Develop An AON Network For This Problem
Develop An AON Network For This Problem
Develop An AON Network For This Problem
IMMEDIATE TIME
Activity
PREDECESSOR (S) DAYS (S)
A -- 2
B -- 5
C -- 1
D B 10
E A, D 3
F C 6
G E, F 8
Total Project Completion Time 26
*Note:
EF = ES + Activity Time (Duration)
LS = LF – Activity Time (Duration)
Slack Time = LS -ES