Professional Documents
Culture Documents
Project Accf-Silchar: A Hospital Building
Project Accf-Silchar: A Hospital Building
PROJECT
Hospital
CALCULATED
DPY
LINAC RAMP-STP
2.5 2.5
-6.4 -6.4
3.9 3.9
CHECKED
RAA/SJT
142.4286
Remarks
DEWATERING REQ
DEWATERING REQ
DEWATERING REQ
OK
OK
DEWATERING REQ
DEWATERING REQ
DEWATERING REQ
GF construction 2.06
1F construction 3.08
2F construction 3.66
LINAC Building
Recomendation Alternative
Construction stages-LINAC
Construction stages-RAMP-STP
Additional
counter weight
req (kN/m2) 3F construction
0.0 OK
0.0 OK
0.0 OK
0.0 OK
0.0 OK
Additional Additional
counter weight 1F Ramp counter weight
req (kN/m2) construction req (kN/m2)
0.0 OK 0.0
0.0 OK 0.0
0.0 OK 0.0
0.0 OK 0.0
0.0 OK 0.0
94 0.5 5.68
94.5 1 11.36
Dewatering
required.
95 1.5 17.04 Permissible Dewatering
GWT level is required.
0.5m below BOR Permissible GWT
95.5 2 22.72 level is 0.3m
above BOR
96 2.5 28.4
96.5 3 34.08
Dewatering
(Option 1)
Dewatering
94.0 0.50 5.68 Not required
Dewatering
(Option 1)
92.625 1 11.36
93.625 2 22.72
Dewatering
94.125 2.5 28.40 required.
Permissible
Dewatering
94.625 3 34.08 GWT level is
0.5m below BOR required.
Permissible GWT
95.125 3.5 39.76 level is 0.5m
above BOR
95.625 4 45.44
STAGES OF CONSTRUCTION
Bunker area Non-bunker area
Additional
Counter weight Dewatering Dewatering Additional Counter Dewatering
(Option 1) (Option 1) weight (Option 2) (Option 1)
(Option 2)
kN/m2 kN/m2
0 Not required Not required 0
0 Not required 5
0 Not required 10
3 Not required 16
ring STP wall construction* 1st During STP wall construction* 2nd During STP cover slab/GF construction During construction of non During 1F Ramp
lift lift STP area column construction
construction above 2.4m
FFL 97.2
During 1F Ramp
construction
Additional
Counter
weight
(Option 2)
kN/m2
6.00
16.00