MONITORING SHOP DRAWING MEP GEDUNG APARTEMEN

JUMLAH TANGGAL PENGAJUAN REVISI 1 REVISI 2 REVISI 3


NO JUDUL GAMBAR
LEMBAR MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS
GEDUNG IRNA
A AIR LIMBAH
1 Diagram skematik air kotor,bekas dan venting GD. apartemen 1.00 17-Jan-19 24-Jan-19 C
2 Denah inst. air kotor,bekas da venting lantai 1 GD. apartemen 1.00 5-Nov-18 6-Nov-19 B
3 Denah parsial-1 inst. air kotor,bekas dan venting lantai 1 1.00 5-Nov-18 6-Nov-19 B
GD. apartemen
4 Denah parsial-2 inst. air kotor,bekas da venting lantai 1 1.00 5-Nov-18 6-Nov-19 B
GD. apartemen
5 Detail 1 & 2 inst. Air kotor,bekas dan venting lantai 1 GD. apartemen 1.00 5-Nov-18 6-Nov-19 B
6 Denah inst. air kotor,bekas dan venting lantai 2 GD. apartemen 1.00 17-Jan-19 24-Jan-19 B
7 Denah parsila-1 inst. air kotor,bekas dan venting lantai 2 1.00 17-Jan-19 24-Jan-19 B
GD. apartemen
8 Denah parsial-2 inst. air kotor,bekas dan venting lantai 2 1.00 17-Jan-19 24-Jan-19 B
GD. Apartemen 1.00 17-Jan-19 24-Jan-19 B
9 Denah inst. air kotor,bekas dan venting lantai maintenance 1.00 17-Jan-19 24-Jan-19 C 21-Feb-19 26-Feb-19 B
GD. Apartemen
10 Standar detail air limbah 1 GD. Apartemen 1.00 17-Jan-19 24-Jan-19 A
11 Standar detail air limbah 1A GD. Apartemen 1.00 17-Jan-19 24-Jan-19 A
12 Standar detail air limbah 1B GD. Apartemen 1.00 17-Jan-19 24-Jan-19 C 21-Feb-19 26-Feb-19 C 14-May-19 16-May-19 B
13 Standar detail air limbah 2 GD. Apartemen 1.00 17-Jan-19 24-Jan-19 A
14 Standar detail air limbah 3 GD. Apartemen 1.00 17-Jan-19 24-Jan-19 A
15 Standar detail air limbah 3A GD. Apartemen 1.00 17-Jan-19 24-Jan-19 A
16 Standar detail air limbah 3B GD. Apartemen 1.00 17-Jan-19 24-Jan-19 A
17 Standar detail air limbah 3C GD. Apartemen 1.00 17-Jan-19 24-Jan-19 A
18 Detail & isometrik toilet air kotor,bekas dan venting GD. Apartemen 1.00 17-Jan-19 24-Jan-19 A

B AIR BERSIH
1 Diagram skematik air bersih GD. Apartemen 1.00 12-Jan-19 17-Jan-19 C 23-Feb-19 1-Mar-19 B
2 Denah inst. air bersih site plan GD. apartemen 1.00 12-Jan-19 17-Jan-19 B
3 Denah inst. air bersih lantai 1 GD. apartemen 1.00 12-Jan-19 17-Jan-19 B
4 Denah parsial-1 inst. air bersih lantai 1 GD. apartemen 1.00 12-Jan-19 17-Jan-19 B
5 Denah parsial-2 inst. air bersih lantai 1 GD. apartemen 1.00 12-Jan-19 17-Jan-19 B
6 Denah inst. air bersih lantai 2 GD. apartemen 1.00 12-Jan-19 17-Jan-19 B
7 Denah parsial-1 inst. air bersih lantai 2 GD. apartemen 1.00 12-Jan-19 17-Jan-19 B
8 Denah parsial-2 inst. air bersih lantai 2 GD. apartemen 1.00 12-Jan-19 17-Jan-19 B
9 Denah inst. air bersih lantai maintenance GD. apartemen 1.00 12-Jan-19 17-Jan-19 C 23-Feb-19 1-Mar-19 B
10 Detail-A inst. air bersih lantai maintenance GD. apartemen 1.00 12-Jan-19 17-Jan-19 C 23-Feb-19 1-Mar-19 B
11 Diagram skematik rumah pompa & GWT air bersih GD. Apartemen 1.00 12-Jan-19 17-Jan-19 C 23-Feb-19 1-Mar-19 B
12 Detail rumah pompa dan GWT air bersih GD.apartemen 1.00 18-Mar-19 5-Apr-19 C 20-Apr-19 8-May-19 B
13 Potongan-A rumah pompa dan GWT air bersih GD.apartemen 1.00 18-Mar-19 5-Apr-19 C 20-Apr-19 8-May-19 B
14 Potongan-B rumah pompa dan GWT air bersih GD.apartemen 1.00 18-Mar-19 5-Apr-19 C 20-Apr-19 8-May-19 B
15 Potongan-C rumah pompa dan GWT air bersih GD.apartemen 1.00 18-Mar-19 5-Apr-19 C 20-Apr-19 8-May-19 B
16 Diagram skematik booster pump air bersih GD. Apartemen 1.00 12-Jan-19 17-Jan-19 C 9-Mar-19 25-Mar-19 B
17 Isometrik toilet air bersih GD. Apartemen 1.00 12-Jan-19 17-Jan-19 A

C PEMADAM KEBAKARAN
1 Diagram skematik hydrant dan apar GD. Apartemen 1.00 17-Jan-19 25-Jan-19 B
2 Denah inst. hydrant dan apar lantai 1 GD. apartemen 1.00 17-Jan-19 25-Jan-19 C 20-Feb-19 26-Feb-19 C 9-Mar-19 25-Mar-19 B
3 Denah inst. hydrant dan apar lantai 2 GD. apartemen 1.00 17-Jan-19 25-Jan-19 C 20-Feb-19 26-Feb-19 B
4 Denah inst. hydrant dan apar lantai maintenance GD. apartemen 1.00 17-Jan-19 25-Jan-19 C 20-Feb-19 26-Feb-19 B
5 Standar detail-1 hydrant dan apar GD. apartemen 1.00 17-Jan-19 25-Jan-19 A
JUMLAH TANGGAL PENGAJUAN REVISI 1 REVISI 2 REVISI 3
NO JUDUL GAMBAR LEMBAR MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS
6 Standar detail-2 hydrant dan apar GD. apartemen 1.00 17-Jan-19 25-Jan-19 A
7 Standar detail-3 hydrant dan apar GD. apartemen 1.00 17-Jan-19 25-Jan-19 A

D AIR HUJAN
1 Diagram skematik saluran air hujan GD. Apartemen 1.00 12-Dec-18 17-Dec-18 A
2 Denah inst. Saluran air hujan lantai 1 GD. Apartemen 1.00 12-Dec-18 17-Dec-18 B
3 Denah inst. Saluran air hujan lantai 2 GD. Apartemen 1.00 12-Dec-18 17-Dec-18 B
4 Denah inst. Saluran air hujan lantai maintenance (atap) 1.00 12-Dec-18 17-Dec-18 B
GD. Apartemen

E VAC
1 Denah inst. AC lantai 1 GD. Apartemen 1.00 17-Jan-19 24-Jan-19 C 29-Jan-19 4-Feb-19 B 2-Apr-19 12-Apr-19 B
2 Denah parsial-1 inst. AC lantai 1 GD. Apartemen 1.00 17-Jan-19 24-Jan-19 C 29-Jan-19 4-Feb-19 B 2-Apr-19 12-Apr-19 B
3 Denah parsial-2 inst. AC lantai 1 GD. Apartemen 1.00 17-Jan-19 24-Jan-19 C 29-Jan-19 4-Feb-19 B 2-Apr-19 12-Apr-19 B
4 Tampak A tata letak outdoor AC GD.apartemen 1.00 2-Apr-19 12-Apr-19 B
5 Tampak A parsial-1 tata letak outdoor AC GD.apartemen 1.00 2-Apr-19 12-Apr-19 B
6 Tampak A parsial-2 tata letak outdoor AC GD.apartemen 1.00 2-Apr-19 12-Apr-19 B
7 Denah inst. AC lantai 2 GD. Apartemen 1.00 17-Jan-19 24-Jan-19 C 29-Jan-19 4-Feb-19 C 21-Feb-19 26-Feb-19 B 2-Apr-19 12-Apr-19 B
8 Denah parsial-1 inst. AC lantai 2 GD. Apartemen 1.00 17-Jan-19 24-Jan-19 C 29-Jan-19 4-Feb-19 C 21-Feb-19 26-Feb-19 B 2-Apr-19 12-Apr-19 B
9 Denah parsial-2 inst. AC lantai 2 GD. Apartemen 1.00 17-Jan-19 24-Jan-19 C 29-Jan-19 4-Feb-19 C 21-Feb-19 26-Feb-19 B 2-Apr-19 12-Apr-19 B
10 Denah tata letak outdoor AC lantai maintenance GD. Apartemen 1.00 2-Apr-19 12-Apr-19 B
11 Denah parsial-1 tata letak outdoor AC lantai maintenance GD.apartemen 1.00 2-Apr-19 12-Apr-19 B
12 Denah parsial-2 tata letak outdoor AC lantai maintenance GD.apartemen 1.00 2-Apr-19 12-Apr-19 B
13 Denah inst. Ventilasi mekanik lantai 1 GD. Apartemen 1.00 17-Jan-19 24-Jan-19 B
14 Denah parsial-1 inst. ventilasi mekanik lantai 1 GD. Apartemen 1.00 17-Jan-19 24-Jan-19 B
15 Denah parsial-2 inst. ventilasi mekanik lantai 1 GD. Apartemen 1.00 17-Jan-19 24-Jan-19 B
16 Denah inst. Ventilasi mekanik lantai 2 GD. Apartemen 1.00 17-Jan-19 24-Jan-19 B
17 Denah parsial-1 inst. ventilasi mekanik lantai 2 GD. Apartemen 1.00 17-Jan-19 24-Jan-19 B
18 Denah parsial-2 inst. ventilasi mekanik lantai 2 GD. Apartemen 1.00 17-Jan-19 24-Jan-19 B

F PENERANGAN
1 Denah inst. penerangan site plan GD. Apartemen 1.00 20-Dec-18 27-Dec-18 B
2 Denah inst. Penerangan lantai 1 GD. Apartemen 1.00 20-Dec-18 27-Dec-18 B
3 Denah parsial-1 inst. Penerangan lantai 1 GD. Apartemen 1.00 20-Dec-18 27-Dec-18 B
4 Denah parsial-2 inst. Penerangan lantai 1 GD. Apartemen 1.00 20-Dec-18 27-Dec-18 B
5 Denah inst. Penerangan lantai 2 GD. Apartemen 1.00 20-Dec-18 27-Dec-18 B
6 Denah parsial-1 inst. Penerangan lantai 2 GD. Apartemen 1.00 20-Dec-18 27-Dec-18 B
7 Denah parsial-2 inst. Penerangan lantai 2 GD. Apartemen 1.00 20-Dec-18 27-Dec-18 B
8 Denah inst. Penerangan lantai maintenance GD. Apartemen 1.00 20-Dec-18 27-Dec-18 B
9 Detail-1 dan 2 inst. Penerangan lantai maintenance GD. Apartemen 1.00 20-Dec-18 27-Dec-18 B
10 Standar-1 detail elektrikal GD. Apartemen 1.00 20-Dec-18 27-Dec-18 A
11 Standar-2 detail elektrikal GD. Apartemen 1.00 20-Dec-18 27-Dec-18 B
12 Standar-3 detail elektrikal GD. Apartemen 1.00 20-Dec-18 27-Dec-18 A
13 Standar detail lampu jalan area GD. Apartemen 1.00 20-Dec-18 27-Dec-18 C
14 Detail inst. penerangan hunian tipe 36 dan 45 GD. Apartemen 1.00 20-Dec-18 27-Dec-18 B

G KOTAK KONTAK
1 Denah inst. Kotak kontak lantai 1 GD. Apartemen 1.00 20-Dec-18 27-Dec-18 B
2 Denah parsial-1 inst. Kotak kontak lantai 1 GD. Apartemen 1.00 20-Dec-18 27-Dec-18 B
3 Denah parsial-2 inst. Kotak kontak lantai 1 GD. Apartemen 1.00 20-Dec-18 27-Dec-18 B
4 Denah inst. Kotak kontak lantai 2 GD. Apartemen 1.00 20-Dec-18 27-Dec-18 C 31-Jan-19 4-Feb-19 B
5 Denah parsial-1 inst. Kotak kontak lantai 2 GD. Apartemen 1.00 20-Dec-18 27-Dec-18 C 31-Jan-19 4-Feb-19 B
6 Denah parsial-2 inst. Kotak kontak lantai 2 GD. Apartemen 1.00 20-Dec-18 27-Dec-18 C 31-Jan-19 4-Feb-19 B
JUMLAH TANGGAL PENGAJUAN REVISI 1 REVISI 2 REVISI 3
NO JUDUL GAMBAR LEMBAR MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS

H DISTRIBUSI LISTRIK
1 Diagram skematik distribusi listrik GD. apartemen 1.00 20-Dec-18 27-Dec-18 B
2 Denah jalur kabel feeder dari power house ke GD. apartemen 1.00 20-Dec-18 27-Dec-18 B
3 Denah distribusi listrik lantai 1 GD. apartemen 1.00 20-Dec-18 27-Dec-18 A
4 Denah distribusi listrik lantai 2 GD. apartemen 1.00 20-Dec-18 27-Dec-18 A
5 Denah tray kabel lantai 1 GD. apartemen 1.00 20-Dec-18 27-Dec-18 B
6 Denah tray kabel lantai 2 GD. apartemen 1.00 20-Dec-18 27-Dec-18 B
7 Standar-1 detail tray kabel GD. apartemen 1.00 20-Dec-18 27-Dec-18 A
8 Standar-2 detail tray kabel GD. apartemen 1.00 20-Dec-18 27-Dec-18 A
9 Standar-3 detail tray kabel GD. apartemen 1.00 20-Dec-18 27-Dec-18 A
10 Standar-4 detail tray kabel GD. apartemen 1.00 20-Dec-18 27-Dec-18 A

I GROUNDING
1 Denah instalasi grounding GD.apartemen 1.00 15-Apr-19 4-May-19 C

J SKEDUL BEBAN LISTRIK


1 Skedul beban SDP GD. Apartemen 1.00 20-Dec-18 27-Dec-18 C 1-Mar-19
2 Skedul beban SDP pompa dan LP-OL GD. Apartemen 1.00 20-Dec-18 27-Dec-18 A
3 Skedul beban power panel lantai 1 GD. Apartemen 1.00 20-Dec-18 27-Dec-18 C 1-Mar-19
4 Skedul beban power panel lantai 2 GD. Apartemen 1.00 20-Dec-18 27-Dec-18 C 1-Mar-19
5 Skedul beban box switch kamar tipe 36 dan 45 GD. Apartemen 1.00 20-Dec-18 27-Dec-18 C 1-Mar-19

K FIRE ALARM
Diagram skematik fire alarm GD. Apartemen 1.00 24-Dec-18 27-Dec-18 C 26-Feb-19 1-Mar-19 B
2 Denah inst. Fire alarm lantai 1 GD. Apartemen 1.00 24-Dec-18 27-Dec-18 C 26-Feb-19 1-Mar-19 B
3 Denah parsial-1 inst. Fire alarm lantai 1 GD. Apartemen 1.00 24-Dec-18 27-Dec-18 C 26-Feb-19 1-Mar-19 B
4 Denah parsial-2 inst. Fire alarm lantai 1 GD. Apartemen 1.00 24-Dec-18 27-Dec-18 C 26-Feb-19 1-Mar-19 B
5 Denah inst. Fire alarm lantai 2 GD. Apartemen 1.00 24-Dec-18 27-Dec-18 C 26-Feb-19 1-Mar-19 B
6 Denah parsial-1 inst. Fire alarm lantai 2 GD. Apartemen 1.00 24-Dec-18 27-Dec-18 C 26-Feb-19 1-Mar-19 B
7 Denah parsial-2 inst. Fire alarm lantai 2 GD. Apartemen 1.00 24-Dec-18 27-Dec-18 C 26-Feb-19 1-Mar-19 B
8 Standar detail fire alarm GD. Apartemen 1.00 24-Dec-18 27-Dec-18 A
9 Detail inst. Fire alarm hunian tipe 36 & 45 GD. Apartemen 1.00 24-Dec-18 27-Dec-18 B

L SOUND SYSTEM
1 Diagram skematik sound system GD. Apartemen 1.00 24-Dec-18 27-Dec-18 B
2 Denah inst. sound system lantai 1 GD. Apartemen 1.00 24-Dec-18 27-Dec-18 B
3 Denah parsial-1 inst. sound system lantai 1 GD. Apartemen 1.00 24-Dec-18 27-Dec-18 B
4 Denah parsial-2 inst. sound system lantai 1 GD. Apartemen 1.00 24-Dec-18 27-Dec-18 B
5 Denah inst. sound system lantai 2 GD. Apartemen 1.00 24-Dec-18 27-Dec-18 C 20-Feb-19 26-Feb-19 B
6 Denah parsial-1 inst. sound system lantai 2 GD. Apartemen 1.00 24-Dec-18 27-Dec-18 C 20-Feb-19 26-Feb-19 B
7 Denah parsial-2 inst. sound system lantai 2 GD. Apartemen 1.00 24-Dec-18 27-Dec-18 C 20-Feb-19 26-Feb-19 B
8 Standar detail sound system GD. Apartemen 1.00 24-Dec-18 27-Dec-18 A
9 Detail inst. sound system hunian tipe 36 & 45 GD. Apartemen 1.00 24-Dec-18 27-Dec-18 B

M TELEPON
1 Diagram skematik telepon GD. Apartemen 1.00 24-Dec-18 27-Dec-18 B
2 Denah inst. Telepon lantai 1 GD. Apartemen 1.00 24-Dec-18 27-Dec-18 B
3 Denah inst. Telepon lantai 2 GD. Apartemen 1.00 24-Dec-18 27-Dec-18 C 20-Feb-19 26-Feb-19 B
4 Standar detail telepon GD. Apartemen 1.00 24-Dec-18 27-Dec-18 A
5 Detail inst. telepon GD. Apartemen 1.00 24-Dec-18 27-Dec-18 A
JUMLAH TANGGAL PENGAJUAN REVISI 1 REVISI 2 REVISI 3
NO JUDUL GAMBAR LEMBAR MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS

N DATA & WIFI


1 Diagram skematik data dan wifi GD. Apartemen 1.00 24-Dec-18 27-Dec-18 A
2 Denah inst. data dan wifi lantai 1 GD. Apartemen 1.00 24-Dec-18 27-Dec-18 B
3 Denah inst. data dan wifi lantai 2 GD. Apartemen 1.00 24-Dec-18 27-Dec-18 B
4 Standar detail data dan wifi GD. Apartemen 1.00 24-Dec-18 27-Dec-18 A

O MATV
1 Diagram skematik MATV GD. Apartemen 1.00 24-Dec-18 27-Dec-18 B
2 Denah inst. MATV lantai 1 GD. Apartemen 1.00 24-Dec-18 27-Dec-18 B
3 Denah inst. MATV lantai 2 GD. Apartemen 1.00 24-Dec-18 27-Dec-18 B
4 Detail inst. MATV hunian tipe 36 & 45 GD. Apartemen 1.00 24-Dec-18 27-Dec-18 A

P CCTV
1 Diagram skematik CCTV GD. Apartemen 1.00 24-Dec-18 7-Jan-19 C 23-Feb-19 26-Feb-19 B
2 Denah inst. CCTV lantai 1 GD. Apartemen 1.00 24-Dec-18 7-Jan-19 B
3 Denah inst. CCTV lantai 2 GD. Apartemen 1.00 24-Dec-18 7-Jan-19 B
4 Standar detail CCTV GD. Apartemen 1.00 24-Dec-18 7-Jan-19 A

Q TOWER AIR
1 Denah inst. pemipaan tower air kap. 50 m3 1.00 12-Dec-19 17-Dec-19 C 31-Jan-19 4-Feb-19 B
2 Potongan.A inst. pemipaan tower air kap. 50 m3 1.00 12-Dec-19 17-Dec-19 C 31-Jan-19 4-Feb-19 B
3 Detail potongan.A inst. pemipaan tower air kap. 50 m3 1.00 12-Dec-19 17-Dec-19 C 31-Jan-19 4-Feb-19 B

R COMPOSITE
APARTEMEN
1 Denah composite armatur MEP lantai 1 GD. Apartemen 1.00 13-Feb-19 21-Feb-19 B
2 Denah parsial-1 composite armatur MEP lantai 1 GD. Apartemen 1.00 13-Feb-19 21-Feb-19 B
3 Denah parsial-2 composite armatur MEP lantai 1 GD. Apartemen 1.00 13-Feb-19 21-Feb-19 B
4 Denah composite armatur MEP lantai 2 GD. Apartemen 1.00 13-Feb-19 21-Feb-19 B
5 Denah parsial-1 composite armatur MEP lantai 2 GD. Apartemen 1.00 13-Feb-19 21-Feb-19 B
6 Denah parsial-2 composite armatur MEP lantai 2 GD. Apartemen 1.00 13-Feb-19 21-Feb-19 B

