Cost of Project (In Millions)
Cost of Project (In Millions)
Land 1.5
Building 2.5
Euipment 1
Misc Fixed Assets 0.5
Preliminary Exp 0.2
Preoperative Exp 1
Contingency Margin 0
Working Capital Margin 0
6.7
Means of Finance
0 0 2.5
0.25 0.575 2.25
0.25 0.5425 2
0.25 0.51 1.75
0.25 0.4775 1.5
0.25 0.445 1.25
0.25 0.4125 1
0.25 0.38 0.75
0.25 0.3475 0.5
0.25 0.315 0.25
0.25 0.2825 0
DEPRECIATION
Depriciation Schedule for Income Tax Purpose (Written Down Value Method)
I II III IV V
Building(10%) 0.32 0.29 0.26 0.23 0.21
Plant & Machiney and 0.6 0.40 0.27 0.18 0.12
Misc. Fixed Assets (33 1/3%)
Total 0.92 0.69 0.53 0.41 0.33
VI VII VIII IX X
0.19 0.17 0.15 0.14 0.12
0.08 0.05 0.04 0.02 0.02
- - - - -
1.62 2.03 2.53 2.92 3.42
NBCR=BCR-1 0.01
Sales 12.45
Fixed Cost 2.32
Variable Cost 9.26
Depreciation 0.23
Disposition of Funds
Capital Expenditure for the Project 5.5
Preliminary Expenses 0.2 0 0 0
Decrease in Long Term Borrowing 0.25 0.25 0.25
Interest on Long Term Borrowings 0 0.325 0.2925 0.26
Taxation 0.00 0.00 0.02
Preoperative Expense 1
Dividend 0 0 0
Total 6.70 0.58 0.54 0.53
Opening Balance 0.00 0.29 0.76
Net Surplus/Deficit 0.00 0.29 0.47 0.74
Closing Balance 0.00 0.29 0.76 1.50
Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10
0 0 0 0 0 0 0
0.25 0.25 0.25 0.25 0.25 0.25 0.25
0.2275 0.2 0.16 0.13 0.0208 0.065 0.0325
0.24 0.34 0.45 0.57 0.71 0.82 0.96
0 0 0 0 0 0 0
0.72 0.79 0.86 0.95 0.98 1.13 1.24
1.50 2.29 3.27 4.48 5.93 7.71 9.74
0.79 0.98 1.21 1.45 1.78 2.03 2.37
2.29 3.27 4.48 5.93 7.71 9.74 12.11