Pollard-Sutherland - EDID6511 Assignment 1,2, and 3 - PROJECT PLAN
Pollard-Sutherland - EDID6511 Assignment 1,2, and 3 - PROJECT PLAN
by
Of the Requirements of
Summer - 2019-2020
Table of Contents
Scope Control.......................................................................................................................................... 14
Scope Change............................................................................................................................................14
Introduction ..............................................................................................................................................15
Critical path……………………………………………………………………………………………….17
Risk identification……………...................................................................................................................... 20
References.....................................................................................................................................................33
Figure 7:…………………………………………………………………………………………………….24
Figure 8:………………………………………………………………………………………………….. 25
Figure 9:…………………………………………………………………………………………………….26
This project charter serves as the blueprint for the project “Developing Library Management System at the Owia Government
School”. It provides documentation of various aspects of requirements and expectations for the project. The document will include
mention of areas such as project goals and objectives, constraints, assumptions, stakeholders, milestones, estimated cost and resources.
It also outlines the project team and gives their roles and responsibilities.
5
PROJECT CHARTER
The library system at the Owia Government The ability of the students to access tens-of The main objectives of the project are: to do research on
School lacks the proper design and database for –thousands of books on open source library system and to establish distinct features that can be
library management system which allow libraries from around the world through applied in developing a library management system OGS
members to register securely while students technology.
read comfortably. To introduce the students to more digital and research-
based learning.
Implement a Library management Content development Academic libraries address their mission to support
system a software used to manages the Access rights by the students research and teaching by building collections and
catalog of a library. Consortium arrangements developing services intended to meet the information needs
Make it spacious and more e-learning Staff training and recruitment of their students.
so that large number of students can Use of technology by the students,
gain its advantage. teachers and library staff.
Creation of e-book facility so that
students are able to access books from
their desktops or laptops from
anywhere
Students
Teachers
Community members
Project Start Date -29th June 2020 Teacher survey on the improvement in the ease of use of the applied features.
Demonstrations of the old versus the new processes
Estimated Completion Date
Design of changes 15th July, 2020 25th July, Project Team All Team Weekly WhatsApp chat
2020 meetings Members
Project approval
Signature Date
Stakeholder
Project Manager
Definition of Scope
The Owia Government School (OGS) Child friendly Library is designed to enhances student learning outcomes by providing
a range of programs, services and resources which support teaching and learning. It also supports and encourages students'
reading experiences. However, the lack of a library management systems hinders the smooth flowing of the library.
This part of the project plan gives the framework of the scope of the Owia Government School child friendly development plan with
the implementation of a Library Management System, project. This section of the plan gives the framework of the scope of the project.
It will provide the definition of the scope, the approach of the scope management, any control associated with scope changes, the
responsibilities of the team members in relation to the scope as well as the Work Breakdown Structure (WBS). The documentation
will also include WBS dictionary for scope clarity, a statement of the scope and the work to be accomplished. This is also produced in
an effort to provide project information to inform project stakeholders. The stakeholders in charge of project approval will be the
In order for the successful completion of the project there are some key persons that play major roles in the overall scope
management. These persons have to be fully informed of their responsibilities and be in agreement to ensure the successful completion
of the project. They will assist in ensuring the scope assigned is practicable in the given timeframe. The key persons’ role and
Project Manager
1. Organizes and implements the necessary tasks for the project within the timeframe.
Stakeholders
Project Team
7
1. Liaison with the project manager to ensure they are up-to-date on timelines and tasks.
3. Access project documents for necessary changes and report such changes to the project manager.
The project product that will be produced is a Library Management System which will automate the major library operations. The
project seeks to upgrade a library system and to establish distinct features that can be applied in developing a library management
system OGS. This library upgrade will provide students with the necessary skills to be more self-reliant and critical thinkers.
Once the necessary documents have been presented and approved with regards to the upgrade to the library. The application will be
completed, along with the necessary training methods. Finally, the product will be approved and signed.
Table 2
Project Assumptions
6. Increased flexibility
Project Constraints
1. -Hardware Constraints
To store persistent date, the system requires a database. So that the database ought to have backup capabilities.
2. -Physical Constraints
no central accommodation to provides access to books, information, audiovisual materials, other media, and reliable Internet
access, therefore focus will be placed specifically on this area.
3.-Human Constraints
various levels of training in library and ICT needs to be ongoing, there will be a library policy with specific guidelines.