145.00 lembar
JUMLAH TANGGAL PENGAJUAN REVISI 1 REVISI 2 REVISI 3
NO JUDUL GAMBAR
LEMBAR MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS
GEDUNG ASRAMA
A AIR BERSIH
1 Diagram skematik air bersih GD.asrama 1.00 18-Mar-19 12-Apr-19 C 24-Apr-19 16-May-19 B
2 Denah Instalasi Air Bersih Panas & Dingin Lantai 1 Gedung ASRAMA 1.00 22-Jan-19 24-Jan-19 C 18-Mar-19 12-Apr-19 B
3 Detail Inst. Air Bersih Panas & Dingin Toilet 1 & 2 Lantai 1 Gedung ASRAMA 1.00 22-Jan-19 24-Jan-19 C 18-Mar-19 12-Apr-19 C 24-Apr-19 16-May-19 B
4 Detail Inst. Air Bersih Panas & Dingin Toilet 3 & 4 Lantai 1 Gedung ASRAMA 1.00 22-Jan-19 24-Jan-19 C 18-Mar-19 12-Apr-19 C 24-Apr-19 16-May-19 B
5 Detail Inst. Air Bersih Panas & Dingin Toilet 5 Lantai 1 Gedung ASRAMA 1.00 22-Jan-19 24-Jan-19 A
6 Isometri Inst. Air Bersih Panas & Dingin Toilet 1 & 2 Lantai 1 Gedung ASRAMA 1.00 22-Jan-19 24-Jan-19 C 18-Mar-19 12-Apr-19 B
7 Isometri Inst. Air Bersih Panas & Dingin Toilet 3 & 4 Lantai 1 Gedung ASRAMA 1.00 22-Jan-19 24-Jan-19 C 18-Mar-19 12-Apr-19 B
8 Isometri Inst. Air Bersih Panas & Dingin Toilet 5 Lantai 1 Gedung ASRAMA 1.00 22-Jan-19 24-Jan-19 A 18-Mar-19 12-Apr-19 B
9 Denah Instalasi Air Bersih Panas & Dingin Lantai 2 Gedung ASRAMA 1.00 22-Jan-19 24-Jan-19 C 18-Mar-19 12-Apr-19 B
10 Detail Inst. Air Bersih Panas & Dingin Toilet 1 & 2 Lantai 2 Gedung ASRAMA 1.00 22-Jan-19 24-Jan-19 C 18-Mar-19 12-Apr-19 C 24-Apr-19 16-May-19 B
11 Detail Inst. Air Bersih Panas & Dingin Toilet 3 & 4 Lantai 2 Gedung ASRAMA 1.00 22-Jan-19 24-Jan-19 C 18-Mar-19 12-Apr-19 B
12 Detail Inst. Air Bersih Panas & Dingin Toilet 5 Lantai 2 Gedung ASRAMA 1.00 22-Jan-19 24-Jan-19 C 18-Mar-19 12-Apr-19 B
13 Isometri Inst. Air Bersih Panas & Dingin Toilet 1 & 2 Lantai 2 Gedung ASRAMA 1.00 22-Jan-19 24-Jan-19 C 18-Mar-19 12-Apr-19 B
14 Isometri Inst. Air Bersih Panas & Dingin Toilet 3 & 4 Lantai 2 Gedung ASRAMA 1.00 22-Jan-19 24-Jan-19 C 18-Mar-19 12-Apr-19 B
15 Isometri Inst. Air Bersih Panas & Dingin Toilet 5 Lantai 2 Gedung ASRAMA 1.00 22-Jan-19 24-Jan-19 C 18-Mar-19 12-Apr-19 B
16 Denah inst. air bersih atap GD.asrama 1.00 18-Mar-19 12-Apr-19 C 24-Apr-19 16-May-19 B
17 Detail inst. air bersih atap GD.asrama 1.00 18-Mar-19 12-Apr-19 C 24-Apr-19 16-May-19 B
18 Diagram skematik rumah pompa dan GWT air bersih GD.asrama 1.00 18-Mar-19 12-Apr-19 C 24-Apr-19 16-May-19 B
19 Detail rumah pompa dan GWT air bersih GD.asrama 1.00 18-Mar-19 12-Apr-19 C 24-Apr-19 16-May-19 B
20 Potongan-A rumah pompa dan GWT air bersih GD.asrama 1.00 18-Mar-19 12-Apr-19 C 24-Apr-19 16-May-19 B
21 Potongan-B rumah pompa dan GWT air bersih GD.asrama 1.00 18-Mar-19 12-Apr-19 B 24-Apr-19 16-May-19 B
22 Potongan-C rumah pompa dan GWT air bersih GD.asrama 1.00 18-Mar-19 12-Apr-19 C 24-Apr-19 16-May-19 B
23 Diagram skematik booster pump air bersih GD.asrama 1.00 18-Mar-19 12-Apr-19 C 24-Apr-19 16-May-19 B
24 Detail toilet air bersih kamar GD.asrama 1.00 18-Mar-19 12-Apr-19 C 24-Apr-19 16-May-19 B
25 Detail toilet air bersih umum GD.asrama 1.00 18-Mar-19 12-Apr-19 C 24-Apr-19 16-May-19 B
26 Isometrik toilet air bersih kamar GD.asrama 1.00 18-Mar-19 12-Apr-19 C 24-Apr-19 16-May-19 B
27 Isometrik toilet air bersih umum GD.asrama 1.00 18-Mar-19 12-Apr-19 C 24-Apr-19 16-May-19 B

B AIR LIMBAH
1 Skematik Diagram Sistem Instalasi Air Limbah Gedung Asrama 1.00 20-Oct-18 26-Oct-18 A
2 Skematik Diagram Sistem Instalasi Air Limbah Parsial 1 Gedung Asrama 1.00 20-Oct-18 26-Oct-18 A
3 Skematik Diagram Sistem Instalasi Air Limbah Parsial 2 Gedung Asrama 1.00 20-Oct-18 26-Oct-18 A
4 Denah Instalasi Air Limbah Lantai 1 Gedung Asrama 1.00 20-Oct-18 26-Oct-18 B
5 Denah Instalasi Air Limbah Parsial 1 Lantai 1 Gedung Asrama 1.00 20-Oct-18 26-Oct-18 B
6 Denah Instalasi Air Limbah Parsial 2 Lantai 1 Gedung Asrama 1.00 20-Oct-18 26-Oct-18 B
7 Detail & Isometri Instalasi Air Limbah Area Toilet Lantai 1 Gedung Asrama 1.00 20-Oct-18 26-Oct-18 B
8 Denah Instalasi Air Limbah Lantai 2 Gedung Asrama 1.00 20-Oct-18 26-Oct-18 B
9 Denah Instalasi Air Limbah Parsial 1 Lantai 2 Gedung Asrama 1.00 20-Oct-18 26-Oct-18 B
10 Denah Instalasi Air Limbah Parsial 2 Lantai 2 Gedung Asrama 1.00 20-Oct-18 26-Oct-18 B
11 Detail & Isometri Instalasi Air Limbah Area Toilet Lantai 2 Gedung Asrama 1.00 20-Oct-18 26-Oct-18 B
12 Standar Detail 1 Pemasangan Instalasi Air Limbah Gedung Asrama 1.00 20-Oct-18 26-Oct-18 A
13 Standar Detail 2 & 3 Pemasangan Inst. Air Limbah Gedung Asrama 1.00 20-Oct-18 26-Oct-18 A
14 Standar Detail 4 Pemasangan Instalasi Air Limbah Gedung Asrama 1.00 20-Oct-18 26-Oct-18 B

C AIR HUJAN
1 Skematik Diagram Sistem Instalasi Air Hujan Gedung Asrama 1.00 7-Jan-19 15-Jan-19 C
2 Denah Instalasi Air Hujan Lantai 1 Gedung Asrama 1.00 7-Jan-19 15-Jan-19 C
3 Denah Instalasi Air Hujan Lantai 2 Gedung Asrama 1.00 7-Jan-19 15-Jan-19 B
4 Denah Instalasi Air Hujan Lantai Atap Gedung Asrama 1.00 7-Jan-19 15-Jan-19 C

D PEMADAM KEBAKARAN
1 Diagram skematik hydrant dan apar GD.asrama 1.00 25-Mar-19 5-Apr-19 B
2 Denah inst.hydrant dan apar lantai.1 GD.asrama 1.00 25-Mar-19 5-Apr-19 C 3-May-19 16-May-19 B
3 Denah inst.hydrant dan apar lantai.2 GD.asrama 1.00 25-Mar-19 5-Apr-19 C 3-May-19 16-May-19 B
4 Denah inst.hydrant dan apar lantai atap GD.asrama 1.00 25-Mar-19 5-Apr-19 B
5 Standar detail-1 hydrant dan apar GD.asrama 1.00 25-Mar-19 5-Apr-19 B
6 Standar detail-2 hydrant dan apar GD.asrama 1.00 25-Mar-19 5-Apr-19 B 3-May-19 16-May-19 B

E PENERANGAN
1 Denah Instalasi Penerangan Lantai 1 Gedung Asrama 1.00 15-Dec-18 18-Dec-18 B
2 Denah Parsial Instalasi Penerangan Zona 1 Lantai 1 Gedung Asrama 1.00 15-Dec-18 18-Dec-18 B
3 Denah Parsial Instalasi Penerangan Zona 2 Lantai 1 Gedung Asrama 1.00 15-Dec-18 18-Dec-18 B
4 Denah Instalasi Penerangan Lantai 2 Gedung Asrama 1.00 15-Dec-18 18-Dec-18 B
5 Denah Parsial Instalasi Penerangan Zona 1 Lantai 2 Gedung Asrama 1.00 15-Dec-18 18-Dec-18 B
6 Denah Parsial Instalasi Penerangan Zona 2 Lantai 2 Gedung Asrama 1.00 15-Dec-18 18-Dec-18 B
JUMLAH TANGGAL PENGAJUAN REVISI 1 REVISI 2 REVISI 3
NO JUDUL GAMBAR
LEMBAR MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS

F STOP KONTAK
1 Denah Instalasi Stop Kontak Lantai 1 Gedung Asrama 1.00 15-Dec-18 18-Dec-18 B
2 Denah Parsial Instalasi Stop Kontak Zona 1 Lantai 1 Gedung Asrama 1.00 15-Dec-18 18-Dec-18 B
3 Denah Parsial Instalasi Stop Kontak Zona 2 Lantai 1 Gedung Asrama 1.00 15-Dec-18 18-Dec-18 B
4 Denah Instalasi Stop Kontak Lantai 2 Gedung Asrama 1.00 15-Dec-18 18-Dec-18 B
5 Denah Parsial Instalasi Stop Kontak Zona 1 Lantai 2 Gedung Asrama 1.00 15-Dec-18 18-Dec-18 B
6 Denah Parsial Instalasi Stop Kontak Zona 2 Lantai 2 Gedung Asrama 1.00 15-Dec-18 18-Dec-18 B

G DISTRIBUSI LISTRIK
1 Diagram skematik distribusi listrik GD.asrama 1.00 12-Apr-19 24-Apr-19 B
2 Denah jalur kabel feeder dari power house ke GD.asrama 1.00 12-Apr-19 24-Apr-19 B
3 Denah distribusi listrik lantai 1 GD.asrama 1.00 12-Apr-19 24-Apr-19 B
4 Denah distribusi listrik lantai 2 GD.asrama 1.00 12-Apr-19 24-Apr-19 B
5 Denah tray kabel lantai 1 GD.asrama 1.00 12-Apr-19 24-Apr-19 B
6 Denah tray kabel lantai 2 GD.asrama 1.00 12-Apr-19 24-Apr-19 B
7 Standar-1 detail tray kabel GD.asrama 1.00 12-Apr-19 24-Apr-19 B
8 Standar-2 detail tray kabel GD.asrama 1.00 12-Apr-19 24-Apr-19 A
9 Standar-3 detail tray kabel GD.asrama 1.00 12-Apr-19 24-Apr-19 A
10 Standar-4 detail tray kabel GD.asrama 1.00 12-Apr-19 24-Apr-19 A

H GROUNDING
1 Denah instalasi grounding GD.asrama 1.00 15-Apr-19 4-May-19 B

I SKEDUL BEBAN LISTRIK


1 Wirring Diagram Sub Distribusi Panel Gedung Asrama 1.00 15-Dec-18 18-Dec-18 A
2 Wirring Diagram Power Panel Lantai 1 Gedung Asrama 1.00 15-Dec-18 18-Dec-18 A
3 Wirring Diagram Power Panel Lantai 2 Gedung Asrama 1.00 15-Dec-18 18-Dec-18 A
4 Wirring Diagram SDP Pompa & Box Switch Kamar Gedung Asrama 1.00 15-Dec-18 18-Dec-18 A

J SOUND SYSTEM
1 Skematik Diagram Sistem Instalasi Tata Suara Gedung Asrama 1.00 24-Dec-18 27-Dec-18 A
2 Denah Instalasi Tata Suara Lantai 1 Gedung Asrama 1.00 24-Dec-18 27-Dec-18 B
3 Denah Instalasi Tata Suara Lantai 2 Gedung Asrama 1.00 24-Dec-18 27-Dec-18 B
4 Standar Detail Pemasangan Instalasi Tata Suara Gedung Asrama 1.00 24-Dec-18 27-Dec-18 A

K FIRE ALARM
1 Skematik Diagram Sistem Instalasi Fire Alarm Gedung Asrama 1.00 24-Dec-18 27-Dec-18 C
2 Denah Instalasi Fire Alarm Lantai 1 Gedung Asrama 1.00 24-Dec-18 27-Dec-18 C
3 Denah Instalasi Fire Alarm Lantai 2 Gedung Asrama 1.00 24-Dec-18 27-Dec-18 C
4 Standar Detail Pemasangan Instalasi Fire Alarm Gedung Asrama 1.00 24-Dec-18 27-Dec-18 A

L DATA & WIFI


1 Skematik Diagram Sistem Instalasi Data & Wifi Gedung Asrama 1.00 24-Dec-18 27-Dec-18 A
2 Denah Instalasi Data & Wifi Lantai 1 Gedung Asrama 1.00 24-Dec-18 27-Dec-18 C 7-Jan-19 10-Jan-19 B
3 Denah Instalasi Data & Wifi Lantai 2 Gedung Asrama 1.00 24-Dec-18 27-Dec-18 C 7-Jan-19 10-Jan-19 B
4 Standar Detail Pemasangan Instalasi Data & Wifi Gedung Asrama 1.00 24-Dec-18 27-Dec-18 A

M TELEPON
1 Skematik Diagram Sistem Instalasi Telephone Gedung Asrama 1.00 24-Dec-18 27-Dec-18 B
2 Denah Instalasi Telephone Lantai 1 Gedung Asrama 1.00 24-Dec-18 27-Dec-18 C 7-Jan-19 10-Jan-19 B
3 Denah Instalasi Telephone Lantai 2 Gedung Asrama 1.00 24-Dec-18 27-Dec-18 C 7-Jan-19 10-Jan-19 B
4 Standar Detail Pemasangan Instalasi Telephone Gedung Asrama 1.00 24-Dec-18 27-Dec-18 A

N MATV
1 Skematik Diagram Sistem Instalasi MATV Gedung Asrama 1.00 24-Dec-18 28-Dec-18 C
2 Denah Instalasi MATV Lantai 1 Gedung Asrama 1.00 24-Dec-18 28-Dec-18 B
3 Denah Instalasi MATV Lantai 2 Gedung Asrama 1.00 24-Dec-18 28-Dec-18 B

O CCTV
1 Skematik Diagram Sistem Instalasi CCTV Gedung Asrama 1.00 24-Dec-18 28-Dec-18 C
2 Denah Instalasi CCTV Lantai 1 Gedung Asrama 1.00 24-Dec-18 28-Dec-18 B
3 Denah Instalasi CCTV Lantai 2 Gedung Asrama 1.00 24-Dec-18 28-Dec-18 B

P TATA UDARA
1 Denah Instalasi Ventilasi Mekanik Lantai 1 Gedung Asrama 1.00 24-Dec-18 28-Dec-18 B
2 Denah Instalasi Ventilasi Mekanik Lantai 2 Gedung Asrama 1.00 24-Dec-18 28-Dec-18 B
3 Denah Instalasi Tata Udara Lantai 1 Gedung Asrama 1.00 24-Dec-18 28-Dec-18 C 2-Apr-19 12-Apr-19 B 25-Apr-19 8-May-19 B
JUMLAH TANGGAL PENGAJUAN REVISI 1 REVISI 2 REVISI 3
NO JUDUL GAMBAR
LEMBAR MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS
4 Denah Instalasi Tata Udara Lantai 2 Gedung Asrama 1.00 24-Dec-18 28-Dec-18 B 2-Apr-19 12-Apr-19 B 25-Apr-19 8-May-19 B
5 Potongan A tata letak outdoor AC GD.asrama 1.00 2-Apr-19 12-Apr-19 B 25-Apr-19 8-May-19 B
6 Denah & potongan-B tata letak outdoor AC lantai atap GD.asrama 1.00 25-Apr-19 8-May-19 B

Q COMPOSITE
1 Denah composite armatur MEP lantai 1 GD. Asrama 1.00 19-Feb-19 23-Feb-19 C 14-Mar-19 12-Apr-19 B
2 Denah parsial-1 composite armatur MEP lantai 1 GD. Asrama 1.00 19-Feb-19 23-Feb-19 C 14-Mar-19 12-Apr-19 B
3 Denah parsial-2 composite armatur MEP lantai 1 GD. Asrama 1.00 19-Feb-19 23-Feb-19 C 14-Mar-19 12-Apr-19 B
4 Denah composite armatur MEP lantai 2 GD. Asrama 1.00 19-Feb-19 23-Feb-19 C 14-Mar-19 12-Apr-19 B
5 Denah parsial-1 composite armatur MEP lantai 2 GD. Asrama 1.00 19-Feb-19 23-Feb-19 C 14-Mar-19 12-Apr-19 B
6 Denah parsial-2 composite armatur MEP lantai 2 GD. Asrama 1.00 19-Feb-19 23-Feb-19 C 14-Mar-19 12-Apr-19 B

112.00 lembar
MONITORING SHOP DRAWING MEP GEDUNG INFRASTRUKTUR
JUMLAH TANGGAL PENGAJUAN REVISI 1 REVISI 2 REVISI 3 REVISI 4
NO JUDUL GAMBAR
LEMBAR MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS
GEDUNG INFRASTRUKTUR
A DISTRIBUSI LISTRIK KAWASAN & POWER HOUSE
1 Denah lokasi power house & titik tiang PLN 1.00 10-Sep-18 13-Sep-18 C 4-Apr-19 9-Apr-19 B
2 Denah & Peralatan Power House 1.00 10-Sep-18 13-Sep-18 C 1-Dec-18 4-Dec-18 C 14-Jan-19 18-Jan-19 C 4-Apr-19 9-Apr-19 B
3 Detail potongan dan Skematik Diagram Sistem Distribusi BBM Genset 1.00 10-Sep-18 13-Sep-18 C 1-Dec-18 4-Dec-18 C 14-Jan-19 18-Jan-19 C 4-Apr-19 9-Apr-19 B
4 Tampak samping & tampak belakang instalasi genset 1.00 4-Apr-19 9-May-19 B
5 Denah instalasi pipa BBM,pipa gas buang genset & distribusi listrik 1.00 10-Sep-18 13-Sep-18 C 1-Dec-18 4-Dec-18 C 14-Jan-19 18-Jan-19 C 4-Apr-19 9-Apr-19 B
power house infrastruktur
6 Denah instalasi busduct power house 1.00 19-Jun-19
CANCEL
7 Potongan instalasi busduct power house 1.00 19-Jun-19
8 Denah instalasi grounding power house 1.00 10-Sep-18 13-Sep-18 C 1-Dec-18 4-Dec-18 C 14-Jan-19 18-Jan-19 C 4-Apr-19 9-Apr-19 B
9 Denah instalasi penerangan, stop kontak, AC & ventilasi mekanik bangunan infrastruktur 1.00 10-Sep-18 13-Sep-18 C 1-Dec-18 4-Dec-18 C 14-Jan-19 18-Jan-19 C 4-Apr-19 9-Apr-19 C 4-May-19 8-May-19 B
10 Detail Tangki Bulanan BBM Genset 1.00 10-Sep-18 13-Sep-18 C 4-Apr-19 9-Apr-19 B
11 Isometrik sistem bahan bakar 1.00 4-Apr-19 9-Apr-19 B
12 Detail tangki harian BBM genset 2000 liter 1.00 4-Apr-19 9-Apr-19 B
13 Standar detail instalasi genset 1.00 4-Apr-19 9-Apr-19 B
14 Denah Posisi KWH Meter Sementara 1.00 13-Sep-18 17-Sep-18 B

B AIR LIMBAH
1 Skematik Diagram Sistem Instalasi Air Limbah Kawasan Infrastruktur 1.00 8-Oct-18 11-Oct-18 C 15-Oct-18 18-Oct-18 C 22-Feb-19 25-Feb-19 C
2 Denah Instalasi Air Limbah Kawasan Infrastruktur 1.00 8-Oct-18 11-Oct-18 C 15-Oct-18 18-Oct-18 C 22-Feb-19 25-Feb-19 B
3 Denah Parsial 1 Instalasi Air Limbah Kawasan Infrastruktur 1.00 8-Oct-18 11-Oct-18 C 15-Oct-18 18-Oct-18 C 22-Feb-19 25-Feb-19 B
4 Denah Parsial 2 Instalasi Air Limbah Kawasan Infrastruktur 1.00 8-Oct-18 11-Oct-18 C 15-Oct-18 18-Oct-18 B 22-Feb-19 25-Feb-19 B
5 Detail Bak Kontrol & Elevasi Instalasi Air Limbak Kawasan 1.00 22-Feb-19 25-Feb-19 C

C PEMADAM KEBAKARAN
1 Skematik Diagram Sistem Instalasi Pemadam Kebakaran Kawasan Infrastruktur 1.00 8-Oct-18 11-Oct-18 C 15-Oct-18 18-Oct-18 C 20-Dec-18 27-Dec-18 C 4-May-19 16-May-19 C
2 Denah Instalasi Pemadam Kebakaran Kawasan Infrastruktur 1.00 8-Oct-18 11-Oct-18 C 15-Oct-18 18-Oct-18 C 20-Dec-18 27-Dec-18 C 4-May-19 16-May-19 B
3 Denah Parsial 1 Instalasi Pemadam Kebakaran Kawasan Infrastruktur 1.00 8-Oct-18 11-Oct-18 C 15-Oct-18 18-Oct-18 C 20-Dec-18 27-Dec-18 C 4-May-19 16-May-19 B
4 Denah Parsial 2 Instalasi Pemadam Kebakaran Kawasan Infrastruktur 1.00 8-Oct-18 11-Oct-18 C 15-Oct-18 18-Oct-18 C 20-Dec-18 27-Dec-18 B 4-May-19 16-May-19 B
5 Denah Parsial 3 Instalasi Pemadam Kebakaran Kawasan Infrastruktur 1.00 8-Oct-18 11-Oct-18 C 15-Oct-18 18-Oct-18 C 20-Dec-18 27-Dec-18 C 4-May-19 16-May-19 B
6 Denah Parsial 4 Instalasi Pemadam Kebakaran Kawasan Infrastruktur 1.00 8-Oct-18 11-Oct-18 C 15-Oct-18 18-Oct-18 C 20-Dec-18 27-Dec-18 B 4-May-19 16-May-19 B
7 Skematik Diagram Sistem Instalasi Pemadam Kebakaran Rumah Pompa Infrastruktur 1.00 8-Oct-18 11-Oct-18 C 15-Oct-18 18-Oct-18 C 20-Dec-18 27-Dec-18 C 4-May-19 16-May-19 C
8 Standar Detail 1 Pemasangan Instalasi Pemadam Kebakaran Kawasan Infrastruktur 1.00 8-Oct-18 11-Oct-18 A
9 Standar Detail 2 Pemasangan Instalasi Pemadam Kebakaran Kawasan Infrastruktur 1.00 8-Oct-18 11-Oct-18 A
10 Standar Detail 3 Pemasangan Instalasi Pemadam Kebakaran Kawasan Infrastruktur 1.00 8-Oct-18 11-Oct-18 A

