Project Name:: H Club

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 5

Team : B

Project name: Tech Club

Project Team:
ID Name
43604565 Mada Hamed Saeed Altowairiqi
43606348 Rahaf Mohammed Saeed Alqahtani
43653486 Maria Abdullah Mohammad Bakhsh
43702887 Nora Abdullah Mehmas Alshdady
43708081 Arwa Turki Awwad Altowairqi
43708357 Hala Abdualaziz Dakhel Altalhi
What are the specific activities that could make up your )1
project? Please list the activities with their information on
immediate predecessor and completion time, in both a table,
.and PERT chart

 See the below Table.

2) What is the total completion time of the project?


The project can be completed in 36 weeks if the individual
activities are completed on schedule.

3) What are the scheduled start and completion time for each
activity?
See the below Table.

4) Which activities are critical and must be completed exactly as


scheduled in order to keep the project on schedule?

All are critical except B, C.


5) How long can the non-critical activities to be delayed before
they cause a delay in the completion time for the project?
Table below shows the slack time associated with each
activity.
Activity Activity Immediate Completio
description Predecessor n time
)Weeks(
A Collection - 6
requirements
B get the approval A 1
C Interface A 2
D Database A 5
E Programming C,D 8
F Implementation E 2
G Testing F 3
H Development G 8
I Design register H 1
J Security I 1
K deploy J,B 2
Total:39
:PERT chart
Activity ES EF LS LF Slack Critical
?Activity
A 0 6 0 6 0 Yes

B 6 7 33 34 27
C 6 8 9 11 3
D 6 11 6 11 0 Yes

E 11 19 11 19 0 Yes
F 19 21 19 21 0 Yes
G 21 24 21 24 0 Yes
H 24 32 24 32 0 Yes

I 32 33 32 33 0 Yes
J 33 34 33 34 0 Yes

K 34 36 34 36 0 Yes