Professional Documents
Culture Documents
PManage
PManage
Contents:
1) Definitions
2) Why Project Management
3) 5 PMBOK Knowledge Areas
4) The Gantt Chart
5) Critical Path Method
6) Responsibility Assignment Matrix
7) Risk Management
8) EVM (Earned Value Method) and Project Control
Project Management
1) Initiating
2) Planning
3) Executing
5) Closing
PHASE 1: INITIATION
PHASE 1: PROJECT INITIATION
This is the start of the project, and the goal of this phase is to define
the project at a broad level.
This phase usually begins with a business case. This is when you will
research whether the project is feasible and if it should be
undertaken. If feasibility testing needs to be done, this is the stage of
the project in which that will be completed.
•to provide an understanding of the project, the reason it is being conducted and its justification
•to establish early on in the project the general scope
•to establish the project manager and his or her authority level
•A note of who will review and approve the Project Charter needs to be included.
Example: The Project Charter will be reviewed by the project team and approved. The final approval will be the Director/Head of
School/DOST-ASTI (find out who will approve it)
Example: The scope of the UP Diliman CubeSat project includes the activities listed below:
Determine the payload
Design the satellite subsystems (power system, mission board, comms boards)
Source and secure supply vendors
Create technical documentation
Build and test CubeSats
5) Major Milestones
A list of the milestones that are needed.
Example:
All vendors selected
Contracts or orders complete with all vendors
Pricing determined
Design reviews completed
Handover to JAXA
6) Major Deliverables
A list of the major deliverables that will result from the project are described.
Example:
Assignment of Project Manager
Procurement of supplies
Delivery of project documentation
2x CubeSats
Project Charter (example)
7) Assumptions
The assumptions in creating the project are to be outlined.
Example:
Launch arrangements will be handled by UP Diliman/DOST with JAXA
UP Diliman students will manage the project and be responsible for ongoing operations.
Mentors from the University faculty or staff will be assigned to mentor students and to provide oversight.
8) Constraints
It is important to define any and all constraints on the project or those working on the project
Example:
CubeSat structure must comply with JAXA requirements
Project must fall within the project budget
Deadline for handover to JAXA is XXXX 2020.
Mass of CubeSat must not exceed XXXX kg.
Example: The goal of this project is to provide satellite design and manufacturing knowledge to the students, while demonstrating the
viability of manufacturing a homegrown CubeSat in the Philippines. The opportunity to achieve this has arisen from knoeledge gained
from the Birds-2 / Maya-1 project.
Example: The procurement team will assemble a proposal based on expected costs for review by the Director/Head of Department
etc.
Scope Statement – A document that clearly defines the business need, benefits of the project,
objectives, deliverables, and key milestones. A scope statement may change during the project, but it
shouldn’t be done without the approval of the project manager and the sponsor.
Work Breakdown Schedule (WBS) –This is a visual representation that breaks down the scope of the
project into manageable sections for the team.
Milestones – Identify high-level goals that need to be met throughout the project and include them in
the Gantt chart.
Gantt Chart – A visual timeline that you can use to plan out tasks and visualize your project timeline.
Communication Plan – This is of particular importance if your project involves outside stakeholders.
Develop the proper messaging around the project and create a schedule of when to communicate with
team members based on deliverables and milestones.
Risk Management Plan – Identify all foreseeable risks and plan on how to mitigate them.
Work Breakdown Structure
https://www.pmi.org/learning/library/moving-work-breakdown-structure-critical-path-6978
Work Breakdown Structure
After the WBS elements have been created and bought into by the
team, each should be assigned to the team member who will be
responsible for their delivery. This member will now be responsible
for the remaining critical components needed for the creations of the
project schedule:
https://www.pmi.org/learning/library/moving-work-breakdown-structure-critical-path-6978
Work Breakdown Structure
https://www.youtube.com/watch?v=4h09ZT0lT8M&index=23&list=PLOAuB8
dR35oeyKU0ojIxD8Muf6Mwc8ugW
https://www.youtube.com/watch?v=Ao8X0nsmqoo&list=PLOAuB8dR35oeyK
U0ojIxD8Muf6Mwc8ugW&index=24
https://www.pmi.org/learning/library/moving-work-breakdown-structure-critical-path-6978
You can use the WBS to note dependencies and
predecessors. Estimate task duration. You can
use this information for creating…
Network Diagrams
From a WBS, you can create a
Network Diagram, and from the
Network Diagram you can
determine the Critical Path, the
project duration, and how much
Float/Hazard there is in the project.
B D
A G H
C E
F
Network Diagrams
Early Early
Activity
Start Finish
Late Late
Duration
Start Finish
B D
ES Activity EF
A G H
C E LS Duration LF
F
Network Diagrams
B D
A G H
C E
F
Network Diagrams
B D
A G H
C E
F
B D
4 5
A G H
3 4 3
C E
2 1
F
2
Network Diagrams
B D
A G H
C E
F
3 B D
4 5
0 A 3 G H
3 4 3
3 C E
2 1
F
2
Forward Pass… ES + Duration=EF
Network Diagrams
B D
A G H
C E
F
3 B 7 7 D 12
4 5
0 A 3 G H
3 4 3
3 C 5 5 E 6
2 1
5 F 7
2
Forward Pass… ES + Duration=EF.