D AIR BERSIH
1 Skematik Diagram Sistem & Denah Instalasi Air Bersih Kawasan Infrastruktur 1.00 20-Oct-18 26-Oct-18 C
2 Detail Potongan GWT & Ruang Pompa 1 Instalasi Air Bersih Kawasan Infrastruktur 1.00 20-Oct-18 26-Oct-18 C
3 Detail Potongan GWT & Ruang Pompa 2 Instalasi Air Bersih Kawasan Infrastruktur 1.00 20-Oct-18 26-Oct-18 C
4 Denah Instalasi Air Bersih Kawasan Insfrastruktur 1.00 20-Oct-18 26-Oct-18 C
5 Denah Parsial 1 Instalasi Air Bersih Kawasan Infrastruktur 1.00 20-Oct-18 26-Oct-18 C
6 Denah Parsial 2 Instalasi Air Bersih Kawasan Infrastruktur 1.00 20-Oct-18 26-Oct-18 C

E GAS MEDIS
1 Denah Instalasi Gas Medis Kawasan Infrastruktur 1.00 27-Mar-19 5-Apr-19 C 9-Apr-19 12-Apr-19 B
2 Potongan-A instalasi gas medis infrastruktur 1.00 9-Apr-19 12-Apr-19 B
3 Detail Bangunan Sentral Gas Medis Kawasan Infrastruktur 1.00 27-Mar-19 5-Apr-19 C 9-Apr-19 12-Apr-19 B

F PENERANGAN
1 Denah Instalasi Penerangan Kawasan Infrastruktur 1.00 18-Feb-19 26-Feb-19 C 1-Mar-19 25-Mar-19 B 26-Apr-19 8-May-19 C 14-May-19 24-May-19 C 13-Jun-19 MK
2 Detail Pemasangan Penerangan Kawasan Infrastruktur 1.00
3 Wiring Diagram Panel Power Penerangan Kawasan Infrastruktur 1.00
4 Denah instalasi penerangan doorlop 1.00 8-Apr-19 12-Apr-19 B

G SKEDUL BEBAN LISTRIK


1 Diagram Single Line Sistem Listrik Kawasan 1.00
2 Skedul Beban Listrik Seluruh Kawasan Rumah Sakit LVMDB 8.00 25-Apr-19 8-May-19 C 8-May-19 MK
3 Skedul Beban Listrik PP. PH & SDP. Pompa 1.00
4 Skedul Beban Listrik PP. Hydrant & PP. Gas Medis 1.00

53.00 lembar
JUMLAH TANGGAL PENGAJUAN REVISI 1 REVISI 2 REVISI 3 REVISI 4
NO JUDUL GAMBAR
LEMBAR MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS
MONITORING SHOP DRAWING MEP GEDUNG IRNA
JUMLAH TANGGAL PENGAJUAN REVISI 1 REVISI 2 REVISI 3
NO JUDUL GAMBAR
LEMBAR MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS
GEDUNG IRNA
A AIR LIMBAH
1 Skematik Diagram Sistem Inst. Air Limbah Gedung IRNA 1.00 27-Sep-18 3-Oct-18 A
2 Skematik Diagram Sistem Inst. Air Limbah Parsial 1 Gedung IRNA 1.00 27-Sep-18 3-Oct-18 A
3 Skematik Diagram Sistem Inst. Air Limbah Parsial 2 Gedung IRNA 1.00 27-Sep-18 3-Oct-18 A
4 Denah Inst. Air Kotor, Bekas & Vent site plan gedung IRNA 1.00 27-Sep-18 3-Oct-18 C INFRA
5 Denah inst. air kotor, bekas & vent site plan parsial 1 gedung IRNA 1.00 27-Sep-18 3-Oct-18 C INFRA
6 Denah Inst. Air Kotor, Bekas & Vent Site Plan parsial 2 gedung IRNA 1.00 27-Sep-18 3-Oct-18 C INFRA
7 Denah Inst. Air Kotor, Bekas & Vent Basement Gedung IRNA 1.00 27-Sep-18 3-Oct-18 C 9-Oct-18 12-Oct-18 B 2-Apr-19 12-Apr-19 B
8 Denah Inst. Air Kotor, Bekas & Vent Basement Parsial 1 Gedung IRNA 1.00 27-Sep-18 3-Oct-18 C 9-Oct-18 10-Dec-18 B 2-Apr-19 12-Apr-19 B
9 Denah Inst. Air Kotor, Bekas & Vent Basement Parsial 2 Gedung IRNA 1.00 27-Sep-18 3-Oct-18 C 9-Oct-18 10-Dec-18 B 2-Apr-19 12-Apr-19 B
10 Denah Inst. Air Kotor, Bekas & Vent Basement Parsial 3 Gedung IRNA 1.00 27-Sep-18 3-Oct-18 C 9-Oct-18 10-Dec-18 B 2-Apr-19 12-Apr-19 B
11 Denah Inst. air kotor, bekas & vent lantai 1 gedung IRNA 1.00 27-Sep-18 3-Oct-18 C 10-Oct-18 15-Oct-18 B
12 Denah Inst. Air Kotor, Bekas & Vent Lantai 1 Parsial 1 Gedung IRNA 1.00 27-Sep-18 3-Oct-18 C 10-Oct-18 15-Oct-18 B
13 Denah Inst. Air Kotor, Bekas & Vent Lantai 1 parsial 2 gedung IRNA 1.00 27-Sep-18 3-Oct-18 C 10-Oct-18 15-Oct-18 B
14 Denah inst. air kotor, bekas & vent lantai 1 parsial 3 gedung IRNA 1.00 27-Sep-18 3-Oct-18 C 10-Oct-18 15-Oct-18 B
15 Denah Inst. air kotor, bekas & vent lantai 2 gedung IRNA 1.00 27-Sep-18 3-Oct-18 C 10-Oct-18 15-Oct-18 B
16 Denah Inst. Air Kotor, Bekas & Vent Lantai 2 Parsial 1 Gedung IRNA 1.00 27-Sep-18 3-Oct-18 C 10-Oct-18 15-Oct-18 B
17 Denah Inst. Air Kotor, Bekas & Vent Lantai 2 Parsial 2 Gedung IRNA 1.00 27-Sep-18 3-Oct-18 C 10-Oct-18 15-Oct-18 B
18 Denah Inst. Air Kotor, Bekas & Vent Lantai 2 Parsial 3 Gedung IRNA 1.00 27-Sep-18 3-Oct-18 C 10-Oct-18 15-Oct-18 B
19 Denah Inst. Air Kotor, Bekas & Vent Lantai 3 Gedung IRNA 1.00 27-Sep-18 3-Oct-18 C 11-Oct-18 15-Oct-18 B
20 Denah Inst. Air Kotor, Bekas & Vent Lantai 3 Parsial 1 Gedung IRNA 1.00 27-Sep-18 3-Oct-18 C 11-Oct-18 15-Oct-18 B
21 Denah Inst. Air Kotor, Bekas & Vent Lantai 3 Parsial 2 Gedung IRNA 1.00 27-Sep-18 3-Oct-18 C 11-Oct-18 15-Oct-18 B
22 Denah Inst. Air Kotor, Bekas & Vent Lantai 3 Parsial 3 Gedung IRNA 1.00 27-Sep-18 3-Oct-18 C 11-Oct-18 15-Oct-18 B
23 Denah Inst. Air Kotor, Bekas & Vent Lantai 4 Gedung IRNA 1.00 27-Sep-18 3-Oct-18 C 11-Oct-18 15-Oct-18 B
24 Detail Instalasi Air Kotor, Bekas & Vent Toilet IRNA 1 & 2 Lantai 1 1.00 27-Sep-18 3-Oct-18 C 11-Oct-18 15-Oct-18
Gedung IRNA
25 Isometri Instalasi Air Kotor, Bekas & Vent Toilet IRNA 1 & 2 Lantai 1 1.00 27-Sep-18 3-Oct-18 C 11-Oct-18 15-Oct-18 B
Gedung IRNA
26 Detail Instalasi Air Kotor, Bekas & Vent Toilet IRNA 3 & 4 Lantai 1 1.00 27-Sep-18 3-Oct-18 C 11-Oct-18 15-Oct-18 B
Gedung IRNA
27 Isometri Instalasi Air Kotor, Bekas & Vent Toilet IRNA 3 & 4 Lantai 1 1.00 27-Sep-18 3-Oct-18 A
Gedung IRNA
28 Detail Instalasi Air Kotor, Bekas & Vent Toilet IRNA 2 & 3 Lantai 2 1.00 27-Sep-18 3-Oct-18 C 11-Oct-18 15-Oct-18 B
Gedung IRNA
29 Isometri Instalasi Air Kotor, Bekas & Vent Toilet IRNA 2 & 3 Lantai 2 1.00 27-Sep-18 3-Oct-18 A
Gedung IRNA
30 Detail & Isometri Inst. Air Kotor, Bekas & Vent Toilet IRNA 4 Lantai 2 1.00 27-Sep-18 3-Oct-18 B
Gedung IRNA
31 Detail Instalasi Air Kotor, Bekas & Vent Toilet IRNA 5 & 6 Lantai 3 1.00 27-Sep-18 3-Oct-18 C 11-Oct-18 15-Oct-18 B
Gedung IRNA
32 Isometri Instalasi Air Kotor, Bekas & Vent Toilet IRNA 5 & 6 Lantai 3 1.00 27-Sep-18 3-Oct-18 C 11-Oct-18 15-Oct-18 B
Gedung IRNA
33 Detail Instalasi Air Kotor, Bekas & Vent Toilet Umum Gedung IRNA 1.00 27-Sep-18 3-Oct-18 C 11-Oct-18 15-Oct-18 B
34 Isometri Instalasi Air Kotor, Bekas & Vent Toilet Umum Gedung IRNA 1.00 27-Sep-18 3-Oct-18 C 11-Oct-18 15-Oct-18 B
35 Standar Detail 1 Pemasangan Inst. Air Limbah Gedung IRNA 1.00 27-Sep-18 3-Oct-18 A
36 Standar Detail 2 Pemasangan Inst. Air Limbah Gedung IRNA 1.00 27-Sep-18 3-Oct-18 A

B AIR BERSIH
1 Diagram Skematik Air Bersih GD. IRNA 1.00 16-Oct-18 20-Oct-18 B
2 Diagram Skematik Air Bersih Parsial-1 GD. IRNA 1.00 16-Oct-18 20-Oct-18 B
3 Diagram Skematik Air Bersih Parsial-2 GD. IRNA 1.00 16-Oct-18 20-Oct-18 B
4 Diagram Skematik Air Panas GD. IRNA 1.00 16-Oct-18 20-Oct-18 C 18-Mar-19 12-Apr-19 B
5 Diagram Skematik Air Panas Parsial-1 GD. IRNA 1.00 16-Oct-18 20-Oct-18 C 18-Mar-19 12-Apr-19 B
6 Diagram Skematik Air Panas Parsial-2 GD. IRNA 1.00 16-Oct-18 20-Oct-18 C 18-Mar-19 12-Apr-19 B
7 Denah Inst. Air Bersih & Panas Lantai Basement GD. IRNA 1.00 16-Oct-18 20-Oct-18 C 18-Mar-19 12-Apr-19 B
8 Denah Inst. Air Bersih & Panas Zona-1 Lantai Basement GD. IRNA 1.00 16-Oct-18 20-Oct-18 C 18-Mar-19 12-Apr-19 B
9 Denah Inst. Air Bersih & Panas Zona-2 Lantai Basement GD. IRNA 1.00 16-Oct-18 20-Oct-18 B
10 Denah Inst. Air Bersih & Panas Zona-3 Lantai Basement GD. IRNA 1.00 16-Oct-18 20-Oct-18 C 18-Mar-19 12-Apr-19 B
11 Denah Inst. Air Bersih & Panas Lantai .1 GD. IRNA 1.00 16-Oct-18 20-Oct-18 B
12 Denah Inst. Air Bersih & Panas Zona-1 Lantai .1 GD. IRNA 1.00 16-Oct-18 20-Oct-18 B
13 Denah Inst. Air Bersih & Panas Zona-2 Lantai .1 GD. IRNA 1.00 16-Oct-18 20-Oct-18 B
14 Denah Inst. Air Bersih & Panas Zona-3 Lantai .1 GD. IRNA 1.00 16-Oct-18 20-Oct-18 B
15 Denah Inst. Air Bersih & Panas Lantai .2 GD. IRNA 1.00 16-Oct-18 20-Oct-18 B
16 Denah Inst. Air Bersih & Panas Zona-1 Lantai .2 GD. IRNA 1.00 16-Oct-18 20-Oct-18 B
17 Denah Inst. Air Bersih & Panas Zona-2 Lantai .2 GD. IRNA 1.00 16-Oct-18 20-Oct-18 B
18 Denah Inst. Air Bersih & Panas Zona-3 Lantai .2 GD. IRNA 1.00 16-Oct-18 20-Oct-18 B
19 Denah Inst. Air Bersih & Panas Lantai .3 GD. IRNA 1.00 16-Oct-18 20-Oct-18 B
20 Denah Inst. Air Bersih & Panas Zona-1 Lantai .3 GD. IRNA 1.00 16-Oct-18 20-Oct-18 B
21 Denah Inst. Air Bersih & Panas Zona-2 Lantai .3 GD. IRNA 1.00 16-Oct-18 20-Oct-18 B
22 Denah Inst. Air Bersih & Panas Zona-3 Lantai .3 GD. IRNA 1.00 16-Oct-18 20-Oct-18 B
23 Denah Inst. Air Bersih & Panas Lantai .4 GD. IRNA 1.00 16-Oct-18 20-Oct-18 B
24 Detail Roof Tank Air Bersih Zona 1 & 3 (Typical) GD. IRNA 1.00 16-Oct-18 20-Oct-18 B
25 Detail Roof Tank Air Bersih Zona 2 GD. IRNA 1.00 16-Oct-18 20-Oct-18 C 18-Mar-19 12-Apr-19 C
26 Diagram Skematik Sentral Pemanas Air Zona 2 GD. IRNA 1.00 16-Oct-18 20-Oct-18 C 18-Mar-19 12-Apr-19 B
27 Detail Inst. Air Bersih Toilet Umum GD. IRNA 1.00 16-Oct-18 20-Oct-18 B
28 Detail Inst. Air Bersih Toilet Kelas-1,VIP,VVIP GD. IRNA 1.00 16-Oct-18 20-Oct-18 B
29 Isometrik Inst. Air Bersih Toilet Umum GD. IRNA 1.00 16-Oct-18 20-Oct-18 A
30 Isometrik Inst. Air Bersih Toilet Kelas-1,VIP GD. IRNA 1.00 16-Oct-18 20-Oct-18 A
31 Isometrik Inst. Air Bersih Toilet VVIP GD. IRNA 1.00 16-Oct-18 20-Oct-18 A

C PEMADAM KEBAKARAN
1 Diagram skematik hydrant & sprinkler GD. IRNA 1.00 7-Jan-19 17-Jan-19 C 16-Feb-19 26-Feb-19 B
2 Denah inst. hydrant & sprinkler site plan GD. IRNA 1.00 7-Jan-19 17-Jan-19 C
3 Denah inst. hydrant & sprinkler lantai basement GD. IRNA 1.00 7-Jan-19 17-Jan-19 C 16-Feb-19 26-Feb-19 B
4 Denah parsial-1 inst. hydrant & sprinkler lantai basement GD. IRNA 1.00 7-Jan-19 17-Jan-19 C 16-Feb-19 26-Feb-19 B
5 Denah parsial-2 inst. hydrant & sprinkler lantai basement GD. IRNA 1.00 7-Jan-19 17-Jan-19 C 16-Feb-19 26-Feb-19 B
6 Denah inst. hydrant & sprinkler lantai 1 kelas 1 GD. IRNA 1.00 7-Jan-19 17-Jan-19 C 16-Feb-19 26-Feb-19 B
7 Denah parsial-1 inst. hydrant & sprinkler lantai 1 kelas 1 GD. IRNA 1.00 7-Jan-19 17-Jan-19 C 16-Feb-19 26-Feb-19 B
8 Denah parsial-2 inst. hydrant & sprinkler lantai 1 kelas 1 GD. IRNA 1.00 7-Jan-19 17-Jan-19 C 16-Feb-19 26-Feb-19 B
9 Denah inst. hydrant & sprinkler lantai 2 kelas VIP GD. IRNA 1.00 7-Jan-19 17-Jan-19 C 16-Feb-19 26-Feb-19 B
10 Denah parsial-1 inst. hydrant & sprinkler lantai 2 kelas VIP GD. IRNA 1.00 7-Jan-19 17-Jan-19 C 16-Feb-19 26-Feb-19 B
11 Denah parsial-2 inst. hydrant & sprinkler lantai 2 kelas VIP GD. IRNA 1.00 7-Jan-19 17-Jan-19 C 16-Feb-19 26-Feb-19 B
12 Denah inst. hydrant & sprinkler lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 7-Jan-19 17-Jan-19 C 16-Feb-19 26-Feb-19 B
13 Denah parsial-1 inst. hydrant & sprinkler lantai 3 kelas VVIP dan VIP 1.00 7-Jan-19 17-Jan-19 C 16-Feb-19 26-Feb-19 B
GD. IRNA
14 Denah parsial-2 inst. hydrant & sprinkler lantai 3 kelas VVIP dan VIP 1.00 7-Jan-19 17-Jan-19 C 16-Feb-19 26-Feb-19 B
GD. IRNA
15 Standar detail hydrant & sprinkler 1 GD. IRNA 1.00 7-Jan-19 17-Jan-19 A
16 Standar detail hydrant & sprinkler 1A GD. IRNA 1.00 7-Jan-19 17-Jan-19 C
17 Standar detail hydrant & sprinkler 1B GD. IRNA 1.00 7-Jan-19 17-Jan-19 A
18 Standar detail hydrant & sprinkler 1C GD. IRNA 1.00 7-Jan-19 17-Jan-19 A
19 Standar detail hydrant & sprinkler 1D GD. IRNA 1.00 7-Jan-19 17-Jan-19 A
20 Standar detail hydrant & sprinkler 2 GD. IRNA 1.00 7-Jan-19 17-Jan-19 A
21 Standar detail hydrant & sprinkler 2A GD. IRNA 1.00 7-Jan-19 17-Jan-19 A
22 Standar detail hydrant & sprinkler 3 GD. IRNA 1.00 7-Jan-19 17-Jan-19 A
23 Standar detail hydrant & sprinkler 3A GD. IRNA 1.00 7-Jan-19 17-Jan-19 A

D AIR HUJAN
1 Diagram skematik air hujan GD. IRNA 1.00 6-Dec-18 17-Dec-18 C 4-Mar-19 12-Apr-19 C 16-Apr-19 8-May-19 B
2 Denah inst. Saluran air hujan lantai basement GD. IRNA 1.00 6-Dec-18 17-Dec-18 C 4-Mar-19 12-Apr-19 C 28-Mar-19 9-May-19 C 16-Apr-19 8-May-19 C
3 Denah parsial-1 inst. Saluran air hujan lantai basement GD. IRNA 1.00 6-Dec-18 17-Dec-18 C 4-Mar-19 12-Apr-19 C 28-Mar-19 9-May-19 C 16-Apr-19 8-May-19 C
4 Denah parsial-2 inst. Saluran air hujan lantai basement GD. IRNA 1.00 6-Dec-18 17-Dec-18 C 4-Mar-19 12-Apr-19 C 28-Mar-19 9-May-19 C 16-Apr-19 8-May-19 C
5 Denah inst. Saluran air hujan lantai 1 GD. IRNA 1.00 6-Dec-18 17-Dec-18 C 4-Mar-19 12-Apr-19 B 16-Apr-19 8-May-19 B
6 Denah parsial-1 inst. Saluran air hujan lantai 1 GD. IRNA 1.00 6-Dec-18 17-Dec-18 C 4-Mar-19 12-Apr-19 B 16-Apr-19 8-May-19 B
7 Denah parsial-2 inst. Saluran air hujan lantai 1 GD. IRNA 1.00 6-Dec-18 17-Dec-18 C 4-Mar-19 12-Apr-19 B 16-Apr-19 8-May-19 B
8 Denah inst. Saluran air hujan lantai 2 GD. IRNA 1.00 6-Dec-18 17-Dec-18 B 28-Mar-19 9-May-19 B
9 Denah parsial-1 inst. Saluran air hujan lantai 2 GD. IRNA 1.00 6-Dec-18 17-Dec-18 B 28-Mar-19 9-May-19 B
10 Denah parsial-2 inst. Saluran air hujan lantai 2 GD. IRNA 1.00 6-Dec-18 17-Dec-18 B 28-Mar-19 9-May-19 B
11 Denah inst. Saluran air hujan lantai 3 GD. IRNA 1.00 6-Dec-18 17-Dec-18 B 28-Mar-19 9-May-19 B
12 Denah parsial-1 inst. Saluran air hujan lantai 3 GD. IRNA 1.00 6-Dec-18 17-Dec-18 B 28-Mar-19 9-May-19 B
13 Denah parsial-2 inst. Saluran air hujan lantai 3 GD. IRNA 1.00 6-Dec-18 17-Dec-18 B 28-Mar-19 9-May-19 B
14 Denah inst. Saluran air hujan lantai 4 dan maintenance lift GD. IRNA 1.00 6-Dec-18 17-Dec-18 C 4-Mar-19 12-Apr-19 B 16-Apr-19 8-May-19 B
15 Denah parsial-1 inst. Saluran air hujan lantai 4 dan maintenance lift 1.00 6-Dec-18 17-Dec-18 C 4-Mar-19 12-Apr-19 B 16-Apr-19 8-May-19 B
GD. IRNA
16 Denah parsial-2 inst. Saluran air hujan lantai 4 dan maintenance lift 1.00 6-Dec-18 17-Dec-18 C 4-Mar-19 12-Apr-19 B 16-Apr-19 8-May-19 B
GD. IRNA
17 Denah inst. Saluran air hujan lantai atap dan helipad GD. IRNA 1.00 6-Dec-18 17-Dec-18 C 4-Mar-19 12-Apr-19 B
18 Denah parsial-1 inst. Saluran air hujan lantai atap dan helipad 1.00 6-Dec-18 17-Dec-18 C 4-Mar-19 12-Apr-19 B
GD. IRNA
19 Denah parsial-2 inst. Saluran air hujan lantai atap dan helipad 1.00 6-Dec-18 17-Dec-18 C 4-Mar-19 12-Apr-19 B
GD. IRNA
20 Standar detail saluran air hujan 1.00 6-Dec-18 17-Dec-18 C 4-Mar-19 12-Apr-19 A

