ACCF-SILCHAR

PROJECT

SILCHAR SITE DEWATERING SCHEME


PARTICULARS

Hospital

NGL to FFL difference (m) 2.5

Bottom of raft is at -6.4

Mmaximum water table above raft Bot. 3.9

Sl no. Stage of construction Load due to


A Hospital Building
1 Raft & pedestal construction PCC-75 thk
2 Isolator instalation/GF construction RAFT+Ped
3 1F construction Sub str+GF
4 2F construction Sub str+GF+1F
5 3F construction Sub str+GF+1F+2F
6 4F construction Sub str+GF+1F+2F+3F
7 5F construction Sub str+GF+1F+2F+3F+4F
8 6F construction Sub str+GF+1F+2F+3F+4F+5F
9 TF construction Sub str+GF+1F+2F+3F+4F+5F+6F
B LINAC Building
1 Raft & pedestal construction PCC-75 thk
2 Wall 1st lift construction w/o filling RAFT+Ped
3 Wall 2nd lift construction w/o filling RAFT+Ped+wall 50%
4 LINAC slab construction w/o filling RAFT+Ped+wall
5 1F construction W/O filling Sub str+wall+GF
LINAC Assymetric pressure
6 Bunker raft area wall 1st lift construction RAFT+Ped
7 Bunker raft area wall 2nd lift construction RAFT+Ped+wall 50%
8 Bunker raft area roof slab construction RAFT+Ped+wall
9 Non-bunker raft area with columns RAFT+Ped+col @ GF
10 Non-bunker raft area with columns+PB+1F RAFT+Ped+col @ 1F+slabs
11 Non-bunker raft area with filling upto GF Sub str+soil 50% +col @ GF
12 Non-bunker raft area with filling upto GF Sub str+soil +col @ GF
C Ramp-STP building
1 STP raft construction PCC-75 thk
2 STP wall 1st lift construction RAFT
3 STP wall 2nd lift construction RAFT+wall 50%

# Sensitivity: LNT Construction Internal Use


4 STP cover slab/GF construction RAFT+WALLS
5 1F Ramp construction Sub str+GF
6 2F Ramp construction Sub str+GF+1F
7 3F Ramp construction Sub str+(GF+1F+2F)
8 4F Ramp construction Sub str+(GF+1F+2F+3F)
7 TF Ramp construction Sub str+(GF+1F+2F+3F+4F)

Recommendations for dewatering


For Hospital building Dewatering shall be done untill casting of 2F beams &
For LINAC building Dewatering shall be done till casting of Walls till half th
For non bunker area, dewatering shall be done till 1.5-
STP-Ramp building Dewatering shall be done till casting of RAMP structure

# Sensitivity: LNT Construction Internal Use


JOB No.
O19035

CALCULATED

DPY
LINAC RAMP-STP

2.5 2.5

-6.4 -6.4

3.9 3.9

Equivalent Total dead load Allowable Water


thickness of per unit raft area DL reduction Factor of safety height above BOR
PCC/RCC (m) (kN/m2) factor against uplift (m)

0.08 1.82 0.95 1.1 0.161


0.86 23.41 0.95 1.1 2.061
0.49 35.61 0.95 1.1 3.135
0.28 42.55 0.95 1.1 3.746
0.25 48.75 0.95 1.1 4.292
0.25 54.96 0.95 1.1 4.838
0.25 61.15 0.95 1.1 5.383
0.25 67.50 0.95 1.1 5.942
0.24 73.46 0.95 1.1 6.467

0.08 1.83 0.95 1.1 0.161


0.92 24.78 0.95 1.1 2.182
0.59 39.41 0.95 1.1 3.470
0.59 54.04 0.95 1.1 4.757
0.14 57.64 0.95 1.1 5.074

1.05 27.96 0.95 1.1 2.461


1.08 54.96 0.95 1.1 4.839
1.08 81.96 0.95 1.1 7.216
0.88 23.86 0.95 1.1 2.101
0.48 35.98 0.95 1.1 3.168
1.43 49.60 0.95 1.1 4.366
2.86 75.33 0.95 1.1 6.632

0.08 1.92 0.95 1.1 0.169


0.91 24.59 0.95 1.1 2.165
0.23 30.38 0.95 1.1 2.674

# Sensitivity: LNT Construction Internal Use


0.46 36.16 0.95 1.1 3.184
0.09 38.46 0.95 1.1 3.386
0.24 44.47 0.95 1.1 3.915
0.23 50.10 0.95 1.1 4.410
0.23 55.73 0.95 1.1 4.906
0.23 61.36 0.95 1.1 5.402

ne untill casting of 2F beams & slabs


ne till casting of Walls till half the height.
ewatering shall be done till 1.5-1.6m filling of soil is completed on the raft after construction of columns till GF.
ne till casting of RAMP structure at 3F. Non-STP areas to be filled with soil after deshuttering of STP walls to avoid ill effects.