4.-Design Constraints
The library will be designed to make the system usability and it is to let users easy to use on the system.
Table :3
Project Deliverables
Assigned to
Figure 1 below gives the breakdown of all aspects of the project. This will assist in the efficiency in the process that will take place.
This aids in allowing for proper initiation, implementation and monitoring of the project. The activities are divided into five major
OGS Library
Managenmnet
system.(LMS)
To reduce ambiguity and increase clarity a WBS Dictionary is presented in Table 4 that follows.
WBS Level WBS Code WBS name WBS Deliverables Budgets Resources
description
Initiating
1.1 Assigning This selection Meeting notes $100 Project
budget, documents.
timeline and
strategy. The
project will
also be
discussed
1.2 Selecting Based on the Documentation $100 Stakeholders
officials and
the project,
items such as
the scope,
risks,
constraints and
deliverables
will be
documented
1.3 Developing Charter is Signatures to $200 Project
signature stakeholders.
Any
modifications
are
communicated
11
to the project
manager.
Charter is
approved when
signatures are
affixed.
Planning
2.1 Establish The project All team $200 Project
ensure project
efficiency.
2.2 Prepare the The team will All team $100 Project
outline to
3.3 Develop Documentation Signatures to $100 Project
purpose of the
scope, risks,
constraints,
assumptions
and deliverable
after computers,
project
Executing
4.1 Reviewing The team will LMS $400 Project
Teachers who
are not so
technologically
new features
od the system.
implementing member
in order to rate
the success of
the project
4.2 Library Both hard and Documentatio $200 Software
members to programmer
most suitable
of the library
Monitoring
and
controlling
5.1 Status A report at Document will $2000 Project
overview and
adjustment if
necessary
Closing
5.2 Develop the The final Approved by $100 Project
project is member
13
prepared
member
Scope Verification
The verification process will entail the stakeholders accepting the scope of the project to include the scope statement, WBS and WBS
Dictionary. This will be done by the major stakeholders. An example of this document is shown in figure 3.
Scope Control
The project will only entail those things that are outlined in the WBS and the WBS Dictionary. The project manager will take the
responsibility of monitoring the actions of the project team for the entire project. The scope management will serve as a guide to
Scope Change
14
Scope changes may be made by the project manager, team members or the major stakeholders. However, all changes have to be
documented using the project change request form as shown in Figure 4. All members should be aware of any changes made to the
project scope. There is no guarantee of a change acceptance however, as they can be rejected or deferred to the project team to decide
Introduction
This time management plan seeks to outline the particular activities that the task members and stakeholders must perform to create the
project deliverables for the Library Management System project. This plan will give the estimating of the quantity of work periods and
their expected due date, individual activities along with the schedule and progress of the project through the use of a blueprint of how
the project will be executed. This will encapsulate the activities from the inception to execution of the project.
15
This schedule management plan considers multiple components, including the identified tasks, resource requirements, the duration of
the activities, estimated completion dates, and resource requirements necessary for initiating, planning, executing, monitoring, and
closing the current project. A set of components such as the milestone list, the Precedence Diagram Method (PDM), the Critical Path
Method (CPM), and precise schedules are developed to prevent wastage of resources.
Milestone List
Despite providing overview of the broad categories of the milestones for this project, this section details the specific events significant
for the success of the current event. As presented in Table, all events will be subject of approval by the project manager to verify their
completion based on the actual end date rather than the estimated date. Thus, all changes proposed are also subject of approval from
Table: 5
Milestone List
Project: Learning Management System at Child Friendly Library at Date: _ / _/ 2020
OGS
No. Milestone Mandatory Estimated Actual Days Verification
manager
3 Selecting project members Mandatory 30/6/2020 30/6/2020 0 Project Manager Approval
4 Developing a project Mandatory 30/6/2020 30/6/2020 0 Project Manager Approval
its purpose
6 Prepare the objectives of Mandatory 12/7/2020 13/7/2020 1 Project Manager Approval
the project
7 Develop project scope Mandatory 16/7/2020 16/7/2020 0 Project Manager Approval
statement
8 Prepare cost, benefits and Mandatory 20/7/2020 20/7/2020 0 Project Manager Approval
risk baseline
9 Prepare the project Mandatory 24/7/2020 24/7/2020 0 Project Manager Approval
duration
10 Identify the benefits and Mandatory 27/7/2020 29/7/2020 2 Project Manager Approval
costs
11 Create Gantt chart Mandatory 30/7/2020 31/7/2020 1 Project Manager Approval
12 Review Mandatory 8/8/2020 - - Project Manager Approval
13 Survey Mandatory 24/8/2020 - - Project Manager Approval
14 Preparation of preliminary Mandatory 30/8/2020 - - Project Manager Approval
report
19 Presenting the final project Mandatory 31/10/2020 - - Project Manager Approval
20 Project end Mandatory 31/10/2020 - - Project Manager Approval
16
The Precedence Diagram Method (PDM) is an essential tool for scheduling various project activities through visual representation.
