09 Samss 089 564ccf69b4fbc

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 22

Materials System Specification

09-SAMSS-089 25 October 2011


Shop-Applied External Fusion
Bonded Epoxy Coating for Steel Line Pipes
Document Responsibility: Paints and Coatings Standards Committee

Saudi Aramco DeskTop Standards


Table of Contents

1 Scope............................................................. 2
2 Conflicts and Deviations................................. 3
3 References..................................................... 3
4 Materials......................................................... 5
5 Handling of Pipe Prior to Coating................... 6
6 Cleaning and Surface Preparation................. 7
7 Coating Application........................................ 8
8 Quality Requirements.................................... 9
9 Inspection Requirements............................. 10
10 Recheck on Coating Material Quality........... 14
11 Repairs......................................................... 14
12 Pipe Storage and
Preparation for Shipment...................... 16

Appendix A – Qualification Procedure


for Initial Product Approval................... 18

Previous Issue: 31 May 2005 Next Planned Update: 25 October 2016


Revised paragraphs are indicated in the right margin Page 1 of 22
Primary contact: Khashram, Maher Saud on 966-3-8809561

Copyright©Saudi Aramco 2011. All rights reserved.


Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-089
Issue Date: 25 October 2011 Shop-Applied External Fusion
Next Planned Update: 25 October 2016 Bonded Epoxy Coating for Steel Line Pipes

1 Scope

1.1 This Specification, together with the Purchase Order and appropriate Data
Sheets, defines the minimum mandatory requirements of shop-applied, heat-
cured external fusion-bonded epoxy (FBE) coating systems for the external
surfaces of steel tubular products and associated fittings and couplings.

1.2 Information Required in Requests for Quotation and in Purchase Orders

Requests for Quotation and Purchase Orders shall identify which of the
following service conditions applies for the coated products:

1.2.1 Buried or immersed, with temperatures not exceeding 65°C in subkha


soil or subsea, or up 93°C in dry soil condition.

1.2.2 Buried or immersed, with temperatures not exceeding 82°C in subkha


soil or subsea.

1.2.3 Buried or immersion with temperature up to 110°C in subkha soil or


subsea.

1.3 Information Required with the Quotation

Cost if burn-off is required to remove oily contaminants from the surface prior
to blast cleaning. (See Paragraph 6.1)

1.4 Definitions

For purposes of this specification only, the following definitions apply:

Approved (Pre-Qualified) Procedure: Procedure referred to in this


specification that has been approved in writing by the RSA. Approved
procedures do not require re-qualification in new purchase orders.

Batch: The quantity of coating material produced during a continuous


production run of not more than eight hours.

Buyer: Saudi Aramco Purchasing Department Representative.

Buyer's Representative: The person or persons designated by the Purchasing


Department to monitor/enforce the contract. Normally, this is the on-site
inspector.

Custom Coated Pieces: All pieces not coated by automated in-plant


equipment. Generally, anything less than a 40 foot pipe joint.

Page 2 of 22
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-089
Issue Date: 25 October 2011 Shop-Applied External Fusion
Next Planned Update: 25 October 2016 Bonded Epoxy Coating for Steel Line Pipes

Cutback: The length of pipe left uncoated at each end for joining purposes.

DFT: Dry film thickness.

FBE: Fusion bond epoxy coating.

Manufacturer: Company manufactures the required coatings.

Pipe: Steel tubular, including line pipe and OCTG casing and tubing.

RSA: Responsible Standardization Agency Representative - Coating Engineer


designated by the Manager of Consulting Services Department to act in his
behalf.

Vendor: Pipe and custom coating applicator.

2 Conflicts and Deviations

2.1 Any conflicts between this specification and other applicable Saudi Aramco
Materials System Specifications (SAMSSs), Engineering Standards (SAESs),
Standard Drawings (SASDs) or industry standards, codes, and forms shall be
resolved in writing by the Company or Buyer Representative through the
Manager, Consulting Services Department.

2.2 Direct all requests to deviate from this specification in writing to the Company or
Buyer Representative, who shall follow internal company procedure SAEP-302
and forward such requests to the Manager, Consulting Services Department of
Saudi Aramco, Dhahran.

3 References

Material or equipment supplied to this specification shall comply with the latest edition
of the references listed below, unless otherwise noted.