E GAS MEDIS
1 Diagram skematik gas medis GD. IRNA 1.00 17-Jan-19 24-Jan-18 C 14-Mar-19 25-Mar-19 B
2 Denah inst. gas medis lantai basement GD. IRNA 1.00 5-Apr-19 12-Apr-19 C
3 Denah parsial-1 inst. gas medis lantai basement GD. IRNA 1.00 5-Apr-19 12-Apr-19 C
4 Denah inst. gas medis lantai 1 kelas 1 GD. IRNA 1.00 17-Jan-19 24-Jan-18 C 14-Mar-19 25-Mar-19 C 5-Apr-19 12-Apr-19 B
5 Denah parsial-1 inst. gas medis lantai 1 kelas 1 GD. IRNA 1.00 17-Jan-19 24-Jan-18 C 14-Mar-19 25-Mar-19 C 5-Apr-19 12-Apr-19 B
6 Denah parsial-2 inst. gas medis lantai 1 kelas 1 GD. IRNA 1.00 17-Jan-19 24-Jan-18 C 14-Mar-19 25-Mar-19 C 5-Apr-19 12-Apr-19 B
7 Denah inst. gas medis lantai 2 kelas VIP GD. IRNA 1.00 17-Jan-19 24-Jan-18 B
8 Denah parsial-1 inst. gas medis lantai 2 kelas VIP GD. IRNA 1.00 17-Jan-19 24-Jan-18 B
9 Denah parsial-2 inst. gas medis lantai 2 kelas VIP GD. IRNA 1.00 17-Jan-19 24-Jan-18 B
10 Denah inst. gas medis lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 17-Jan-19 24-Jan-18 B
11 Denah parsial-1 inst. gas medis lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 17-Jan-19 24-Jan-18 B
12 Denah parsial-2 inst. gas medis lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 17-Jan-19 24-Jan-18 B
13 Standar detail 1 gas medis GD. IRNA 1.00 17-Jan-19 24-Jan-18 C 14-Mar-19 25-Mar-19 B
14 Standar detail 1A gas medis GD. IRNA 1.00 17-Jan-19 24-Jan-18 C 14-Mar-19 25-Mar-19 B

F PNEUMATIC TUBE
1 Diagram skematik pnumatic tube gedung IRNA 1.00 29-Mar-19 5-Apr-19 B
2 Denah inst.pneumatic tube lantai basement GD.IRNA 1.00 14-May-19 16-May-19 B
3 Denah inst.pneumatic tube lantai 1 kelas 1 GD.IRNA 1.00 29-Mar-19 5-Apr-19 C 14-May-19 16-May-19 B
4 Denah inst.pneumatic tube lantai 2 kelas VIP GD.IRNA 1.00 29-Mar-19 5-Apr-19 B
5 Denah inst.pneumatic tube lantai 3 kelas VVIP & VIP GD.IRNA 1.00 29-Mar-19 5-Apr-19 B

G VAC
1 Denah inst. AC lantai basement GD. IRNA 1.00 20-Dec-18 27-Dec-18 C 24-Jan-19 4-Feb-19 B
2 Detail.A inst. AC lantai basement GD. IRNA 1.00 20-Dec-18 27-Dec-18 C 24-Jan-19 4-Feb-19 B
3 Denah inst. AC lantai 1 kelas 1 GD. IRNA 1.00 20-Dec-18 27-Dec-18 C 24-Jan-19 4-Feb-19 B
4 Denah parsial-1 inst. AC lantai 1 kelas 1 GD. IRNA 1.00 20-Dec-18 27-Dec-18 C 24-Jan-19 4-Feb-19 C 11-May-19 16-May-19 B
5 Denah parsial-2 inst. AC lantai 1 kelas 1 GD. IRNA 1.00 20-Dec-18 27-Dec-18 C 24-Jan-19 4-Feb-19 B
6 Denah parsial-3 inst. AC lantai 1 kelas 1 GD. IRNA 1.00 20-Dec-18 27-Dec-18 C 24-Jan-19 4-Feb-19 C 11-May-19 16-May-19 B
7 Denah inst. AC lantai 2 kelas VIP GD. IRNA 1.00 20-Dec-18 27-Dec-18 C 24-Jan-19 4-Feb-19 B
8 Denah parsial-1 inst. AC lantai 2 kelas VIP GD. IRNA 1.00 20-Dec-18 27-Dec-18 C 24-Jan-19 4-Feb-19 C 11-May-19 16-May-19 B
9 Denah parsial-2 inst. AC lantai 2 kelas VIP GD. IRNA 1.00 20-Dec-18 27-Dec-18 C 24-Jan-19 4-Feb-19 B
10 Denah parsial-3 inst. AC lantai 2 kelas VIP GD. IRNA 1.00 20-Dec-18 27-Dec-18 C 24-Jan-19 4-Feb-19 C 11-May-19 16-May-19 B
11 Denah inst. AC lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 20-Dec-18 27-Dec-18 C 24-Jan-19 4-Feb-19 B
12 Denah parsial-1 inst. AC lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 20-Dec-18 27-Dec-18 C 24-Jan-19 4-Feb-19 C 11-May-19 16-May-19 B
13 Denah parsial-2 inst. AC lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 20-Dec-18 27-Dec-18 C 24-Jan-19 4-Feb-19 B
14 Denah parsial-3 inst. AC lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 20-Dec-18 27-Dec-18 C 24-Jan-19 4-Feb-19 C 11-May-19 16-May-19 B
15 Denah inst. AC lantai 4 dan maintenance lift GD. IRNA 1.00 20-Dec-18 27-Dec-18 B
16 Denah parsial-1 inst. AC lantai 4 dan maintenance lift GD. IRNA 1.00 20-Dec-18 27-Dec-18 B
17 Denah parsial-2 inst. AC lantai 4 dan maintenance lift GD. IRNA 1.00 20-Dec-18 27-Dec-18 C 24-Jan-19 4-Feb-19 C 11-May-19 16-May-19 B
18 Denah parsial-3 inst. AC lantai 4 dan maintenance lift GD. IRNA 1.00 20-Dec-18 27-Dec-18 B
19 Standar detail AC-1 GD. IRNA 1.00 20-Dec-18 27-Dec-18 A
20 Standar detail AC-1A GD. IRNA 1.00 20-Dec-18 27-Dec-18 A
21 Standar detail AC-1B GD. IRNA 1.00 20-Dec-18 27-Dec-18 A
22 Standar detail AC-2 GD. IRNA 1.00 20-Dec-18 27-Dec-18 A
23 Standar detail AC-2A GD. IRNA 1.00 20-Dec-18 27-Dec-18 A
24 Standar detail AC-2B GD. IRNA 1.00 20-Dec-18 27-Dec-18 A
25 Standar detail AC-2C GD. IRNA 1.00 20-Dec-18 27-Dec-18 A

1 Denah inst. drain AC lantai basement GD. IRNA 1.00 17-Jan-19 4-Feb-19 C 14-Mar-19 9-Apr-19 C 10-May-19 16-May-19 B
2 Denah parsial-1 inst. drain AC lantai basement GD. IRNA 1.00 17-Jan-19 4-Feb-19 C 14-Mar-19 9-Apr-19 C 10-May-19 16-May-19 B
3 Denah parsial-2 inst. drain AC lantai basement GD. IRNA 1.00 17-Jan-19 4-Feb-19 C 14-Mar-19 9-Apr-19 C 10-May-19 16-May-19 B
4 Denah inst. drain AC lantai 1 kelas 1 GD. IRNA 1.00 17-Jan-19 4-Feb-19 C 14-Mar-19 9-Apr-19 B
5 Denah parsial-1 inst. drain AC lantai 1 kelas 1 GD. IRNA 1.00 17-Jan-19 4-Feb-19 C 14-Mar-19 9-Apr-19 B
6 Denah parsial-2 inst. drain AC lantai 1 kelas 1 GD. IRNA 1.00 17-Jan-19 4-Feb-19 C 14-Mar-19 9-Apr-19 B
7 Denah inst. drain AC lantai 2 kelas VIP GD. IRNA 1.00 17-Jan-19 4-Feb-19 C 14-Mar-19 9-Apr-19 B
8 Denah parsial-1 inst. drain AC lantai 2 kelas VIP GD. IRNA 1.00 17-Jan-19 4-Feb-19 C 14-Mar-19 9-Apr-19 B
9 Denah parsial-2 inst. drain AC lantai 2 kelas VIP GD. IRNA 1.00 17-Jan-19 4-Feb-19 C 14-Mar-19 9-Apr-19 B
10 Denah inst. drain AC lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 17-Jan-19 4-Feb-19 C 14-Mar-19 9-Apr-19 B
11 Denah parsial-1 inst. drain AC lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 17-Jan-19 4-Feb-19 C 14-Mar-19 9-Apr-19 B
12 Denah parsial-2 inst. drain AC lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 17-Jan-19 4-Feb-19 C 14-Mar-19 9-Apr-19 B
13 Denah inst. drain AC lantai 4 dan maintenance lift GD. IRNA 1.00 17-Jan-19 4-Feb-19 C 14-Mar-19 9-Apr-19 B

1 Denah inst. ventilasi mekanik lantai basement GD. IRNA 1.00 28-Jan-19 7-Feb-19 C 14-Mar-19 5-Apr-19 B
2 Denah parsial-1 inst. ventilasi mekanik lantai basement GD. IRNA 1.00 28-Jan-19 7-Feb-19 C 14-Mar-19 5-Apr-19 B
3 Denah parsial-2 inst. ventilasi mekanik lantai basement GD. IRNA 1.00 28-Jan-19 7-Feb-19 C 14-Mar-19 5-Apr-19 B
4 Denah inst. ventilasi mekanik lantai 1 kelas 1 GD. IRNA 1.00 28-Jan-19 7-Feb-19 C 14-Mar-19 5-Apr-19 C 10-May-19 16-May-19 B
5 Denah parsial-1 inst. ventilasi mekanik lantai 1 kelas 1 GD. IRNA 1.00 28-Jan-19 7-Feb-19 C 14-Mar-19 5-Apr-19 C 10-May-19 16-May-19 B
6 Denah parsial-2 inst. ventilasi mekanik lantai 1 kelas 1 GD. IRNA 1.00 28-Jan-19 7-Feb-19 C 14-Mar-19 5-Apr-19 C 10-May-19 16-May-19 B
7 Denah inst. ventilasi mekanik lantai 2 kelas VIP GD. IRNA 1.00 28-Jan-19 7-Feb-19 C 14-Mar-19 5-Apr-19 C 10-May-19 16-May-19 B
8 Denah parsial-1 inst. ventilasi mekanik lantai 2 kelas VIP GD. IRNA 1.00 28-Jan-19 7-Feb-19 C 14-Mar-19 5-Apr-19 C 10-May-19 16-May-19 B
9 Denah parsial-2 inst. ventilasi mekanik lantai lantai 2 kelas VIP 1.00 28-Jan-19 7-Feb-19 C 14-Mar-19 5-Apr-19 C 10-May-19 16-May-19 B
GD. IRNA
10 Denah inst. ventilasi mekanik lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 28-Jan-19 7-Feb-19 C 14-Mar-19 5-Apr-19 C 10-May-19 16-May-19 B
11 Denah parsial-1 inst. ventilasi mekanik lantai 3 kelas VVIP dan VIP 1.00 28-Jan-19 7-Feb-19 C 14-Mar-19 5-Apr-19 C 10-May-19 16-May-19 B
GD. IRNA
12 Denah parsial-2 inst. ventilasi mekanik lantai 3 kelas VVIP dan VIP 1.00 28-Jan-19 7-Feb-19 C 14-Mar-19 5-Apr-19 C 10-May-19 16-May-19 B
GD. IRNA
13 Denah inst. ventilasi mekanik lantai 4 dan maintenance lift GD. IRNA 1.00 28-Jan-19 7-Feb-19 B
14 Denah parsial-1 inst. ventilasi mekanik lantai 4 dan maintenance lift 1.00 28-Jan-19 7-Feb-19 B
GD. IRNA
15 Denah parsial-2 inst. ventilasi mekanik lantai 4 dan maintenance lift 1.00 28-Jan-19 7-Feb-19 B
GD. IRNA
16 Denah inst. ventilasi mekanik lantai atap dan helipad GD. IRNA 1.00 28-Jan-19 7-Feb-19 B
17 Standar detail-1 ventilasi mekanik GD. IRNA 1.00 28-Jan-19 7-Feb-19 A
18 Standar detail-2 ventilasi mekanik GD. IRNA 1.00 28-Jan-19 7-Feb-19 A

H PENERANGAN
1 Denah inst. penerangan lantai basement GD. IRNA 1.00 10-Dec-18 17-Dec-18 C 16-Feb-19 26-Feb-19 B
2 Denah inst. penerangan zona 1 lantai basement GD. IRNA 1.00 10-Dec-18 17-Dec-18 C 16-Feb-19 26-Feb-19 B
3 Denah inst. penerangan zona 2 lantai basement GD. IRNA 1.00 10-Dec-18 17-Dec-18 C 16-Feb-19 26-Feb-19 B
4 Denah inst. penerangan zona 3 lantai basement GD. IRNA 1.00 10-Dec-18 17-Dec-18 C 16-Feb-19 26-Feb-19 B
5 Denah inst. penerangan lantai 1 kelas 1 GD. IRNA 1.00 10-Dec-18 17-Dec-18 C 16-Feb-19 26-Feb-19 B
6 Denah inst. penerangan zona 1 lantai 1 kelas 1 GD. IRNA 1.00 10-Dec-18 17-Dec-18 C 16-Feb-19 26-Feb-19 B
7 Denah inst. penerangan zona 2 lantai 1 kelas 1 GD. IRNA 1.00 10-Dec-18 17-Dec-18 C 16-Feb-19 26-Feb-19 B
8 Denah inst. penerangan zona 3 lantai 1 kelas 1 GD. IRNA 1.00 10-Dec-18 17-Dec-18 C 16-Feb-19 26-Feb-19 B
9 Denah inst. penerangan lantai 2 kelas VIP GD. IRNA 1.00 10-Dec-18 17-Dec-18 C 16-Feb-19 26-Feb-19 B
10 Denah inst. penerangan zona 1 lantai 2 kelas VIP GD. IRNA 1.00 10-Dec-18 17-Dec-18 C 16-Feb-19 26-Feb-19 B
11 Denah inst. penerangan zona 2 lantai 2 kelas VIP GD. IRNA 1.00 10-Dec-18 17-Dec-18 C 16-Feb-19 26-Feb-19 B
12 Denah inst. penerangan zona 3 lantai 2 kelas VIP GD. IRNA 1.00 10-Dec-18 17-Dec-18 C 16-Feb-19 26-Feb-19 B
13 Denah inst. penerangan lantai 3 kelas VVIP & VIP GD. IRNA 1.00 10-Dec-18 17-Dec-18 C 16-Feb-19 26-Feb-19 B
14 Denah inst. penerangan zona 1 lantai 3 kelas VVIP & VIP GD. IRNA 1.00 10-Dec-18 17-Dec-18 C 16-Feb-19 26-Feb-19 B
15 Denah inst. penerangan zona 2 lantai 3 kelas VVIP & VIP GD. IRNA 1.00 10-Dec-18 17-Dec-18 C 16-Feb-19 26-Feb-19 B
16 Denah inst. penerangan zona 3 lantai 3 kelas VVIP & VIP GD. IRNA 1.00 10-Dec-18 17-Dec-18 C 16-Feb-19 26-Feb-19 B
17 Denah inst. penerangan lantai 4 dan maintenance lift GD. IRNA 1.00 10-Dec-18 17-Dec-18 C 4-Mar-19 25-Mar-19 C
18 Denah inst. penerangan zona 1 lantai 4 dan maintenance lift 1.00 10-Dec-18 17-Dec-18 C 4-Mar-19 25-Mar-19 C
GD. IRNA
19 Denah inst. penerangan zona 2 lantai 4 dan maintenance lift 1.00 10-Dec-18 17-Dec-18 C 4-Mar-19 25-Mar-19 C
GD. IRNA
20 Denah inst. Penerangan zona 3 lantai 4 dan maintenance lift 1.00 10-Dec-18 17-Dec-18 C 4-Mar-19 25-Mar-19 C
GD. IRNA
21 Denah inst. penerangan lantai atap dan helipad GD. IRNA 1.00 10-Dec-18 17-Dec-18 C 4-Mar-19 25-Mar-19 C
22 Denah inst. penerangan zona 1 lantai atap dan helipad GD. IRNA 1.00 10-Dec-18 17-Dec-18 C 4-Mar-19 25-Mar-19 C
23 Denah inst. penerangan zona 2 lantai atap dan helipad GD. IRNA 1.00 10-Dec-18 17-Dec-18 C 4-Mar-19 25-Mar-19 C
24 Denah inst. penerangan zona 3 lantai atap dan helipad GD. IRNA 1.00 10-Dec-18 17-Dec-18 C 4-Mar-19 25-Mar-19 B
25 Standar-1 detail elektrikal 1.00 10-Dec-18 17-Dec-18 B
26 Standar-2 detail elektrikal 1.00 10-Dec-18 17-Dec-18 B
27 Standar-3 detail elektrikal 1.00 10-Dec-18 17-Dec-18 A
28 Standar detail lampu jalan 1.00 10-Dec-18 17-Dec-18 B

I KOTAK KONTAK
1 Denah inst. Kotak kontak lantai basement GD. IRNA 1.00 13-Dec-18 20-Dec-18 B
2 Denah inst. Kotak kontak zona 1 lantai basement GD. IRNA 1.00 13-Dec-18 20-Dec-18 B
3 Denah inst. Kotak kontak zona 2 lantai basement GD. IRNA 1.00 13-Dec-18 20-Dec-18 B
4 Denah inst. Kotak kontak zona 3 lantai basement GD. IRNA 1.00 13-Dec-18 20-Dec-18 B
5 Denah inst. Kotak kontak lantai 1 kelas 1 GD. IRNA 1.00 17-Dec-18 15-Jan-19 C 30-Jan-19 4-Feb-19 B
6 Denah inst. Kotak kontak ZONA 1 lantai 1 kelas 1 GD. IRNA 1.00 17-Dec-18 15-Jan-19 C 30-Jan-19 4-Feb-19 B
7 Denah inst. Kotak kontak ZONA 2 lantai 1 kelas 1 GD. IRNA 1.00 17-Dec-18 15-Jan-19 C 30-Jan-19 4-Feb-19 B
8 Denah inst. Kotak kontak ZONA 3 lantai 1 kelas 1 GD. IRNA 1.00 17-Dec-18 15-Jan-19 C 30-Jan-19 4-Feb-19 B
9 Denah inst. Kotak kontak lantai 2 kelas VIP GD. IRNA 1.00 13-Dec-18 20-Dec-18 C 30-Jan-19 4-Feb-19 B
10 Denah inst. Kotak kontak ZONA 1 lantai 2 kelas VIP GD. IRNA 1.00 13-Dec-18 20-Dec-18 C 30-Jan-19 4-Feb-19 B
11 Denah inst. Kotak kontak ZONA 2 lantai 2 kelas VIP GD. IRNA 1.00 13-Dec-18 20-Dec-18 C 30-Jan-19 4-Feb-19 B
12 Denah inst. Kotak kontak ZONA 3 lantai 2 kelas VIP GD. IRNA 1.00 13-Dec-18 20-Dec-18 C 30-Jan-19 4-Feb-19 B
13 Denah inst. Kotak kontak lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 13-Dec-18 20-Dec-18 C 30-Jan-19 4-Feb-19 B
14 Denah inst. Kotak kontak zona 1 lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 13-Dec-18 20-Dec-18 C 30-Jan-19 4-Feb-19 B
15 Denah inst. Kotak kontak zona 2 lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 13-Dec-18 20-Dec-18 C 30-Jan-19 4-Feb-19 B
16 Denah inst. Kotak kontak zona 3 lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 13-Dec-18 20-Dec-18 C 30-Jan-19 4-Feb-19 B
17 Denah inst. Kotak kontak lantai 4 dan maintenance lift GD. IRNA 1.00 13-Dec-18 20-Dec-18 B
18 Denah inst. Kotak kontak zona 1 lantai 4 dan maintenance lift 1.00 13-Dec-18 20-Dec-18 B
GD. IRNA
19 Denah inst. Kotak kontak zona 2 lantai 4 dan maintenance lift 1.00 13-Dec-18 20-Dec-18 B
GD. IRNA
20 Denah inst. Kotak kontak zona 3 lantai 4 dan maintenance lift 1.00 13-Dec-18 20-Dec-18 B
GD. IRNA