Network Diagrams
B D
A G H
C E
F Project
Duration
3 B 7 7 D 12
4 5
0 A 3 12 G 16 16 H 19
3 4 3
3 C 5 5 E 6
2 1
5 F 7
2
If there are 2 outputs pick the highest
Network Diagrams
B D
A G H
C E
F
3 B 7 7 D 12
4 5
0 A 3 12 G 16 16 H 19
3 4 3 19
3 C 5 5 E 6
2 1
5 F 7
2
Find Critical Path with Backward Pass… (LF-Duration=LS)
Network Diagrams
B D
A G H
C E
F
3 B 7 7 D 12
4 7 7 5 12
0 A 3 12 G 16 16 H 19
3 12 4 16 16 3 19
3 C 5 5 E 6
2 11 1 12
5 F 7
14 2 16
Find Critical Path with Backward Pass… (LF-Duration=LS)
Network Diagrams
B D
A G H
C E
F
3 B 7 7 D 12
4 7 7 5 12
0 A 3 12 G 16 16 H 19
3 12 4 16 16 3 19
3 C 5 5 E 6
2 11 11 1 12
5 F 7
14 2 16
Where there are 2 options, take the SMALLEST number
Network Diagrams
B D
A G H
C E
F
3 B 7 7 D 12
3 4 7 7 5 12
0 A 3 12 G 16 16 H 19
0 3 3 12 4 16 16 3 19
3 C 5 5 E 6
9 2 11 11 1 12
5 F 7
14 2 16
Critical Path
To find the critical path, follow the path where the Earliest
Finish is the same as the Late Finish.
3 B 7 7 D 12
3 4 7 7 5 12
0 A 3 12 G 16 16 H 19
0 3 3 12 4 16 16 3 19
3 C 5 5 E 6
9 2 11 11 1 12
5 F 7
14 2 16
Critical Path
To find the critical path, follow the path where the Earliest
Finish is the same as the Late Finish.
3 B 7 7 D 12
3 4 7 7 5 12
0 A 3 12 G 16 16 H 19
0 3 3 12 4 16 16 3 19
3 C 5 5 E 6
9 2 11 11 1 12
5 F 7
14 2 16
5 F 7
14 2 16
TF=0 TF=0
3 B 7 7 D 12
TF=0 3 4 7 7 5 12 TF=0 TF=0
0 A 3 12 G 16 16 H 19
TF=6 TF=6
0 3 3 12 4 16 16 3 19
3 C 5 5 E 6
9 2 11 11 1 12
TF=9
5 F 7
14 2 16
TF=0 TF=0
3 B 7 7 D 12
TF=0 3 4 7 7 5 12 TF=0 TF=0
0 A 3 FF=0 FF=0 12 G 16 16 H 19
0 3 3 TF=6 TF=6 12 4 16 16 3 19
FF=0 3 C 5 5 E 6 FF=0 FF=0
9 2 11 11 1 12
FF=0 FF=6
TF=9
5 F 7
14 2 16
FF=9
TF=0 TF=0
3 B 7 7 D 12
TF=0 3 4 7 7 5 12 TF=0 TF=0
0 A 3 FF=0 FF=0 12 G 16 16 H 19
0 3 3 TF=6 TF=6 12 4 16 16 3 19
FF=0 3 C 5 5 E 6 FF=0 FF=0
9 2 11 11 1 12
FF=0 FF=6
TF=9
5 F 7
14 2 16
FF=9
A Risk Statement is prepared for each risk. There are two essential
components:
There are a number of constructs that may be used in developing the risk
statement, but the preferred construct is as follows: “Given that a condition
exists, there is a possibility that a consequence will occur.” Figure 2 illustrates a
preferred format for risk statement writing.
https://ntrs.nasa.gov/archive/nasa/casi.ntrs.nasa.gov/20120000033.pdf
Phase 3: Execution
Tasks completed during the Execution Phase include:
•Develop team
•Assign resources
•Execute project management plans
•Procurement management if needed
•PM directs and manages project execution
•Set up tracking systems
•Task assignments are executed (DO THE WORK!)
•Status meetings
•Update project schedule
•Modify project plans as needed
During this time, PMs may need to adjust schedules and resources to ensure the
project is on track.
Phase 5: Project Closure
This phase represents the completed project.
Contractors hired to work specifically on the project are terminated at this time.
Some PMs even organize small work events for people who participated in the
project to thank them for their efforts.
1) Integration Management
2) Scope Management
3) Schedule Management
4) Cost Management
5) Quality Management
6) Resource Management
7) Communications Management
8) Risk Management
9) Procurement Management
10) Stakeholder Management
https://www.projectengineer.net/the-10-pmbok-knowledge-areas/