Professional Documents
Culture Documents
Construction Management Major Project Assignment
Construction Management Major Project Assignment
SEM 2 2020/21
Title: An Overview into the Project Management of the construction of National Bakery’s
retail outlet on Balmoral Avenue
Names:
Imani Sewell-1806320
Lecturer: M. McIntyre
Table of Contents
Introduction 4
Project Summary 5
Inception 6
Purpose of Project 6
Team 7
Timeline 7
Contract Awardment/Procurement 7
Project Cost 7
Procurement of Labour 8
Procurement of Materials 8
Procurement of Equipment 9
Pre-Construction Dependables 9
Project Charter 9
Project Scope 12
Staffing Plan 14
Worker’s Contract 14
Payment 14
Communication Management 16
1
Risk Management 16
Accidents 17
Financial Risks 17
Procurement Management 17
Stakeholder management 18
Time Management 18
Procurement Management 18
Executing 19
Manage Communications 25
Conduct Procurement 26
Controlling 28
2
Project Risk Management 44
Closing 47
What is Closing? 47
Commissioning 48
References 49
3
Introduction
This document is a representation of the project plan used to construct the National
Bakery Retail Outlet located on 9-11 Balmoral Avenue in Kingston 10. It is an analysis of
methods and practices used to manage construction versus the best practice approach. This
project shows a critique of the activities taken place on site. It generally speaks to the 5 process
groups of management which are initiating (Pre-Contract), planning (and design) , executing,
monitoring/controlling and closing. The ten knowledge areas of project management were also
used to guide the analysis. The ten knowledge areas of project management includes
Integration Scope, Time, Quality, Human Resource, Risk, Communication, Procurement and
Stakeholders. The project was introduced to the contractors at Deverm Engineering Company
4
Project Summary
Budget: $ 160,000,000
5
Project Pre Contract Phase
Gilliland (2019) essentially sums up the pre contract phase of construction as activities involved
prior to the commencement of construction. These include the preparation of tenders to bid for
the project, the development of designs and strategic project planning. It also involves the
procurement of various permits and grants and assets such as materials tools and labour that are
Inception
The stakeholders at the National’s Baking Company Ltd had a vision to grow and expand its
operations. This would be achieved by acquiring a plot of land located at 9-11 Balmoral Avenue,
Kingston 10, St. Andrew. The site of the project in question is located between the busy business
Purpose of Project
The purpose of the project was to erect a structure that would serve as an outlet and production
facility that would give license to the company to produce and sell their products.
Stakeholders
Stakeholders for this particular project are the clients, the contractor, the municipal, the
6
Team
The Deverm Engineering Company was awarded the contract in early 2017. The project team
Timeline
The initial timeline that was stipulated for the construction of the new National’s Bakery
Company was an eight month project, which commenced in April of 2017 was schedule to end
in November 2017. However, the project went 4 months over schedule and was completed in
March 2018 as a result of improper planning, frequent changes to working drawings, incorrect
work executed due to poor and insufficient supervision, poor time controlling and a scheduling,
Contract Awardment/Procurement
The contract was awarded to Deverm Engineering by means of selective tendering. The contract
was awarded through this avenue as the client had previously contracted said company with pior
projects.
Project Cost
The cost of the project was budgeted at 160 million. This budget was drafted to cover the
expenses of the entire project which are subjected, but not limited to, property purchase,
The site in question is located at 9-11 Balmoral Avenue, Kingston 10, St. Andrew. The site could
7
Feasibility Study- Site Services
For the site in question, there were existing services such as a clean, potable source of water
from pipes. However, electricity had to be sourced from the Jamaica Public Service (JPS).
Upon the first site visit, it was noted that there was an existing warehouse structure. Additionally,
Procurement of Labour
For this project, skilled and unskilled labour sourced in and around Kingston. The labourers
Procurement of Materials
Materials were sourced from local hardware stores in Kingston.. Such stores include tankweld
and national supply. Additionally, said materials were stored at onsite in a secured storage
container.
Procurement of Equipment
Machinery and tools that were used in the execution of the project were rented. *make a list of
the tools/machinery* Entities such as gastron were engaged for the rental of a backhoe, while
total tools for work tools. These tools were kept in a safe and secure spot onsite.
