TAKT TIME

Number of units to be manufacture = 800 units


Number of working shift = 3 Shifts
Total time in 3 shift = 1440 min
Time required to manufacture one unit
on MIG welding machine = 3 min
Downtime per shift (Breaks, Cleanup) = 50 min
Time remain after downtime in 3 shifts= 1290 min
At 75 % proformance time remain in 3 shifts = 967.5 min
Time required to produce one unit = 967.5/800
= 1.20 min(takt time)
Number of machines required = 0.500/1.20
= 2.5 machines

RESPONSIBILITY TABLE
S. NO. ITEM NAME
1 EXPLODED GLENN
2 BOM TABLE GLENN, ANMOL
3 SCRAP RATE TABLE MANINDER, ANMOL
4 TAKT TIME CALCULATION ANMOL, AMANDEEP