Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

Journal of Applied Engineering (JOAE), 2 (10), October-2014 (Volume-II, Issue-X)

ISSN: 2348-4802

A Study on Structural Failures & Lessons Learnt


Mohammad Adil Dar1, Prof (Dr) A.R. Dar2 , Jayalakshmi Raju3 ,Shazia Shafi Bhat4
1&3
PG Scholar, Department of Civil Engineering, Kurukshetra University, Haryana, India
2
Professor & Head, Department of Civil Engineering, NIT, Srinagar, India
4
PG Scholar, Department of Civil Engineering, NIT, Srinagar, India

Abstract: Structural failure is the loss of the load carrying capacity of the component or member within structure
or structure itself. Structural failure initiated when the material is stressed to it’s strength limit which causes the
cracks & excessive deformation. Any structure has several components/members like super-structure, sub-structure
& foundations. The loads of super structures transfers to the sub-structure & then sub-structures to the
foundations. Like a building frame receive the loads from super structure & transfer to the sub-structures & finally
to the foundations. Similarly a highway bridge to support the live load due to traffic & dead load of bridge itself &
several other loads such as snow loads, wind loads etc. Then when the structure does not able to transmit these
loads safely to the foundations then it under go failure which is called the structural failure [1][2].

Keywords: Structural failure, stressed, load transfer, foundations, bridge.

INTRODUCTION lateral ties. Insufficient lap length is also a major


We can learn much more from failure than success. design deficiency because the reinforcement bar
We can also say that the failure is stepping stone of can slip from each other, so the lap distance should
the success but there is a high price to pay in terms be sufficient to form a stronger bond between the
of energy, time & money. The structural failure is reinforcement.FIGURE-2 shows insufficient lap
the night mare of Architects, Engineers, Contractors length.
& clients. It hunts the construction industry resulting  Insufficient allowance for expansion or
the humiliations, financial catastrophe & at time loss contraction.
of the life[3][5].It is interesting to know that the  Absence of weathering of construction materials.
failures have occurred in the past, to occur today &  Incorrectly placed damp – proof courses.
continue to occur in future. The process of learning  Poor jointing between different materials or
from experience & education is a life time exercise components. Mostly the structure fails due to the
beginning at birth, continuing through childhood, on inadequate connection that is connection between
to university & then to the practical life. Professional the beam-column, beam-slab. We always design
training has different needs & experienced based on the beam, slab & column but we do not
individuals needs. concentrate on the design of the beam-column or
beam-slab design.
CAUSES OF STRUCTURAL FAILURE  Poor specification & inadequate provisions for
access to carry out maintenance activities.
DESIGN DEFICIENCIES
 Poor detailing at the design stage. FIGURE-1  Lack of adequate consideration of future
shows failure caused by insufficient lateral ties in maintenance problems.
the column as well as the spacing between the

179
Journal of Applied Engineering (JOAE), 2 (10), October-2014 (Volume-II, Issue-X)

FIGURE-1 Failure is caused by the insufficient FIGURE-2 Insufficient lap length


lateral ties &more spacingbetween them in the
column

CONSTRUCTION ERROR  Failure of client, builder, designer or architect to


 Lack of supervision during construction period. reject sub-standard materials.
 Failure to understand or follow exactly the  Improper inspection of materials by supplier or
specifications and/or drawings. receiver.
 Failure to replace defective work.  Inadequate storage facilities on site.
 Failure of Designer/Architect/or Engineer  Inadequate/or inconsistent mixing of materials on
monitoring work in progress. site.
 Lack of skilled labor.
 Over emphasis or need for quantity rather than FOUNDATION FAILURE
quality. Even an excellently designed and constructed
 Failure to fully appreciate the consequences of structure will not stand on a bad foundation.
shady or poor and/or materials. FIGURE-3 shows Although the structure will carry its loads, the earth
failure caused by the corrosion in reinforcement & beneath it may not be able to sustain loads so it will
inadequate concrete cover. cause whole structure failure. The Leaning Tower of
Pisa is a famous example of bad foundations[4][7],
but there are many others. The displacements due to
bad foundations may alter the stress distribution
significantly. A small eccentricity can result great
moment and failure of structure.

A Foundation is subjected to the following loads


 The dead load of the building, which is the sum of
the weights of the frame; the floors, roofs, and
walls; the electrical and mechanical equipment;
and the foundation itself.
 The live load, which is the sum of the weights of
FIGURE-3 Failure caused by the corrosion in
the people in the building; the furnishings and
reinforcement & inadequate concrete cover. equipment they use; and snow, ice, and water on
the roof.
FAULTY MATERIALS  Wind loads, which can apply lateral, downward,
and uplift loads to a foundation.