3.1 Saudi Aramco References

Saudi Aramco Engineering Procedure


SAEP-302 Instructions for Obtaining a Waiver of a
Mandatory Saudi Aramco Engineering
Requirement

Saudi Aramco Engineering Standards


SAES-H-002 Internal and External Coatings for Steel Pipelines
and Piping

Page 3 of 22
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-089
Issue Date: 25 October 2011 Shop-Applied External Fusion
Next Planned Update: 25 October 2016 Bonded Epoxy Coating for Steel Line Pipes

SAES-H-100 Appendix I Qualification Procedure for Sand for


Abrasive Blasting

Saudi Aramco Materials System Specification


01-SAMSS-024 Pipe Handling and Nesting

Saudi Aramco Inspection Requirements


Form 175-091300 Shop-Applied External FBE Coating

3.2 Industry Codes and Standards

American Society for Testing and Materials


ASTM D714 Standard Method of Evaluating the Degree of
Blistering of Paint
ASTM D4060 Standard Test Method for Abrasion Resistance of
Organic Coatings by the Taber Abraser
ASTM G8 Test for Cathodic Disbonding of Pipeline Coatings
ASTM G14 Test for Impact Resistance of Pipeline Coatings
ASTM G42 High temperature test for Cathodic Disbonding of
Pipeline Coatings

International Organization for Standardization


ISO 8501-1/SIS Pictorial Surface Preparation Standard for
Painting Steel Surfaces

Swedish Standard Institute


SS 05 59 00 Pictorial Surface Preparation Standard for
Painting Steel Surfaces

The Society for Protective Coatings (SSPC)


SSPC PA 2 Measurement of Dry Coating Thickness with
Magnetic Gages
SSPC SP 1 Solvent Cleaning
SSPC SP 10 Very Thorough Blast Cleaning (near white metal
blast)

Canadian Standards Association


CAN/CSA-Z245.20 - 02 External Fusion Bond Epoxy Coating for Steel
Pipe

Page 4 of 22
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-089
Issue Date: 25 October 2011 Shop-Applied External Fusion
Next Planned Update: 25 October 2016 Bonded Epoxy Coating for Steel Line Pipes

NACE International
NACE PR0394 - 94 Application, Performance, and Quality Control of
Plant-Applied Fusion Bonded Epoxy External
Pipe Coating

4 Materials

4.1 Coating

4.1.1 Material for the shop-applied external coating shall be thermosetting


resin powder for application by the fusion bond process, with or without
primer, as tested and approved by Saudi Aramco, and applied according
to the Manufacturer's recommendation. Use of reclaimed powder shall
not exceed the Manufacturer's recommendation. In no case shall such
use be greater than a maximum of 10% by weight without written
approval from the RSA.

4.1.2 The Vendor may select any of the Saudi Aramco-approved products
given in APCS-104 or another equal alternative agreed upon by the RSA
in writing.

4.1.3 Proposed alternative coating materials must proceed and pass the
relevant qualification tests in Appendix A of this Specification.

4.1.4 Powder coating materials (and materials used for touch-up and repairs)
supplied to the Vendor shall be marked with the following information:
a) The Manufacturer's name
b) The material identification number
c) The batch number
d) Date of manufacture
e) The shelf life (or expire date)

4.1.5 The Vendor shall retain samples of each powder batch for a period of
1 year. The sample shall be of sufficient size for the following tests, if
required:
a) Instrumental Analyses, IR and DTA
b) Gel Time
c) Moisture Content
d) Bend tests

Page 5 of 22
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-089
Issue Date: 25 October 2011 Shop-Applied External Fusion
Next Planned Update: 25 October 2016 Bonded Epoxy Coating for Steel Line Pipes

e) Cathodic disbonding tests

4.1.6 Coating material shall be stored and handled in accordance with the
coating Manufacturer's recommendations.

4.2 Repair Materials

Touch-up or repair shall be made with FBE or other Saudi Aramco approved
materials tested in accordance with, and meeting the requirements for adhesion,
hardness, and cathodic disbonding performance in Appendix A of this
specification. Touch-up material shall also be approved by the Manufacturer.

4.3 Blast Abrasives

4.3.1 Material for blast cleaning shall be steel grit or other abrasives that contain
less than 100 ppm sulfates, and chlorides, less than 2% carbonates, and of
a particle size that will produce a clean angular surface profile as specified
in paragraphs 6.3 and 6.4. The abrasives shall be stored in a dry condition
and maintained dry during use. Sand is prohibited and shall not be used as
an abrasive in accordance with SAES-H-100.

4.3.2 The Vendor shall furnish a chemical analysis for all batches of abrasives
to verify that carbonates, chlorides, and sulfates do not exceed the limits
in paragraph 4.3.1.

5 Handling of Pipe Prior to Coating

5.1 Proper equipment for handling, unloading and temporary storage of bare pipe
shall be used to avoid any damage to bare pipe, pipe ends or obliteration of
necessary pipe markings.

5.2 The Vendor shall take special care to avoid damage to any internal coatings
during all phases of the external coating process and to avoid corrosion damage
to bare steel surfaces during storage.

5.3 The stacking height of bare pipe shall be limited by the requirements of
01-SAMSS-024.

5.4 Pipe or fittings received in a damaged condition or showing serious defects that
may impair the coating, such as extensive laminations, burrs, gouges, metal slivers
or cold laps, shall be reported to the Buyer's Representative for disposition.
The Vendor shall determine final disposition due to the surface coat ability.

5.5 Vendor shall have an approved procedure (see paragraph 1.4) for handling,
loading, unloading, storage and preparation for shipment for pipe and fittings
prior to coating.

