Ponton Pancang Jam 0.0190 0.00 0.00
3. Crane on Track Jam 0.0100 1,500,000.00 15,000.00
4. File drive + Hammer Jam 0.1200 1,200,000.00 144,000.00
5. Alat Bantu Ls 1.00 2,500.00 2,500.00

JUMLAH HARGA PERALATAN 161,500.00

D. JUMLAH HARGA ( A + B + C ) 448,631.50


DAFTAR ANALISA HARGA SATUAN PEKERJAAN

Pekerjaan : Pengadaan Sheet Piles Type W.350 B Analisa EI.


Satuan : 1 Batang

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Jam 4.0145 0.00 0.00


2. Mandor Jam 0.4015 0.00 0.00

JUMLAH HARGA TENAGA 0.00

B. BAHAN

1. Sheet Piles Type W.350 B M1 12.0000 0.00 0.00


2. Kayu Ganjal M3 0.0513 0.00 0.00

JUMLAH HARGA BAHAN -

C. PERALATAN

1 Crane Jam 0.7250 0.00 0.00


2 Tronton Jam 0.9500 0.00 0.00
2. Alat Bantu Jam 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA ( A + B + C ) 0.00


DAFTAR ANALISA HARGA SATUAN PEKERJAAN

Pekerjaan : Pengadaan Spun Piles Ø 45 Analisa EI.


Satuan : 1 Batang

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Jam 4.0145 110,000.00 441,595.00


2. Mandor Jam 0.4015 175,000.00 70,262.50

JUMLAH HARGA TENAGA 511,857.50

B. BAHAN

1. Spun Pile Ø 45 M1 12.0000 250,000.00 3,000,000.00


1. Spun Pile Ø 45 M1 8.0000 0.00 0.00
2. Kayu Ganjal M3 0.0084 0.00 0.00

JUMLAH HARGA BAHAN 3,000,000.00

C. PERALATAN

1 Crane Jam 0.4015 1,500,000.00 602,250.00


2 Tronton Jam 0.6500 2,500,000.00 1,625,000.00
3 Alat Bantu Jam 1.0000 5,000.00 5,000.00

JUMLAH HARGA PERALATAN 2,232,250.00

D. JUMLAH HARGA ( A + B + C ) = 12 Meter 5,744,107.50


D. JUMLAH HARGA ( A + B + C ) = 8 Meter 2,744,107.50
DAFTAR ANALISA HARGA SATUAN PEKERJAAN

Pekerjaan : Pemasangan Cerucut Bambu Analisa EI


Satuan : 1 M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Hr/Org 0.5013 0.00 0.00


2 Mandor Hr/Org 0.1750 0.00 0.00

JUMLAH HARGA TENAGA 0.00

B. BAHAN

1. Bambu Batang 6.0000 0.00 0.00

JUMLAH HARGA BAHAN 0.00

C. PERALATAN

1. Alat Bantu @ 3 Set Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA ( A + B + C ) 0.00


DAFTAR ANALISA HARGA SATUAN PEKERJAAN

Pekerjaan : Sambung Tiang Pancang Analisa EI


Satuan : Buah

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Hr/Org 0.2465 110,000.00 27,115.00


2. Tukang Hr/Org 0.1764 130,000.00 22,932.00
3. Kepala Tukang Hr/Org 0.1300 155,000.00 20,150.00
4. Mandor Hr/Org 0.1000 175,000.00 17,500.00