# Sensitivity: LNT Construction Internal Use


SHEET DATE
1 10-Apr-21

CHECKED

RAA/SJT

142.4286

Remarks

DEWATERING REQ 0.016363


DEWATERING REQ 0.210073
DEWATERING REQ 0.319541
DEWATERING REQ 0.381881
OK 0.437493
OK 0.4932
OK
OK
OK

DEWATERING REQ
DEWATERING REQ
DEWATERING REQ
OK
OK

DEWATERING REQ 473.87


OK
OK
DEWATERING REQ 426.98
DEWATERING REQ
OK
OK

DEWATERING REQ
DEWATERING REQ
DEWATERING REQ

# Sensitivity: LNT Construction Internal Use


DEWATERING REQ
DEWATERING REQ
OK
OK
OK
OK

walls to avoid ill effects.

# Sensitivity: LNT Construction Internal Use


Location Lakhimpur
Hospital
NGL to FFL difference (m) 3.90
Bottom of raft is at -5.83
Mmaximum water table above raft Bot. 1.93

Construction stages Allowable GWT above


raft bottom (m)
Hospital Building

Raft & pedestal construction 0.16


Isolator instalation 2.06

GF construction 2.06

1F construction 3.08

2F construction 3.66
LINAC Building

Raft & pedestal construction-Bunker 0.16


Wall 1st lift construction w/o filling 2.10
Wall 2nd lift construction w/o filling 3.34

Non-bunker raft area with columns till GF 1.67


STP-ramp building

STP raft construction 0.16


STP wall construction 1.87

STP cover slab/GF construction 3.03

1F Ramp construction 3.55

# Sensitivity: LNT Construction Internal Use


LINAC RAMP-STP
3.90 3.90
-5.83 -5.83
1.93 1.93

Recomendation Alternative

Dewatering till recommended


level and dry condition is Draingae trench and pit if
achieved GWT is not very high
Dewatering is must -
Continue draingae of
No dewatering required. stagnating water
Continue draingae of
No dewatering required. stagnating water
Continue draingae of
No dewatering required. stagnating water

Dewatering till recommended


level and dry condition is Draingae trench and pit if
achieved GWT is not very high
No dewatering required. - 1.37 0.761111
No dewatering required. -
Filling of soil till GF or
atleast for 1.5m & no
Dewatering required dewatering required 2.752294

Dewatering till recommended


level and dry condition is Draingae trench and pit if
achieved GWT is not very high
Dewatering required -
Partly filled with water
hetght of 1.9m & no
Dewatering required dewatering required

water filled up in STP tank


for minimum 1.5m & no
Dewatering required dewatering required

# Sensitivity: LNT Construction Internal Use


Location Lakhimpur
Average FFL 107.9
Average EGL 104

Height of Counter weight


RL of GWT GWT above required including Raft & pedestal
(m) BOR (m) FOS (kN/m2) construction
102.2 0.1 1.14 OK
102.6 0.5 5.68 Dewatering req.
103.1 1 11.36 Dewatering req.
103.6 1.5 17.04 Dewatering req.
104.0 1.925 21.87 Dewatering req.

Height of Counter weight


RL of GWT GWT above required including Raft & pedestal
(m) BOR (m) FOS (kN/m2) construction
102.2 0.1 1.14 OK
102.6 0.5 5.68 Dewatering req.
103.1 1 11.36 Dewatering req.
103.6 1.5 17.04 Dewatering req.
104.0 1.925 21.87 Dewatering req.

Height of Counter weight


RL of GWT GWT above required including STP raft
(m) BOR (m) FOS (kN/m2) construction
102.175 0.1 1.14 OK
102.575 0.5 5.68 Dewatering req.
103.075 1 11.36 Dewatering req.
103.575 1.5 17.04 Dewatering req.
104 1.925 21.87 Dewatering req.