Page 6 of 22
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-089
Issue Date: 25 October 2011 Shop-Applied External Fusion
Next Planned Update: 25 October 2016 Bonded Epoxy Coating for Steel Line Pipes

6 Cleaning and Surface Preparation

6.1 Prior to abrasive cleaning, all oil, grease and other deleterious materials shall be
removed by solvent cleaning in accordance with SSPC SP 1 or by detergent
washing or steam cleaning. No residue that will affect adhesion shall be left on
the surface.

Oven burn-off at a temperature of 370-400°C may also be employed, if, in the


opinion of the Vendor, this is the only satisfactory method of ensuring that the
steel is free of oily contaminants. The reported oily contamination shall be
investigated and confirmed by the Buyer's Representative and written approval
shall be obtained from the Buyer prior to burn-off. (See paragraph 1.3.1.)

6.2 The surface temperature of pipe or fittings shall be at least 3°C above the
dew point before and during abrasive blasting and until start of pre-heating.
If preheating is used, it shall be carried out in a uniform manner to avoid
distortion of the pipe and/or damage to any internal coating.

6.3 The surface to be coated shall be abrasive cleaned to a near white metal surface
finish equal to Sa 2-1/2 as described in ISO 8501-1/SIS SS 05 59 00 or SSPC
(SP10). Any internal coating shall be protected from damage by the blasting
material at all times.

6.4 The blast pattern shall be a uniform angular anchor profile with a height of
38 - 100 micrometers (1.5 to 4 mils).

6.5 Chloride Contamination

6.5.1 The blasted surface of pipes and fittings that will not be subsequently
treated with a phosphoric acid and fresh water wash shall be tested for
the presence of residual chlorides after blasting using a test method that
has been prior-approved in writing by the RSA. Residual Chlorides shall
be no greater than 40 mg/m². Test the first pipe and/or fitting coated on
any given day. After that, test one out of every 50 pipes or 50 fittings.

In the event of a failure, re-test the piece. If it fails the re-test, test all
pieces that were blast cleaned both before and after the contaminated
piece until three in a row pass the test. All pieces coated since the last
good test must be re-blasted, re-tested, and re-coated.

If the phosphoric acid and fresh water wash is permitted prior to


application of the FBE powder. The Vendor must use an approved
procedure (see paragraph 1.4). Pipe or fittings treated in this manner do
not require testing for chloride contamination.

Page 7 of 22
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-089
Issue Date: 25 October 2011 Shop-Applied External Fusion
Next Planned Update: 25 October 2016 Bonded Epoxy Coating for Steel Line Pipes

Commentary:

For high temperature FBE powder coatings application, the residual


Chlorides shall be not greater than 25 mg/m².

6.6 Defect Repair and Disposition

6.6.1 After abrasive cleaning and before coating, the surface to be coated shall
be carefully inspected for metal defects. The Vendor shall be responsible
for the repair of any defects, which can be repaired by filing or grinding,
and for restoring the anchor pattern at the locations of such repairs when
the size exceeds 75 mm in any direction. The tools and manner employed
to remove metal defects shall not contaminate the surface.

6.6.2 Any pipes or fittings containing surface defects that are significantly
serious or extensive that they cannot be readily repaired shall be set aside
for disposition by the Buyer's Representative.

6.6.3 If these defects are significant so that the production is severely


disrupted, the coating process shall be stopped and both the Buyer and
the Buyer's Representative shall be informed. The Vendor shall advise
them of any remedial measures that could be taken to achieve an
acceptable coating. The final decision, whether the affected pipe and
fittings can be coated, shall be made by the Vendor after consultation
with the Buyer's Representative.

6.7 Dew Point readings shall be recorded at the start and every 2 hours during the
blasting operation in the immediate vicinity of the operation. Blasting and
coating operations shall be suspended if the substrate temperature is less than
3°C above the dew point.

6.8 Any metal surface showing evidence of flash rusting shall be re-blasted prior to
coating.

7 Coating Application

7.1 The coating material shall be applied according to the Vendor's approved written
application procedure (see paragraph 1.4) incorporated with the Manufacturer's
recommendations.

7.2 In no case shall steel tubular products and associated fittings and couplings,
which have been internally coated, be exposed to a temperature detrimental to
the internal coating.

7.3 The coating dry film thickness shall be as follows:

Page 8 of 22
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-089
Issue Date: 25 October 2011 Shop-Applied External Fusion
Next Planned Update: 25 October 2016 Bonded Epoxy Coating for Steel Line Pipes

7.3.1 350 to 525 micrometers (14 to 21 mils) for the services described in
paragraph 1.2.1

7.3.2 575 to 750 micrometers (23 to 30 mils) for the service described in
paragraph 1.2.2

7.3.3 575 to 750 microns (23 to 30 mils) for the service described in paragraph
1.2.3

7.3.4 Fittings and couplings are allowed a maximum DFT of 1000 micrometers
(40 mils) regardless of service.

7.4 Any steel tubular products and associated fittings and couplings having less than
the specified minimum dry film thickness shall be re-blasted and coated at no
cost to Saudi Aramco.

