Rate Analysis of Plastering With Cement Mortar - Quantity Calculation

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

2019/10/26 Rate Analysis of Plastering with Cement Mortar -Quantity Calculation

(https://theconstructor.org/) 

Rate Analysis of Plastering with Cement


Mortar -Material Quantity Calculation

SPONSORED SEARCHES

building estimate brick masonry

building plastering brick wall

Rate analysis of plastering with cement mortar requires the quantity estimation of
materials cement mortar, i.e. quantity of cement, sand and water for various grades
of mortar required. Grades of mortar used for plastering is generally same grade as
used in the masonry work.

There are different grades of mortar that can be used for plastering of masonry
structural members such as in CM 1:2, 1:4, 1:6, 1:8 etc. Cement Mortar in ratio 1:6 is
generally used for plastering work.

For the calculation of quantity of cement and sand in mortar, volume of mortar
required for plastering is calculated based on thickness of plastering surface and
surface area of the structural member.

https://theconstructor.org/practical-guide/rate-analysis-of-plastering-with-cement-mortar/9620/ 1/4
2019/10/26 Rate Analysis of Plastering with Cement Mortar -Quantity Calculation

Let us take an example of a wall to be plastered:

SPONSORED SEARCHES

analysis of rate for plastering

plastering labour calculation

plastering work rate

brick masonry

house plastering

Length of wall = 2m

Width of wall = 1.5m

Thickness of plaster to be used = 20mm

Plaster to be carried out in two layers of 10mm each.

The quantity of cement mortar required will be: 2 x 1.5 x (20/1000) = 0.06 m3 of
mortar.

The rate analysis of mortar need to be done for the calculated quantity required.
Read here the rate analysis of cement mortar
(https://theconstructor.org/practical-guide/rate-analysis-for-cement-
mortar/7071/) to know how to calculate quantity of cement and sand in mortar.

Once the quantity of cement and sand is calculated, the labor cost required for
mixing of mortar is calculated. The coefficients of labor for plastering work are
taken from the Rate Analysis by CPWD.

The cost of mixing of calculated quantity of mortar remains constant, but the cost of
application of mortar varies with number of layers in which the mortar is applied.
Thus, the cost of mason depends on area to be plastered and number of layers of
plaster to be applied. The cost of other labors varies with the quantity of cement
mortar to be mixed and number of layers of plasters to be applied.

The coefficients of mason and labors are as follows per m2 area per layer of
plaster to be applied:

https://theconstructor.org/practical-guide/rate-analysis-of-plastering-with-cement-mortar/9620/ 2/4
2019/10/26 Rate Analysis of Plastering with Cement Mortar -Quantity Calculation

Mason – 0.07435 days

Labors – 0.0929 days

Bhishti – 0.0929 days (the one who carries materials and water for mixing)

These coefficients are multiplied with the given quantity of cement mortar required
for plaster in m3 and number of layers or plasters.

The number of days of mason required = 0.07435 x No. of layers x surface area

= 0.07435 x 2 x (2 x1.5) = 0.44610 days

For Labors and Bhishti = 0.0929 x 2 x (2 x 1.5) = 0.5574 days for each.

The labor and bhishti days required for mixing of cement mortar is also calculated
as given in rate analysis of cement mortar (https://theconstructor.org/practical-
guide/rate-analysis-for-cement-mortar/7071/).

For example, labor required = 0.21 x 0.06 = 0.0126 days

Bhishti required = 0.0929 x 0.06 = 0.005574 days.

Thus total number of days for plastering in two-layers of plaster for


1.5mx2mx20mm plaster:

Mason = 0.44610 days

Labor = 0.5574 + 0.0126 = 0.57 days

Bhishti = 0.5574 + 0.005574 = 0.562974 days.

The daily wages of masons and labors are multiplied with number of days required
by them to get the cost.

The excel calculation for rate analysis of plastering is shown below:

Read More:

Rate Analysis of Civil Works -Elements and Requirements


(https://theconstructor.org/practical-guide/rate-analysis-of-civil-works-
elements-and-requirements/10952/)

https://theconstructor.org/practical-guide/rate-analysis-of-plastering-with-cement-mortar/9620/ 3/4
2019/10/26 Rate Analysis of Plastering with Cement Mortar -Quantity Calculation

Rate Analysis for Cement Mortar (https://theconstructor.org/practical-


guide/rate-analysis-for-cement-mortar/7071/)

Quantity of Cement & Sand Calculation in Mortar


(https://theconstructor.org/practical-guide/quantity-of-cement-sand-
calculation-in-mortar/6925/)

Analysis of Rates for Civil Engineering Works


(https://theconstructor.org/construction/analysis-of-rates-for-civil-engineering-
works/6488/)

Rate Analysis for Brick Masonry (https://theconstructor.org/practical-


guide/rate-analysis-for-brick-masonry/7102/)

Special Plastering Materials for Different Purposes Used in Building


Construction (https://theconstructor.org/building/special-plastering-materials-
types-uses/15901/)

Types of Plaster Finishes and External Rendering for Buildings


(https://theconstructor.org/building/types-plaster-finishes-external-rendering-
buildings/14532/)

About Gopal Mishra


(https://theconstructor.org/author/gopal-mishra/)

Gopal Mishra is a Civil Engineer from NIT Calicut and has more than 10 years of
experience in Civil Engineering and Construction. He is the founder of The Constructor.

©2019 The Constructor - Civil Engineering Home

https://theconstructor.org/practical-guide/rate-analysis-of-plastering-with-cement-mortar/9620/ 4/4