# Sensitivity: LNT Construction Internal Use


Construction stages-Hospital

Additional Isolator Additional Additional


counter weight instalation/GF counter weight counter weight
req (kN/m2) construction req (kN/m2) 1F construction req (kN/m2) 2F construction
0.0 OK 0.0 OK 0.0 OK
3.9 OK 0.0 OK 0.0 OK
9.5 OK 0.0 OK 0.0 OK
15.2 OK 0.0 OK 0.0 OK
20.0 OK 0.0 OK 0.0 OK

Construction stages-LINAC

Additional Bunker raft area Additional Bunker raft area Additional


counter weight wall 1st lift counter weight wall 2nd lift counter weight Non-bunker raft
req (kN/m2) construction req (kN/m2) construction req (kN/m2) area with columns
0.0 OK 0.0 OK 0.0 OK
3.9 OK 0.0 OK 0.0 OK
9.5 OK 0.0 OK 0.0 OK
15.2 OK 0.0 OK 0.0 OK
20.0 OK 0.0 OK 0.0 OK

Construction stages-RAMP-STP

Additional Additional Additional


counter weight STP wall 1st lift counter weight STP wall 2nd lift counter weight STP cover slab/GF
req (kN/m2) construction req (kN/m2) construction req (kN/m2) construction
0.0 OK 0.0 OK 0.0 OK
3.8 OK 0.0 OK 0.0 OK
9.4 OK 0.0 OK 0.0 OK
15.1 OK 0.0 OK 0.0 OK
19.9 OK 0.0 OK 0.0 OK

# Sensitivity: LNT Construction Internal Use


NGL to FFL difference (m)
Bottom of raft is at
Mmaximum water table abov

Additional
counter weight
req (kN/m2) 3F construction
0.0 OK
0.0 OK
0.0 OK
0.0 OK
0.0 OK

Additional Non-bunker raft Additional


counter weight area with counter weight
req (kN/m2) columns+PB+1F req (kN/m2)
0.0 OK 0.0
0.0 OK 0.0
0.0 OK 0.0
0.0 OK 0.0
0.0 OK 0.0

Additional Additional
counter weight 1F Ramp counter weight
req (kN/m2) construction req (kN/m2)
0.0 OK 0.0
0.0 OK 0.0
0.0 OK 0.0
0.0 OK 0.0
0.0 OK 0.0

# Sensitivity: LNT Construction Internal Use


Hospital LINAC RAMP-STP
NGL to FFL difference (m)3.9 3.9 3.9
Bottom of raft is at -5.825 -5.825 -5.825
Mmaximum water table abov1.925 1.925 1.925

# Sensitivity: LNT Construction Internal Use


Hospital building - Dewatering requirement:

During Isolator installation


without completion of retaining
Total Counter wall construction
Height of
RL of GWT weight During Raft &
GWT above
(m) required Pedestal
BOR (m) 2
(kN/m ) construction
Dewatering
(Option 1)

93.6 0.1 1.14 Not required

94 0.5 5.68

94.5 1 11.36
Dewatering
required.
95 1.5 17.04 Permissible Dewatering
GWT level is required.
0.5m below BOR Permissible GWT
95.5 2 22.72 level is 0.3m
above BOR

96 2.5 28.4

96.5 3 34.08

LINAC building - Dewatering requirement:


RL of GWT Height of Total Counter STAG
(m) GWT above weight
BOR (m) required with Bunker area
FOS (kN/m2)

During Bunker area wall 1st lift


During Raft & construction
Pedestal
construction

Dewatering
(Option 1)

93.6 0.10 1.14 Not required

# Sensitivity: LNT Construction Internal Use

Dewatering
94.0 0.50 5.68 Not required

94.5 1.00 11.36 Dewatering Not required


required.
Permissible
GWT level is
0.5m below BOR

95.0 1.50 17.04 Dewatering


required.
Permissible GWT
level is 1.0m
95.5 2.00 22.72 above BOR

96.0 2.50 28.4


96.5 3.00 34.08

Ramp-STP building - Dewatering requirement:


RL of GWT Height of Total Counter During
(m) GWT above weight foundation
BOR (m) required with construction fpr
FOS (kN/m2) STP & Non-STP During STP wall construction* 1st
area lift

Dewatering
(Option 1)