7.5 The finished coating shall have a cut back at each end in the range of 38 to
65 mm measured from end of pipe, dependant on the diameter of the pipes.

7.6 The cured coating shall be of uniform color and gloss, and shall be free of
blisters, and fish eyes as defined in SSPC vol. 1. Cosmetic sags, runs, and other
non-injurious irregularities are acceptable as long as the area affected is less than
0.5 % of the total coated area.

7.7 For girth weld areas the allowable DFT shall be in the range of 400 to
1000 micrometers (16 to 40 mils). Lower limit is determined by the service
(see paragraph 1.2).

8 Quality Requirements

The Vendor's quality assurance system shall include, as a minimum, the following:
a) Checking cleanliness of pipe immediately prior to blasting (see paragraph 6.1).
b) Monitoring of size, shape, dryness and cleanliness of the blasting material and
process (see paragraph 4.3).
c) Checking visually, in good light, the surface of the pipes for metal defects, dust
and surface debris (see paragraph 6.6.1).
d) Checking pipe surface blast profile (see paragraph 6.4).
e) Checking temperature control of the pipe surface (see paragraphs 6.2 and 7.2).
f) Checking coating thickness of cured FBE (see paragraphs 7.3 and 9.3).
g) Checking on the coating adhesion properties (see paragraph 9.4).

Page 9 of 22
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-089
Issue Date: 25 October 2011 Shop-Applied External Fusion
Next Planned Update: 25 October 2016 Bonded Epoxy Coating for Steel Line Pipes

h) Holiday detection of l00% of the coated surface area of all pipes (see paragraphs
9.5 and 11.4).
i) Supervision of adequate and proper repair of all defects (see paragraph 11).
j) Checking of coating color, appearances and uniformity (see paragraph 7.6).
k) Visual examination for damage to internal coating (see paragraph 5.2).
l) Cure Test - see paragraph 9.7
m) Checking for residual chloride contamination (see paragraph 6.5.1).

9 Inspection Requirements

9.1 Notice

The Vendor shall notify the Buyer's Representative not less than 5 days in
advance of the start of each production run. The Vendor shall provide the
Buyer's Representative with a detailed time schedule to permit him to witness or
monitor all processing and testing phases.

9.2 Responsibility for Inspection

9.2.1 The Vendor shall be responsible for all quality control checking
including visual inspection, thickness measurements, and holiday testing,
and shall keep records on the results of all such inspections in a form
suitable to the Buyer's Representative.

9.2.2 The Buyer's Representative shall have access to each part of the process,
and shall have the right and opportunity to witness or monitor any of the
quality control tests and/or perform such tests himself on a random
sampling basis.

9.2.3 The Buyer's Representative shall have the right to halt this work pending
alterations or corrections to the process to correct all faults found in the
work that result in failure to conform to this specification.

9.3 Coating Thickness Test

Every pipe and spool piece shall be checked in accordance with SSPC (PA-2) in
at least five (5) equidistant places. Loose fittings shall be checked in at least
5 locations. All coating thickness measurements shall be made using a
non-destructive type of thickness gauge, which has been calibrated as required
in paragraph 9.8.1. All results shall be as specified in paragraph 7.3 of this
Specification, and shall be recorded.

Page 10 of 22
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-089
Issue Date: 25 October 2011 Shop-Applied External Fusion
Next Planned Update: 25 October 2016 Bonded Epoxy Coating for Steel Line Pipes

Exception:

Except that fittings 6-inch and smaller shall be checked in at least 3 locations.

9.4 Adhesion Test

The adhesion of the coating shall be determined at one location on a pipe for
each of the following cases:
a) The first production joint,
b) The first joint after any interruption in production and
c) Once every hour or twenty pipe lengths, whichever is more frequent.

If 3 tests have been successful, the frequency may be reduced to once every
2 hours or 50 pipe lengths, whichever is sooner. Custom coated pieces shall
have one sample per production lot subjected to this test. Failure of the test shall
require lot narrowing by testing the pipes/fittings until three in a row (coated
both before and after the piece that failed) show satisfactory adhesion. A lot is
defined as one shift's production, except in the case of custom coated pieces
where a lot is defined as any number of pieces processed through the custom
coating oven at the same time.

9.4.1 Test Procedure

9.4.1.1 With a sharp narrow bladed knife, two incisions


(approximately 13 mm long) shall be made, in the form of an
X, through to the metal substrate.

9.4.1.2 At the intersection of the X, an attempt shall be made to force


the coating from the steel substrate with the knife point.
The point of the knife shall be inserted horizontally i.e., the flat
of the blade under the coating at the point of intersection of the
X such that the blade point is on the metal surface. Using a
levering action, the flat point shall be forced away from the steel
in an attempt to pry off the coating. Refusal of the coating to
disbond from the substrate shall be recorded as a pass. A pass
shall also be recorded where the coating fails cohesively. Partial
or complete adhesive failure between the coating and the
substrate shall be recorded as a failure. Disbondment at the
point of the intersection is common due to the action of marking
the 'X' cut. Therefore, for 1 mm away from the tip of the
intersection any disbondment shall be ignored.

