Construction of Woqod Petrol Station at Onaiza-2

PRE-QUALIFICATION DOCUMENT
FOR
CONDUCTING OF SURVEY WORKS & UTILITY SCAN
(CONCORD SURVEYING WORKS CO.)

Contract No.: TAAWL/ESD/14/01/19

Document No.: ALCO-WQD-CIV-PRQ-0001 Rev.: 0

Project Phase: Construction

Prepared by: HSE Reviewed by Reviewed by: Approved by:


Name Mr. Leonard Jason Mr. Mohammed Abdullah Mr. Ali Rauf Engr. Praphul Kumar
Baltazar

Job Title QA/QC Engineer HSE Manager Project Coordinator Project Manager

Signature

Date JUL. 27, 2019 JUL. 27, 2019 JUL. 27, 2019 JUL. 27, 2019
HISTORY LOG

Rev No. Issue Date Purpose of Issue Revised Sections

0 JUL. 27, 2019 Issued for Approval


CONTENTS

1. Scope Detail
2. Company profile
2.1 Introduction
2.2 Vision & Mission
2.3 Services
2.4 Work Execution Chart
3. QHSE Certificate
4. Company Certificate
4.1 CR Certificate
4.2 Accreditation Certificate
5. QHSE Policy
5.1 HSE Policy
5.2 Quality Policy
6. Previous Approvals
7. Project List
8. Others
8.1 Instruments
8.2 Organization Chart
8.3 CV
1. SCOPE DETAIL
1. Scope of Works

This prequalification document covers the works of the all survey works including utility
scanning (Concord Surveying Works) in this project of Construction of Woqod Petrol
Station – Onaiza 2.

The survey works & utility scanning will conduct all the required works such as the
following:

• QCS 2014 Section 6 Part 1.2 – Benchmark & Monuments


• QCS 2014 Section 1 Part 7.2.2 – Topographic Survey
• QCS 2014 Section 6 Part 1.2.3 – Setting Out
• QCS 2014 Section 1 Part 10.5.4 – Utility Scan

The Concord Surveying Works will also ensure that all works & scanning will comply
in accordance with the project specification.
2. COMPANY PROFILE
2.1 Introduction
2.2 Vision & Mission
2.3 Services
2.4 Work Execution Chart
2.1 Introduction
2.2 Vision & Mission
2.3 Services
2.4 Work Execution Chart
3. QHSE CERTIFICATE
4. COMPANY CERTIFICATE
4.1 CR Certificate
4.2 Accreditation Certificate
4.1 CR Certificate
4.2 Accreditation Certificate
5. QHSE POLICY
5.1 HSE Policy
5.2 Quality Policy
5.1 HSE Policy
5.2 Quality Policy
6. PREVIOUS APPROVALS
7. PROJECT LIST
8. OTHERS
8.1 Instruments
8.2 Organization Chart
8.3 CV
8.1 Instruments
8.2 Organization Chart
8.3 CV