Professional Documents
Culture Documents
Reliability Problems With Lange Power Transformers and Shunt Reactors - Typical Failure Nodes and Failure Causes
Reliability Problems With Lange Power Transformers and Shunt Reactors - Typical Failure Nodes and Failure Causes
Reliability Problems With Lange Power Transformers and Shunt Reactors - Typical Failure Nodes and Failure Causes
0,30
0,20
Statistical distribution in 1955-1977 0,10
0
-3
-5
-1
-3
-4
-1
-2
-2
-3
30
35
0
3
corresponded to Weibull distribution
10
15
20
25
b t
λ (t ) = exp( ) ⋅ ( ) b−1 Figure 3
a a Bar graphs of failure rates of autotransformers
with form parameter b=0.3-0.75. 500/220 kV
Improvement of transformer design with years
resulted in increase of form parameter and
approaching curve shape to exponential one 4,00
3,50
3,00
Statistical distribution in 1963-2005 2,50
Fig.1 - 4 present statistical distribution of large power 2,00
transformers over 100 MVA in a wide time-span. 1,50
Four large groups of transformers of fairly same type 1,00
have been analyzed: autotransformers 125-200 MVA, 0,50
220/110 kV (observation period 1964-2005, 27,505 0,00
transformer-years), 125-200 MVA, 330/110 kV 3 -5 0 5 0 5 0
- -1 -1 -2 -2 -3
(1963-2005, 9,477 transformer-years; 167 MVA 0 3 5 10 15 20 25
500/220 kV (1965-2005, 13,749 transformer-years),
and generator transformers 400 MVA, 330 kV (1969- Figure 4
2005, 1,600 transformer-years) Bar graphs of failure rates of generator transformers
400 MVA, 330 kV
..2
..2
..3
..3
-4
5.
35
10
15
20
25
30
15 5
20 0
25 5
30 0
5
0
.1
..1
..2
..2
..3
..3
-4
5.
35
Apparently, with years one can expect gain in weight compare with relevant data reported in 1996-98 by
of the third cause and automatically increase Doble clients (52 failures).
influence of initial design margin as well as Table 2 shows failure –modes for transformers of
operational stresses. The entire factors should be different application
considered in integrity. The data show that average age of failed transformer
Table 2 is still between 20-22 years however contribution of
Failure modes of power station transformers of generation “after 25” is becoming more weighty
different application Transformer application predetermines likely failure -
modes
Mode GSU Auxiliary Start up Transmission transformers: Dielectric mode HV and
TW windings insulation, bushings, movement of
Dielectric 49 28.5 35.7 common and tertiary windings
Generator transformers :
Thermal 13.3 7.2
Dielectric mode windings (HV) insulation; trend to
Mechanical 4.4 14.3 28.5 increasing thermal-mode failures; Leads and
Core 4.4 - connections overheating
Leads 13.3 14.3 Auxiliary power plant transformers
OLTC insulation contamination & contacts heating
Bushings 13.3 14.3 Leads and connection
Winding (LV,TW) movement
OLTC 6.5. 42.8 14.3
Total 100 100 100 Dielectric-mode failures
failures,%
Damage of major insulation has been observed in
In period 2000-2005 was documented 108 major 11% of failed generator transformer and in 17% of
failures of large power transformers manufactured by transmission transformers 220-500 kV. Failure-
9 different companies . Table 1 allows to examine modes were associated with of oil gap breakdown
failure-modes of generator and transmission (particularly of large gap “shield of bushing-turret”),
transformers, and shunt reactors separately and surface contamination and degradation of impulse
strength, and critical overvoltage (resonance-mode).
3
CIGRE A2 COLLOQUIUM MOSCOW RUSSIA, 2005
Damage of minor winding insulation occurred
predominantly on HV windings (about 80%) and
fairly stressed Regulating Windings (RW) due to free
water enter, contamination with particles and
degradation of impulse strength, wearing out of tap
coils of HV winding, which subjected to frequent
mechanical and electrical stress, underestimated
impulse overvoltage and poor performance.