9.4.1.3 The pipe or fitting shall be allowed to cool to below 80°C prior
to conducting the adhesion test. Failure of the test shall require

Page 11 of 22
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-089
Issue Date: 25 October 2011 Shop-Applied External Fusion
Next Planned Update: 25 October 2016 Bonded Epoxy Coating for Steel Line Pipes

each piece coated on that day to be subjected to the test until a


total of three tests in a row (three done both before and after
the piece which failed) are satisfactory.

9.5 Holiday Detection

9.5.1 l00% of the coated pipe or fittings surface area shall be holiday detected
with a hot spark pulse-type DC detector employing an audible signaling
device. The electrode used for locating holidays shall be designed to
ensure direct contact with the coating, (with no visible gaps). Holiday
detection shall not be conducted if the surface temperature of the pipe is
above 80°C.

9.5.2 Travel rate of the detectors electrode shall not exceed 75 cm/s and shall
not be allowed to remain stationary while the power is on.

9.5.3 Holiday test voltage shall be 125 volts DC per 25 micrometers (0.001 in)
of maximum coating thickness. However, to eliminate the need for
continual adjustment during shop production, a maximum voltage of
2400 volts ± 50 volts may be used for the coating thickness range 350 to
750 micrometers (14 to 30 mils). Holidays shall be clearly marked for
repair.

9.6 Bend Test

9.6.1 Once per shift or every one hundred pipe lengths (whichever is the more
frequent) and at the start of using a new batch of powder the flexibility of
the coating shall be determined by a bend test. The powder utilized for
the test shall be taken from the plant application fluid bed. (Bend testing
is not required for custom coated fittings.)

9.6.2 Two test bars measuring approximately 25 mm x 192 mm x 9.5 mm shall


be coated at a dry film thickness of 425 - 525 micrometers (17 - 21 mils)
for the services in paragraph 1.2.1 and 575 - 750 micrometers (23 to
30 mils) for the service in paragraph 1.2.2 and 1.2.3.

9.6.3 The coating thickness shall be measured at 5 locations 25 mm apart on


each sample, and the thickness recorded. The average of these readings
shall fall in the range in 9.6.2.

9.6.4 Test bars shall be holiday detected in accordance with paragraph 9.5.3 of
this specification, and all holidays marked and recorded.

9.6.5 Specimens shall be at a temperature of 25°C ± 3°C when clamped in the


bender with the coated side up. The specimens shall be bent flatwise at
60 degrees over a 25.4 mm thick shoe of the following dimensions:

Page 12 of 22
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-089
Issue Date: 25 October 2011 Shop-Applied External Fusion
Next Planned Update: 25 October 2016 Bonded Epoxy Coating for Steel Line Pipes

- Shoe radius 95.2 mm


- Chord 152 mm
- Arc 178 mm

9.6.6 Bending shall be accomplished in less than 30 seconds.

9.6.7 The coated specimens shall show no cracks to base metal when
examined at 10X magnification except where gripped or clamped.
If visual examination cannot determine whether a crack extends to base
metal, holiday testing using the hot spark detector method with a
conductive rubber electrode shall be used. Tests are to be carried out as
required in 9.5.3 of this specification.

9.6.8 If either of the bend tests fail, the tests shall be repeated.

9.6.8.1 If both bend re tests are satisfactory, the bend test shall be
accepted.

9.6.8.2 If either (or both) of the re tests fail, all pipes coated since the
previous successful bend test shall be set aside. Further
coating application with the suspect batch of powder shall be
immediately discontinued.

Two specimens with the same dimensions as given in


paragraph 9.6.2 shall be cold cut from the first coated pipe with
the suspect batch or since the last successful bend test,
whichever occurred later. The edges of the specimens as
necessary shall be chamfered to remove stress raisers.

If the samples fail the bend test, all pipe that has been coated
with the suspect material shall be blasted off and the pipes shall
be recoated. If the samples pass the bend test, lot narrowing
shall be used until the Buyer's Representative is satisfied that
all pipes with substandard coatings have been identified.
These pipes shall be blasted and recoated.

9.7 Cure Test

Twice per shift the coating on production pipes shall be tested by Differential
Scanning Calorimeter analysis. Custom coated fittings shall be subjected to the
same test at a frequency of one sample per production lot. Girth welds shall be
checked twice per day. Failure of the test shall require each piece coated on that
day to be subjected to the test until a total of three tests in a row (three done both
before and after the piece which failed) are satisfactory. The glass transition

Page 13 of 22
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-089
Issue Date: 25 October 2011 Shop-Applied External Fusion
Next Planned Update: 25 October 2016 Bonded Epoxy Coating for Steel Line Pipes

difference (Tg2-Tg1) must be in the range specified by the FBE manufacturer to


be acceptable.