Pre-Construction Dependables
These are works that are needed to be executed prior to construction. These works included but
8
Project Charter
General Information
Project Scope The National’s Bakery Company has its main office
Manager/Contractor
Company
9
complete production outlet with parking and
boundary walls.
The planning and design phase of construction is a crucial process to ensure efficiency
and cost effectiveness. Design is a process of creating the description of a new facility, usually
activities and resources required to make the design a physical reality according to Carnegie
Mellon University (n.d). Early planning can significantly impact upon project outcome but clear
targets must be agreed and established early to enable the correct decisions to be taken at the
right time (Sherif & Price, 1999). The planning and design phase also gives an opportunity to
10
To achieve this goal, managers of the projects have to write management plans, building
plans and the other necessary construction documents such as permits, boundary surveys,
contracts/agreements, bill of quantities, financial statements, project schedule ect. When one is
considering planning and design, numerous operational tasks must be performed with a variety
Project Scope
The project analyzed is a retail outlet for National Bakery Company Ltd parented by the
Continental Baking Company on 9 &11 Balmoral Avenue in Kingston 10, St. Andrew. The
company involved in the construction of the storefront was Deverm Engineering, a small
engineering company located in Westmead, Bridgeport, St. Catherine. The project was acquired
by selective tendering where the client brought the project and concept to the contractors at
Deverm. The architectural company involved was the Lighthouse Project Ltd and the structural
engineering consultants were from SkyCon Engineering. The facility will also host an outlet for
Copperwood Pork.
The idea of the operations of the establishment is that baked products will be brought to the
store from the main bakery to be distributed, a similar procedure is applicable for the sales of
meat. The site had an existing building constructed of and a portion of it was incorporated in the
final building construction and this was the direct request of the client. This part of the project
has a roof structure made from I Beams. This portion of the building was assessed in term of the
structural resilience of the building and was approved by the engineers at SkyCon Engineering.
This facility would have to be designed with temperature control using suitable HVAC systems.
11
The facility has biodigesters as well. The project began in April 2017 and was scheduled to end
in Nov 2017. The budget for the project was 160 Million.
● 2 Cold Rooms
● Delivery Ramp
● Several Restrooms
● Storage Area
● Retail Area
● Office Spaces
● Lounges
● Locker Rooms
● Services/Maintenance Rooms
● Parking lot
The main goal of effective human resource management is to ensure project success by
acquiring the best persons with optimal skill. The project that was analyzed had no solid human
resource plan, however considerations were made when hiring was done. The
recommendations that we have for the project as it relates to human resource management
includes:
1. Staffing Plans
2. Payment
12
3. Welfare Planning ( Accommodation planning, safety gears. insurance ect)
Staffing Plan
The contractor for the project is the individual who acquired the workers from previous projects.
The contractor hired the best tradesmen to tasks done as well as their associated labourers.
Additional workers were brought on site as the need arose.The skills that he sought included
steel fabricators, welders , masons and carpenters. The clients also had their own mechanical,
plumbing, air conditioning, and electrical specialists to work on the project;. This eliminated the
need for sub-contracting work as well as the client would be more comfortable using individuals
they trust. As was previously mentioned the project was brought to the contractor. So it can be
observed that the client is quite specific in how they would like the work to be completed.
Worker’s Contract
Establishing roles and responsibilities of each individual throughout the project, this is basically
a synopsis of each job, these would be distributed among the various members of the project
irrespective of the level. This contract will also state the pay rates as well as the duration of the
project. In the case of the extension of the project then contracts will be renewed to reflect these
critical changes.
Payment
A combination of payment options were used on-site. Cheques and Cash was used to pay
workers on-site. We would not recommend that cash is used for paying workers. The site is
13
located in a very volatile area where robbery could take place. If the site is being watched by
criminals then they may be able to ascertain when payments are going to be made on payday.
Workers could be then targeted and robbed. The option of cheques is more feasible as it relates
to safety. The option of bank transfers could be feasible if workers have bank accounts. As a
employed. There were instances where tradesmen were responsible for paying the additional
workers.
Welfare
As it relates to welfare of the workers there were some considerations taken. The
accommodation aspect of welfare attracted an additional development of a nearby lot which the
company purchased to host the workers. The food options that were available to the workers
was at a proximity that is unfavourable to effective time management . What the company
decided to do was allow workers to take work breaks in shifts to prevent losses. What we
suggest is that food is cooked on-site perhaps at a cost or the make arrangement with an
affordable independent cook to bring the food onsite ? The company initially did not offer
safety gears to workers nor did the supervisors ensure that persons were wearing personal
protective equipment.