For this project, a schedule network program is constructed to connect different activities to show the dependencies. The green arrows
in Figure 5 show finish-start dependence relationship among the tasks while the figures below task statements represent the duration
required in days. For instance, both developing a project charter and signing on it, and establishing project team and its purpose can
only be started after project members have already been selected. Thus, this visual representation tool is essential in depicting not only
the precise tasks involved in the project but also their order of completion alongside the duration required.
Figure 4
Schedule
This section highlights the schedule of activities to be conducted alongside the projected time for starting and finishing each
project deliverable.
A schedule update is distributed regularly to provide project stakeholders with an assessment of the progress of the project. The
Critical Path for the project “Library Management System at the Owia Government School” is shown in figure 5 below with the use
of the arrows. The Critical Path Method illustrates the longest duration of the network of activities. It gives the early start and late
finish each activity can start or finish without prolonging the project.
17
Number (Days)
Project Initiation 29/6/2020 30/6/2020 1
1 Assigning a project manager 29/6/2020 30/6/2020 1
2 Selecting project members 29/6/2020 30/6/2020 1
3 Developing a project charter and 29/6/2020 30/6/2020 1
signing on it
purpose
project
3 Develop project scope statement 13/7/2020 16/7/2020 3
4 Prepare cost, benefits and risk 17/7/2020 20/7/2020 3
baseline
5 Prepare the project duration 22/7/2020 24/7/2020 2
6 Identify the benefits and costs 25/7/2020 27/7/2020 2
7 Create Gantt chart 28/7/2020 30/7/2020 1
and design
4 Building the program 2/9/2020 23/9/2020 21
5 Testing the program 24/9/2020 30/9/2020 6
controlling
1 Status report 3/10/2020 10/10/2020 7
The critical path is the longest distance that a team can use to finish the project. According to Aliyu (2012), the time required on a
critical path is the entire duration of the project. In this case, there is only one critical path that totals to 86 days. The critical path is
presented with red arrows in Figure 6. Since the project begun on June 29, 2020, it is expected that it will take at least 12 weeks and 2
days for the Learning Management System at Child Friendly Library at OGS to be ready if all tasks provided in the work-breakdown
schedule are done at their normal times. Furthermore, having one critical path indicates that this project is not expected to undergo
Figure 5
18
Figure 6
Risk Identification
This section identifies the possible risks likely to occur when implementing the project. It also highlights the possible causes of
the identified risks as listed in Table 2. From the Table 2, the current project is vulnerable to at least 8 risks identified alongside
multiple causes.
Table :7
Education
2 Change in Change in the deliverables required to execute precise
team
5 Lack of cooperation Lack of team work traits among the group members
the team
6 Redundancy in Failure of technological devices, such as laptops and
cause delays
7 If a similar software Poor research to identify the gap to be filled in the
cancelled
This section provides an overview of the risk qualification and prioritization based on their consequences, likelihood of occurrence;
impact when they occur, risk rating and the priority number. The consequences column indicates the possible effects that each risk can
have on the project if it occurs while the likelihood section depicts the possibility of the risk to happen while implementing this
project. Furthermore, the impact column indicates the degree of the risk in affecting the project if it occurs as the rating and priority
numbers ranks individual risks based on their projected effects. This information is summarized in Table 8.
Table :8
Number
1 The time that Delay of the Possible Minor Moderate 7
can be subsequent
payments to the
stakeholders
3 Not full Delayed project Possible Moderate High 2
command of execution
the Compromised
supervisor of sponsor
the project
would not be
able to
support the
team
5 Lack of Waste more time Possible Major High 3
in subsequent
project will
be totally
cancelled
This section provides the possible responses and contingencies appropriate to the identified risks as presented in Table 9.
Table 9
No.
