Arcadis Design and Consultancy Modon Properties Amana Contracting & Steel Building LLC
METHOD STATEMENT
FOR
COMMMISSIONING OF AUTOMATIC FOAM SYSTEM
Table of Contents
1.0 PURPOSE..........................................................................................................................................2
2.0 SCOPE..............................................................................................................................................2
3.0 REFERENCE DOCUMENTS................................................................................................................2
4.0 TOOLS & EQUIPMENT / MATERIAL..................................................................................................2
5.0 RESPONSIBILITY...............................................................................................................................3
6.0 PROCEDURE / METHOD TO BE EMPLOYED......................................................................................4
6.1 GENERAL REQUIREMENTS...............................................................................................................4
6.2 HANDLING AND STORAGE...............................................................................................................4
6.3 MATERIAL INSPECTION....................................................................................................................4
6.4 PRE-COMMENCMENT REQUIREMENTS...........................................................................................5
6.5 IINSTALLATION PROCEDURE............................................................................................................5
6.5.1 PREPERATION..................................................................................................................................5
6.5.2 FABRICATION oF PIPES.....................................................................................................................6
6.5.3 INSTALLATION OF FOAM TANK........................................................................................................7
6.5.4 INSTALLATION oF SUPPORTS AND BRACKETS..................................................................................7
6.5.5 NOZZLE INSTALLATION....................................................................................................................7
6.5.6 DELUGE VALVE AND SPRIKLER INSTALLATION.................................................................................7
6.5.7 PRESSURE TEST................................................................................................................................8
7.0 QA/QC RECORDS..............................................................................................................................8
8.0 SAFETY REQUIREMENTS..................................................................................................................8
9.0 ATTACHMENTS................................................................................................................................9
1.0 PURPOSE
The purpose of this method statement is to identify the requirement for installation of
Automatic Foam System as per the contract specification, drawings and as per the DC &
NFPA regulations for “CONSTRUCTION OF MINI ZAYED FISHER’S MAN WHARF
FISH MARKET, ABU DHABI, UAE “
2.0 SCOPE
This method statement is applicable to all activities related to installation of Automatic Foam system
for “CONSTRUCTION OF MINI ZAYED FISHER’S MAN WHARF FISH MARKET, ABU
DHABI, UAE “All works shall be conducted in conformance with relevant project drawings/
specifications, authorities concerned, Manufacturer Recommendations and good industry practices.
5.0 RESPONSIBILITY
5.1 Project Manager shall be responsible for overall project execution, he will coordinate with
client and head office, progress monitoring, attending review meeting, resource management,
overall he will be responsible for timely completion of project in accordance to all contractual
requirements.
5.2 Project Engineer shall be responsible for co-ordination and monitoring construction activities
and construction groups and ensure that work is done as per specification and approved
drawings and all safety measures are implemented. Allocation of manpower and machineries in
consultation with construction manager
Achieving target progress, backlog if any, he will consult with construction manager for its
recovery action plan.
Monitoring whether work is going on as per approved method
statement/drawing/specification etc.
Monitoring lines, levels as per approved drawings.
Monitoring timely materials supply at construction location.
Raising RFI and other necessary inspection and test records and forward to QA/QC
Engineer for further process.
5.4 Foreman shall be responsible for checking & setting out alignments, levels and installation etc.
5.5 Safety Officer shall be responsible for monitoring and implementation of HSE requirements,
daily checking of work permit, supervising whether each worker are using necessary PPE.
Supervising whether each worker is working in safe manner following applicable safety rules
and regulations.
7 QA/QC RECORDS
7.1 Request for Material Inspection & Approval
7.2 Request For Installation Inspection & Approval
7.3 Installation Checklist
8 SAFETY REQUIREMENT
8.1 Appropriate work permit to be obtained prior to start of work.
8.2 Toolbox talks to be conducted prior to commencement of works.
8.3 All necessary barriers, signage lighting etc. to be provided and maintained.
8.4 Appropriate PPE to be worn / used.
8.5 Close supervision on safety requirement shall be provided.
8.6 Adequate signage to be provided during the work.
9 ATTACHMENTS
9.1 Inspection and Test Plan
9.2 Checklist
9.3 Risk Assessment