The workers did not have insurance to offset some of the costs in the event of accidents,
injury or death. There was an accident on site where a 15 ft deep excavation for a biodigester
which did not have a shoring system and it collapsed with the reinforcement which could have
been fatal if a steel fabricator was still working inside the trench. A worker fell off two flights of
14
scaffoldings, he sustained injuries and the succumbed to his injuries afterwards. After this tragic
incident, the construction company sought to get insurance packages for their workers as well as
tightened the safety measures. Safety became of utmost importance, workers were required to
wear safety gears. We would have suggested a proactive approach to this as opposed to this
reactive approach.
Communication Management
The communication style can make or break any organization. Bi weekly meetings were held to
discuss changes and distribute information among the project team. Planning also took place at
these meetings and as it relates to each phase of the project. Oftentimes the schedule had to be
amended to reflect changes especially seeing that the project went overtime severely.
Variations and other queries were addressed between clients, contractors and other members of
the team. The administrator on-site was responsible for communicating meeting dates among the
staff site as well as issuing memos and distributing other communication documents via email
Risk Management
Risk management in construction is designed to plan, monitor and control those measures needed
to prevent exposure to risk. To do this it is necessary to identify the hazard, assess the extent of
the risk, provide measures to control the risk and manage any residual risks. (Stakeholder Map,
n.d )
15
Environmental and Occupational Safety
As it relates to the actual location of the site, the site was in an area that is considered to be
somewhat volatile, where crime occurs frequently. The contractor, client and likewise were
privy to this and the necessary precautions were taken and planning was done to mitigate
against loses due to theft and vandalism. As it relates to occupational safety, the site was
lacking in terms of making sure that workers were outfitted with personal protective gear. The
occupational safety was breached in terms of not following proper construction techniques in
Accidents
Accidents were generally avoided on site due to the high diligence of management staff and
workers. Open excavations were taped off, striking of formwork was done in teams to reduce
the risk of formwork falling on persons, rebar ends were capped and safety gears were issued.
However, despite their efforts few accidents did occur on site as a worker fell from a two (2)
Financial Risks
These risks include damage or theft of building material, down time on tools and equipment,
variations in works, corrective works, lost days due to bad weather and late or non payment
from client.
Procurement Management
This speaks to the risks in obtaining goods and services needed for construction. Materials
could be delivered late or be incorrect which would impact project time, needed items might
16
not be instock. Quality skilled workers might not be available when needed or might only be
Stakeholder management
and among stakeholders based on the medium chosen, delays in feedback and responses,
Time Management
In terms of risk management as it relates to time, the contractor did not manage the
project in terms of time effectively and subsequently the project went overtime by months. The
contractor faced losses due to this as workers and equipment time were accounted for. The
Procurement Management
successfully operate a business or complete a project. In construction, this refers to the goods and
services needed to successfully complete a build from start to finish (TowerEight, 2019). The
contractor who played the role of project manager had authority to allocate the funds in the
budget with the projects’ best interest in mind. These following strategies were used to ensure
cost effectiveness.
17
1. Most material was purchased from the same vendor in bulk to get a cheaper rate and an
easier and less frequent delivery. This was ideal for location as delivery trucks had a
difficult time maneuvering the area. This ensured that there was a lower downtime as
well. Tools were also rented from one place to reduce delivery costs.
2. The client was also responsible for the procurement of construction materials. This has its
advantages and disadvantages. The contractor can spend histamine doing something else
other than seeking resources, however if the material is of poor quality the quality of the
overall work will be of substandard. The main advantage of the client purchasing
construction material is that the client may feel more in control and satisfied.
3. The site administrator was responsible for requesting quotations for materials from
various companies and keeping record of deliveries and equipment and machinery
Executing
Executing in project management means to integrate people and other resources to carry
out the project plans for the project. This phase, also called the construction phase, begins the
activities to complete the work that was defined in the initiation and planning phases. During this
phase of the project, the project manager procures the team members to complete the actual
project work. Execution is not just about the work getting done, however, it is about how the
project is managed. The execution phase of the project usually takes the most time and resources
to complete. This is the work that is commonly thought of as project management. The project
manager works to get the team focused on the work and activities to complete the deliverables
defined in the project planning phase. The construction phase also has the most opportunities for
cost overruns due to changes and delays, disputes with contractors, and the resulting contract
changes and claims. Construction operations are the actual work that it takes to build the project.
