Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Using LiDAR survey to release line capacity

A Western Power Distribution case study

I n common with all UK DNOs in recent years, Western


Power Distribution has seen a rapid rise in the number
of connection applications for renewable generation
Western Power Distribution
Western Power Distribution is responsible
schemes. Cornwall, in particular, proved to be very for electricity distribution in the Midlands,
popular with developers of such schemes. With a fairly South West and Wales. Serving over 7.8 million
sparse population and with little in the way of heavy customers through a network of over 220,000
industry there is relatively little demand for electric kilometres of lines and cables and 185,000
power in this region. transformers, they are committed to providing a
safe and dependable power supply with minimal
However, the rapid increase in connection environmental impact.
applications meant that there were periods of time
when the region as a whole was predicted to be a
About the project
significant net exporter of power, to the extent that
parts of the 132kV network (the highest voltage used
One overhead line in particular was the cause of
by DNOs) were limiting the amount of connections that
significant constraint – the “K” line running through
could be accepted by Western Power Distribution.
Cornwall and North Devon. In total, this double circuit
line runs for approximately 100km, and was originally
designed and constructed utilising a 175mm2 “Lynx”
ACSR conductor. Although a 30km stretch running
through Cornwall was re-conductored with 300mm2
“Upas” AAAC, there remains a 70km section still strung
with “Lynx” conductor, and profiled for a 50°C rated
temperature.

Removing the constraint is, in theory, relatively


straightforward – re-conductor the rest of the line with
300mm2 Upas. However, in practice, this is far from
a straightforward solution. The length of the line, the
mechanical strength limitations of the structures, and
the sequence and duration of outages required would
AS350 Eurocopter with laser scanner attached
mean that work would take several years to complete.

NM Group
A T R I M B L E CO M PA N Y
www.nmgroup.com PAGE 1
In the meantime, a more rapid solution was needed so Technology focus
the possibility of increasing the rated temperature of
the line was investigated.
NM Group used high-accuracy laser scanners

An aerial LiDAR survey and clearance assessment of attached to aircraft, this system takes thousands of

the line was commissioned, with NM Group undertaking LiDAR measurements of the power network and the

both the point cloud acquisition and conductor surrounding area.

clearance evaluation. The survey revealed that while the Through collecting meteorological data and the
line was not suitable for immediate uprating, measured precise electrical load of the line at the time of survey,
clearances indicated that the conductors had been PLS-CADD™ can be used to model the circuit to identify
strung at lower tensions than normally used – instead thermal constraints.
of a typical tension basis of 20% of breaking strength at
10°C, the line appeared to be strung to just 18%.

With the tower designs based on an assumption of


20% breaking strength at 10°C, there was clearly scope
for re-tensioning sections of the line without affecting
design structural loads. NM Group identified locations
where re-tension was required and confirmed that
these re-tensions could be achieved without exceeding
the original tension limits.

Re-tensioning was carried out on a total of 35


132kV line modelled in PLS-CADD™
circuit sections over a series of outages between July
and October 2017. Additionally, NM Group’s analysis Using a CAD model, thermal up-rating studies
identified one location where the re-tension to the a range of options to increase capacity on the line.
original tension limit would not achieve the required Including, but not limited to, re-conductoring, adjusting
clearance at the desired rated temperature. In this case the tension on the conductor and removing ground or
NM Group proposed adoption of a ‘floating dead end’, vegetation.
where strain insulators are connected mechanically to
a short suspension unit. This was found to achieve the Project Summary
required clearance at the desired temperature.
• Re-tension was completed avoiding a lengthy re-

“ Combining LiDAR survey


PLS-CADD™-based engineering analysis makes it
data

possible to accurately evaluate options for releasing


with a


furbishment project

Line rating increased from 50°C to 75°C

line capacity.
” Paul Richardson
Director of Engineering, NM Group
• Additional 50MW of additional capacity available
to WPD

Consequently, one suspension tower attachment


was thus modified in order to raise the conductor www.nmgroup.com
attachment point. The result of this work was that the
rated temperature of the Lynx conductor could be
raised to 75°C, with an associated rating increase of
around 30MW per circuit. This increase has allowed
WPD to accept approximately 50MW of additional info@nmgroup.com
generation connections while deferring the need for a
full refurbishment of the line.

NM Group
A T R I M B L E CO M PA N Y
www.nmgroup.com PAGE 2

You might also like