9.8 Calibration of Inspection Equipment

9.8.1 Coating thickness gauge (reference paragraph 10.3) shall be calibrated at


the start of production and every 3 hours during production, at
approximately the mid-range of the coating thickness against a certified
or known standard.

9.8.2 Holiday detector shall be calibrated at least twice per 8 hours shift
against a suitable calibrated voltmeter and adjusted to ensure that voltage
is sufficiently high to detect an intentional pinhole holiday through the
coating on the pipe.

10 Recheck on Coating Material Quality

The Buyer's Representative at any time may require that the Vendor to prepare a set of
test specimens as defined in Appendix A, and arrange for the performance of any or all
of the tests covered by Appendix A at a third-party laboratory. Provided the coating on
the specimens passes the tests, the Buyer shall pay for the tests; otherwise the Vendor
shall pay the costs.

11 Repairs

11.1 General

11.1.1 Each length of coated pipe leaving the Vendor's premises shall be free
of holidays and visual coating defects.

11.1.2 Defects shall be repaired in accordance with the criteria and methods
below.

11.2 Small Defects (Areas of damage up to 1450 mm²)

11.2.1 For small pinholes, metal slivers, or minor damage repair materials shall
be as specified under paragraph 4.2, and repairs shall be in accordance
with the coating Manufacturer's recommended procedure.

11.2.2 Repaired areas shall be tested in accordance with paragraph 9.5, and
shall be holiday free.

11.3 Large Defects (Areas of damage exceeding 1450 mm²)

When the Buyer's Representative approves large repairs, the following


procedure shall be followed using material outlined under paragraph 4.2. If the

Page 14 of 22
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-089
Issue Date: 25 October 2011 Shop-Applied External Fusion
Next Planned Update: 25 October 2016 Bonded Epoxy Coating for Steel Line Pipes

total damaged area exceeds 1860 cm², the joint shall be totally recoated.
Exception:

Hot melt sticks shall not be used for the repair of FBE used for services described
in paragraph 1.2.3.

11.3.1 Preparation of Surface

The pipe surface to be recoated shall be cleaned to remove all dirt and
damaged or disbonded coating using abrasive blasting or other approved
and suitable means. The edges of the original coatings shall be
“feathered out” approximately 50 mm around the specific area to be
coated, and all dust cleaned off before applying the patch coating.

11.3.2 Patch Coating

The preferred method for patching large defects shall be to heat the area
locally with induction heating or other heating means and blow on
(flock) the same type powder used on the production coating line.

11.3.3 Alternative Patch Coating

When equipment is not available for patching by the method covered in


11.3.2, the following procedures shall be used:
a) The material for patch coating in the shop shall be catalytically
two-part cured epoxy coating supplied or approved by the
Manufacturer of the powder coating or by the RSA.
b) The repair coating shall be applied by spatula, brush, roller or spray
depending on the size and nature of the damaged area being repaired.
c) The patch coating shall not be applied when the pipe surface
temperature is less than 3°C above the dew point.

11.3.4 Curing Patched Area

Freshly patched coated areas shall be allowed to cure according to the


coating Manufacturer's recommendations prior to handling, and the
repaired area shall be holiday tested in accordance with paragraph 9.5.

11.4 Defect Acceptance Criteria

11.4.1 Mechanical Damage

Any coated joint with mechanically damaged coating exceeding


1860 cm², shall be rejected, blasted and coated at the expense of the

Page 15 of 22
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-089
Issue Date: 25 October 2011 Shop-Applied External Fusion
Next Planned Update: 25 October 2016 Bonded Epoxy Coating for Steel Line Pipes

Vendor. Mechanical damage repairs shall be per paragraphs 11.2 and


11.3 of this Specification.

11.4.2 Holidays

11.4.2.1 The allowable number of holidays rate that can be repaired


before other special measures are required, is 1 per 1.0 m² of
coated pipe surface.

11.4.2.2 If the cause of holidays is determined to be improper coating


application or defective coating materials, the joint shall be
rejected and totally recoated at the Vendor's expense.

11.4.2.3 If the holiday repair exceeds 1 holiday per 1.0 m² of coated


pipe surface, and the cause is determined to be defects in the
pipe surface, such as slivers, cold-laps or pitting, the
following procedure shall apply:
a. Any coated joint having a holiday rate of 2 holidays per
1.0 m² or less shall be 100% repaired.
b. If the holiday rate exceeds 2 holidays per 1.0 m², the
Vendor, in consultation with the Buyer's Representative
(and the Buyer, if needed), shall either reject the affected
pipes as “not coatable” or shall increase the coating
thickness to the maximum specified in paragraph 7.3 in
order to reduce the holiday rate to 1 per 1.0 m² or less.
c. After increasing the coating thickness, if the holiday rate
is still excessive, the Vendor shall advise the Buyer and
the coating operation shall be stopped.
d. The Vendor shall advise the Buyer of remedial measures
that could be taken to achieve an acceptable coating for
the Buyer's approval.