18
This includes laying out the foundation, placing the concrete, laying the block, setting the steel,
framing the walls, installing the roof, installing the electrical, running the plumbing, and doing
every other construction activity needed. As the construction moves forward, the ultimate goal is
The diagram below shows the tasks that were undertaken during the execution phase of
the project.
Project’s W.B.S
19
Direct and Manage work
guiding, counselling, motivating and leading. Instructions were issued vocally and written down
for clarity and reference. If a particular worker was unsure of what to do the Foreman or
supervisor would guide the particular work in carrying out the task at hand. Workers were also
counselled and motivated to perform by sharing past experiences, pay incentive and refreshment.
Quality assurance (QA) takes a long-range view toward developing systems that produce
these natures were in place on this project such as the use of rebar bending template to ensure
Picture showing template for rebar bending and rebar fabrication area
20
Equipment such as a laser level and optical levels were used to transfer and mark levels for
various uses such as finish floors in all rooms, lintel heights, sidewalk levels, levels for floor and
21
Picture showing Optical Level
Concrete mixes were done using a mechanical mixer to achieve a consistent concrete mix and to
match standards established in structural drawings. It was used to mix concrete for structural
components, concrete full block pockets, mortar to lay blocks and mortar for rendering.
22
Standardized tools such as aluminum rods were used in rendering operation to ensure the proper
and contractor, was acquired by the client of the project, Continental Baking Company.
Over the course of the project, various development of the project team took place. The
contractor engaged his own Engineering consultant, draftsman and experienced supervisor to
increase production speed, achieving and maintaining the required quality. The contractor also
23
secured the services of an administrator to handle purchases orders and handle the payment of
workers. The project Engineer also increased personnel to provide greater support to the project.
Drone technology was also fielded by the Engineer to achieve unique angles to aid with site
designs.
The project team was managed by the Project manager through Bi-weekly site meetings,
Manage Communications
Bi-weekly site meetings served as a major communication medium during the execution
stage. Construction drawings were the main construction document for the project and were
updated at regular intervals with new hard copies made available to the contractor. These
updated drawings were used to communicate changes and variations on site to trades persons by
the contractor. Copies of these drawings were also given to various skilled works to use on site
to further disseminate information. Internet connection was installed on site so the emails could
be sent and received instantaneously. These emails were between contractor and client, Engineer,
Architect, Project manager, suppliers, municipal corporation and Ministry officials. Some
signage at the main entrance of the site was to communicate safety requirements and to urge
24
Picture showing entrance to site
Conduct Procurement
Procurement was conducted of various equipment, material and services. Some materials
such as cement, aggregates, steel and lumber were procured and delivered to the site. As such
was a constant supply of these materials on site and were ordered when stocks were running low.
Tools were rented for the duration that they were needed and returned after. Concrete for large
volumes was procured from ready-mix suppliers such as Pre-mix. It was ordered on a “as
needed” basis. An independent Engineer was engaged to perform services such as setting levels
25
for roof and floor screed, leveling surveying and grid surveying to establish levels. His services
26
Manage Stakeholder Engagement
Stakeholder management was very important throughout the execution phase. The client,
Engineer, Architect and Project manager were all engaged through Bi-weekly site meetings, site
visits, emails and phone calls. Workers on site were engaged through the foreman and
supervisor, in terms of issuing instructions and the handling of on site issues. Suppliers were
engaged through email and phone calls to request quotes, send purchase orders and set delivery
dates. Subcontractors were engaged by the client and worked in coordination with the main
contractor.
Controlling
Controlling involves the comparison of performance to plan. This means that in every
compare this with plans. The show if the process is being made or whether the project is failing.
