Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

Junio 3, 10, 17, 24

Sistemas HVDC
CONVERSATORIO :

SESIÓN 1 :
Aspectos claves del diseño y especificación de sistemas HVDC

HVDC SPECIFICATION DEVELOPMENT

RICK VALIQUETTE
Teshmont - Canada

Un evento:
CONVERSATORIO : Sistemas HVDC

HVDC System Life Cycle

2
CONVERSATORIO : Sistemas HVDC

Typical AC Project Development

• Project designed/developed by utility/TFO using standard design and equipment


specifications. Not a significant amount of customization.
• Self performed all or parts thereof (engineering, procurement and construction) or
developed under an EPC contract lead by an EPC contractor.
• Equipment usually sourced from a variety of different vendors.
• The major risk is construction.

3
CONVERSATORIO : Sistemas HVDC

Typical HVDC Project Development

• Project procured by utility/TFO under an EPC arrangement (not


self performed).
• Manufacturers complete detailed studies, design and integration of
the equipment to form the HVDC system.
• Manufacturers typically lead the project who engage or partner
with contractors to perform the construction and installation
portions of the project.
• Bidding documents contain the technical and commercial
requirements for supply of the HVDC System (not individual
pieces of equipment).
• Major risks are technical and construction.

4
CONVERSATORIO : Sistemas HVDC

HVDC Project – Need To Consider

 There are a limited number of HVDC manufacturers.


 High reliability and availability expectations
 HVDC Systems typically can significantly impact the AC network.
 Outage costs are generally significant.
 AC System upgrade costs associated with addition of an HVDC system can be significant.
 Operating and maintenance practices are unique.
 HVDC project risk profile is unique.

5
CONVERSATORIO : Sistemas HVDC

Project Feasibility and Planning


Studies
 Define a rating (nominal, overload requirements, transient).
 AC System studies need to identify any system upgrades, remedial action schemes or
special control functions.
 Consult with stakeholders inside and outside of the company to make sure applicable
issues are addressed (operations and maintenance for instance).
 Budgetary pricing accuracy. A good practice has been to issue a mini-spec with sufficient
detail and allow a reasonable amount of time for suppliers to respond.
 When comparing alternatives include the full project life cycle costs (losses, O&M costs,
future refurbishments, owners costs, escalation etc) and additional benefits to the system
over the useful life of the asset.
 Get manufacturers buy-in to the project.

6
CONVERSATORIO : Sistemas HVDC

Specification Development

• The specification is a contract document, detailed technical specifications are critical to


provide manufactures with the appropriate information and requirements, get accurate
bids and avoid future issues.
• Don’t ignore the ‘little things’ – auxiliary systems need to be looked at carefully as they
impact cost, reliability, availability and maintainability.
• Avoid requirements which force the manufacturer to deviate from their core design and
standard offering.
• Define your reliability requirements - impact project configuration, levels of redundancy
and spare equipment requirements.
• Define utility and regional environmental requirements (communication interference,
audible noise, power quality, harmonics, pollution etc.).

7
CONVERSATORIO : Sistemas HVDC

Specification Development

• Equipment studies need to be completed to get functional and performance requirements


and provide a common set of system data for the bidders:
• Define real and reactive power exchange requirements (normal and overload as well
as dynamic response requirements, ramp rates etc).
• Identify any special control requirements (damping, modulation, special operating
modes, SPS etc.) or at least have a provision for this.
• Provide system equivalents and other system data for all bidders to get pricing based
on consistent inputs and not based on varying assumptions.
• Provide background harmonic measurements to address possible filter requirements
and to avoid any possible resonant conditions which can limit power transfer.
• Provide system harmonic impedance.

8
CONVERSATORIO : Sistemas HVDC

Specification Development

• Provide any applicable internal standard equipment specifications e.g. standard ac


breakers, battery banks, chargers etc.
• Consider requesting equipment to be provided from factories that are recognized centers
of excellence. Have bidders identify factories of origin.
• Specify maximum replacement times for major pieces of equipment (transformers and
reactors).
• Specify digital simulation models to be provided, and the level of detail. Be aware of
Intellectual property concerns.
• Penalty clauses for losses, availability, failure rates are useful to ensure expected
performance and consequences are defined. Feed into the commercial specification.
• Define any transportation limits as they may impact design and delivery of major
components such as transformers.

9
CONVERSATORIO : Sistemas HVDC

Specification Development

• Factory testing needs to be properly defined – What configurations to be tested? What


happens when certain tests are not passed – at what point can an order be rejected
entirely?
• Specify documentation and training to be provided.
• Specify mandatory and optional spare parts as well as any special tools and maintenance
equipment.
• Civil is a significant risk item, do some ground work, provide as much detailed information
at the specification stage as possible.
• The design should consider future refurbishment requirements such as controls.
• Include in the process time to solicit comments from suppliers on draft specification and
commercial terms. Get manufacturers buy-in.

10
CONVERSATORIO : Sistemas HVDC

Tendering

• Allow sufficient time for manufacturers to respond.


• Allow sufficient time complete thorough evaluation.
• Prepare tender forms requesting specific information from the bidders in common format
to facilitate careful review and comparisons between vendors.
• Develop evaluation criteria early and stick to it.
• Prepare a conformed specification after award taking into account all negotiated
deviations.

11
Gracias

12

You might also like