12 Pipe Storage and Preparation for Shipment

12.1 Each coated length of pipe shall be externally Stenciled at a point approximately
60 cm (2 feet) from the end to reproduce the original marking and to identify the
type of coating applied, Purchase Order number, pipe size, pipe grade and date
coated. For pipe double-jointed at the Vendor's shop, the shop weld number
shall be included in the stencil.

12.2 All pipes shall be stored on padded elevated racks or polyethylene sheathed sand
berms until time for delivery. Non-compressible rubber pads 10 mm thick 3 per

Page 16 of 22
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-089
Issue Date: 25 October 2011 Shop-Applied External Fusion
Next Planned Update: 25 October 2016 Bonded Epoxy Coating for Steel Line Pipes

12.2 m length, 5 per 24.4 m length shall be used to separate the pipe for yard
transportation and storage.

12.3 Padding material and procedures shall be approved by the Buyer's


Representative.

12.4 All booms, hooks, forks, supports and skids used in handling or storing coated
pipe shall be designed and maintained in such a manner as to prevent any
damage to the pipe or to the coating, and shall be approved by Buyer's
Representative.

12.5 The Buyer's Representative will have authority to stop any storage procedure or
means of transport from the yard, if in his opinion there is a possibility of
damage to the coating because of improper procedures.

Revision Summary
25 October 2011 Revised the "Next Planned Update". Reaffirmed the contents of the document, and reissued
with editorial revisions including removing the committee members list.

Page 17 of 22
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-089
Issue Date: 25 October 2011 Shop-Applied External Fusion
Next Planned Update: 25 October 2016 Bonded Epoxy Coating for Steel Line Pipes

Appendix A – Qualification Procedure for Initial Product Approval

1. General Requirements

1.1 In order to qualify FBE powder coating material as acceptable under this
Specification, the Supplier of the coating material must submit the following
certification in writing to the Buyer's Representative, who for materials
prequalification purposes is hereafter referred to as the Responsible
Standardization Agency Representative (RSA).
a) Certification from an independent testing laboratory that they witnessed or
performed the preparation and testing of the samples, and that all
procedures were in accordance with this qualification procedure.
b) Certification by the Supplier that the proposed coating meets the following:
- Has passed all the tests and met all the requirements of this
qualification procedure.
- Is suitable for the intended service conditions as detailed in Saudi
Aramco Engineering Standard SAES-H-002, APCS-104, “Shop or
Field-applied Fusion-Bonded Epoxy (External).”
c) A record of all test results.

1.2 All initial qualification tests shall be carried out at no cost to Saudi Aramco.
The RSA shall decide if the data presented by the Supplier satisfy the
requirements of the tests outlined below.

2. Qualification Tests

2.1 Instrumental Analysis

Instrumental analysis of the coating powder material shall be conducted by the


infra red (IR) and differential thermal analysis (DTA) techniques, in a laboratory
acceptable to the RSA.

2.2 Preparation of Test Specimens

2.2.1 Test specimens shall be as outlined in the applicable test Specification


unless otherwise stated.

2.2.2 Surface preparation, application, dry film thickness and curing


parameters for the test specimens shall be identical to that used in this
coating Specification for the intended service.

Page 18 of 22
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-089
Issue Date: 25 October 2011 Shop-Applied External Fusion
Next Planned Update: 25 October 2016 Bonded Epoxy Coating for Steel Line Pipes

2.2.3 Prior to each test the specimens shall be conditioned for 24 hours at 25°C
and 50% relative humidity.

2.3 Glass Transition Temperature and Degree of Cure (CAN/CSA Z 245.20 - 02)

2.3.1 The glass transition temperature shall equal or exceed 93°C as minimum
requirement for all FBE powder coatings.

2.3.2 High Temperature FBE powder, the glass transition temperature shall
equal or exceed 115°C.

2.3.3 When determining the degree of cure, the difference in glass transition
temperatures (Tg2 – Tg1) shall be in accordance with the powder
manufacturer's specification.

2.4 Flexibility and Bending Test

2.4.1 Selection and Measurement

2.4.1.1 Three (3) test specimens of approximately 25 mm x 192 mm x


9.5 mm shall be cold cut from a coated pipe section in the
longitudinal direction, or test bars of this size coated in
accordance with 09-SAMSS-089 can also be used for this test.

2.4.1.2 The coating thickness shall be measured at 5 locations 25 mm


apart on each specimen, and the thickness recorded.

2.4.2 The specimens shall be holiday detected in accordance with paragraph 9.5
of this Specification, and all holidays shall be marked and recorded.