The fluctuation between performance and plan changes in some cases, e.g., work is
delayed due to weather conditions. In these cases, controlling and monitoring is crucial in these
cases as a manager who is in control will increase the labour force to make up for lost time; this
then increases the chances of a reasonable comparison of performance with plan. There are some
27
· Time
· Safety
· Cost
· Quality of work
They are six (6) different functions through which management operates. These are:
· Planning
· Organizing
· Staffing
· Leading / Directing
· Controlling / Monitoring
· Motivation
All six of the management areas are dependent one each to successfully operate. In case of
controlling / monitoring; all five management process areas are dependent on how they are
controlled. In other worlds properly controlling the management areas can develop into better
Planning, Organizing, Staffing, Leading / Directing, and motivation. Let us take planning into
consideration, when planning is controlled; the results varys from planning for the future to
28
planning within a scope e.g., deciding what needs to happen in 2 weeks; this was utilized with
Planning - There were meetings kept every two weeks on site with all the members of the project
team; Architect, Client’s representative, Contractor, Engineer. During these meetings the work
produced over the past two weeks would be compared with the plans / requirements that were
stated at the last meeting; as a means of controlling the planning needed for the upcoming weeks.
A new schedule was created at every meeting for what needs to be done within the upcoming
two weeks before the next meeting is held again. It was observed that planning was well
controlled to ensure that the work produced within the two weeks was done within time and if
not, could be addressed quickly; within two weeks time at the next meeting, as a means of
Organizing - The time available and amount of work that needs to be completed, plays an
important role in the organizing phase, as this will help the contractor to decide the role of
organizing which will be the most beneficial effort of the project. After the meetings the
contractor would assemble his team of trades-men and organize the work that needed to be done
based on the schedule produced at the bi-weekly meetings. E.g The west side of the building
needs to be constructed, the contractor starts by procuring all the necessary materials needed to
complete this phase of the project. Materials such as: concrete blocks, fine aggregates, cement,
steel, timble etc. As stated above the time available impacts the methods of how work is
organized between the trads-men, e.g for the construction of the west-side of the building to be
completed there will be a need for formworks. To decide whether to fabricate the formwork
29
needed or to procure ready made formwork; the contractor would compare the available time
with the option that would take the longest amount of time, in this case it would be the
fabrication of formwork. Based on the comparison in time taken and time available a decision
will be made whether fabrication will be done on-site, whether he procure ready had formwork
Staffing - Staffing was decided based on the amount of work-flow that is needed to be
completed. This determines the demand and the amount of labour-force required to be on site. If
there is an abundance amount of work that is needed to be completed. The specified amount of
workers will be hired, while on the other hand; if there is a small amount of work needed to be
Leading / Directing - Leading and Directing was done mostly in-office, in meetings with the
contractor and his head trades-men. After the by-week meetings the contractor would hold in-
office meetings with himself and his head trades-men to distribute and inform them as to what he
needs to be done within the two weeks before the next meeting is held with the team of the
project.
Controlling and Monitoring - In terms of controlling and monitoring. This seemed mostly on-site
leading and directing, the contractor would visit the site occasionally to inspect the work done as
means of controlling; comparing the plans / requirements with the produced work, ensuring that
all labourers were doing the work that needed to be done. In instances where the produced work
wasn’t meeting the plans / requirements, the contractor would communicate with his head trades-
men informing them that the produced work wasn’t meeting the plans / requirements; these head
treads-men would then speak to the labourers. Checks that were done by the contractor again
30
ensuring that the work produced was within the plans and requirements. Checks such as:
formworks, steel reinforcements were fabricated, were done to ensure standards were meat.
implement any. Motivation came in the form of an incentive on pay cheques on holidays, this
management, as it provides the core fundamentals necessary for the completion of any project.
The PMBOK is a collection of processes and knowledge areas that are accepted world-wide as
The Monitoring / Controlling as well as the Closing are two for the 5 basic Process
Groups that the P.M.B.O.K provides along with ten (10) Knowledge Areas. The Monitoring /
Controlling process plays a crucial role in most of the Knowledge Areas, as it is required to be
implemented in nine (9) of the (10) Knowledge Areas to successfully complete any project.
Now, let’s expound more and see how these two important Process Groups impacted the
process and completion of The National Bakery Company, located at 9 and 11 Balmoral AVE.
