PROJECT PLANNING

Table 1.1. Task List for the Project, "Feasibility of Liquid Dispensing Using a Bamboo Container" by Aduana, Nievares, & Rosano (2021)

TASK ASSIGNED
TASK CODE DESCRIPTION TO PREDECESSOR ACTIVITIES

PA – enter separately in columns

Planning
Task 1 Choose Topic ALL
Get Background
Task 2 Information ALL

Task 3 Refine Topic ALL 1 2


Perform Literature
Task 4 Search
ALL 2

Gather and Cite


Task 5 Sources for RRL
ALL 3 4

Generating Design Solutions


Task 6 Proposal ALL 3 5
Task 7 Design Planning ALL 5
Task 8 Design Sketch ALL 7
Task 9 Finalizing Design ADUANA 7 8

Manufacturing, Performance, Control, and Final Revisions

Gathering of Parts and


Task 10 Materials
ADUANA 9

Task 11 Testing Methodology ADUANA 9

Task 12 Paper Revision ALL 11


Task 13 Finalize Intro ALL 12
Task 14 Finalize RRL ALL 12

Task 15 Finalize Methodology ALL 11 12

Task 16 Finalize Test Design ROSANO 11 12

Task 17 Assembly ADUANA 10

Task 18 Testing: Durability ROSANO 10


NIEVARES &
Task 19 Record Data 18 20
ROSANO
NIEVARES &
Task 20 Testing: Flow Rate 10
ROSANO
Finalize Results NIEVARES &
Task 21 19
ROSANO
Task 22 Finalize Paper ALL 12 14 15 16 19
& Rosano (2021)

ESTIMATED
S DURATION (in
days)

mns

3
7
3
4

20

14
2
4

7
10

21 5