2.4.3 Bending

2.4.3.1 The specimens shall be placed in a freezer at 0°C for 30 minutes,


then removed and clamped in the bender with the coated side up.
The test specimens shall be bent flat wise at 60 degrees over a
25.4 mm thick shoe of the following dimensions.
 Shoe radius 95.2 mm
 Chord 152 mm
 Arc 178 mm

2.4.3.2 Bending shall be accomplished in less than 30 seconds. Allow


the coated specimens to return to ambient temperature and
inspect.

Page 19 of 22
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-089
Issue Date: 25 October 2011 Shop-Applied External Fusion
Next Planned Update: 25 October 2016 Bonded Epoxy Coating for Steel Line Pipes

2.4.4 Acceptance Criteria

2.4.4.1 The coated specimens shall show no cracks when examined at


10 X magnification, except where clamped or gripped.

2.4.4.2 Holiday test on the bent specimens will show no holidays in


addition to those already marked and recorded prior to bending.

2.4.4.3 Flexibility at 25°C is 5.5° / pipe diameter, at 0°C 3.75° / pipe


diameter.

2.4.5 The flexibility and bending qualification tests must be carried out at
thickness 575 -750 microns (23-30 mils) DFT.

2.5 Impact Resistance (ASTM G14)

2.5.1 Seven (7) specimens shall be tested for impact resistance at a


temperature of 10°C in accordance with ASTM G14.

2.5.2 Impact resistance of all seven specimens shall be 6.8 J (60 inch lbs) or
more. Freedom from penetration shall be verified using a low voltage
(67.5 volts DC) wet sponge holiday detector.

2.5.3 Minimum requirements for the impact resistance for coatings approved
for service in the higher temperature range shall be 11.3 J (100 inch lbs)

2.6 Adhesion Test

Three adhesion tests shall be conducted on a section from the production coated
pipe. The test procedure and evaluation shall be in accordance with paragraph
9.4.1

2.7 Cathodic Disbonding (ASTM G8)

Three specimens shall be tested by the procedure given in ASTM G8. The cured
powder coating when subjected to an impressed current at 1.5 volts shall not
disbond more than 12 mm radius from the edge of the intentional holiday in
30 days, at a test temperature of 25°C.

2.8 Chemical Resistance, Immersion Test

2.8.1 Three (3) specimens shall be half immersed for 30 days in each of the
following solutions at 80°C:
a) Distilled water
b) 5% Sodium Hydroxide

Page 20 of 22
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-089
Issue Date: 25 October 2011 Shop-Applied External Fusion
Next Planned Update: 25 October 2016 Bonded Epoxy Coating for Steel Line Pipes

c) 5% Sodium Chloride

2.8.2 Specimens shall also be tested in synthetic seawater at 93°C for 90 days.
Longer period test may be required if the specimens showed
irreproducible results.

2.8.3 None of the coated specimens shall show evidence of cracking, softening,
loss of adhesion, swelling, and discoloration. Blisters shall be not more
than (#6) or less in size as determined and defined by ASTM D714.

3. Tests for FBE Coatings to be used in Hot Subkha Service (up to 115°C)

3.1 Cathodic Disbonding ASTM G42 (Modified for higher temperature)

Three specimens shall be tested by the procedure given in ASTM G42.


The cured powder coating when subjected to an impressed current at 1.5 volts
shall not disbond more than 15 mm radius from the edge of the intentional
holiday in 30 days, at a test temperature of 82°C.

For High Temperature FBE powder coating, repeat the same test for the duration
of 60 days, at a temperature of 93°C. Coating shall not disbond more than
10 mm radius from the edge of the holiday.

3.2 The cathodic disbonding tests shall be carried out on panels with dry film
thickness not exceeding 625 microns (25 mils).
Commentary Note:

Should a coating pass the tests below this thickness, it would be considered
satisfactory at the specified thickness.

3.3 Cross-Section and Interface Porosity

To determine the degree or porosity and voids in the applied coating cross
section and interface. The coating manufacturer shall consult with the RSA to
determine which test and acceptance criteria shall be considered in accordance
with international standard that shall be used.

3.4 Electrochemical Impedance Spectroscopy (EIS)

3.4.1 Prepare three (3) steel panels in accordance with Section 4.1.

3.4.2 Conduct electrochemical impedance spectroscopy (EIS) measurements,


after exposing the coated panels to 3%NaCl solution for no less than
24 hours, to obtain initial electrochemical impedance values. The initial
values must be greater than 1x108 ohm.cm². Coatings with

Page 21 of 22
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-089
Issue Date: 25 October 2011 Shop-Applied External Fusion
Next Planned Update: 25 October 2016 Bonded Epoxy Coating for Steel Line Pipes

recommended film thickness exhibiting lower electrochemical


impedance values shall be rejected.

3.5 Fingerprinting for Coating Identification

As part of the qualification procedure of a coating system, the supplier shall


submit to the RSA, a fingerprint of the coating obtained in accordance with
ISO 20340 (Annex B). The fingerprint shall be used in subsequent routine batch
testing of coating supplied for use in the field, to confirm that the supplied
coating is similar to the coating tested in the qualification stage.

Page 22 of 22

You might also like