1 The time that can be assigned to the Try using the time Allocating sufficient
as scheduled to accommodate
delays
2 Change in requirements will cause extra Reject non-impactful Accommodate the
while minimizing
impact on the
activities
3 Not full command of the developing The developing tools Identify possible
any delay
4 It may happen that the supervisor of the Try to convince the Identify two possible
setting expectations
6 Redundancy in information that may Reducing the Allocating sufficient
project
7 If a similar software already exists, the Verify if a similar Research at least two
be included in the
arises
Risk monitoring, controlling, and reporting will form a significant part of the risk management approach for this project. It will ensure
that all the risk plans are executed effectively to reduce the likelihood of the risk occurrences. Precisely, monitoring process will
involve keeping track of identified risks in each task; thus, triggering conditions for contingencies. At the same time, residual risks as
well as new ones that might arise will be monitored throughout the project implementation process. Multiple documents including
event recording registers and risk alert forms will be used to help the project team monitor and report all risks to control them. The
event recording register designed for this project is presented in Table 9 while the risk alert form is represented in Table 10.
Table : 10
Sr. No. Date of Is the event already Risk Action Actual Date
occurrenc identified in the risk Treatment - taken impact of
e of event register? If “Yes”… Mitigation to on the reporting
Risk Risk (Terminate, mitigate project the risk
Reference Mitigatio Treat, or
No. n Plan Transfer, reduce
Accept) the
risk
Table: 11
Risk Alert
Date of Occurrence _ / _/ 2020
Event occurred/which may
occur
The sequence of event (in
brief)
Possible causes
Urgent countermeasures
The quality management objectives are formulated to lead both quality control and quality assurance processes based on their
provisions. For this project, a set of 4 objectives were developed as provided in Table 11.
Table 11.
cost-effective.
The project implementation process should be
simultaneously.
The e-book facility should allow students to
Quality Control
Conducting quality control process is significant in this project as will allow the project team to measure the developed the Learning
Management System at Child Friendly Library at OGS based on the pre-determined standards. The specific inputs, tools and
techniques, and outputs for the quality control for this project are highlighted in Figure 7. the project team will create cause and effect
diagrams, run charts, engage in flowcharting, and review defect repairs to ensure that the digital library system developed is not only
spacious but also accessible regardless of the students’ location. Thus, quality control measurements such as the system’s capacity and
accessibility will be adjusted to meet the project demands and changes reflected in the project documents.
Figure :7
Quality Assurance
Similar to quality control, conducting quality assurance is essential for the current project as it will allow the project team to determine
if the project is complying with multiple policies and procedures required in the Owia Government School, Child Friendly Library,
and the Learning Management System under development. As aforementioned, the major objective for this activity is to use minimum
time and low costs possible throughout the project life-cycle. Thus, multiple materials, including the risk register and stakeholder
register will be analyzed frequently during quality audits and process analysis to identify and conduct change requests while updating
Figure 8.
Change requests
Project management plan updates
project documents updates
Outputs Project process assets updates
The quality team will have numerous roles and responsibilities, as follows:
Initiating quality definition by determining the standards desired for the quality of the project through planning.
Making sure that quality is observed in every project task and activity through observation and analysis.
The project manager will work closely with the quality team to not only discuss but also resolve quality issues in the project. Both
reports and metrics will be essential in communicating the status of the quality program and the results to other stakeholders. Table
represents a type of report that the project leader will generate in the plan of reporting quality problem.
Table 12.
schedule
Furthermore, developing a quality assurance status review report can be helpful in conducting the problem reporting plan while
managing the quality of a project. In this case, the document will include summary of the system evaluation, activities to be conducted
in the following week as well as a summary of risks and concerns as depicted in Table 13.
Table 13.
While cost management is viewed as a continuous process, it helps to split the function into four steps: resource planning, estimation,
budgeting, and control. They are mostly sequential, but it's possible that some resource changes happen midway through the project,
forcing the budgets to be adjusted. Cost management involves engaging in a feasible project and conducting appropriately based on
the parameters set during the preparation stage. All activities highlighted in the work-breakdown schedule are associated with different
forms of costs to ensure that the project is completed not only within the allocated time but also within the approved budget to
enhance its performance rate. In this section, the precise roles and responsibilities associated with the financial resources, cost
baseline, estimating costs, and reporting and cost change control are covered as represented in Figure 8.
Figure 9.
