Power Plant Terms and Factors
Power Plant Terms and Factors
Power Plant Terms and Factors
1. CONNECTED LOAD
a. Classification of Consumers/Customers
Residential
Commercial: Schools, Offices, Hospitals, Restaurants,
Supermarket, Department Store, Wellness Center, etc.
Industrial: Ice and Cold Storage Plant, Food Manufacturing
Plants, Brewery Plants, Oil Refinery, Automotive Assembly Plant,
Dairy Plant, etc.
Street Lightings and Public Areas: Manila Zoo, Rizal Park, Ninoy
Aquino Wild Park, Paco Park, Fort Santiago, etc.
Average Load
Load factor = Peak Load
Determine the average load for the following given daily load curve:
Load, MW
10 MW
12 MN 12 MN
Load, MW
10 MW
5MW
A1 A2
Time
12 MN 12NN 12 MN
6.25 MW
Daily load factor = 10 MW = 0.625 or 62.50%
Example: A power station has a maximum demand of 55,000 kW when supplying three
substations. For the following maximum daily demands on each substation, find the
following: (a) diversity factor between substations; (b) diversity factor between
distribution lines on substation A; (c) diversity factor between distribution lines on
substation B; (d) diversity factor between distribution lines on substation C.
24 hours
8760 hours = 365 days x day
Why 8760 hours? Maximum possible energy output for one year
40 MW
25 MW Unit 1