J DISTRIBUSI LISTRIK
1 Diagram skematik distribusi listrik GD. IRNA 1.00 14-Dec-18 20-Dec-18 A
2 Denah jalur kabel feeder dari power house ke GD. IRNA 1.00 14-Dec-18 20-Dec-18 B
3 Denah tray kabel lantai basement GD. IRNA 1.00 14-Dec-18 20-Dec-18 C 20-Feb-19 26-Feb-19 B
4 Denah parsial-1 tray kabel lantai basement GD. IRNA 1.00 14-Dec-18 20-Dec-18 C 20-Feb-19 26-Feb-19 B
5 Denah parsial-2 tray kabel lantai basement GD. IRNA 1.00 14-Dec-18 20-Dec-18 C 20-Feb-19 26-Feb-19 B
6 Denah tray kabel lantai 1 kelas 1 GD. IRNA 1.00 14-Dec-18 20-Dec-18 C 20-Feb-19 26-Feb-19 B
7 Denah parsial-1 tray kabel lantai 1 kelas 1 GD. IRNA 1.00 14-Dec-18 20-Dec-18 C 20-Feb-19 26-Feb-19 B
8 Denah parsial-2 tray kabel lantai 1 kelas 1 GD. IRNA 1.00 14-Dec-18 20-Dec-18 C 20-Feb-19 26-Feb-19 B
9 Denah tray kabel lantai 2 kelas VIP GD. IRNA 1.00 14-Dec-18 20-Dec-18 C 20-Feb-19 26-Feb-19 B
10 Denah parsial-1 tray kabel lantai 2 kelas VIP GD. IRNA 1.00 14-Dec-18 20-Dec-18 C 20-Feb-19 26-Feb-19 B
11 Denah parsial-2 tray kabel lantai 2 kelas VIP GD. IRNA 1.00 14-Dec-18 20-Dec-18 C 20-Feb-19 26-Feb-19 B
12 Denah tray kabel lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 14-Dec-18 20-Dec-18 C 20-Feb-19 26-Feb-19 B
13 Denah parsial-1 tray kabel lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 14-Dec-18 20-Dec-18 C 20-Feb-19 26-Feb-19 B
14 Denah parsial-2 tray kabel lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 14-Dec-18 20-Dec-18 C 20-Feb-19 26-Feb-19 B
15 Denah tray kabel lantai 4 dan maintenance lift GD. IRNA 1.00 14-Dec-18 20-Dec-18 C 20-Feb-19 26-Feb-19 C 18-Mar-19 5-Apr-19 B
16 Denah parsial-1 tray kabel lantai 4 dan maintenance lift GD. IRNA 1.00 14-Dec-18 20-Dec-18 C 20-Feb-19 26-Feb-19 C 18-Mar-19 5-Apr-19 B
17 Denah parsial-2 tray kabel lantai 4 dan maintenance lift GD. IRNA 1.00 14-Dec-18 20-Dec-18 C 20-Feb-19 26-Feb-19 C 18-Mar-19 5-Apr-19 B
18 Standar-1 detail tray kabel GD. IRNA 1.00 14-Dec-18 20-Dec-18 A
19 Standar-2 detail tray kabel GD. IRNA 1.00 14-Dec-18 20-Dec-18 A
20 Standar-3 detail tray kabel GD. IRNA 1.00 14-Dec-18 20-Dec-18 A
21 Standar-4 detail tray kabel GD. IRNA 1.00 14-Dec-18 20-Dec-18 A

K GROUNDING
1 Denah instalasi grounding GD. IRNA 1.00 15-Apr-19 4-May-19 B

L SKEDUL BEBAN LISTRIK


1 Skedul beban SDP GD irna 1.00 28-Feb-19 1-Mar-19 B
2 Skedul beban PP lift dan PP elektronik GD irna 1.00 28-Feb-19 1-Mar-19 B
3 Skedul beban SDP pompa dan LP OL GD irna 1.00 28-Feb-19 1-Mar-19 C
4 Skedul beban PP basement-2, PP 1-2 dan PP 2-2 zona 2 GD irna 1.00 28-Feb-19 1-Mar-19 B
5 Skedul beban PP 3-2, PP 4-2 dan PPAC basement-2 zona 2 GD irna 1.00 28-Feb-19 1-Mar-19 B
6 Skedul beban PPAC 1-2 dan PPAC 2-2 zona 2 GD irna 1.00 28-Feb-19 1-Mar-19 B
7 Skedul beban PPAC 3-2 dan PPAC 4-2 zona 2 GD irna 1.00 28-Feb-19 1-Mar-19 B
8 Skedul beban SDP zona-1 dan PP basement-1 zona 1 GD irna 1.00 28-Feb-19 1-Mar-19 C
9 Skedul beban PP 1-1 zona 1 GD irna 1.00 28-Feb-19 1-Mar-19 B
10 Skedul beban PP 2-1 zona 1 GD irna 1.00 28-Feb-19 1-Mar-19 B
11 Skedul beban PP 3-1 dan PP 4-1 zona 1 GD irna 1.00 28-Feb-19 1-Mar-19 B
12 Skedul beban PPAC 1-1 dan PPAC 2-1 zona 1 GD irna 1.00 28-Feb-19 1-Mar-19 B
13 Skedul beban PPAC 3-1 zona 1 GD irna 1.00 28-Feb-19 1-Mar-19 B
14 Skedul beban SDP zona-3 dan PP basement-3 zona 3 GD irna 1.00 28-Feb-19 1-Mar-19 B
15 Skedul beban PP 1-3 zona 3 GD irna 1.00 28-Feb-19 1-Mar-19 B
16 Skedul beban PP 2-3 zona 3 GD irna 1.00 28-Feb-19 1-Mar-19 B
17 Skedul beban PP 3-3 dan PP 4-3 zona 3 GD irna 1.00 28-Feb-19 1-Mar-19 B
18 Skedul beban PPAC 1-3 dan PPAC 2-3 zona 3 GD irna 1.00 28-Feb-19 1-Mar-19 B
19 Skedul beban PPAC 3-3 zona 3 GD irna 1.00 28-Feb-19 1-Mar-19 B

M ELEVATOR
1 Diagram skematik elevator 1.00 BELUM
2 Rencana elevator lantai basement 1.00 BELUM
3 Rencana elevator lantai 1 kelas 1 1.00 BELUM
4 Rencana elevator lantai 2 kelas VIP 1.00 BELUM
5 Rencana elevator lantai 3 kelas VVIP & VIP 1.00 BELUM

N FIRE ALARM
1 Diagram skematik fire alarm GD. IRNA 1.00 17-Dec-18 17-Jan-19 B
2 Denah Inst. Fire alarm lantai basement GD. IRNA 1.00 17-Dec-18 17-Jan-19 C 30-Jan-19 4-Feb-19 B
3 Denah parsial-1 Inst. Fire alarm lantai basement GD. IRNA 1.00 17-Dec-18 17-Jan-19 B
4 Denah parsial-2 Inst. Fire alarm lantai basement GD. IRNA 1.00 17-Dec-18 17-Jan-19 C 30-Jan-19 4-Feb-19 B
5 Denah parsial-3 Inst. Fire alarm lantai basement GD. IRNA 1.00 17-Dec-18 17-Jan-19 B
6 Denah Inst. Fire alarm lantai 1 kelas 1 GD. IRNA 1.00 17-Dec-18 17-Jan-19 C 30-Jan-19 4-Feb-19 C 18-Feb-19 26-Feb-19 B
7 Denah parsial-1 Inst. Fire alarm lantai 1 kelas 1 GD. IRNA 1.00 17-Dec-18 17-Jan-19 C 30-Jan-19 4-Feb-19 C 18-Feb-19 26-Feb-19 B
8 Denah parsial-2 Inst. Fire alarm lantai 1 kelas 1 GD. IRNA 1.00 17-Dec-18 17-Jan-19 C 30-Jan-19 4-Feb-19 C 18-Feb-19 26-Feb-19 B
9 Denah parsial-3 Inst. Fire alarm lantai 1 kelas 1 GD. IRNA 1.00 17-Dec-18 17-Jan-19 C 30-Jan-19 4-Feb-19 C 18-Feb-19 26-Feb-19 B
10 Denah Inst. Fire alarm lantai 2 kelas VIP GD. IRNA 1.00 17-Dec-18 17-Jan-19 C 30-Jan-19 4-Feb-19 C 18-Feb-19 26-Feb-19 B
11 Denah parsial-1 Inst. Fire alarm lantai 2 kelas VIP GD. IRNA 1.00 17-Dec-18 17-Jan-19 C 30-Jan-19 4-Feb-19 C 18-Feb-19 26-Feb-19 B
12 Denah parsial-2 Inst. Fire alarm lantai 2 kelas VIP GD. IRNA 1.00 17-Dec-18 17-Jan-19 C 30-Jan-19 4-Feb-19 C 18-Feb-19 26-Feb-19 B
13 Denah parsial-3 Inst. Fire alarm lantai 2 kelas VIP GD. IRNA 1.00 17-Dec-18 17-Jan-19 C 30-Jan-19 4-Feb-19 C 18-Feb-19 26-Feb-19 B
14 Denah Inst. Fire alarm lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 17-Dec-18 17-Jan-19 C 30-Jan-19 4-Feb-19 C 18-Feb-19 26-Feb-19 B
15 Denah parsial-1 Inst. Fire alarm lantai 3 kelas VVIP dan VIP 1.00 17-Dec-18 17-Jan-19 C 30-Jan-19 4-Feb-19 C 18-Feb-19 26-Feb-19 B
GD. IRNA
16 Denah parsial-2 Inst. Fire alarm lantai 3 kelas VVIP dan VIP 1.00 17-Dec-18 17-Jan-19 C 30-Jan-19 4-Feb-19 C 18-Feb-19 26-Feb-19 B
GD. IRNA
17 Denah parsial-3 Inst. Fire alarm lantai 3 kelas VVIP dan VIP 1.00 17-Dec-18 17-Jan-19 C 30-Jan-19 4-Feb-19 C 18-Feb-19 26-Feb-19 B
GD. IRNA
18 Denah Inst. Fire alarm lantai 4 dan maintenance lift GD. IRNA 1.00 17-Dec-18 17-Jan-19 B
19 Denah parsial-1 Inst. Fire alarm lantai 4 dan maintenance lift 1.00 17-Dec-18 17-Jan-19 A
GD. IRNA
20 Denah parsial-2 Inst. Fire alarm lantai 4 dan maintenance lift 1.00 17-Dec-18 17-Jan-19 B
GD. IRNA
21 Denah parsial-3 Inst. Fire alarm lantai 4 dan maintenance lift 1.00 17-Dec-18 17-Jan-19 A
GD. IRNA
22 Standar detail fire alarm GD. IRNA 1.00 17-Dec-18 17-Jan-19 A

O SOUND SYSTEM
1 Diagram skematik sound system GD. IRNA 1.00 3-Jan-19 10-Jan-19 C 9-Feb-19 25-Mar-19 B
2 Denah inst. sound system lantai basement GD. IRNA 1.00 3-Jan-19 10-Jan-19 C 9-Feb-19 25-Mar-19 B
3 Denah parsial 1 inst. sound system lantai basement GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
4 Denah parsial 2 inst. sound system lantai basement GD. IRNA 1.00 3-Jan-19 10-Jan-19 C 9-Feb-19 25-Mar-19 B
5 Denah parsial 3 inst. sound system lantai basement GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
6 Denah inst. sound system lantai 1 kelas 1 GD. IRNA 1.00 3-Jan-19 10-Jan-19 C 9-Feb-19 25-Mar-19 B
7 Denah parsial 1 inst. sound system lantai 1 kelas 1 GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
8 Denah parsial 2 inst. sound system lantai 1 kelas 1 GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
9 Denah parsial 3 inst. sound system lantai 1 kelas 1 GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
10 Denah inst. sound system lantai 2 kelas VIP GD. IRNA 1.00 3-Jan-19 10-Jan-19 C 9-Feb-19 25-Mar-19 B
11 Denah parsial 1 inst. sound system lantai 2 kelas VIP GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
12 Denah parsial 2 inst. sound system lantai 2 kelas VIP GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
13 Denah parsial 3 inst. sound system lantai 2 kelas VIP GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
14 Denah inst. sound system lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 3-Jan-19 10-Jan-19 C 9-Feb-19 25-Mar-19 B
15 Denah parsial 1 inst. sound system lantai 3 kelas VVIP dan VIP 1.00 3-Jan-19 10-Jan-19 B
GD. IRNA
16 Denah parsial 2 inst. sound system lantai 3 kelas VVIP dan VIP 1.00 3-Jan-19 10-Jan-19 B
GD. IRNA
17 Denah parsial 3 inst. sound system lantai 3 kelas VVIP dan VIP 1.00 3-Jan-19 10-Jan-19 B
GD. IRNA
18 Denah inst. sound system lantai 4 dan maintenance lift GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
19 Denah parsial 1 inst. sound system lantai 4 dan maintenance lift 1.00 3-Jan-19 10-Jan-19 B
GD. IRNA
20 Denah parsial 2 inst. sound system lantai 4 dan maintenance lift 1.00 3-Jan-19 10-Jan-19 B
GD. IRNA
21 Denah parsial 3 inst. sound system lantai 4 dan maintenance lift 1.00 3-Jan-19 10-Jan-19 B
GD. IRNA
22 Standar detail sound system GD. IRNA 1.00 3-Jan-19 10-Jan-19 A

P TELEPON
1 Diagram skematik telepon GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
2 Denah inst. telepon lantai basement GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
3 Detail .A inst. telepon lantai basement GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
4 Denah inst. telepon lantai 1 kelas 1 GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
5 Denah parsial 1 inst. telepon lantai 1 kelas 1 GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
6 Denah parsial 2 inst. telepon lantai 1 kelas 1 GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
7 Denah parsial 3 inst. telepon lantai 1 kelas 1 GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
8 Denah inst. telepon lantai 2 kelas VIP GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
9 Denah parsial 1 inst. telepon lantai 2 kelas VIP GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
10 Denah parsial 2 inst. telepon lantai 2 kelas VIP GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
11 Denah parsial 3 inst. telepon lantai 2 kelas VIP GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
12 Denah inst. telepon lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
13 Denah parsial 1 inst. telepon lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
14 Denah parsial 2 inst. telepon lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
15 Denah parsial 3 inst. telepon lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
16 Standar detail telepon GD. IRNA 1.00 3-Jan-19 10-Jan-19 A

Q DATA & WIFI


1 Diagram skematik data dan wifi GD. IRNA 1.00 8-Jan-19 10-Jan-19 B
2 Denah inst. data dan wifi lantai basement GD. IRNA 1.00 8-Jan-19 10-Jan-19 B
3 Detail .A inst. data dan wifi lantai basement GD. IRNA 1.00 8-Jan-19 10-Jan-19 B
4 Denah inst. data dan wifi lantai 1 kelas 1 GD. IRNA 1.00 8-Jan-19 10-Jan-19 C 21-Feb-19 26-Feb-19 B
5 Denah parsial 1 inst. data dan wifi lantai 1 kelas 1 GD. IRNA 1.00 8-Jan-19 10-Jan-19 C 21-Feb-19 26-Feb-19 B
6 Denah parsial 2 inst. data dan wifi lantai 1 kelas 1 GD. IRNA 1.00 8-Jan-19 10-Jan-19 C 21-Feb-19 26-Feb-19 B
7 Denah inst. data dan wifi lantai 2 kelas VIP GD. IRNA 1.00 8-Jan-19 10-Jan-19 C 21-Feb-19 26-Feb-19 B
8 Denah parsial 1 inst. data dan wifi lantai 2 kelas VIP GD. IRNA 1.00 8-Jan-19 10-Jan-19 C 21-Feb-19 26-Feb-19 B
9 Denah parsial 2 inst. data dan wifi lantai 2 kelas VIP GD. IRNA 1.00 8-Jan-19 10-Jan-19 C 21-Feb-19 26-Feb-19 B
10 Denah inst. data dan wifi lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 8-Jan-19 10-Jan-19 C 21-Feb-19 26-Feb-19 B
11 Denah parsial 1 inst. data dan wifi lantai 3 kelas VVIP dan VIP 1.00 8-Jan-19 10-Jan-19 C 21-Feb-19 26-Feb-19 B
GD. IRNA
12 Denah parsial 2 inst. data dan wifi lantai 3 kelas VVIP dan VIP 1.00 8-Jan-19 10-Jan-19 C 21-Feb-19 26-Feb-19 B
GD. IRNA
13 Standar detail data dan wifi GD. IRNA 1.00 8-Jan-19 10-Jan-19 A

R MATV
1 Diagram skematik MATV GD. IRNA 1.00 8-Jan-19 10-Jan-19 A
2 Denah inst. MATV lantai basement GD. IRNA 1.00 8-Jan-19 10-Jan-19 C 2-Feb-19 9-Feb-19 B
3 Detail .A inst. MATV lantai basement GD. IRNA 1.00 8-Jan-19 10-Jan-19 C 2-Feb-19 9-Feb-19 B
4 Denah inst. MATV lantai 1 kelas 1 GD. IRNA 1.00 8-Jan-19 10-Jan-19 C 2-Feb-19 9-Feb-19 B
5 Denah parsial 1 inst. MATV lantai 1 kelas 1 GD. IRNA 1.00 8-Jan-19 10-Jan-19 C 2-Feb-19 9-Feb-19 B
6 Denah parsial 2 inst. MATV lantai 1 kelas 1 GD. IRNA 1.00 8-Jan-19 10-Jan-19 C 2-Feb-19 9-Feb-19 B
7 Denah inst. MATV lantai 2 kelas VIP GD. IRNA 1.00 8-Jan-19 10-Jan-19 C 2-Feb-19 9-Feb-19 B
8 Denah parsial 1 inst. MATV lantai 2 kelas VIP GD. IRNA 1.00 8-Jan-19 10-Jan-19 C 2-Feb-19 9-Feb-19 B
9 Denah parsial 2 inst. MATV lantai 2 kelas VIP GD. IRNA 1.00 8-Jan-19 10-Jan-19 C 2-Feb-19 9-Feb-19 B
10 Denah inst. MATV lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 8-Jan-19 10-Jan-19 C 2-Feb-19 9-Feb-19 B
11 Denah parsial 1 inst. MATV lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 8-Jan-19 10-Jan-19 C 2-Feb-19 9-Feb-19 B
12 Denah parsial 2 inst. MATV lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 8-Jan-19 10-Jan-19 C 2-Feb-19 9-Feb-19 B
13 Denah inst. MATV lantai 4 dan maintenance lift GD. IRNA 1.00 8-Jan-19 10-Jan-19 B

S CCTV
1 Diagram skematik CCTV GD. IRNA 1.00 10-Jan-19 21-Jan-19 C 22-Feb-19 26-Feb-19 C 23-May-19 MK
2 Denah inst. CCTV lantai basement GD. IRNA 1.00 10-Jan-19 21-Jan-19 C 22-Feb-19 26-Feb-19 C 23-May-19 MK
3 Denah parsial-1 inst. CCTV lantai basement GD. IRNA 1.00 10-Jan-19 21-Jan-19 C 22-Feb-19 26-Feb-19 C 23-May-19 MK
4 Denah parsial-2 inst. CCTV lantai basement GD. IRNA 1.00 10-Jan-19 21-Jan-19 C 22-Feb-19 26-Feb-19 C 23-May-19 MK
5 Denah inst. CCTV lantai 1 kelas 1 GD. IRNA 1.00 10-Jan-19 21-Jan-19 C 22-Feb-19 26-Feb-19 C 23-May-19 MK
6 Denah parsial-1 inst. CCTV lantai 1 kelas 1 GD. IRNA 1.00 10-Jan-19 21-Jan-19 C 22-Feb-19 26-Feb-19 C 23-May-19 MK
7 Denah parsial-2 inst. CCTV lantai 1 kelas 1 GD. IRNA 1.00 10-Jan-19 21-Jan-19 C 22-Feb-19 26-Feb-19 C 23-May-19 MK
8 Denah inst. CCTV lantai 2 kelas VIP GD. IRNA 1.00 10-Jan-19 21-Jan-19 C 22-Feb-19 26-Feb-19 C 23-May-19 MK
9 Denah parsial-1 inst. CCTV lantai 2 kelas VIP GD. IRNA 1.00 10-Jan-19 21-Jan-19 C 22-Feb-19 26-Feb-19 C 23-May-19 MK
10 Denah parsial-2 inst. CCTV lantai 2 kelas VIP GD. IRNA 1.00 10-Jan-19 21-Jan-19 C 22-Feb-19 26-Feb-19 C 23-May-19 MK
11 Denah inst. CCTV lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 10-Jan-19 21-Jan-19 C 22-Feb-19 26-Feb-19 C 23-May-19 MK
12 Denah parsial-1 inst. CCTV lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 10-Jan-19 21-Jan-19 C 22-Feb-19 26-Feb-19 C 23-May-19 MK
13 Denah parsial-2 inst. CCTV lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 10-Jan-19 21-Jan-19 C 22-Feb-19 26-Feb-19 C 23-May-19 MK
14 Standar detail CCTV GD. IRNA 1.00 10-Jan-19 21-Jan-19 C 22-Feb-19 26-Feb-19 C 23-May-19 MK

T NURSE CALL
1 Diagram skematik nurse call GD. IRNA 1.00 3-Jan-19 10-Jan-19 C 22-Feb-19 26-Feb-19 B
2 Denah inst. nurse call lantai basement GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
3 Detail .A inst. nurse call lantai basement GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
4 Denah inst. nurse call lantai 1 kelas 1 GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
5 Denah parsial 1 inst. nurse call lantai 1 kelas 1 GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
6 Denah parsial 2 inst. nurse call lantai 1 kelas 1 GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
7 Denah inst. nurse call lantai 2 kelas VIP GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
8 Denah parsial 1 inst. nurse call lantai 2 kelas VIP GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
9 Denah parsial 2 inst. nurse call lantai 2 kelas VIP GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
10 Denah inst. nurse call lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 3-Jan-19 10-Jan-19 C 22-Feb-19 26-Feb-19 C 9-Mar-19 25-Mar-19 B
11 Denah parsial 1 inst. nurse call lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 3-Jan-19 10-Jan-19 C 22-Feb-19 26-Feb-19 C 9-Mar-19 25-Mar-19 B
12 Denah parsial 2 inst. nurse call lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 3-Jan-19 10-Jan-19 B
13 Standar detail nurse call GD. IRNA 1.00 3-Jan-19 10-Jan-19 A