Reporting and
Cost Baseline
Control
Estimatig costs
As presented in Figure , presence of financial resources leads to people assuming roles and responsibilities to enhance accountability
of the expenditures. The project manager and stakeholders will have various roles and responsibilities in the cost management of this
project. Firstly, the project manager will be required to oversee and draft all document preparations, reports, and approvals, including
the financial ones. At the same time, the individual will have a duty of managing all project resources and apply necessary changes as
the project progresses towards the completion stage. Secondly, stakeholders of this project will be required to provide approvals and
funding the project deliverables. However, the project team members will not have direct roles and responsibilities concerning the
project financial resources but will be essential in making decisions that impact the cost of tasks and activities provided in the work-
breakdown schedule.
Cost Baseline
Allocating the estimated expenses of resources, tasks, and activities into cost accounts is critical in measuring and assessing the cost
performance of this project. Precisely, developing a cost baseline will allow the project manager and other stakeholders to determine
the degree in which the present project is attaining its financial goals. The cost baseline depicted in Table 3 is time-phased based on
the schedule provided in the time management plan. From Table 3, the project costs are divided into the monthly durations beginning
with June, when the project was initiated, to October, the projected month for the project closure.
Table 14.
WBS WB WBS name June July August Septemb October Total Resources
Level S er
Cod
26
e
Initiating
1.1 Assigning $100 $100 Project
project Manager
manager
1.2 Selecting $100 $100 Stakeholde
project rs
members
1.3 Developing $200 $200 Project
a project manager
charter and
signature
Planning
2.1 Establish $200 $200 Project
and its
purpose
objectives of manager
the project
3.3 Develop $100 $100 Project
project manager
statement member
member
Executing
4.1 Reviewing $400 $400 Project
and team
member
manager
and team
member
Managemen designer,
t system network
27
contents manager
and
programm
er
Monitori
ng and
controllin
g
5.1 Status $2000 $2000 Project
reports manager
and team
member
Closing
5.2 Develop the $100 $100 Project
member
member
Estimating Costs
Cost estimating has always been a predictive process in which the projected expenses of deliverables are quantified in a project. For
this reason, the aim of this section is to convert quantified technical information about project tasks and activities into finance data.
Thus, the outputs obtained from cost estimates will be utilized primarily for multiple stages during the implementation process of this
project, including planning phase, cost analysis, and decisions making sessions when conducting schedule control processes. While
developing the cost estimates presented in Table 4, the projected time duration of the deliverables was considered concurrently with
the expenses. This approach is significant since costs are, in most cases, dependent on the duration of an activity as the resource
Table 15.
Cod Totals l
e
Initiating $400 8%
1.1 Assigning 1 $100 $100 Project
project Manager
28
manager
1.2 Selecting 4 $25 $100 Stakeholde
project rs
members
1.3 Developing 2 $100 $200 Project
a project manager
charter and
signature
Planning $600 12%
2.1 Establish 10 $20 $200 Project
and its
purpose
objectives of manager
the project
3.3 Develop 1 $100 $100 Project
project manager
statement member
member
and team
member
manager
and team
member
Managemen designer,
t system network
contents manager
29
and
programm
er
ng and
controllin
g
5.1 Status 200 $10 $2000 Project
reports manager
and team
member
Closing $400 8%
5.2 Develop the 5 $20 $100 Project
member
member
Project cost control will include monitoring cost performance as the implementation process continues towards the completion.
Besides, the project manager will ensure that only significant changes are incorporated in the revised cost baseline to avoid incurring
unnecessary expenses. At the same time, the project manager will inform all stakeholders of the authorized changes made to the
project deliverables at the earliest time possible whenever they are projected to affect the project costs. Thus, cost control will be
conducted effectively as a way of ensuring that the current project is completed within the forecasted budget. Furthermore, the Earned
Value Management (EVM) technique will be employed to integrate scope, time, and cost data while measuring the performance of the
project deliverables. One of the major considerations while using the EVM mechanism to help in controlling costs for this project will
be entering actual information periodically. This practice will enhance the probability of attaining the budget objectives. Table Z
represents an example of the EV form designed to help in controlling costs in this project.
Table 16.
References
31
A Guide to the Project Management Body of Knowledge (PMBOK Guide): Fifth Edition. Project Management Institute:
Pennsylvania: USA
Rose, K. H. (2013). A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—Fifth Edition. Project management
journal, 44(3), e1-e1.