Figure 6
Short-circuit between coils due to introducing free
water through poor bushing top sealing
Figure 8
Underestimating impulse overvoltage. This Failure of 330 kV winding contaminated with
phenomenon is basically related to underestimation conductive oil by-products under lighting surge
of impulse transient function. E.g. 220 kV
transformer, which was frequently subjected Thermal-mode failures
switching transient during vacuum circuit breaker
commutations failed due to short circuit between Analysis has shown the following failure causes:
coils of Tap Winding (Fig 7)
4
CIGRE A2 COLLOQUIUM MOSCOW RUSSIA, 2005
Overheating of tap leads located between regulating
coils of HV winding connected to no-load tap Damage of leads and connections
changer. Events occurred after 30-37 years service.
Overheating of the coils of winding blocked with
angle collars preventing oil flow and proper cooling. Over 13% of failures of generator transformers are
Underestimation of winding temperature, especially associated with overheating leads and connections.
of LV winding in large generator transformers with Basically three failure modes have been observed:
OFAF cooling system. Overheating the insulation of winding exit leads;
Hence the main reason of failures was not normal Overheating soldered connections; Overheating
aging but design deficiency bolted connection to bushings
Figure 9
Failure of 700 MVA generator transformer after 25
years due to overheating the two top coils of LV
winding (CTC wire) resulting in short circuit between
parallels and then between turns
5
CIGRE A2 COLLOQUIUM MOSCOW RUSSIA, 2005
Tilting-mode deformation and significantly loosed Likely defects can be grouped under two general
winding clamping was revealed on the LV winding of headings: 1) Defects associated with main magnetic
step-down transformer that experienced 3 phases flux, and 2)Those associated with stray flux.
short-circuit with limited current but for long
duration (during 1,530 sec). Defects associated with main magnetic flux form
Tilting of conductors of HV winding was found also loops for circulation current linked with main flux. In
in GSU transformer as a results of short-circuit event fact this group makes up about 20% however it
on HV side. It was revealed that the 300 kV winding results in dissipation of high energy and intensive gas
performed as helical type and safety margin to axial generation with activation of Buchholz relay. The
stresses was only 0.84. cases observed were basically attributed to loosening
winding press bolts and short-circuit to metallic press
Design review using modern method reveled that in rings or to core yoke.
most cases dynamic stability was not sufficient to Defects associated with stray magnetic flux present
stand specified stresses. We used the method, which the main cause of localized oil overheating and gas
was developed by Dr. Lazarev (Zaporozhye). The generation. They can be classified into two groups:
method allows pinpointing not only likely damaged 1) Overheating under effect of eddy current
winding but also form of loss stability). In most cases induced by intensive stray flux;
when for winding was used wire from annealed 2) Overheating and (or) sparking in a loop for
copper with yield strength of the conductors around circulating current, linked with stray flux.
80 MPA predominantly radial form of loss stability In the first group typical defects are overheating of
could be anticipated. core frame due to absence or improper disposition of
For example step-down 80/33 kV transformer failed magnetic shields on the frame (Fig.12), overheating
due to dramatic distortion of LV winding (Fig 11). It of pressing of the pressure bolt that situated just
was found that transformer, which was manufactured under the core yoke, overheating a part of the tank
in 1974 has very low radial stability (Tabl. 1). Taking wall due to improper shielding
into account a long service life and inevitable loosing
the winding claming half-shifted for of deformation
was expected
Table 3
Winding, tap position Safety margin
Radial Axial
RW, max 6.4 6.4
LV, max 0.54 0.94
HV, max - 3.63
Figure 12
Overheating the bottom frame and adjusted insulation
in 730 MVA generator transformer due to improper
disposition of magnetic shields
Figure 13
Overheating in the loosed place between
members forming loop for circulating current in
700 MVA transformer
Bushings failure
Failure of OLTC
8
CIGRE A2 COLLOQUIUM MOSCOW RUSSIA, 2005