Kingston 10. To Understand the impact that the Monitoring / Controlling and Closing Possess
Groups had on the duration of this project; we first must understand how these Process Groups
31
Project Integration Management
This knowledge area is concerned with identifying and defining the work of the project
and then combining and integrating with the appropriate processes. The knowledge area is
impacted by all Five process groups. The Controlling / Monitoring aspects of this Knowledge
Area suggested that the monitoring / controlling of the project work and performing integrated
As it related to the Monitoring and Controlling of the Nation Bakery Project, In the early
states of construction there was a lot of monitoring done by the Contractor and the Fore-man on
site. The client's representative visited the site to make checks to the site occasionally. In any
effort to maintain the necessary standards; whenever any major structural-works was done the
Engineer was present on site to monitor and control the work being done also in an effort to
mitigate the amount of potential risk that may occur in the furter, due to improper structural
work, e,g Whenever that foundations is being casted; the Engineer will visit the site to make
checks such as: the reinforcements, spacings between the reinforcements and the wall of the
foundation; all this information geather was then compared with the requirements and standard.
The Engineer controlled the work done by comparing the plan / requirements necessary, to the
32
Picture of spacing of in the Roof
There were needs for changes in planning and controlling, these changes were necessary
due to improper planning. In one incessant during the excavation of the Biodigester at fifteen feet
(15ft) in loose soil. Based on observation, sufficient planning wasn’t executed. It was evident
that no excavation support calculation was done are that no accommodations were made for the
excavation of the biodigester this was proven based on: the location of this bio-digester was of
inconvenience as trafficking of people and resources were put on hold during the excavation; this
caused an secondary entrance to be constructed, the method of excavation and the equipment that
was provided; the backhoe wasn’t able to reach the required depth, a ramp had to be built in the
biodigester to give the backhoe access to reach the required depth; unfavored weather presented
itself and due to the absence of trench support for the wall of the resulting in the erosion of the
33
soil that was present in the walls of the biodigester. In an effort to control this the contractor
hired a new supervisor to check the work being produced as well as to introduce experience to
34
Picture of Bio-digester reinforcement
35
Picture of Water Sewer Plan Show the Bio - Digester location Highlight in Red and and entrance
The project scope is concerned with the amount of work needed to complete the project.
Clarifying boundaries helps to identify what is included in the scope of the project and what is
not. The project scope management within PMBOK revolves around the requirements of the
details measured from the end results, this creates a project scope. Monitoring / Controlling the
scope of the project is significant as it helps to manage and maintain what is included in the
project; in other words what is needed to be done. This helps to prevent overworking or
underworking. To successfully Monitor / control the scope of the project PMBOK suggests that
the proposed scope must be validated and controlled to include what is necessary to successfully
Relating this to the Nation Bakery Project, there wasn’t any large change in the scope of
the project, only some slight variation: during the grading of the site, a new plot of land was
purchased to house the accommodation for the labourers and a soak-aways was moved from its
original location. The project ultimately reached its scope goals but wasn’t very controlled as it
relates to time. The estimated time for the project was six (6) months but finished off schedule by
five (5) months, the project took eleven (11) months to complete. A W.B.S of the project wasn’t
constructed or used. The W.B.S was an informal one that was given to the head-tradesmen
36
Picture of Soakaways
37
38
Project Time Management
This Knowledge Area mostly involves the estimation of activity resources and activity
duration to successfully create a working schedule. The Knowledge area is also including the
controlling the timeframe for the project is crucial to any project as it is the key factor in the
determines what all the work put in planning will be useful or not.
Activities weren’t defined in the early stages of the project. However, as time went on the
project stages weren't being completed in time, the activities that were not being completed
within the specified scheduled time were then defined and addressed. As it relates to the
estimation of resources needed as well as the duration of activities, this was done at the bi-week
39
meetings with the members of the project team. This did benefit the project in a small way; in
cases where it was observed that the contractor needed curtain tasks to be done within a certain
amount of time.
The estimating of the resources required and the project budget; these are all the key-
goals of this Knowledge Area. When referring to resources, it is not just about the people
invested in the project, but the assets involved such as: Materials, equipment, facilities, and
contracts, these play important roles providing the necessary resources and services needed to
properly complete the project. The monitoring and controlling the of; cost, resources and
services is crucial as it determines the budget and if the estimated cost was accurate.
As it relates to the National Bakery project the Monitoring of cost, resources and
services; the project went over budget due to improper planning and execution of the project
stages, this caused most of the work to be redo which increased that amount of time spent to
complete the project. As it relates to the estimation of cost of materials, equipment, facilities and
contracts needed; how this estimation was done bi-weekly meetings by the Project-Manager.
Afterwards, this need will then be provided to the contractor who will then procure the services.