U CODE RED & CODE BLUE


1 Diagram skematik code red & code blue GD. IRNA 1.00 28-Jan-19 7-Feb-19 C 21-Feb-19 26-Feb-19 B
2 Denah inst. code red & code blue lantai 1 kelas 1 GD. IRNA 1.00 28-Jan-19 7-Feb-19 C 21-Feb-19 26-Feb-19 B
3 Denah parsial-1 inst. code red & code blue lantai 1 kelas 1 GD. IRNA 1.00 28-Jan-19 7-Feb-19 C 21-Feb-19 26-Feb-19 B
4 Denah parsial-2 inst. code red & code blue lantai 1 kelas 1 GD. IRNA 1.00 28-Jan-19 7-Feb-19 C 21-Feb-19 26-Feb-19 B
5 Denah inst. code red & code blue lantai 2 kelas VIP GD. IRNA 1.00 28-Jan-19 7-Feb-19 B
6 Denah parsial-1 inst. code red & code blue lantai 2 kelas VIP 1.00 28-Jan-19 7-Feb-19 B
GD. IRNA
7 Denah parsial-2 inst. code red & code blue lantai 2 kelas VIP 1.00 28-Jan-19 7-Feb-19 B
GD. IRNA
8 Denah inst. code red & code blue lantai 3 kelas VVIP dan VIP 1.00 28-Jan-19 7-Feb-19 B
GD. IRNA
9 Denah parsial-1 inst. code red & code blue lantai 3 kelas VVIP 1.00 28-Jan-19 7-Feb-19 B
dan VIP GD. IRNA
10 Denah parsial-2 inst. code red & code blue lantai 3 kelas VVIP 1.00 28-Jan-19 7-Feb-19 B
dan VIP GD. IRNA

V COMPOSITE ARMATUR MEP


1 Denah composite armatur MEP lantai basement GD. IRNA 1.00 26-Mar-19 9-May-19 C 15-Apr-19 4-May-19 B
2 Denah parsial-1 composite armatur MEP lantai basement GD. IRNA 1.00 26-Mar-19 9-May-19 C 15-Apr-19 4-May-19 B
3 Denah parsial-2 composite armatur MEP lantai basement GD. IRNA 1.00 26-Mar-19 9-May-19 C 15-Apr-19 4-May-19 B
4 Denah parsial-3 composite armatur MEP lantai basement GD. IRNA 1.00 26-Mar-19 9-May-19 C 15-Apr-19 4-May-19 B
5 Denah parsial-4 composite armatur MEP lantai basement GD. IRNA 1.00 26-Mar-19 9-May-19 C 15-Apr-19 4-May-19 B
6 Denah parsial-5 composite armatur MEP lantai basement GD. IRNA 1.00 26-Mar-19 9-May-19 C 15-Apr-19 4-May-19 B
7 Denah parsial-6 composite armatur MEP lantai basement GD. IRNA 1.00 26-Mar-19 9-May-19 C 15-Apr-19 4-May-19 B
8 Denah composite armatur MEP lantai 1 kelas 1 GD. IRNA 1.00 26-Jan-19 30-Jan-19 C 9-Feb-19 19-Feb-19 B
9 Denah parsial-1 composite armatur MEP lantai 1 kelas 1 GD. IRNA 1.00 26-Jan-19 30-Jan-19 C 9-Feb-19 19-Feb-19 B
10 Denah parsial-2 composite armatur MEP lantai 1 kelas 1 GD. IRNA 1.00 26-Jan-19 30-Jan-19 C 9-Feb-19 19-Feb-19 B
11 Denah parsial-3 composite armatur MEP lantai 1 kelas 1 GD. IRNA 1.00 26-Jan-19 30-Jan-19 C 9-Feb-19 19-Feb-19 B
12 Denah parsial-4 composite armatur MEP lantai 1 kelas 1 GD. IRNA 1.00 26-Jan-19 30-Jan-19 C 9-Feb-19 19-Feb-19 B
13 Denah parsial-5 composite armatur MEP lantai 1 kelas 1 GD. IRNA 1.00 26-Jan-19 30-Jan-19 C 9-Feb-19 19-Feb-19 B
14 Denah parsial-6 composite armatur MEP lantai 1 kelas 1 GD. IRNA 1.00 26-Jan-19 30-Jan-19 C 9-Feb-19 19-Feb-19 B
15 Denah composite armatur MEP lantai 2 kelas VIP GD. IRNA 1.00 9-Feb-19 19-Feb-19 B
16 Denah parsial-1 composite armatur MEP lantai 2 kelas VIP GD. IRNA 1.00 9-Feb-19 19-Feb-19 B
17 Denah parsial-2 composite armatur MEP lantai 2 kelas VIP GD. IRNA 1.00 9-Feb-19 19-Feb-19 B
18 Denah parsial-3 composite armatur MEP lantai 2 kelas VIP GD. IRNA 1.00 9-Feb-19 19-Feb-19 B
19 Denah parsial-4 composite armatur MEP lantai 2 kelas VIP GD. IRNA 1.00 9-Feb-19 19-Feb-19 B
20 Denah parsial-5 composite armatur MEP lantai 2 kelas VIP GD. IRNA 1.00 9-Feb-19 19-Feb-19 B
21 Denah parsial-6 composite armatur MEP lantai 2 kelas VIP GD. IRNA 1.00 9-Feb-19 19-Feb-19 B
22 Denah composite armatur MEP lantai 3 kelas VVIP dan VIP GD. IRNA 1.00 9-Feb-19 19-Feb-19 B
23 Denah parsial-1 composite armatur MEP lantai 3 kelas VVIP dan VIP 1.00 9-Feb-19 19-Feb-19 B
GD. IRNA
24 Denah parsial-2 composite armatur MEP lantai 3 kelas VVIP dan VIP 1.00 9-Feb-19 19-Feb-19 B
GD. IRNA
25 Denah parsial-3 composite armatur MEP lantai 3 kelas VVIP dan VIP 1.00 9-Feb-19 19-Feb-19 B
GD. IRNA
26 Denah parsial-4 composite armatur MEP lantai 3 kelas VVIP dan VIP 1.00 9-Feb-19 19-Feb-19 B
GD. IRNA
27 Denah parsial-5 composite armatur MEP lantai 3 kelas VVIP dan VIP 1.00 9-Feb-19 19-Feb-19 B
GD. IRNA
28 Denah parsial-6 composite armatur MEP lantai 3 kelas VVIP dan VIP 1.00 9-Feb-19 19-Feb-19 B
GD. IRNA

437.00 Lembar
MONITORING SHOP DRAWING MEP GEDUNG MEDIK
JUMLAH TANGGAL PENGAJUAN REVISI 1 REVISI 2 REVISI 3 REVISI 4
NO JUDUL GAMBAR
LEMBAR MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS
GEDUNG MEDIK
A AIR BERSIH
1 Skematik Diagram Sistem Instalasi Air Bersih Dingin Gedung MEDIK 1.00
2 Skematik Diagram Sistem Instalasi Air Bersih Panas Gedung MEDIK 1.00
3 Denah Instalasi Air Bersih Lantai Basement Gedung MEDIK 1.00 7-Jan-19 17-Jan-19 C 8-Feb-19 16-Feb-19 C 21-Mar-19 9-Apr-19 B
4 Denah Parsial Instalasi Air Bersih Lantai Basement Gedung MEDIK 1.00 7-Jan-19 17-Jan-19 C 8-Feb-19 16-Feb-19 C 21-Mar-19 9-Apr-19 B
5 Denah Instalasi Air Bersih Lantai 1 Gedung MEDIK 1.00 7-Jan-19 17-Jan-19 C 8-Feb-19 16-Feb-19 C 21-Mar-19 9-Apr-19 B
6 Denah Parsial 1 Instalasi Air Bersih Lantai 1 Gedung MEDIK 1.00 7-Jan-19 17-Jan-19 C 8-Feb-19 16-Feb-19 C 21-Mar-19 9-Apr-19 B
7 Denah Parsial 2 Instalasi Air Bersih Lantai 1 Gedung MEDIK 1.00 7-Jan-19 17-Jan-19 C 8-Feb-19 16-Feb-19 C 21-Mar-19 9-Apr-19 B
8 Denah Instalasi Air Bersih Lantai 2 Gedung MEDIK 1.00 7-Jan-19 17-Jan-19 C 8-Feb-19 16-Feb-19 C 21-Mar-19 9-Apr-19 B
9 Denah Parsial 1 Instalasi Air Bersih Lantai 2 Gedung MEDIK 1.00 7-Jan-19 17-Jan-19 C 8-Feb-19 16-Feb-19 C 21-Mar-19 9-Apr-19 B
10 Denah Parsial 2 Instalasi Air Bersih Lantai 2 Gedung MEDIK 1.00 7-Jan-19 17-Jan-19 C 8-Feb-19 16-Feb-19 C 21-Mar-19 9-Apr-19 B
11 Denah Parsial 3 Instalasi Air Bersih Lantai 2 Gedung MEDIK 1.00 7-Jan-19 17-Jan-19 C 8-Feb-19 16-Feb-19 C 21-Mar-19 9-Apr-19 B
12 Denah Instalasi Air Bersih Lantai 3 Gedung MEDIK 1.00 7-Jan-19 17-Jan-19 C 8-Feb-19 16-Feb-19 C
13 Denah Parsial 1 Instalasi Air Bersih Lantai 3 Gedung MEDIK 1.00 7-Jan-19 17-Jan-19 C 8-Feb-19 16-Feb-19 C
14 Denah Parsial 2 Instalasi Air Bersih Lantai 3 Gedung MEDIK 1.00 7-Jan-19 17-Jan-19 C 8-Feb-19 16-Feb-19 C
15 Denah Parsial 3 Instalasi Air Bersih Lantai 3 Gedung MEDIK 1.00 7-Jan-19 17-Jan-19 C 8-Feb-19 16-Feb-19 C
16 Denah Instalasi Air Bersih Lantai 4 Gedung MEDIK 1.00
17 Detail Instalasi Air Bersih Toilet Lantai 1 Gedung MEDIK 1.00
18 Isometri Instalasi Air Bersih Toilet Lantai 1 Gedung MEDIK 1.00
19 Detail Instalasi Air Bersih Toilet Lantai 2 Gedung MEDIK 1.00
20 Isometri Instalasi Air Bersih Toilet Lantai 2 Gedung MEDIK 1.00
21 Detail Instalasi Air Bersih Toilet Lantai 3 Gedung MEDIK 1.00
22 Isometri Instalasi Air Bersih Toilet Lantai 3 Gedung MEDIK 1.00
23 Detail Instalasi Air Bersih Rooftank Lantai Atap Gedung MEDIK 1.00
24 Detail Instalasi Air Bersih GWT & Ruang Pompa Gedung MEDIK 1.00
25 Skematik Diagram Sistem Instalasi Ruang Pompa 1.00

B AIR LIMBAH
1 Skematik Diagram Sistem Instalasi Air Kotor, Bekas & Vent Gedung MEDIK 1.00 9-Oct-18 12-Oct-18 C 15-Oct-18 18-Oct-18 A
2 Denah Instalasi Air Kotor, Bekas & Vent Lantai Basement Gedung MEDIK 1.00 9-Oct-18 12-Oct-18 C 15-Oct-18 18-Oct-18 B
3 Denah Parsial Inst. Air Kotor, Bekas & Vent Zona 1 Lantai Basement Gedung MEDIK 1.00 9-Oct-18 12-Oct-18 C 15-Oct-18 18-Oct-18 B
4 Denah Parsial Inst. Air Kotor, Bekas & Vent Zona 2 Lantai Basement Gedung MEDIK 1.00 9-Oct-18 12-Oct-18 C 15-Oct-18 18-Oct-18 B
5 Denah Parsial Inst. Air Kotor, Bekas & Vent Zona 3 Lantai Basement Gedung MEDIK 1.00 9-Oct-18 12-Oct-18 C 15-Oct-18 18-Oct-18 B
6 Denah Instalasi Air Kotor, Bekas & Vent Lantai 1 Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 C 15-Oct-18 18-Oct-18 B 27-Apr-19 8-May-19 B
7 Denah Parsial Inst. Air Kotor, Bekas & Vent Zona 1 Lantai 1 Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 C 15-Oct-18 18-Oct-18 B 27-Apr-19 8-May-19 B
8 Denah Parsial Inst. Air Kotor, Bekas & Vent Zona 2 Lantai 1 Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 B 15-Oct-18 18-Oct-18 B 27-Apr-19 8-May-19 B
9 Denah Parsial Inst. Air Kotor, Bekas & Vent Zona 3 Lantai 1 Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 B 15-Oct-18 18-Oct-18 B
10 Denah Instalasi Air Kotor, Bekas & Vent Lantai 2 Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 C 15-Oct-18 18-Oct-18 B
11 Denah Parsial Inst. Air Kotor, Bekas & Vent Zona 1 Lantai 2 Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 C 15-Oct-18 18-Oct-18 B
12 Denah Parsial Inst. Air Kotor, Bekas & Vent Zona 2 Lantai 2 Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 C 15-Oct-18 18-Oct-18 B
13 Denah Parsial Inst. Air Kotor, Bekas & Vent Zona 3 Lantai 2 Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 B 15-Oct-18 18-Oct-18 B
14 Denah Instalasi Air Kotor, Bekas & Vent Lantai 3 Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 B 15-Oct-18 18-Oct-18 B
15 Denah Parsial Inst. Air Kotor, Bekas & Vent Zona 1 Lantai 3 Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 B 15-Oct-18 18-Oct-18 B
16 Denah Parsial Inst. Air Kotor, Bekas & Vent Zona 2 Lantai 3 Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 B 15-Oct-18 18-Oct-18 B
17 Denah Parsial Inst. Air Kotor, Bekas & Vent Zona 3 Lantai 3 Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 B 15-Oct-18 18-Oct-18 B
18 Denah Instalasi Air Kotor, Bekas & Vent Lantai 4 Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 B
19 Detail Instalasi Air Kotor, Bekas & Vent Toilet Umum 1 & 2 Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 C 15-Oct-18 18-Oct-18 B
20 Isometri Instalasi Air Kotor, Bekas & Vent Toilet Umum 1 & 2 Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 A
21 Detail Instalasi Air Kotor, Bekas & Vent Toilet 1, 2 & 3 Lantai 2 Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 B 15-Oct-18 18-Oct-18 B
22 Isometri Instalasi Air Kotor, Bekas & Vent Toilet 1, 2 & 3 Lantai 2 Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 A
23 Detail Instalasi Air Kotor, Bekas & Vent Toilet 1, 2 & 3 Lantai 3 Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 B 15-Oct-18 18-Oct-18 B
24 Isometri Instalasi Air Kotor, Bekas & Vent Toilet 1, 2 & 3 Lantai 3 Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 A
25 Detail Instalasi Air Kotor, Bekas & Vent Toilet 4, 5 & 6 Lantai 3 Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 B 15-Oct-18 18-Oct-18 B
26 Isometri Instalasi Air Kotor, Bekas & Vent Toilet 4, 5 & 6 Lantai 3 Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 A
27 Standar Detail 1 Pemasangan Inst. Air Kotor, Bekas & Vent Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 A
28 Standar Detail 2 Pemasangan Inst. Air Kotor, Bekas & Vent Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 A
29 Standar Detail 3 Pemasangan Inst. Air Kotor, Bekas & Vent Gedung MEDIK 1.00 9-Oct-18 11-Oct-18 B

C AIR HUJAN
1 Diagram skematik saluran air hujan GD.MEDIK 1.00 2-May-19 16-May-19 B
2 Denah inst. Saluran air hujan lantai basement GD.MEDIK 1.00 2-May-19 16-May-19 C
3 Denah parsial-1 inst. Saluran air hujan lantai basement GD.MEDIK 1.00 2-May-19 16-May-19 C
JUMLAH TANGGAL PENGAJUAN REVISI 1 REVISI 2 REVISI 3 REVISI 4
NO JUDUL GAMBAR
LEMBAR MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS
4 Denah parsial-2 inst. Saluran air hujan lantai basement GD.MEDIK 1.00 2-May-19 16-May-19 B
5 Denah inst. Saluran air hujan lantai 1 GD.MEDIK 1.00 2-May-19 16-May-19 C
6 Denah parsial-1 inst. Saluran air hujan lantai 1 GD.MEDIK 1.00 2-May-19 16-May-19 B
7 Denah parsial-2 inst. Saluran air hujan lantai 1 GD.MEDIK 1.00 2-May-19 16-May-19 C
8 Denah inst. Saluran air hujan lantai 2 GD.MEDIK 1.00 2-May-19 16-May-19 C
9 Denah parsial-1 inst. Saluran air hujan lantai 2 GD.MEDIK 1.00 2-May-19 16-May-19 C
10 Denah parsial-2 inst. Saluran air hujan lantai 2 GD.MEDIK 1.00 2-May-19 16-May-19 C
11 Denah inst. Saluran air hujan lantai 3 GD.MEDIK 1.00 2-May-19 16-May-19 C
12 Denah parsial-1 inst. Saluran air hujan lantai 3 GD.MEDIK 1.00 2-May-19 16-May-19 C
13 Denah parsial-2 inst. Saluran air hujan lantai 3 GD.MEDIK 1.00 2-May-19 16-May-19 C
14 Denah inst. Saluran air hujan lantai 4 GD.MEDIK 1.00 2-May-19 16-May-19 C
15 Denah parsial-1 inst. Saluran air hujan lantai 4 GD.MEDIK 1.00 2-May-19 16-May-19 C
16 Denah parsial-1 inst. Saluran air hujan lantai 4 GD.MEDIK 1.00 2-May-19 16-May-19 C
17 Denah inst. Saluran air hujan lantai Atap GD.MEDIK 1.00 2-May-19 16-May-19 B
18 Denah parsial-1 inst. Saluran air hujan lantai Atap GD.MEDIK 1.00 2-May-19 16-May-19 B
19 Denah parsial-1 inst. Saluran air hujan lantai Atap GD.MEDIK 1.00 2-May-19 16-May-19 B
20 Detail bak pompa sumpit air hujan GD.MEDIK 1.00 2-May-19 16-May-19 B

D PEMADAM KEBAKARAN
1 Skematik Diagram Sistem Inst. Pemadam Kebakaran Gedung MEDIK 1.00 16-Nov-18 17-Nov-18 C 13-Mar-19 25-Apr-19 C
2 Skematik Diagram Sistem Inst. Pemadam Kebakaran Zona 1 Gedung MEDIK 1.00 16-Nov-18 17-Nov-18 C 13-Mar-19 25-Apr-19 C
3 Skematik Diagram Sistem Inst. Pemadam Kebakaran Zona 2 Gedung MEDIK 1.00 16-Nov-18 17-Nov-18 C 13-Mar-19 25-Apr-19 C
4 Denah Instalasi Pemadam Kebakaran Lantai Basement Gedung MEDIK 1.00 16-Nov-18 17-Nov-18 C 3-Apr-19 12-Apr-19 C 27-Apr-19 8-May-19 B
5 Denah Instalasi Pemadam Kebakaran Zona 3 Lantai Basement Gedung MEDIK 1.00 16-Nov-18 17-Nov-18 C 3-Apr-19 12-Apr-19 C Sudah ACC masuk di zona 1 & 2
6 Denah Instalasi Pemadam Kebakaran Zona 2 Lantai Basement Gedung MEDIK 1.00 16-Nov-18 17-Nov-18 C 3-Apr-19 12-Apr-19 C 27-Apr-19 8-May-19 B
7 Denah Instalasi Pemadam Kebakaran Zona 1 Lantai Basement Gedung MEDIK 1.00 16-Nov-18 17-Nov-18 C 3-Apr-19 12-Apr-19 C 27-Apr-19 8-May-19 B
8 Detail Pemasangan Instalasi Pemadam Kebakaran Gedung MEDIK 1.00 16-Nov-18 17-Nov-18 C
9 Denah Instalasi Pemadam Kebakaran Lantai 1 1.00 27-Dec-18 28-Dec-18 C 13-Mar-19 25-Apr-19 C
10 Denah Parsial 1 Instalasi Pemadam Kebakaran Lantai 1 Gedung MEDIK 1.00 27-Dec-18 28-Dec-18 C 13-Mar-19 25-Apr-19 C
11 Denah Parsial 2 Instalasi Pemadam Kebakaran Lantai 1 Gedung MEDIK 1.00 27-Dec-18 28-Dec-18 C 13-Mar-19 25-Apr-19 C
12 Denah Instalasi Pemadam Kebakaran Lantai 2 Gedung MEDIK 1.00 8-Jan-19 15-Jan-19 B 13-Mar-19 25-Apr-19 B
13 Denah Parsial Instalasi Pemadam Kebakaran Zona 1 Lantai 2 Gedung MEDIK 1.00 8-Jan-19 15-Jan-19 B 13-Mar-19 25-Apr-19 B
14 Denah Parsial Instalasi Pemadam Kebakaran Zona 2 Lantai 2 Gedung MEDIK 1.00 8-Jan-19 15-Jan-19 B 13-Mar-19 25-Apr-19 B
15 Denah Instalasi Pemadam Kebakaran Lantai 3 Gedung MEDIK 1.00 8-Jan-19 15-Jan-19 C 13-Mar-19 25-Apr-19 C
16 Denah Parsial Instalasi Pemadam Kebakaran Zona 1 Lantai 3 Gedung MEDIK 1.00 8-Jan-19 15-Jan-19 B 13-Mar-19 25-Apr-19 C
17 Denah Parsial Instalasi Pemadam Kebakaran Zona 2 Lantai 3 Gedung MEDIK 1.00 8-Jan-19 15-Jan-19 C 13-Mar-19 25-Apr-19 B