JUMLAH HARGA TENAGA 87,697.00

B. BAHAN

1. Besi Plat 10 mm Kg 4.1500 25,000.00 103,750.00


2. Elektroda Kg 2.1900 75,000.00 164,250.00

JUMLAH HARGA BAHAN 268,000.00

C. PERALATAN

1. Ponton Kerja Jam 0.6250 0.00 0.00


2. Mesin Las Jam 0.7520 250,000.00 188,000.00
3. Alat Bantu @ 3 Set Ls 1.0000 10,000.00 10,000.00

JUMLAH HARGA PERALATAN 198,000.00

D. JUMLAH HARGA ( A + B + C ) 553,697.00


DAFTAR ANALISA HARGA SATUAN PEKERJAAN

Pekerjaan : Tes Pile Analisa EI


Satuan : Buah

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

1. Bahan Pancang Midle 10 m Btg 1.0000 5,744,107.50 5,744,107.50

2. Biaya Pemancangan Midle M1 7.0000 448,631.50 3,140,420.50

3. Biaya Samb. Tiang Pancang Buah 1.0000 553,697.00 553,697.00

JUMLAH HARGA PERALATAN 9,438,225.00


DAFTAR ANALISA HARGA SATUAN PEKERJAAN

Pekerjaan : Pemasangan Geotextile Wofen 300 gram Analisa EI


Satuan : 1 M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Jam 0.9333 0.00 0.00


2. Tukang Jam 0.2333 0.00 0.00
3. Mandor Jam 0.1167 0.00 0.00

JUMLAH HARGA TENAGA 0.00

B. BAHAN

1. Geotextile Type TS.70 M2 1.0000 0.00 0.00

JUMLAH HARGA BAHAN -

C. PERALATAN

1. Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA ( A + B + C ) 0.00


DAFTAR ANALISA HARGA SATUAN PEKERJAAN

Pekerjaan : Kantor Direksi Lantai Papan Analisa EI


Satuan : 1 M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Hr/Org 2.0000 0.00 0.00


2. Tukang Hr/Org 2.0000 0.00 0.00
3. Kepala Tukang Hr/Org 0.3000 0.00 0.00
4. Mandor Hr/Org 0.0500 0.00 0.00

JUMLAH HARGA TENAGA 0.00

B. BAHAN

1. Dolken Kayu Galang Dia. 8-10 Btg 1.2500 0.00 0.00


2. Kayu Klas II (Balok) M3 0.1800 0.00 0.00
3. Seng Gelombang BJLS 30 kaki 4.7600 0.00 0.00
4. Tripleks 3 mm Lbr 0.3470 0.00 0.00
5. Paku Campur Kg 0.0200 0.00 0.00
6. Kayu Klas II (Papan) M3 0.0200 0.00 0.00

JUMLAH HARGA BAHAN -

C. PERALATAN

1. Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA ( A + B + C ) 0.00


DAFTAR ANALISA HARGA SATUAN PEKERJAAN

Pekerjaan : Pembuatan Gudang Dan Alat-alat Analisa EI


Satuan : 1 M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Hr/Org 1.0000 0.00 0.00


2. Tukang Hr/Org 2.0000 0.00 0.00
3. Kepala Tukang Hr/Org 0.2000 0.00 0.00
4. Mandor Hr/Org 0.0500 0.00 0.00

JUMLAH HARGA TENAGA 0.00

B. BAHAN

1. Dolken Kayu Galang Dia. 8-10 Btg 1.1000 0.00 0.00


2. Kayu Klas II (Balok) M3 0.1750 0.00 0.00
3. Seng Gelombang BJLS 30 kaki 4.5000 0.00 0.00
4. Tripleks 3 mm Lbr 0.3470 0.00 0.00
5. Paku Campur Kg 0.0200 0.00 0.00

JUMLAH HARGA BAHAN -

C. PERALATAN

1. Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA ( A + B + C ) 0.00


DAFTAR ANALISA HARGA SATUAN PEKERJAAN

Pekerjaan : Pemasangan Geotextile Non Wofen 300 gram Analisa EI


Satuan : 1 M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Jam 0.9333 0.00 0.00


2. Tukang Jam 0.2333 0.00 0.00
3. Mandor Jam 0.1167 0.00 0.00

JUMLAH HARGA TENAGA 0.00

B. BAHAN

1. Geotextile Type HRS.300 M2 1.0000 0.00 0.00

JUMLAH HARGA BAHAN -

C. PERALATAN

1. Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 0.00

D. JUMLAH HARGA ( A + B + C ) 0.00

You might also like