In terms of the estimation of the necessary facilities needed; restrooms, site office and an
The controlling of the quality of the project management and creating the project’s main
goals to a standard where the quality of the work produced is acceptable are the two main areas
40
that this Knowledge area focuses on. PMBOK suggests that in order to properly Monitor and
Control the quality of the project’s work produced, it is necessary to conduct a Quality
Assurance check; this is a comparison of the required quality to the “control” measured quality
to ensure that the appropriate quality standards and operational definitions are used. The
PMBOK advises that a Quality Control check be implemented to control the results of the
project's outcome.
During the process of executing the (National Bakery Project) there were a lot of checks
done. The checks were carried out by the Contractor on site as a means to control the quality of
work produced. Checks were also done before major works before they started; as stated above
whenever any large structural works (casting of the Roofs and Floors) are to be done the
Engineer would visit the site and conduct checks for such as: the spacing of rebars etc.
After all these checks were done they were all compared with the plans / requirements
that were established at the commencement of these activities, if in cases where the checks didn’t
meet the standard the work would have to be redo and this would impact both the schedule as
well as the budget estimated for the project. In one instance, during the project the client visited
the site and noticed that the walls openings for the doors weren’t leveled; it was checked and it
wasn’t leveled; the client’s exact words were”What if I didn’t see that; what would be the
outcome of this?”
41
42
Project Communication Management
identify stakeholders, plan meetings, shear information, produce reports, etc. It is to be noted that
communication is not only interacting with humans but involves meeting management and
action, risk actions and assessment, project plans, reviews, and walk-throughs. Based on
P.M.B.O.K communications plans are not “dead papers' ', but live documents that should be
updated.
There was a lot of communication invested during The National Bakery Project, as there
were bi-weekly meetings to address the activities arising and those that are just completing.
There was a lot of communication done, even out-side of meetings; phone-calls were made and
emails were sent within the members of the project team. In other words; calls and emails were
sent between: the client and their representative, contractor, architects, engineers etc. All these
communications were planned, emails were sent frequently between the project’s team members,
phones weren’t necessarily planned; whenever something arose calls were made to inform the
There were misunderstandings; the reasons why misunderstanding occurred was due to
the fact that most of the communication that was done wasn’t documented, the reason for this
was that communication was improperly done over the phone. Hence, there was nothing to back
refer to check or access the conditions of some situations; in cases where communications were
documented there weren’t checked, verified or validated. This ultimately caused some issues;
during the closing phase of the project a wall was incorrectly placed, this was noticed by the
Clerks of Works, who then decided that the wall had to be demolished; due to the fact that the
43
construction of the wall wasn’t communicated with the Clerks of Works. The Clerks of Works
continued to suggest that based on the time they lasted meat this kind of work was happening for
a while now, and if the project is late then the contractor will be penalized $ 40,000 everyday the
project is late.
Based on the PMBOK risk can be both beneficial as well as detrimental. You may be
asking yourself; how can a risk be beneficial? In terms of opportunities; this should be seen as a
risk and therefore should be visualized with uncertainty. However, risks are associated with
negative impacts, resulting in the taking of any actions that eliminate their appearance. As it
relates to Monitoring and controlling the risks associated with any project a Risk identification
should be implemented. This is best done during the planning phase of any project; this provides
Relating this to the National Bakery Project, there were risks that were for-see and
communicated with the contractor, be advice wasn’t taken into consideration and the
consequences were detrimental as can be seen in the incident with death on site as well as the
biodigester. The use of protective gears for workers weren’t enforced; this resulted in the death
of a worker on the construction site, in the construction of the biodigester, it was communicated
with the contractor that trench supports were needed due to the conditions of the soil again there
were consequences with steel reinforcements were destroyed and the excavation had to redo.
When efforts were made to redo the excavation, replace the steel reinforcements and fabricate
formwork this ultimately led to the project's delay falling behind schedule and increasing the
44
There weren't any financial opportunities. However, opportunities presented itself in
terms of growth for the unskilled labourer, or in the case of supervisor Landel Smith, where on
site he was exposed to wide variety of construction works, such as: Civil Work - drainage,
Works - Rebrications of both steel works and Metal Fabrications as a section of the building was
There were any risks associated with the project, the project was located in a very close
to a very volatile community there was always a risk that violence occuring on site, while on the
other hand most of the skilled labourers lived out-side of Kingston and St. Andrew area, this had
its own challenges; it was observed that whenever the labourer got paid on Fridays they wouldn’t
return until Monday in the afternoon. This results in no or little work being done on the
Whenever a team is working on the behalf of someone; this someone is known as the
consumer while the supplier is reasonable for the creation of the project’s products. This is
known as a customer / supplier environment. The purchase or acquiring of produces and services
provided by outside of the team managing and controlling the projects has to do with this phase.