E ELEVATOR
1 Technical Drawing Lift 01 & 02 Gedung MEDIK 1.00 16-Nov-18 17-Nov-18 C 10-Jan-19 19-Jan-19 B
1 Technical Drawing Lift 01 & 02 Gedung MEDIK 1.00 16-Nov-18 17-Nov-18 C 10-Jan-19 19-Jan-19 B
2 Technical Drawing Separator Beam & Machine Beam Lift 01 & 02 Gedung MEDIK 1.00 16-Nov-18 17-Nov-18 C 10-Jan-19 19-Jan-19 A
3 Technical Drawing Lift 03 & 04 Gedung MEDIK 1.00 16-Nov-18 17-Nov-18 C 10-Jan-19 19-Jan-19 B
3 Technical Drawing Lift 03 & 04 Gedung MEDIK 1.00 16-Nov-18 17-Nov-18 C 10-Jan-19 19-Jan-19 B
4 Technical Drawing Separator Beam & Machine Beam Lift 03 & 04 Gedung MEDIK 1.00 16-Nov-18 17-Nov-18 C 10-Jan-19 19-Jan-19 A
5 Technical Drawing Dumbweiter 01 & 02 Gedung MEDIK 1.00 16-Nov-18 17-Nov-18 C 10-Jan-19 19-Jan-19 C 26-Feb-19 25-Mar-19 B
6 Technical Drawing Separator Beam & Machine Beam Dumbweiter 01 & 02 Gedung MEDIK 1.00 16-Nov-18 17-Nov-18 C 10-Jan-19 19-Jan-19 C 26-Feb-19 25-Mar-19 B
7 Technical Drawing Dumbweiter 03 Gedung MEDIK 1.00 16-Nov-18 17-Nov-18 C 10-Jan-19 19-Jan-19 C 26-Feb-19 25-Mar-19 C
8 Technical Drawing Separator Beam & Machine Beam Dumbweiter 03 Gedung MEDIK 1.00 16-Nov-18 17-Nov-18 C 10-Jan-19 19-Jan-19 C 26-Feb-19 25-Mar-19 C
9 Technical Drawing Dumbweiter 04 Gedung MEDIK 1.00 16-Nov-18 17-Nov-18 C 10-Jan-19 19-Jan-19 C 26-Feb-19 25-Mar-19 C
10 Technical Drawing Separator Beam & Machine Beam Dumbweiter 04 Gedung MEDIK 1.00 16-Nov-18 17-Nov-18 C 10-Jan-19 19-Jan-19 C 26-Feb-19 25-Mar-19 C

F SKEDUL BEBAN LISTRIK


1 Skedul beban SDP Zona 1 GD medik 1.00 6-Mar-19 25-Apr-19
2 Skedul beban LP B1 dan PPAC B1 zona 1 GD medik 1.00 6-Mar-19 25-Apr-19
3 Skedul beban PP pompa dan PP elektronik GD medik 1.00 6-Mar-19 25-Apr-19
4 Skedul beban LP 1.1 zona 1 GD medik 1.00 6-Mar-19 25-Apr-19
5 Skedul beban PPAC 1.1A dan PPAC 1.1B zona 1 GD medik 1.00 6-Mar-19 25-Apr-19
6 Skedul beban LP 2.1 zona 1 GD medik 1.00 6-Mar-19 25-Apr-19
7 Skedul beban PPAC 2.1A dan PPAC 2.1B zona 1 GD medik 1.00 6-Mar-19 25-Apr-19
8 Skedul beban LP 3.1 zona 1 GD medik 1.00 6-Mar-19 25-Apr-19
9 Skedul beban PPAC 3 GD medik 1.00 6-Mar-19 25-Apr-19
10 Skedul beban PP.ICU dan PP critikal GD medik 1.00 6-Mar-19 25-Apr-19
11 Skedul beban SDP 4.1 GD medik 1.00 6-Mar-19 25-Apr-19
12 Skedul beban LP 4.1 dan PPAC 4.1 zona 1 GD medik 1.00 6-Mar-19 25-Apr-19
JUMLAH TANGGAL PENGAJUAN REVISI 1 REVISI 2 REVISI 3 REVISI 4
NO JUDUL GAMBAR
LEMBAR MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS
13 Skedul beban SDP Zona 2 GD medik 1.00 6-Mar-19 25-Apr-19
14 skedul beban LP B.2 dan PPAC B.2 zona 2 GD medik 1.00 6-Mar-19 25-Apr-19
15 Skedul beban LP OL, PP loundry dan PP CSSD GD medik 1.00 6-Mar-19 25-Apr-19
16 Skedul beban LP 1.2 zona 2 GD medik 1.00 6-Mar-19 25-Apr-19
17 Skedul beban BS tenant 1, BS tenant 2 dan BS tenant ATM GD medik 1.00 6-Mar-19 25-Apr-19
18 Skedul beban PPAC 1.2A dan PPAC 1.2B zona 2 GD medik 1.00 6-Mar-19 25-Apr-19
19 Skedul beban LP 2.2 zona 2 GD medik 1.00 6-Mar-19 25-Apr-19
20 Skedul beban PPAC 2.2 zona 2 GD medik 1.00 6-Mar-19 25-Apr-19
21 Skedul beban PP NICU GD medik 1.00 6-Mar-19 25-Apr-19
22 Skedul beban LP 3.2 zona 2 GD medik 1.00 6-Mar-19 25-Apr-19
23 Skedul beban SDP 4.2 GD medik 1.00 6-Mar-19 25-Apr-19
24 Skedul beban LP 4.2 dan PPAC 4.2 GD medik 1.00 6-Mar-19 25-Apr-19
25 Skedul beban PP.OK 1,2,3,5,6,7 GD medik 1.00 6-Mar-19 25-Apr-19
26 Skedul beban PP.OK 4 GD medik 1.00 6-Mar-19 25-Apr-19
27 Skedul beban PP.OK 8 GD medik 1.00 6-Mar-19 25-Apr-19
28 Skedul beban PP.OK 9 GD medik 1.00 6-Mar-19 25-Apr-19
29 Skedul beban SDP emergency utama GD medik 1.00 6-Mar-19 25-Apr-19
30 Skedul beban SDP emergency 1 dan PP press fan 1 GD medik 1.00 6-Mar-19 25-Apr-19
31 Skedul beban SDP emergency 2 dan PP press fan 2 GD medik 1.00 6-Mar-19 25-Apr-19

G DISTRIBUSI LISTRIK & KABEL TRAY


1 Skematik Diagram Sistem Distribusi Listrik Gedung MEDIK 1.00 19-Feb-19 22-Feb-19 C 25-Jun-19 MK
2 Denah Instalasi Kabel Tray Lantai Basement Gedung MEDIK 1.00 19-Feb-19 22-Feb-19 C 25-Jun-19 MK
3 Denah Instalasi Kabel Tray Lantai 1 Gedung MEDIK 1.00 19-Feb-19 22-Feb-19 B
4 Denah Instalasi Kabel Tray Lantai 2 Gedung MEDIK 1.00 19-Feb-19 22-Feb-19 B
5 Denah Instalasi Kabel Tray Lantai 3 Gedung MEDIK 1.00 19-Feb-19 22-Feb-19 B
6 Denah Instalasi Kabel Tray Lantai 4 Gedung MEDIK 1.00 25-Jun-19 MK
7 Standar-1 detail tray kabel Gedung MEDIK 1.00 25-Jun-19 MK
8 Standar-2 detail tray kabel Gedung MEDIK 1.00 25-Jun-19 MK
9 Standar-3 detail tray kabel Gedung MEDIK 1.00 25-Jun-19 MK
10 Standar-4 detail tray kabel Gedung MEDIK 1.00 25-Jun-19 MK

H PENERANGAN
1 Denah Instalasi Penerangan Lantai Basement Gedung MEDIK 1.00 13-Sep-18 17-Sep-18 B
2 Denah Parsial Inst. Penerangan Lantai Zona 1 Lantai Basement Gedung MEDIK 1.00 13-Sep-18 17-Sep-18 B
3 Denah Parsial Inst. Penerangan Lantai Zona 2 Lantai Basement Gedung MEDIK 1.00 13-Sep-18 17-Sep-18 B
4 Denah Instalasi Penerangan Lantai 1 Gedung MEDIK 1.00 13-Sep-18 17-Sep-18 B
5 Denah Parsial Inst. Penerangan Lantai Zona 1 Lantai 1 Gedung MEDIK 1.00 13-Sep-18 17-Sep-18 B
6 Denah Parsial Inst. Penerangan Lantai Zona 2 Lantai 1 Gedung MEDIK 1.00 13-Sep-18 17-Sep-18 B
7 Denah Instalasi Penerangan Lantai 2 Gedung MEDIK 1.00 13-Sep-18 17-Sep-18 B
8 Denah Parsial Inst. Penerangan Lantai Zona 1 Lantai 2 Gedung MEDIK 1.00 13-Sep-18 17-Sep-18 B
9 Denah Parsial Inst. Penerangan Lantai Zona 2 Lantai 2 Gedung MEDIK 1.00 13-Sep-18 17-Sep-18 B
10 Denah Instalasi Penerangan Lantai 3 Gedung MEDIK 1.00 13-Sep-18 17-Sep-18 C 11-Oct-18 16-Oct-18 B
11 Denah Parsial Inst. Penerangan Lantai Zona 1 Lantai 3 Gedung MEDIK 1.00 13-Sep-18 17-Sep-18 B 11-Oct-18 16-Oct-18 B
12 Denah Parsial Inst. Penerangan Lantai Zona 2 Lantai 3 Gedung MEDIK 1.00 13-Sep-18 17-Sep-18 C 11-Oct-18 16-Oct-18 B
13 Denah Instalasi Penerangan Lantai 4 Gedung MEDIK 1.00 13-Sep-18 17-Sep-18 B
14 Detail Pemasangan Instalasi Penerangan Gedung MEDIK 1.00 13-Sep-18 17-Sep-18 A

I STOP KONTAK
1 Denah Instalasi Stop Kontak Lantai Basement Gedung MEDIK 1.00 27-Sep-18 3-Oct-18 A
2 Denah Instalasi Stop Kontak Lantai Basement Parsial 1 Gedung MEDIK 1.00 27-Sep-18 3-Oct-18 A
3 Denah Instalasi Stop Kontak Lantai Basement Parsial 2 Gedung MEDIK 1.00 27-Sep-18 3-Oct-18 A
4 Denah Instalasi Stop Kontak Lantai 1 Gedung MEDIK 1.00 27-Sep-18 3-Oct-18 C 11-Oct-18 16-Oct-18 B 18-Mar-19 21-Mar-19 C 15-Apr-19 8-May-19 C
5 Denah Instalasi Stop Kontak Lantai 1 Parsial 1 Gedung MEDIK 1.00 27-Sep-18 3-Oct-18 B 11-Oct-18 16-Oct-18 B 18-Mar-19 21-Mar-19 C 15-Apr-19 8-May-19 C
6 Denah Instalasi Stop Kontak Lantai 1 Parsial 2 Gedung MEDIK 1.00 27-Sep-18 3-Oct-18 C 11-Oct-18 16-Oct-18 B 18-Mar-19 21-Mar-19 C 15-Apr-19 8-May-19 C
7 Denah Instalasi Stop Kontak Lantai 2 Gedung MEDIK 1.00 27-Sep-18 3-Oct-18 C 11-Oct-18 16-Oct-18 C 18-Mar-19 21-Mar-19 C 15-Apr-19 8-May-19 B
8 Denah Instalasi Stop Kontak Lantai 2 Parsial 1 Gedung MEDIK 1.00 27-Sep-18 3-Oct-18 B 11-Oct-18 16-Oct-18 C 18-Mar-19 21-Mar-19 C 15-Apr-19 8-May-19 B
9 Denah Instalasi Stop Kontak Lantai 2 Parsial 2 Gedung MEDIK 1.00 27-Sep-18 3-Oct-18 C 11-Oct-18 16-Oct-18 C 18-Mar-19 21-Mar-19 C 15-Apr-19 8-May-19 B
10 Denah Instalasi Stop Kontak Lantai 3 Gedung MEDIK 1.00 27-Sep-18 3-Oct-18 C 11-Oct-18 16-Oct-18 C 18-Mar-19 21-Mar-19 C 15-Apr-19 8-May-19 C
11 Denah Instalasi Stop Kontak Lantai 3 Parsial 1 Gedung MEDIK 1.00 27-Sep-18 3-Oct-18 C 11-Oct-18 16-Oct-18 C 18-Mar-19 21-Mar-19 C 15-Apr-19 8-May-19 B
12 Denah Instalasi Stop Kontak Lantai 3 Parsial 2 Gedung MEDIK 1.00 27-Sep-18 3-Oct-18 C 11-Oct-18 16-Oct-18 B 18-Mar-19 21-Mar-19 C 15-Apr-19 8-May-19 hg
13 Denah Instalasi Stop Kontak Lantai 4 Gedung MEDIK 1.00 27-Sep-18 3-Oct-18 C 11-Oct-18 16-Oct-18 C
14 Detail Pemasangan Stop Kontak Bedhead Gedung MEDIK 1.00 27-Sep-18 3-Oct-18 B 11-Oct-18 16-Oct-18 B
JUMLAH TANGGAL PENGAJUAN REVISI 1 REVISI 2 REVISI 3 REVISI 4
NO JUDUL GAMBAR
LEMBAR MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS
J PENYALUR PETIR & GROUNDING
1 Diagram skematik & daerah proteksi penyalur petir 1.00 11-Apr-19 24-Apr-19 B
2 Denah tata letak dan radius proteksi penyalur petir 1.00 11-Apr-19 24-Apr-19 B
3 Denah grounding basement GD.Medik 1.00 11-Apr-19 24-Apr-19 C
4 Denah parsial-1 grounding basement GD.Medik 1.00 11-Apr-19 24-Apr-19 B
5 Denah parsial-2 grounding basement GD.Medik 1.00 11-Apr-19 24-Apr-19 C
6 Standar detail penyalur petir 1.00 11-Apr-19 24-Apr-19 C

K FIRE ALARM
1 Skematik Diagram Sistem Instalasi Fire Alarm Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 C 30-Mar-19 12-Apr-19 B
2 Denah Instalasi Fire Alarm Lantai Basement Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 C 30-Mar-19 12-Apr-19 B
3 Denah Parsial Instalasi Fire Alarm Zona 1 Lantai Basement Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 C 30-Mar-19 12-Apr-19 B
4 Denah Parsial Instalasi Fire Alarm Zona 2 Lantai Basement Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 C 30-Mar-19 12-Apr-19 C 15-Apr-19 4-May-19 C
5 Denah Instalasi Fire Alarm Lantai 1 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 C 30-Mar-19 12-Apr-19 B
6 Denah Parsial Instalasi Fire Alarm Zona 1 Lantai 1 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 C 30-Mar-19 12-Apr-19 B
7 Denah Parsial Instalasi Fire Alarm Zona 2 Lantai 1 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 C 30-Mar-19 12-Apr-19 B
8 Denah Instalasi Fire Alarm Lantai 2 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 C 30-Mar-19 12-Apr-19 B
9 Denah Parsial Instalasi Fire Alarm Zona 1 Lantai 2 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 C 30-Mar-19 12-Apr-19 B
10 Denah Parsial Instalasi Fire Alarm Zona 1 Lantai 2 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 C 30-Mar-19 12-Apr-19 B
11 Denah Instalasi Fire Alarm Lantai 3 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 C 30-Mar-19 12-Apr-19 B
12 Denah Parsial Instalasi Fire Alarm Zona 1 Lantai 3 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 C 30-Mar-19 12-Apr-19 B
13 Denah Parsial Instalasi Fire Alarm Zona 1 Lantai 3 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 C 30-Mar-19 12-Apr-19 B
14 Denah Instalasi Fire Alarm Lantai 4 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 B
15 Detail Standar Pemasangan Instalasi Fire Alarm Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 A

L SOUND SYSTEM
1 Skematik Diagram Sistem Instalasi Tata Suara Gedung MEDIK 1.00 11-Dec-18 17-Dec-18 C 1-Feb-19 9-Feb-19 B
2 Denah Instalasi Tata Suara Lantai Basement Gedung MEDIK 1.00 11-Dec-18 17-Dec-18 C 1-Feb-19 9-Feb-19 C 12-Feb-19 16-Feb-19 C 30-Mar-19 5-Apr-19 B 30-Mar-19 5-Apr-19 B
3 Denah Parsial Instalasi Tata Suara Zona 1 Lantai Basement Gedung MEDIK 1.00 11-Dec-18 17-Dec-18 C 1-Feb-19 9-Feb-19 C 12-Feb-19 16-Feb-19 C 30-Mar-19 5-Apr-19 B 30-Mar-19 5-Apr-19 B
4 Denah Parsial Instalasi Tata Suara Zona 2 Lantai Basement Gedung MEDIK 1.00 11-Dec-18 17-Dec-18 C 1-Feb-19 9-Feb-19 C 12-Feb-19 16-Feb-19 C 30-Mar-19 5-Apr-19 B 30-Mar-19 5-Apr-19 B
5 Denah Instalasi Tata Suara Lantai 1 Gedung MEDIK 1.00 11-Dec-18 17-Dec-18 C 1-Feb-19 9-Feb-19 B
6 Denah Parsial Instalasi Tata Suara Zona 1 Lantai 1 Gedung MEDIK 1.00 11-Dec-18 17-Dec-18 B
7 Denah Parsial Instalasi Tata Suara Zona 2 Lantai 1 Gedung MEDIK 1.00 11-Dec-18 17-Dec-18 C 1-Feb-19 9-Feb-19 B
8 Denah Instalasi Tata Suara Lantai 2 Gedung MEDIK 1.00 11-Dec-18 17-Dec-18 B
9 Denah Parsial Instalasi Tata Suara Zona 1 Lantai 2 Gedung MEDIK 1.00 11-Dec-18 17-Dec-18 B
10 Denah Parsial Instalasi Tata Suara Zona 2 Lantai 2 Gedung MEDIK 1.00 11-Dec-18 17-Dec-18 B
11 Denah Instalasi Tata Suara Lantai 3 Gedung MEDIK 1.00 11-Dec-18 17-Dec-18 C 1-Feb-19 9-Feb-19 B 15-Apr-19 4-May-19 B
12 Denah Parsial Instalasi Tata Suara Zona 1 Lantai 3 Gedung MEDIK 1.00 11-Dec-18 17-Dec-18 C 1-Feb-19 9-Feb-19 B 15-Apr-19 4-May-19 B
13 Denah Parsial Instalasi Tata Suara Zona 2 Lantai 3 Gedung MEDIK 1.00 11-Dec-18 17-Dec-18 C 1-Feb-19 9-Feb-19 B 15-Apr-19 4-May-19 B
14 Denah Instalasi Tata Suara Lantai 4 Gedung MEDIK 1.00 11-Dec-18 17-Dec-18 C
15 Standar Detail Pemasangan Instalasi Tata Suara Gedung MEDIK 1.00 11-Dec-18 17-Dec-18 A

M TELEPON
1 Skematik Diagram Sistem Instalasi Telephone Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 C 24-Dec-18 26-Dec-18 B
2 Denah Instalasi Telephone Lantai Basement Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 B
3 Denah Parsial Instalasi Telephone Zona 1 Lantai Basement Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 B
4 Denah Parsial Instalasi Telephone Zona 2 Lantai Basement Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 B
5 Denah Instalasi Telephone Lantai 1 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 B
6 Denah Parsial Instalasi Telephone Zona 1 Lantai 1 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 B
7 Denah Parsial Instalasi Telephone Zona 2 Lantai 1 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 B
8 Denah Instalasi Telephone Lantai 2 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 B
9 Denah Parsial Instalasi Telephone Zona 1 Lantai 2 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 B
10 Denah Parsial Instalasi Telephone Zona 2 Lantai 2 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 B
11 Denah Instalasi Telephone Lantai 3 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 C 24-Dec-19 26-Dec-18 B 15-Apr-19 MK
12 Denah Parsial Instalasi Telephone Zona 1 Lantai 3 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 C 24-Dec-19 26-Dec-18 B 15-Apr-19 MK
13 Denah Parsial Instalasi Telephone Zona 2 Lantai 3 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 C 24-Dec-19 26-Dec-18 B 15-Apr-19 MK
14 Detail Standar Pemasangan Instalasi Telephone Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 A

N DATA & WIFI


1 Skematik Diagram Sistem Instalasi Data & Wifi Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 C 11-Dec-18 14-Dec-18 A
2 Denah Instalasi Data & Wifi Lantai Basement Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 B
3 Denah Parsial Inst. Data & Wifi Zona 1 Lantai Basement Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 B
4 Denah Parsial Inst. Data & Wifi Zona 2 Lantai Basement Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 B
5 Denah Instalasi Data & Wifi Lantai 1 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 B
JUMLAH TANGGAL PENGAJUAN REVISI 1 REVISI 2 REVISI 3 REVISI 4
NO JUDUL GAMBAR
LEMBAR MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS
6 Denah Parsial Inst. Data & Wifi Zona 1 Lantai 1 Lantai 1 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 B
7 Denah Parsial Inst. Data & Wifi Zona 2 Lantai 1 Lantai 1 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 B
8 Denah Instalasi Data & Wifi Lantai 2 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 B
9 Denah Parsial Inst. Data & Wifi Zona 1 Lantai 2 Lantai 2 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 B
10 Denah Parsial Inst. Data & Wifi Zona 2 Lantai 2 Lantai 2 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 B
11 Denah Instalasi Data & Wifi Lantai 3 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 C 11-Dec-18 14-Dec-18 B 15-Apr-19 24-Apr-19 C
12 Denah Parsial Inst. Data & Wifi Zona 1 Lantai 3 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 C 11-Dec-18 14-Dec-18 B 15-Apr-19 24-Apr-19 B
13 Denah Parsial Inst. Data & Wifi Zona 2 Lantai 3 Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 C 11-Dec-18 14-Dec-18 B 15-Apr-19 24-Apr-19 C
14 Detail Standar Pemasangan Instalasi Data & Wifi Gedung MEDIK 1.00 28-Nov-18 1-Dec-18 A