180
Journal of Applied Engineering (JOAE), 2 (10), October-2014 (Volume-II, Issue-X)

 Horizontal pressures of earth and water against  If a builder built a house for a man & do not make
basement walls. it’s construction meet the requirement & a wall fall
 In some buildings, horizontal thrusts from arches, in, that builder shall strengthen the wall of his own
rigid frames, domes, vaults, or tensile structures. expense.
 On some building sites, buoyant uplift forces from
underground water, identical to the forces that Similarly NAPOLEONIC (1804) has given a law
cause a boat to float. against the failure that, If there is a loss in
 During earthquake, horizontal & vertical forces serviceability in a constructed project within 10
caused by the motion of the ground relative to the years of its completion because of a foundation
building. failure or from poor workmanship, the contractor
and architect (luckily not the engineer!) will be sent
Requirements for a satisfactory foundation to prison.
 The foundation, including the underlying soil and
rock, must be safe against structural failure that METHODOLOGY
could result in a collapse. Physical observations
 During the life of the building, the foundation must The physical analysis was concreted on :
not settle in such way as to damage the structure or  The splitting of hinges.
impair its function.  Corrosion of reinforcing bar at different parts of
 The foundation must be feasible both technically the structure.
and economically and practical to build without  Distress in column.
adverse effects to surrounding property.  Cracking of raft beams.
 Cracks in trough ribs.
HISTORY PENALTIES
In this era, the maximum structural failures are Structural design check
caused by the human errors. Even the failure due to According to the name this is understood that we
the earthquake is also occurred due to the human shall check the design & drawing of the structure.
errors because generally we see that some structure NDT (Non Destructive Testing)
remains stable in the earthquake also. This test is done for check the strength of the
Do we ever think why these structures remains hardened concrete by the following methods.
stable & others are fail. It is because the stability of  Ultrasonic test:- This is done for check the
the structure depends upon the human errors & the compressive strength of the column.
human errors in these structures was negligible.  Rebound hammer test:- This is also done for
check the compressive strength of the column. In
Let us take a example, we must have seen some old this method first we remove the plaster on the
days structures which lasted for a decades, even a columns at selected points (top, centre & bottom)
centuries but do we ever think why these structures then equipment is done in bare concrete.
lasted for a long time. This is due to the some simple  Load test:- This test is done for check the
laws to prevent the failure by punishment of structural soundness of the beams, slabs & check
defaulters. It might have worked. The some laws the deflection by the dial gauge & compare this
given by the famous Babylon king HAMMURABI deflection with maximum allowable deflection.
(2200 BC) .According to him:
 If a builder built a house for a man & do not make NECESSARY STEPS FOR
it’s construction firm & the house which he has IMPLEMENTATION
built collapse & cause the death of the owner of •Creating awareness in the community, policy
the house – builder should be put to death. makers, even technicians / engineers and all
 If it cause the death of son of the owner of the stakeholders.
house – they shall put to death a son of that • Translate available knowledge in end user's
builder. language.
 If it cause the death of a slave of the owner of the • Capacity Building of Engineers/Technicians.
house – he shall give to the owner of the house a • Develop demand and supply mechanism for
slave of equal value. seismic safety.
 If it destroy property, he shall restore whatever it
destroyed, & because he did not make the house CONCLUSION
which he built firm & it collapsed, he shall built It is impossible to control all the above factors
the house which collapsed at his own expense. during design, construction and occupations stages

181
Journal of Applied Engineering (JOAE), 2 (10), October-2014 (Volume-II, Issue-X)

of buildings. However, considering these factors and REFERENCES


minimizing their effect will definitely reduce the 1) Structural Failures – Case Histories by R.
amount and need for maintenance. To avoid or JAGADISH.
minimize the failures of structure we must learn 2) "Breakdown: Deadly Technological
from the mistakes which other has committed due to Disasters", by Neil Schlager, Visible Ink
any reason. Lesson learned from the past structural Press, Detroit, 1995.
failures is discussed below: 3) "Set Phasers on Stun", by Steven Casey,
 The design should be checked manually by the Aegean Publishing Co., Santa Barbara,
various designers before it is released for the 1993.
construction. 4) "To Engineer is Human", by Henry
 Quality control of material and construction, Petroski, Vintage Books, New York, 1992.
excellent workmanship and work according to the 5) "Design Paradigms : Case Histories of
drawing must be ensured by the site supervisor. Error and Judgment in Engineering", by
 Integrity and continuity in construction such that it Henry Petroski, Cambridge University
forms a continuous load path between the Press, Cambridge, 1994.
foundations to all diaphragm levels should be 6) "Civil Engineering Practice: Engineering
maintained. Success by Analysis of Failure", by David
 Sufficient gap must be provided to avoid close D.A. Piesold, McGraw-Hill Professional,
proximity or pounding effect. New York, 1991.
 Proper reinforcement should be ensured according 7) "Inviting Disaster: Lessons From the Edge
to the cross sectional area of the structural of Technology", by James R. Chiles, Harper
member. Temperature reinforcement should also Business, New York, 2002.
be provided to nullify freezing and thawing.
 Shear wall should be employed for increasing
stiffness in both the principle direction.
 To avoid short column effect proper attention
should be given while designing these members.

182

You might also like