All these factors are relating to the Project procurement knowledge area. The monitoring and
controlling of procurement is important as it provides the team with resources that are not in-
The National Bakery project was done in a customer / supplier environment where the
project team mostly the contractor would procure goods and services from a supplier. The
45
supplier provided all the materials needed, Labour was procured too in a sense, where the labour
force was provided by the neighboring community, equipment was procured. In an effort to
control the procurement process all materials were procured from the same supplier as well as
The knowledge area has to do with the stakeholders that are invented in the project.
These stakeholders play one of the most important roles in the project’s success completion, As
the stakeholders are the customers that will use the product being provided. Monitoring and
Controlling the relationships between stakeholders is easily one of the greatest aspects that
determines the success of a project. Adjusting strategies and plan to fit the needs of stakeholders
During the process of the National Bakery project, there were some adjustments that
needed to be made, to ensure the safety of the stakeholder working on site as well as the public.
As it relates to the safety of the labours protective gears are provided. However, the wearing of
safety gears were enforced after a death; hoarding was constructed to protect the public from
flying and harmful projectiles. A boundary wall had to be adjusted as it wasn’t to the standard of
the Parish Council; the heights needed to be adjusted as well as the angle at which that wall was
placed, due to this the sidewalk had to be redo to be aligned with the new boundary wall. The
Client requested that floor drains are to be constructed in the Cold-room / Meat area.
46
Closing
What is Closing?
The closing process also play an important role as of the ten knowledge areas it is only
suggested that is some be implemented on only two of the ten knowledge areas, which are:
Closing of both the Integration Management and the Project Procurement Management
knowledge areas is important as it acts as transitions to the following nine Knowledge areas. The
closing of both the knowledge areas shows that all the following Process Group has been
executed; leading the way to implementing the project beyond its planning and procurement
phases.
The lifecycle of any project is built around four (4) phases. Closing and Controlling and
Monitoring impacts all these phases in many ways. However, Closing has the greatest impact on
the one of the phases which is the “In-Use” phase; this is one of the four (4) phases; it basically
Let’s dive in more into the In-Use phase to analyze the impact that monitoring /
controlling and closing has on its process and how this relates to the project in interest (Nation
Bakery).
47
Commissioning
The commissioning of any project occurs whenever the project has successfully “closing”
and is moving into the main purpose of use. This includes the “closing-out” and starting-up of
activities, conducting quality checks (Controlling / Monitoring), officially handing over the
The Maintenance and Repairs; these two important factors occur at the completion of the
· Establishing of a maintenance routine – This helps to control the scope of the maintenance
· Provision for major repairs – Making provisions for major repairs is always important; it is
always good to make sure that the planning is controlled. Promoting to planning within a scope.
48
References
Process.https://www.cmu.edu/cee/projects/PMbook/03_The_Design_And_Constructio
n_Process.html
Brian Cooke & Peter Williams, 2004, Construction Planning, Programming and
https://gillilandcm.com/2019/04/08/what-is-the-pre-construction-phase/
Houston S.M., Bove L.A. (2007) Execution Phase. In: Project Management for Healthcare
Jackson, J. B. (n.d.). Construction Management JumpStart, Second Edition. Wiley Publishing, Inc.
from https://milmc.gnomio.com/course/view.php?id=6
49
Sears, K. S., Sears, A. G., Clough, H. R. (2008). Construction Project Management: A Practical
Guide to Field Construction Management, Fifth Edition. John Wiley & Sons, Inc.
https://www.researchgate.net/publication/281204615_A_FRAMEWORK_FOR_PRE-
PROJECT_PLANNING
https://www.stakeholdermap.com/risk/risk-management-construction.html
https://www.towereight.com/what-is-procurement-strategy-
construction/#:~:text=Procurement%20is%20the%20acquisition%20of,build%20from
%20start%20to%20finish.
50