MATV
1 Skematik Diagram Sistem Instalasi MATV Gedung Medik 1.00 11-Dec-18 12-Dec-18 A
2 Denah Instalasi MATV Lantai Basement Gedung Medik 1.00 11-Dec-18 12-Dec-18 B
3 Denah Instalasi MATV Lantai 1 Gedung Medik 1.00 11-Dec-18 12-Dec-18 B
4 Denah Parsial Instalasi MATV Zona 1 Lantai 1 Gedung Medik 1.00 11-Dec-18 12-Dec-18 B
5 Denah Parsial Instalasi MATV Zona 2 Lantai 1 Gedung Medik 1.00 11-Dec-18 12-Dec-18 B
6 Denah Instalasi MATV Lantai 2 Gedung Medik 1.00 11-Dec-18 12-Dec-18 B
7 Denah Parsial Instalasi MATV Zona 1 Lantai 2 Gedung Medik 1.00 11-Dec-18 12-Dec-18 B
8 Denah Parsial Instalasi MATV Zona 2 Lantai 2 Gedung Medik 1.00 11-Dec-18 12-Dec-18 B
9 Denah Instalasi MATV Lantai 3 Gedung Medik 1.00 11-Dec-18 12-Dec-18 B
10 Denah Parsial Instalasi MATV Zona 1 Lantai 3 Gedung Medik 1.00 11-Dec-18 12-Dec-18 B

O CCTV
1 Diagram skematik CCTV GD. MEDIK 1.00 19-Jun-19 MK
Denah inst. CCTV lantai basement GD. MEDIK 1.00 19-Jun-19 MK
Denah parsial-1 inst. CCTV lantai basement GD. MEDIK 1.00 19-Jun-19 MK
Denah parsial-2 inst. CCTV lantai basement GD. MEDIK 1.00 19-Jun-19 MK
Denah inst. CCTV lantai 1 GD. MEDIK 1.00 19-Jun-19 MK
Denah parsial-1 inst. CCTV lantai 1 GD. MEDIK 1.00 19-Jun-19 MK
Denah parsial-2 inst. CCTV lantai 1 GD. MEDIK 1.00 19-Jun-19 MK
Denah inst. CCTV lantai 2 GD. MEDIK 1.00 19-Jun-19 MK
Denah parsial-1 inst. CCTV lantai 2 GD. MEDIK 1.00 19-Jun-19 MK
Denah parsial-2 inst. CCTV lantai 2 GD. MEDIK 1.00 19-Jun-19 MK
Denah inst. CCTV lantai 3 GD. MEDIK 1.00 19-Jun-19 MK
Denah parsial-1 inst. CCTV lantai 3 GD. MEDIK 1.00 19-Jun-19 MK
Denah parsial-2 inst. CCTV lantai 3 GD. MEDIK 1.00 19-Jun-19 MK
Standar detail CCTV GD. MEDIK 1.00 19-Jun-19 MK

P NURSE CALL
1 Skematik Diagarm Sistem Instalasi Nurse Call Gedung MEDIK 1.00 14-Dec-18 19-Dec-18 A
2 Denah Instalasi Nurse Call Lantai 2 Gedung MEDIK 1.00 14-Dec-18 19-Dec-18 C 7-Jan-19 10-Jan-19 C 1-Feb-19 8-Feb-19 B
3 Denah Parsial Instalasi Nurse Call Lantai 2 Gedung MEDIK 1.00 14-Dec-18 19-Dec-18 C 7-Jan-19 10-Jan-19 C 1-Feb-19 8-Feb-19 B
4 Denah Instalasi Nurse Call Lantai 3 Gedung MEDIK 1.00 14-Dec-18 19-Dec-18 C 7-Jan-19 10-Jan-19 B
5 Denah Parsial Instalasi Nurse Call Lantai 3 Gedung MEDIK 1.00 14-Dec-18 19-Dec-18 C 7-Jan-19 10-Jan-19 B

Q SISTEM ANTRIAN
1 Skematik Diagram Instalasi Sistem Antrian Gedung MEDIK 1.00 25-Jan-19 31-Jan-19 C 9-Mar-19 12-Apr-19 C
2 Denah Instalasi Sistem Antrian Lantai 1 Gedung MEDIK 1.00 25-Jan-19 31-Jan-19 C 9-Mar-19 12-Apr-19 B
3 Denah Parsial 1 Instalasi Sistem Antrian Lantai 1 Gedung MEDIK 1.00 25-Jan-19 31-Jan-19 C 9-Mar-19 12-Apr-19 B
4 Denah Parsial 2 Instalasi Sistem Antrian Lantai 1 Gedung MEDIK 1.00 25-Jan-19 31-Jan-19 C 9-Mar-19 12-Apr-19 B
5 Denah Instalasi Sistem Antrian Lantai 2 Gedung MEDIK 1.00 25-Jan-19 31-Jan-19 C 9-Mar-19 12-Apr-19 B
6 Denah Parsial Instalasi Sistem Antrian Lantai 2 Gedung MEDIK 1.00 25-Jan-19 31-Jan-19 C 9-Mar-19 12-Apr-19 B

R TATA UDARA
1 Denah Instalasi Power AC Lantai Basement Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 C 29-Nov-18 17-Dec-18 C 13-Jun-19 MK
2 Denah Parsial Instalasi Power AC Zona 1 Lantai Basement Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 C 29-Nov-18 17-Dec-18 C 5-Mar-19 9-Mar-19 B 13-Jun-19 MK
3 Denah Parsial Instalasi Power AC Zona 2 Lantai Basement Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 C 29-Nov-18 17-Dec-18 C 13-Jun-19 MK
4 Denah Parsial Instalasi Power AC Zona 3 Lantai Basement Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 C 29-Nov-18 17-Dec-18 B
5 Denah Instalasi Drain AC Lantai Basement Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 C 29-Nov-18 17-Dec-18 C 5-Mar-19 9-Mar-19 B 13-Jun-19 MK
6 Denah Parsial Instalasi Drain AC Zona 1 Lantai Basement Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 C 29-Nov-18 17-Dec-18 C 5-Mar-19 9-Mar-19 B 13-Jun-19 MK
7 Denah Parsial Instalasi Drain AC Zona 2 Lantai Basement Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 C 29-Nov-18 17-Dec-18 B 13-Jun-19 MK
8 Denah Parsial Instalasi Drain AC Zona 3 Lantai Basement Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 C 29-Nov-18 17-Dec-18 B
9 Denah Instalasi Power AC Lantai 1 Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 C 29-Nov-18 17-Dec-18 C 12-Feb-19 23-Feb-19 B 13-Jun-19 MK
10 Denah Parsial Instalasi Power AC Zona 1 Lantai 1 Lantai 1 Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 C 29-Nov-18 17-Dec-18 C 12-Feb-19 23-Feb-19 B 13-Jun-19 MK
JUMLAH TANGGAL PENGAJUAN REVISI 1 REVISI 2 REVISI 3 REVISI 4
NO JUDUL GAMBAR
LEMBAR MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS
11 Denah Parsial Instalasi Power AC Zona 2 Lantai 1 Lantai 1 Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 C 29-Nov-18 17-Dec-18 C 12-Feb-19 23-Feb-19 B 13-Jun-19 MK
12 Denah Parsial Instalasi Power AC Zona 3 Lantai 1 Lantai 1 Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 C 29-Nov-18 17-Dec-18 C 12-Feb-19 23-Feb-19 B
13 Denah Instalasi Drain AC Lantai 1 Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 C 29-Nov-18 17-Dec-18 C 12-Feb-19 23-Feb-19 C 13-Jun-19 MK
14 Denah Parsial Instalasi Drain AC Zona 1 Lantai 1 Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 C 29-Nov-18 17-Dec-18 C 12-Feb-19 23-Feb-19 C 13-Jun-19 MK
15 Denah Parsial Instalasi Drain AC Zona 2 Lantai 1 Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 C 29-Nov-18 17-Dec-18 C 12-Feb-19 23-Feb-19 C 13-Jun-19 MK
16 Denah Parsial Instalasi Drain AC Zona 3 Lantai 1 Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 C 29-Nov-18 17-Dec-18 C 12-Feb-19 23-Feb-19 C
17 Denah Instalasi Power AC Lantai 2 Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 B 12-Feb-19 23-Feb-19 B 13-Jun-19 MK
18 Denah Parsial Instalasi Power AC Zona 1 Lantai 2 Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 B 12-Feb-19 23-Feb-19 B 13-Jun-19 MK
19 Denah Parsial Instalasi Power AC Zona 2 Lantai 2 Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 B 12-Feb-19 23-Feb-19 B 13-Jun-19 MK
20 Denah Parsial Instalasi Power AC Zona 3 Lantai 2 Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 B 12-Feb-19 23-Feb-19 B
21 Denah Instalasi Drain AC Lantai 2 Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 B 12-Feb-19 23-Feb-19 B 13-Jun-19 MK
22 Denah Parsial Instalasi Drain AC Zona 1 Lantai 2 Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 B 12-Feb-19 23-Feb-19 B 13-Jun-19 MK
23 Denah Parsial Instalasi Drain AC Zona 2 Lantai 2 Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 B 12-Feb-19 23-Feb-19 B 13-Jun-19 MK
24 Denah Parsial Instalasi Drain AC Zona 3 Lantai 2 Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 B 12-Feb-19 23-Feb-19 B
25 Denah Instalasi Ducting AC Lantai 2 Gedung MEDIK 1.00 10-Nov-18 14-Nov-18 C 29-Nov-18 17-Dec-18 B 15-Apr-19 8-May-19 C
26 Denah Instalasi Power AC Lantai 3 Gedung MEDIK 1.00 13-Mar-19 16-Mar-19 C 13-Jun-19 MK
27 Denah Parsial Instalasi Power AC Zona 1 Lantai 3 Gedung MEDIK 1.00 13-Mar-19 16-Mar-19 C 13-Jun-19 MK
28 Denah Parsial Instalasi Power AC Zona 2 Lantai 3 Gedung MEDIK 1.00 13-Mar-19 16-Mar-19 C 13-Jun-19 MK
29 Denah Parsial Instalasi Power AC Zona 3 Lantai 3 Gedung MEDIK 1.00 13-Mar-19 16-Mar-19 C
30 Denah Instalasi Drain AC Lantai 3 Gedung MEDIK 1.00 13-Mar-19 16-Mar-19 C 13-Jun-19 MK
31 Denah Parsial Instalasi Drain AC Zona 1 Lantai 3 Gedung MEDIK 1.00 13-Mar-19 16-Mar-19 C 13-Jun-19 MK
32 Denah Parsial Instalasi Drain AC Zona 2 Lantai 3 Gedung MEDIK 1.00 13-Mar-19 16-Mar-19 C 13-Jun-19 MK
33 Denah Parsial Instalasi Drain AC Zona 3 Lantai 3 Gedung MEDIK 1.00 13-Mar-19 16-Mar-19 C
34 Denah Instalasi Ducting Ruang OK Lantai 3 Gedung MEDIK 1.00 13-Mar-19 16-Mar-19 C 15-Apr-19 8-May-19 B
35 Denah Instalasi Ducting Lantai 3 Gedung MEDIK 1.00 13-Mar-19 16-Mar-19 C 13-Jun-19 MK
36 Denah instalasi ducting AC zona 1 lantai 3 GD.MEDIK 1.00 13-Jun-19 MK
37 Denah instalasi ducting AC zona 2 lantai 3 GD.MEDIK 1.00 13-Jun-19 MK
38 Denah instalasi power AC lantai 4 GD.MEDIK 1.00 13-Jun-19 MK
39 Denah instalasi drain AC lantai 4 GD.MEDIK 1.00 13-Jun-19 MK
40 Denah instalasi ducting AC lantai 4 GD.MEDIK 1.00 13-Jun-19 MK

S VENTILASI MEKANIK
1 Denah Instalasi Ventilasi Mekanik Lantai Basement Gedung MEDIK 1.00 13-Jun-19 MK
2 Denah Parsial Instalasi Ventilasi Mekanik Zona 1 Lantai Basement Gedung MEDIK 1.00 13-Jun-19 MK
3 Denah Parsial Instalasi Ventilasi Mekanik Zona 2 Lantai Basement Gedung MEDIK 1.00 13-Jun-19 MK
4 Denah Parsial Instalasi Ventilasi Mekanik Zona 3 Lantai Basement Gedung MEDIK 1.00
5 Denah Parsial Instalasi Ducting Toilet Lantai Basement Gedung MEDIK 1.00
6 Denah Instalasi Ventilasi Mekanik Lantai 1 Gedung MEDIK 1.00 22-Dec-18 27-Dec-18 C 13-Jun-19 MK
7 Denah Parsial Instalasi Ventilasi Mekanik Zona 1 Lantai 1 Gedung MEDIK 1.00 22-Dec-18 27-Dec-18 C 13-Jun-19 MK
8 Denah Parsial Instalasi Ventilasi Mekanik Zona 2 Lantai 1 Gedung MEDIK 1.00 22-Dec-18 27-Dec-18 C 13-Jun-19 MK
9 Denah Parsial Instalasi Ventilasi Mekanik Zona 3 Lantai 1 Gedung MEDIK 1.00 22-Dec-18 27-Dec-18 C
10 Denah Parsial Instalasi Ducting Toilet Lantai 1 Gedung MEDIK 1.00 22-Dec-18 27-Dec-18 C
11 Denah Instalasi Ventilasi Mekanik Lantai 2 Gedung MEDIK 1.00 13-Jun-19 MK
12 Denah Parsial Instalasi Ventilasi Mekanik Zona 1 Lantai 2 Gedung MEDIK 1.00 13-Jun-19 MK
13 Denah Parsial Instalasi Ventilasi Mekanik Zona 2 Lantai 2 Gedung MEDIK 1.00 13-Jun-19 MK
14 Denah Parsial Instalasi Ventilasi Mekanik Zona 3 Lantai 2 Gedung MEDIK 1.00
15 Denah Parsial Instalasi Ducting Toilet Lantai 2 Gedung MEDIK 1.00
16 Denah Instalasi Ventilasi Mekanik Lantai 3 Gedung MEDIK 1.00 13-Jun-19 MK
17 Denah Parsial Instalasi Ventilasi Mekanik Zona 1 Lantai 3 Gedung MEDIK 1.00 13-Jun-19 MK
18 Denah Parsial Instalasi Ventilasi Mekanik Zona 2 Lantai 3 Gedung MEDIK 1.00 13-Jun-19 MK
19 Denah Parsial Instalasi Ventilasi Mekanik Zona 3 Lantai 3 Gedung MEDIK 1.00
20 Denah Parsial Instalasi Ducting Toilet Lantai 3 Gedung MEDIK 1.00
21 Standar detail 1 ventilasi mekanik GD.MEDIK 1.00 13-Jun-19 MK
22 Standar detail 2 ventilasi mekanik GD.MEDIK 1.00 13-Jun-19 MK

T GAS MEDIS
1 Skematik Diagram Sistem Instalai Gas Medis 1.00 7-Dec-18 21-Dec-18 C 20-Dec-18 21-Dec-18 C 5-Apr-19 12-Apr-19 B
2 Denah Instalasi Gas Medis Lantai Basement Gedung MEDIK 1.00 7-Dec-18 21-Dec-18 C 20-Dec-18 21-Dec-18 B
3 Denah Parsial Instalasi Gas Medis Lantai Basement Gedung MEDIK 1.00 7-Dec-18 21-Dec-18 C 20-Dec-18 21-Dec-18 B
4 Denah Instalasi Gas Medis Lantai 1 Gedung MEDIK 1.00 7-Dec-18 21-Dec-18 B
5 Denah Parsial Instalasi Gas Medis Zona 1 Lantai 1 Gedung MEDIK 1.00 7-Dec-18 21-Dec-18 B
6 Denah Parsial Instalasi Gas Medis Zona 2 Lantai 1 Gedung MEDIK 1.00 7-Dec-18 21-Dec-18 B
7 Denah Instalasi Gas Medis Lantai 2 Gedung MEDIK 1.00 7-Dec-18 21-Dec-18 B
8 Denah Parsial Instalasi Gas Medis Zona 1 Lantai 2 Gedung MEDIK 1.00 7-Dec-18 21-Dec-18 B
JUMLAH TANGGAL PENGAJUAN REVISI 1 REVISI 2 REVISI 3 REVISI 4
NO JUDUL GAMBAR
LEMBAR MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS MASUK KEMBALI STATUS
9 Denah Parsial Instalasi Gas Medis Zona 2 Lantai 2 Gedung MEDIK 1.00 7-Dec-18 21-Dec-18 B
10 Denah Instalasi Gas Medis Lantai 3 Gedung MEDIK 1.00 7-Dec-18 21-Dec-18 C 20-Dec-18 21-Dec-18 B 5-Apr-19 12-Apr-19 B
11 Denah Parsial Instalasi Gas Medis Zona 1 Lantai 3 Gedung MEDIK 1.00 7-Dec-18 21-Dec-18 C 20-Dec-18 21-Dec-18 B 5-Apr-19 12-Apr-19 B
12 Denah Parsial Instalasi Gas Medis Zona 2 Lantai 3 Gedung MEDIK 1.00 7-Dec-18 21-Dec-18 B
13 Standar Detail 1 Pemasangan Instalasi Zone Valve & Area Alarm 1.00 7-Dec-18 21-Dec-18 C 20-Dec-18 21-Dec-18 C 5-Apr-19 12-Apr-19 C
14 Standar Detail 2 Pemasangan Instalasi Gas Medis & Outlet Gas Medis 1.00 7-Dec-18 21-Dec-18 C 20-Dec-18 21-Dec-18 B

U PNEUMATIC TUBE
1 Skematik Diagram Sistem Instalasi Pneumatic Gedung MEDIK 1.00 25-Jan-19 29-Jan-19 B
2 Denah Instalasi Pneumatic Lantai Basement Gedung MEDIK 1.00 25-Jan-19 29-Jan-19 B
3 Denah Instalasi Pneumatic Lantai 1 Gedung MEDIK 1.00 25-Jan-19 29-Jan-19 C 1-Feb-19 9-Feb-19 B
4 Denah Instalasi Pneumatic Lantai 2 Gedung MEDIK 1.00 25-Jan-19 29-Jan-19 C 1-Feb-19 9-Feb-19 B
5 Denah Instalasi Pneumatic Lantai 3 Gedung MEDIK 1.00 25-Jan-19 29-Jan-19 C 1-Feb-19 9-Feb-19 B

V PENERANGAN INTERIOR
1 Denah Instalasi Penerangan Interior Lantai 1 Gedung MEDIK 1.00
2 Denah Instalasi Penerangan Interior Lantai 2 Gedung MEDIK 1.00
3 Denah Instalasi Penerangan Interior Lantai 3 Gedung MEDIK 1.00

W COMPOSITE
1 Denah Komposite Lantai Basement Gedung MEDIK 1.00 17-May-19 MK
2 Denah Parsial Komposite Zona 1 Lantai Basement Gedung MEDIK 1.00 17-May-19 MK
3 Denah Parsial Komposite Zona 2 Lantai Basement Gedung MEDIK 1.00 17-May-19 MK
4 Denah Parsial Komposite Zona 3 Lantai Basement Gedung MEDIK 1.00 17-May-19 MK
5 Denah Parsial Komposite Zona 4 Lantai Basement Gedung MEDIK 1.00 17-May-19 MK
6 Denah Parsial Komposite Zona 5 Lantai Basement Gedung MEDIK 1.00 17-May-19 MK
7 Denah Parsial Komposite Zona 6 Lantai Basement Gedung MEDIK 1.00 17-May-19 MK
8 Denah Komposite Lantai 1 Gedung MEDIK 1.00 15-Jan-19 17-Jan-19 C 21-Jan-19 29-Jan-19 C 12-Feb-19 18-Feb-19 B
9 Denah Parsial Komposite Zona 1 Lantai 1 Gedung MEDIK 1.00 15-Jan-19 17-Jan-19 C 21-Jan-19 29-Jan-19 C 12-Feb-19 18-Feb-19 B
10 Denah Parsial Komposite Zona 2 Lantai 1 Gedung MEDIK 1.00 15-Jan-19 17-Jan-19 C 21-Jan-19 29-Jan-19 C 12-Feb-19 18-Feb-19 B
11 Denah Parsial Komposite Zona 3 Lantai 1 Gedung MEDIK 1.00 15-Jan-19 17-Jan-19 C 21-Jan-19 29-Jan-19 C 12-Feb-19 18-Feb-19 B
12 Denah Parsial Komposite Zona 4 Lantai 1 Gedung MEDIK 1.00 15-Jan-19 17-Jan-19 C 21-Jan-19 29-Jan-19 C 12-Feb-19 18-Feb-19 B
13 Denah Parsial Komposite Zona 5 Lantai 1 Gedung MEDIK 1.00 15-Jan-19 17-Jan-19 C 21-Jan-19 29-Jan-19 C 12-Feb-19 18-Feb-19 B
14 Denah Parsial Komposite Zona 6 Lantai 1 Gedung MEDIK 1.00 15-Jan-19 17-Jan-19 C 21-Jan-19 29-Jan-19 C 12-Feb-19 18-Feb-19 B
15 Denah Komposite Lantai 2 Gedung MEDIK 1.00 25-Feb-19 26-Feb-19 B
16 Denah Parsial Komposite Zona 1 Lantai 2 Gedung MEDIK 1.00 25-Feb-19 26-Feb-19 B
17 Denah Parsial Komposite Zona 2 Lantai 2 Gedung MEDIK 1.00 25-Feb-19 26-Feb-19 B
18 Denah Parsial Komposite Zona 3 Lantai 2 Gedung MEDIK 1.00 25-Feb-19 26-Feb-19 B
19 Denah Parsial Komposite Zona 4 Lantai 2 Gedung MEDIK 1.00 25-Feb-19 26-Feb-19 B
20 Denah Parsial Komposite Zona 5 Lantai 2 Gedung MEDIK 1.00 25-Feb-19 26-Feb-19 B
21 Denah Parsial Komposite Zona 6 Lantai 2 Gedung MEDIK 1.00 25-Feb-19 26-Feb-19 B
22 Denah Komposite Lantai 3 Gedung MEDIK 1.00 BELUM
23 Denah Parsial Komposite Zona 1 Lantai 3 Gedung MEDIK 1.00 BELUM
24 Denah Parsial Komposite Zona 2 Lantai 3 Gedung MEDIK 1.00 BELUM
25 Denah Parsial Komposite Zona 3 Lantai 3 Gedung MEDIK 1.00 BELUM
26 Denah Parsial Komposite Zona 4 Lantai 3 Gedung MEDIK 1.00 BELUM
27 Denah Parsial Komposite Zona 5 Lantai 3 Gedung MEDIK 1.00 BELUM
28 Denah Parsial Komposite Zona 6 Lantai 3 Gedung MEDIK 1.00 BELUM

383.00 lembar