KWAME

NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY, KUMASI


SCHOOL OF ENGINEERING

PRACTICE EXAM Score



Fourth Year



CE 462: CONSTRUCTION MANAGEMENT PART B


INDEX NUMBER

INTRUCTIONS: Use the data presented below to answer the accompanying


questions in the spaces provided in this workbook

A project network analysis is to be carried out using the data provided below.

Depends only on the


Activity Duration (weeks)
Completion of Activity:

A 2 Start activity

B 5 C

C 1 A

D 3 C

E 7 B, F, G

F 2 C

G 9 A

H 5 F

I 7 H

Activities E, D and I are concluding activities

1
Question (1): Develop the Network Diagram for the project in the space below

2
Question (2)

(2a) Compute the Earliest Start Time, Latest Start Time, Earliest Finish Time, Latest Finish Time,
and Total Float for each activity and record your answers in the spaces provided below.

Earliest Earliest Latest Finish Latest Start


Activity Start Time Finish Time Time Total Float
Time

Question (2b): How long would it take to complete the project?

Question (2c): Which activities can the project manager not afford to delay?

Question (2d): How long can activity D be delayed before it



becomes critical?