91.725 0.1 1.14 Not required

92.125 0.5 5.68 Not required

92.625 1 11.36

93.125 1.5 17.04

93.625 2 22.72
Dewatering
94.125 2.5 28.40 required.
Permissible
Dewatering
94.625 3 34.08 GWT level is
0.5m below BOR required.
Permissible GWT
95.125 3.5 39.76 level is 0.5m
above BOR

95.625 4 45.44

# Sensitivity: LNT Construction Internal Use


Permissible GWT
level is 0.5m
above BOR

96.125 4.5 51.12

96.5 4.875 55.37

BOR Bottom of Raft


GWT Ground water table
Option-1 Dewatering shall be done to lower GWT to allowable limit
Option-2 Additional counterweight shall be added instead of dewatering.
FOS Factor Of Safety
* All waalls in STP shall be constructed upto a height of 2.4m as per GFC drawing.

# Sensitivity: LNT Construction Internal Use


STAGES OF CONSTRUCTION

During Isolator installation During Isolator installation & GF


thout completion of retaining construction with retaining wall During 1F construction During 2F construction
wall construction constructed

Additional Additional Additional


Counter weight Dewatering Counter weight Dewatering (Option Counter weight
(Option 2) (Option 1) (Option 2) 1) (Option 2) Dewatering (Option 1)

kN/m2 kN/m2 kN/m2

0 Not required 0 Not required 0 Not required

0 Not required 0 Not required 0 Not required

0 Not required 0 Not required 0 Not required

0 Not required 0 Not required 0 Not required

3.6 3.6 Not required 0 Not required


Dewatering
required.
9.2 Permissible GWT 9.2 0.75 Not required
level is 1.6m Dewatering required.
above BOR Permissible GWT level
is 2.4m above BOR
14.9 14.9 6.43 Not required

STAGES OF CONSTRUCTION
Bunker area Non-bunker area

During Bunker During GF/Plinth


uring Bunker area wall 1st lift During Non-bunker area column beam
wall 2nd lift
construction construction construction in
construction
non-bunker area

Additional
Counter weight Dewatering Dewatering Additional Counter Dewatering
(Option 1) (Option 1) weight (Option 2) (Option 1)
(Option 2)
kN/m2 kN/m2
0 Not required Not required 0

# Sensitivity: LNT Construction Internal Use


0 Not required 0

0 Not required Dewatering 0


Soil filling shall
required. be done upto
Permissible GWT FGL.
level is 0.3m
above BOR
0 Not required 3

0 Not required 5
0 Not required 10
3 Not required 16

STP area Non-STP area

ring STP wall construction* 1st During STP wall construction* 2nd During STP cover slab/GF construction During construction of non During 1F Ramp
lift lift STP area column construction
construction above 2.4m

Additional Dewatering Additional Dewatering (Option Additional Dewatering (Option 1) Dewatering


Counter weight (Option 1) Counter weight 1) Counter weight (Option 1)
(Option 2) (Option 2) (Option 2)

kN/m2 kN/m2 kN/m2

0 Not required 0 Not required 0 Not required

0 Not required 0 Not required 0 Not required

0 Not required 0 Not required 0 Not required

0 Not required 0 Not required 0 Not required

4.00 Not required 0 Not required 0 Not required

9.00 2.00 Not required 0 Not required


Soil filling shall be done
upto FGL.
15.00 8.00 Not required 0 Not required

20.00 Dewatering 13.00 6.00 Not required


required.
Permissible GWT
26.00 level is 2.0m 19.00 12.00
above BOR Dewatering required. Dewatering
Permissible GWT level required.
is 3.0m above BOR Permissible
GWT level is
3.5m above
BOR
# Sensitivity: LNT Construction Internal Use
Dewatering
required.
Permissible GWT
level is 2.0m
above BOR Dewatering required. Dewatering
Permissible GWT level required.
32.00 25.00 is 3.0m above BOR 17.00 Permissible
GWT level is
3.5m above
BOR
36.00 29.00 21.00

of 2.4m as per GFC drawing.

# Sensitivity: LNT Construction Internal Use


Lakhimpur

FFL 97.2

Average EGL 96.5

# Sensitivity: LNT Construction Internal Use


TP area

During 1F Ramp
construction

Additional
Counter
weight
(Option 2)

kN/m2

6.00

# Sensitivity: LNT Construction Internal Use


11.00

16.00

# Sensitivity: LNT Construction Internal Use